1-Technical Specifications and Special Provisions.pdf

PDF 272 KB Posted

Attached to
OYSTER BAY RESTORATION PROJECT
Solicitation number
2026-0723
Issued by
Baldwin County, Alabama

About this file

This technical specifications and special provisions document outlines the requirements for the Oyster Bay Restoration Project in Baldwin County, Alabama, administered by the City of Gulf Shores. The project consists of installing three precast concrete box culverts (8 feet by 4 feet) under Waterway West Boulevard, along with associated road and safety improvements and cleaning and modifications of four existing drainage structures. The work includes clearing and grubbing, structure excavation and backfill, minor structure concrete, stabilized roadbed installation, aggregate base course, bituminous surface treatment, asphalt surfacing, traffic striping, aluminum beam guardrails with end anchors, temporary soil erosion and sediment control, underground utility adjustments for communication lines, and record documentation. The entire project must be completed within 180 working days. The specifications reference the Alabama Department of Transportation Standard Specifications for Highway Construction (2018 Edition) as the governing standard for site work, roads, and stormwater construction, with additional technical provisions detailed throughout the document including requirements for pre-construction hazard surveys with magnetometer surveys and ground-truthing, mobilization and demobilization, performance and labor and materials bonds for contracts exceeding $50,000, and comprehensive stormwater management planning.

The contract utilizes a unit pricing structure with lump sum pricing for specific line items including mobilization and demobilization, performance and labor and materials bonds, record documents, temporary soil erosion and sediment control, and traffic control devices for construction zones. Payment for mobilization is structured at 60 percent upon complete mobilization to the site and 40 percent upon final acceptance and completion of final clean-up. Extensive environmental protection provisions are required, with the contractor responsible for submitting a comprehensive Environmental Protection Plan at least seven days prior to the pre-construction meeting, addressing protection of land and water resources, wildlife species including threatened and endangered species, cultural and archeological resources, air quality, chemical and solid waste disposal, and noise control. The project is federally funded through RESTORE Act grant awards and subject to extensive federal compliance requirements including SAM.gov registration, verification against the federal Excluded Parties List, debarment certifications, non-discrimination and equal employment opportunity requirements, domestic procurement preferences, small business and minority business enterprise participation, and environmental compliance with NEPA, the Endangered Species Act, the Clean Water Act, and the Coastal Zone Management Act. Contractors must maintain SAM.gov registration throughout the project period, ensure all federal compliance requirements flow down to subcontractors and vendors, and submit semi-annual Federal Financial Reports and performance reports, with all records retained for a minimum of three years.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OYSTER BAY RESTORATION

TECHNICAL SPECIFICATIONS AND SPECIAL PROVISIONS

Final Design (100%) Specifications.

This document should not be considered a certified document.

100% Specifications

Table of Contents

I. GENERAL

OYSTER BAY RESTORATION PROJECT DESCRIPTION

SUMMARY OF THE WORK

SCOPE

PHYSICAL DATA

ENVIRONMENTAL PROTECTION PROVISIONS

II. MATERIALS AND EXECUTION

STANDARD SPECIFICATIONS

PRE-CONSTRUCTION HAZARD SURVEY

MOBILIZATION AND DEMOBILIZATION

PERFORMANCE AND LABOR & MATERIALS BONDS

CLEARING AND GRUBBING

CLEANING EXISTING DRAINAGE STRUCTURES

PARTIAL REMOVAL OF EXISTING DRAINAGE STRUCTURES

EMBANKMENT

STRUCTURE EXCAVATION AND BACKFILL FOR DRAINAGE AND MINOR

STRUCTURES

REINFORCED CONCRETE BOX CULVERTS

MINOR STRUCTURE CONCRETE

STABILIZED ROADBED

AGGREGATE BASE

BITUMINOUS SURFACE TREATMENT

TACK COAT

ASPHALT SURFACE

TRAFFIC STRIPE

GUARDRAIL AND BARRIER RAIL

TEMPORARY SOIL EROSION AND SEDIMENT CONTROL

MINOR UTILITY ADJUSTMENTS

RECORD DOCUMENTS

WORK AREA

CONSTRUCTION ACCESS

STAGING AND LAYDOWN AREAS

MISPLACED MATERIAL, PLANT MACHINERY, EQUIPMENT, OR APPLIANCE

FINAL CLEAN-UP

SCHEDULE OF DELIVERABLES

List of Appendices

• Appendix A: Geotechnical Report

• Appendix B: USACE Permit Information

• Appendix C: Referenced Sections of the Alabama Department of Transportation -

Standard Specifications for Highway Construction 2018 Edition

• Appendix D: Required Attachments for RESTORE Council-Selected Component

I. GENERAL

1. OYSTER BAY RESTORATION PROJECT DESCRIPTION

The Oyster Bay Restoration is located in Baldwin County, Alabama on Oyster Bay Road (County Road 4). The Project consists of installing three (3)-eight foot (8’) by four foot (4’) precast concrete box culverts, associated road and safety improvements, and the cleaning and modifications of four (4) existing drainage structures.

2. SUMMARY OF THE WORK

The Project includes the following items in accordance with the Contract Documents:

• Pre-Construction Hazard Survey;

• Mobilization and Demobilization;

• Performance and Labor & Materials Bonds;

• Clearing and Grubbing;

• Cleaning Existing Drainage Structures (less than or equal to 48" horizontal opening);

• Partially Removal of Drainage Structures;

• Structure Excavation;

• Foundation Backfill, Commercial;

• Precast Concrete Box Culverts;

• Minor Structure Concrete;

• Roadbed Stabilizing Material, LBR 40;

• Aggregate Base Course, Type A, Plant Mixed, 8 inches;

• Bituminous Treatment, Type A (Prime Coat);

• Tack Coat;

• Superpave Bituminous Concrete Wearing Surface, 3/8" Maximum Aggregate Size Mix, ESAL

Range C/D (3 inches);

• Broken Yellow, Class 2, Type A Traffic Stripe;

• Aluminum Beam Guardrail, Class A;

• Guardrail End Anchor, Type 20 Series;

• Temporary Soil Erosion and Sediment Control;

• Traffic Control Devices for Construction Zones;

• Underground Utility Adjustment (Communication); and

• Record Documents.

3. SCOPE

The CONTRACTOR shall provide all labor, materials, tools, equipment, plant, supplies, superintendence, submittals, incidentals, and services necessary or required to fully complete the work for “Oyster Bay Restoration” in accordance with these Specifications and shown on the Plans. Major tasks associated with this work include the items described in Paragraph I-2 of these Technical Specifications and Special Provisions of the Specifications.

4. PHYSICAL DATA

Information and data furnished or referred to in the Contract Documents are furnished for the CONTRACTOR'S information. However, it is expressly understood that the OWNER will not be responsible for any interpretation or conclusion drawn there from by the CONTRACTOR.

Likewise, the OWNER will not be responsible for any information provided to the CONTRACTOR by any information agency or other party.

The physical conditions of the Project Construction Site indicated on the Plans and in the Specifications are the results of site investigations conducted using topographic surveys, cultural resources surveys, and sediment sampling. While the OWNER’S topographic survey, cultural resources surveys and sediment samples are representative of surface or subsurface conditions at their specific locations and vertical reaches, variations in the characteristics of the surface or subsurface materials are possible and should be expected. Interpretations as shown in the Plans between sampling points are estimates of expected average conditions in these areas and are provided for the convenience and use of the CONTRACTOR but should not be taken as the actual conditions at each point beyond the sampling points. Should any questions or discrepancies arise, the CONTRACTOR shall report conditions to the OWNER immediately.

Copies of the boring logs are included in Appendix A: Geotechnical Report of these Technical Specifications and Special Provisions of the Specifications.

4.1 Weather Conditions:

The Project Construction Site generally has a mild subtropical climate and may be affected by tropical storms and hurricanes primarily from June through November and by stormy and/or rainy weather, including severe thunderstorms, during any time of the year. The CONTRACTOR shall be responsible for obtaining information concerning rain and wind conditions that could influence safety and construction operations prior to making a bid. A list of publications containing climatological and meteorological observations and data for the Project Construction Site is provided below. Other publications or information sources are available in addition to the following:

4.1.1 Local Climatological Data:

Monthly Summary published by the National Oceanic and Atmospheric Administration (NOAA), Asheville, NC. Subscription price and ordering information is available from the National Climatic Data Center, Federal Building, Asheville, NC 22801. This publication gives hourly wind speed and direction observations. The Annual Summary gives a summary of the observations for the period of record.

4.1.2 Summary of Synoptic Meteorological Observations:

North American Coastal Marine Areas Atlantic and Gulf Coasts. Produced by the National Weather Service, U.S. Department of Commerce. Distributed by the National Technical Information Service, U.S. Department of Commerce.

4.2 Access to the Project Construction Site:

Land access to the Project Construction Site will be provided by the OWNER via County Road 4.

5. ENVIRONMENTAL PROTECTION PROVISIONS

5.1 Scope:

The Environmental Protection Provisions address CONTRACTOR responsibilities for the prevention of pollution and other environmental damage as the result of construction operations under the Contract Documents. For the purpose of this Specification, pollution and other environmental damages are defined as the presence of chemical, physical, or biological elements or agents that adversely affect human health or welfare;

unfavorably alter ecological balances of importance to human life; affect other species of importance to man; degrade the utility of the environment for aesthetic, cultural, and/or historical purposes; or unnecessarily damage/destroy environmental resources. The control of pollution and damage requires consideration of air, water, land, and the marine environment and includes management of construction activities, visual aesthetics, noise, solid waste, radiant energy, and radioactive materials, as well as other pollutants. The CONTRACTOR shall fulfill these provisions at the CONTRACTOR'S expense.

5.2 Quality Control:

The CONTRACTOR shall establish and maintain quality control for environmental protection for all items set forth herein. The CONTRACTOR shall record on any problems in complying with laws, regulations, and ordinances, as well as project Permits and corrective action taken.

5.3 Permits:

The CONTRACTOR shall comply with all requirements under the terms and conditions set out in all permits applicable to the work. The OWNER has received the appropriate approvals for Coastal Zone Consistency from the Alabama Department of Environmental Management and the U.S. Army Corps of Engineers. Applicable Permit information and Permits are included in Appendix B of these Technical Specifications and Special Provisions of the Specifications and are part of the Contract Documents. Specifically, the CONTRACTOR will familiarize themselves with general and specific conditions contained in the Permits. Any other licenses, easements, or approvals required, including, but not limited to, those which may be required by Baldwin County or the OWNER, shall be secured and paid for by the CONTRACTOR.

5.4 Subcontractors:

Assurance of compliance with all sections of the Contract by Subcontractors shall be the responsibility of the CONTRACTOR, including compliance with all environmental and Permit requirements.

5.5 Notification:

The OWNER will notify the CONTRACTOR of any known non-compliance with the aforementioned Federal, State, or Local laws or regulations, Permits, and other elements of the CONTRACTOR'S Environmental Protection Plan. Nevertheless, it remains the sole responsibility of the CONTRACTOR to comply with all applicable Federal, State, and Local laws and regulations, Permits, and all elements of the Environmental Protection Plan. If there is known non-compliance, the OWNER will determine what action will be taken and such response will be transmitted to the CONTRACTOR by the OWNER, which may include stopping construction of the work at the cost of the CONTRACTOR until the CONTRACTOR complies with the Environmental Protection Plan. It shall also be the CONTRACTOR'S responsibility that all subcontractors comply with all applicable laws, regulations, Permit requirements, and all elements of the Environmental Protection Plan.

5.6 Protection of Environmental Resources:

The environmental resources within the Project Construction Site and those affected outside the limits of Project Construction Site under this Contract shall be protected during the entire period of this Contract. The CONTRACTOR shall, at all times, maintain adequate stakes or other markers required to delineate areas of the work to ensure the protection of resources. The disturbance of lands and waters that are outside the Project Construction Site limits is prohibited, except as found necessary and approved by the OWNER and any associated Permits. The CONTRACTOR shall conduct his work in such manner as to prevent the entry of fuels, oils, bituminous materials, chemicals, sewage, or other harmful materials into streams, lakes, marshlands, bays, or the Intracoastal Waterway. All waterways shall be cleared as soon as practicable of false work, stakes, piling, debris, or other obstructions placed during construction operations and not a part of the finished work. Details regarding environmental protection shall be as stated in the following subparagraphs.

5.6.1 Protection of Land Resources:

Prior to the beginning of any work, and at the request of the CONTRACTOR, the OWNER shall identify land resources (if any) to be preserved within the CONTRACTOR'S Project Construction Site. Unless indicated in the Plans or directed by the OWNER, the CONTRACTOR shall not remove, cut, deface, injure, or destroy land resources including marsh or berm vegetation, trees, shrubs, vines, grasses, topsoil, and landforms without direct written permission from the OWNER. No ropes, cables, or guy lines shall be fastened to or attached to any trees for anchorage unless specifically authorized by the OWNER. Where such special emergency use is allowed, the CONTRACTOR shall provide effective protection for land and vegetation resources at all times as defined in the following paragraphs. The CONTRACTOR shall be responsible for the replacement of any damaged or destroyed vegetation outside the Project Construction Site and outside the approved work areas as indicated on the Plans and the restoration of any water bottoms and land forms to the satisfaction of the OWNER. Failure to replace damaged or destroyed vegetation or failure to restore damaged water bottoms and land forms outside the Project Construction Site and outside the approved work areas as indicated on the Plans by the CONTRACTOR may result in replacement by the OWNER; the cost of replacement may be deducted from any money due, or to become due, to the CONTRACTOR or may be recovered under their bond.

5.6.2 Project Construction Site Limits:

Isolated areas (if any) within the Project Construction Site which are to be saved and protected shall also be identified by the OWNER and marked or fenced by the CONTRACTOR. All survey monuments and markers shall be protected before construction operations commence. The CONTRACTOR shall convey to all Subcontractors and personnel the purpose of marking and/or protection for all necessary objects.

5.6.3 Disposal of Solid Wastes:

Solid wastes (including cleared debris) and rubbish resulting from the CONTRACTOR’S activities shall be picked up daily and placed in containers.

These containers shall be removed from the Project Construction Site and emptied on a regular schedule. The CONTRACTOR shall empty containers when three-quarters full and will avoid overflow conditions. The CONTRACTOR shall not burn any rubbish at the Project Construction Site. Disposal of rubbish shall be at an approved off-site location and in a manner that complies with State and Local laws and regulations. The CONTRACTOR shall be solely responsible for all costs associated with the collection, removal, and disposal of rubbish. All handling and disposal shall be conducted to prevent contamination. No steel, cables, wire, pipe, drums, or any other solid waste or debris shall be permitted to be disposed overboard into the waters of Oyster Bay, Intracoastal Waterway, or any other water body. Disposal of solid wastes or debris in Oyster Bay, Intracoastal Waterway, or the Gulf of Mexico and other water bodies is a violation of State and/or Federal laws. If such debris is found, the debris shall be removed by the CONTRACTOR at his own cost. Failure to remove debris by the CONTRACTOR may result in removal by the OWNER. The cost of removal may be deducted from any money due, or to become due, to the CONTRACTOR or may be recovered under their bond.

5.6.4 Disposal of Chemical Waste:

Chemical waste shall be stored in corrosion resistant containers, removed from the Project Construction Site, and disposed of in accordance with Federal, State, and Local regulations. The CONTRACTOR shall perform all maintenance of equipment, including but not limited to refueling, filter changes, and replacement of hydraulic lines in a manner so as not to contaminate soils, ground or surface waters, or any other natural resources.

5.6.5 Disposal of Discarded Materials:

Discarded materials other than those which can be included in the solid waste category will be handled by the CONTRACTOR as directed by the OWNER.

5.6.6 Use of Equipment:

The use of any wheeled or tracked vehicles outside the Project Construction Site is prohibited. Any damage to wetland vegetation, vegetation, trees or change in the existing elevation (e.g., ruts, tracks, excavation) in wetland areas, bay bottom, flats, etc. occurring on the Project Construction Site, outside approved Project Construction Site limits or adjacent to the Project Construction Site, as a result of construction operations, shall be repaired by the CONTRACTOR at no additional expense to the OWNER.

5.6.7 Siltation / Turbidity Control:

The CONTRACTOR shall conduct work in a manner that will not cause damaging siltation or pollution of any water bodies. All applicable Federal and State regulations of agencies and statutes relating to the prevention and abatement of pollution shall be complied with in the performance of the Contract.

5.6.8 Protection of Water, Fish, and Wildlife Resources:

The CONTRACTOR shall keep all work under continued surveillance, management, and control to minimize interference with, disturbance to, and damage of water, fish, and wildlife resources. Species that require specific consideration, as well as measures for their protection, shall be addressed in the CONTRACTOR'S Environmental Protection Plan prior to the beginning of work.

Refer to Paragraph 5.12.1 for additional requirements.

5.6.9 Protection of Commercial Fisheries:

The CONTRACTOR shall note that bays, water bottoms, creeks, and ponds in the vicinity of the Project Construction Site may include numerous publicly- and privately-issued leases for the cultivation and harvest of oysters and other commercial fishery resources. There are no known leases within the Project Construction Site footprint. The CONTRACTOR shall conduct all aspects of its operations to avoid any and all impacts to such leases not acquired for the project.

5.6.10 Protection of Air Resources:

The CONTRACTOR shall keep construction activities under surveillance, management, and control to minimize pollution of air resources. All activities, equipment, processes, and work operated or performed by the CONTRACTOR in accomplishing the specified construction shall be in strict accordance with the applicable air pollution standards of the State of Alabama and all Federal emission and performance laws and standards.

5.6.11 Dispensing of Fuel:

Secondary containment, which is capable of holding at minimum one hundred ten (110) percent of the tank contents, shall be provided by the CONTRACTOR for each fuel storage tank. Fuel dispensers shall have a four (4)-foot square, sixteen (16)-gauge metal pan with borders banded up and welded at the corners right below the bibb. The edges of the pans shall have an eight (8)-inch minimum in depth to ascertain that no contamination of the ground takes place. Pans shall be cleaned by an approved method immediately after every dispensing of fuel and wastes disposed of offsite in an approved area. Should any spilling of fuel occur, the CONTRACTOR shall immediately contain the spill and contact the OWNER and the appropriate local authorities. The CONTRACTOR shall be solely responsible for any fines, penalties, or other legal activities related to fuel spills. If the CONTRACTOR’S fuel cells exceed the thresholds set forth in the applicable Code of Federal Regulations, Title 40 the CONTRACTOR shall provide a spill plan and containment equipment accordingly (Paragraph 5.12.1.7 through Paragraph 5.12.1.10 below.)

5.6.12 Temporary Sanitary Facility:

The CONTRACTOR shall furnish and maintain chemical toilets for use by its employees and the OWNER on the Project Construction Site. Chemical toilets shall be cleaned on a regular basis to ensure that odor does not become a nuisance. The CONTRACTOR shall be responsible to coordinate, maintain, and monitor a cleaning schedule that is appropriate for the number of CONTRACTOR personnel on the Project Construction Site.

5.6.13 Storage of Lubricants:

All lubricants and other potential liquid pollutants shall be stored in sealed, non-corrosive containers. Individual containers shall be stored in metal pans with borders banded up and welded at the corners right below the bibb. Pans shall be deep enough to prevent contamination of the ground. Pans shall be kept clean of all spillage or leakage.

5.7 Protection of Resources:

5.7.1 Protection of Bird Resources:

Certain bird species are protected by the U.S. Fish and Wildlife Service and the Alabama Department of Environmental Management. Protected bird species most likely to be encountered include, but are not limited to, wood stork and bald eagle.

Other bird species are protected by Federal and State laws, including but not limited to the Migratory Bird Treaty Act. The CONTRACTOR shall employ personnel familiar with protected birds to allow for easy identification of birds encountered during the execution of work under this Contract.

5.7.1.1 Bald Eagle: If bald eagle breeding or nesting behaviors are observed or a nest is discovered or known, all work activities shall avoid the nest by a minimum of six hundred sixty feet (660’). If the nest is protected by a vegetated buffer where there is no line of sight to the nest, then the minimum avoidance distance is three hundred thirty feet (330’).

If a bald eagle or a potential bald eagle nest is observed, the CONTRACTOR shall immediately notify the OWNER.

5.7.2 Protection of Fish and Other Wildlife Resources:

The CONTRACTOR shall keep all work activities under surveillance, management and control to minimize interference with, disturbance to and damage of fish and wildlife. Prior to the beginning of the work, the CONTRACTOR shall list species that require specific attention and describe measures for their protection. Threatened and endangered species which have the potential to exist within the boundaries of the Project Construction Site include Alabama red-bellied turtle, and eastern indigo snake. The CONTRACTOR shall review and comply with the restrictions listed below regarding construction activities.

5.7.3 Protection of Cultural Resources:

CONTRACTOR shall immediately notify the OWNER if any unknown historic or archeological remains are found in the project vicinity and await further instruction from the OWNER.

5.8 Final Construction Clean Up:

The CONTRACTOR shall clean-up any Project Construction Site areas used for construction as stated in Section 32 below.

5.9 Restoration of Landscape Damage:

The CONTRACTOR shall restore all landscape features, land resources, water resources, and fish and wildlife resources damaged or destroyed during the work operations that are outside the limits of the Project Construction Site as indicated in the Plans. Such restoration shall be in accordance with a plan submitted for approval by the OWNER.

This work shall be accomplished at the CONTRACTOR'S expense. Final payment to the CONTRACTOR shall not occur until the OWNER is satisfied with the CONTRACTOR'S effort to restore landscape or any other damage caused by the CONTRACTOR or his subcontractors.

5.10 Maintenance of Pollution Control Facilities:

The CONTRACTOR shall maintain constructed facilities and portable pollution control devices for the duration of the Contract or for that length of time that work activities create the particular pollutant.

5.11 Training of Contractor Personnel in Pollution Control and Environmental Protection The CONTRACTOR shall train all Subcontractors and personnel in all phases of environmental protection. Personnel and Subcontractors shall be familiar with Permit requirements and with the necessity of protection of all habitats. The training shall include methods of detecting and avoiding pollution, familiarization with pollution standards, both statutory and contractual, and installation and care of facilities to insure adequate and continuous environmental pollution control. Quality Control and supervisory personnel shall be thoroughly trained in the proper use of monitoring devices and abatement equipment and shall be thoroughly knowledgeable of Federal, State, and Local laws, regulations, and Permits as listed in the Environmental Protection Plan submitted by the CONTRACTOR.

5.12 Submittals:

5.12.1 Environmental Protection Plan:

At least seven (7) days prior to the pre-construction meeting, the CONTRACTOR shall submit in writing an Environmental Protection Plan to the OWNER.

Approval of the CONTRACTOR'S plan will not relieve the CONTRACTOR of his responsibility for adequate and continuing control of pollutants and other environmental protection measures. The Environmental Protection Plan shall include but may not be limited to the following:

5.12.1.1 Methods for limiting impacts to features and habitats within authorized Project Construction Site areas. The CONTRACTOR shall prepare a listing of methods to protect resources needing protection (i.e. all vegetation, trees, shrubs, vines, grasses and ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, archeological and cultural resources, and environmental resources).

5.12.1.2 Procedures to be implemented by the CONTRACTOR to

assure compliance with the environmental protection requirements of Section 5.6.1 above and to comply with the applicable Permits, laws, and regulations. The CONTRACTOR shall address each element of Environmental Protection described in Paragraph 5.6.1 above. The CONTRACTOR shall also provide written assurance that immediate corrective action will be taken to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures set out in accordance with the Environmental Protection Plan.

5.12.1.3 Procedures to be implemented by the CONTRACTOR to

assure compliance with the protection of water, fish, and wildlife resources, per the requirements of Paragraph 5.6.8 above, and to comply with the applicable Permits, laws, and regulations. The CONTRACTOR shall address each element of the protection of water, fish, and wildlife resources as described in Paragraph 5.6.8. The CONTRACTOR shall also provide written assurance that immediate corrective action will be taken to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures set out in accordance with the Environmental Protection Plan.

5.12.1.4 A list of Federal, State, and Local laws, regulations, and Permits concerning environmental protection, pollution control, and abatement that are applicable to the CONTRACTOR'S proposed operations and the requirements imposed by those laws, regulations, and permits.

5.12.1.5 Drawings showing locations of any proposed material

storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials.

5.12.1.6 Environmental monitoring plans for the Project

Construction Site, including land, water, air, and noise monitoring.

5.12.1.7 Oil and fuel spill prevention.

5.12.1.8 Oil spill contingency plan.

5.12.1.9 Fuel spill plan (if applicable).

5.12.1.10 Explanation of where spill response and containment materials and equipment will be stored and accessed if needed.

5.12.1.11 A protection plan for threatened and/or endangered

species within the Project Construction Site.

5.12.1.12 Work area plan showing the proposed work activity in each portion of the Project Construction Site and identifying the Project Construction Site areas of limited use or nonuse.

The plan shall include measures for marking the limits of use of Project Construction areas.

5.12.1.13 The location of the solid disposal area.

5.12.1.14 A statement as to the person who will be responsible for implementation of the Environmental Protection Plan. The CONTRACTOR personnel responsible shall report directly to the CONTRACTOR'S top management and shall have the authority to act for the CONTRACTOR in all environmental protection matters.

5.12.1.15 A statement acknowledging that the CONTRACTOR is

responsible for environmental protection, including all of the CONTRACTOR'S personnel and Subcontractors.

5.12.1.16 The Environmental Protection Plan shall be dated and endorsed by the individual of top management in charge of the construction.

5.13 Noise Control:

The CONTRACTOR shall comply with all Federal, State, and Local sound control and noise level ordinances, regulations, and laws that apply to the Project Construction Site.

All hauling and excavating equipment used on this work shall be equipped with satisfactory mufflers or other noise abatement devices.

II. MATERIALS AND EXECUTION

6. STANDARD SPECIFICATIONS

This City of Gulf Shores (OWNER) Project uses the “Alabama Department of Transportation Standard Specifications for Highway Construction, Current Edition” as the governing specification for site work, roads and stormwater construction. These technical specifications and special provision contains specific clauses that add to or revise the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018” or supplement specifications, setting forth conditions varying from or additional to the Standard Specifications and are applicable to this project. Sections of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018” which are referenced in the Technical Specifications and Special Provisions are provided in Appendix C of these Technical Specifications and Special Provisions of the Specifications.

7. PRE-CONSTRUCTION HAZARD SURVEY

7.1 Description:

CONTRACTOR shall furnish all the materials, submittals, labor and equipment necessary to perform a pre-construction hazard survey. Prior to commencing any work at the Project Construction Site, the CONTRACTOR shall conduct a magnetometer survey and ground-truthing by probing to determine the depth of cover of the magnetometer hits and any other surveys and investigations within the Project Construction Site. All surveys shall be performed by personnel who are under the direct supervision of a professional land surveyor licensed in the State of Alabama. Survey data shall reference the North American Datum of 1983 (NAD 83), Alabama West Zone, U.S. Survey Feet for horizontal control, and the North American Vertical Datum of 1988 (NAVD 88), U.S.

Survey Feet for vertical control. Horizontal and vertical control shall be established by using the monument specified in the Plans. All suspected or known utilities, pipelines or other obstructions shall be probed in coordination with utilities/pipeline/obstruction owner and appropriately marked throughout the work.

7.2 Submittals:

CONTRACTOR shall submit pre-construction hazard survey drawings to the OWNER prior to commencing any work. A report documenting the survey methodology, results, and a summary of associated interpretations and recommendations shall also be submitted to the OWNER. In addition, all potential hazards or obstructions shall be plotted on the pre-construction survey drawing submittal. Drawings shall clearly show all track lines, coordinates, amplitudes, signature types, and signature widths of all hits. The survey shall also show the coordinates, top elevation and depth of ground cover for all pipelines, utilities, or obstructions, if any. Pre-construction hazard survey submittal shall be signed and sealed by a professional land surveyor licensed in the State of Alabama.

7.3 Notification:

CONTRACTOR shall notify the OWNER no later than five (5) working days prior to performing pre-construction hazard survey so that OWNER and Construction Observer designee may accompany the survey crew and witness the work.

7.4 Basis of Payment:

The CONTRACTOR may apply for payment on the monthly Application for Payment for the pre-construction hazard survey once the completed survey has been submitted to and accepted by the OWNER. All costs connected with the Pre-Construction Hazard Survey will be paid for at the Contract Lump Sum Price for Pre-Construction Hazard Survey (Line Item 001-A).

8. MOBILIZATION AND DEMOBILIZATION

8.1 Description:

Per Section 600 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

8.2 Special Provisions:

Material costs for items listed or subsidiary to the major work items listed on the Schedule of Prices shall not be included under mobilization and demobilization.

In the event the OWNER considers that the cost for mobilization does not bear a reasonable relation to the cost of the entire work in this Contract, the OWNER may require the CONTRACTOR to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the OWNER will result in payment of estimated mobilization costs, as determined by the OWNER at the completion of mobilization, and payment of the remainder of this item in the final payment under this Contract.

8.3 Basis of Payment:

Sixty percent (60%) of the mobilization/demobilization Contract Lump Sum Price will be paid to CONTRACTOR upon complete mobilization to the Project Construction Site.

The remaining forty percent (40%) will be paid to CONTRACTOR upon final acceptance of the work and completion of Final Clean-up. All costs connected with mobilization and demobilization will be paid for at the Contract Lump Sum Price for Mobilization and Demobilization (Line Item 600-A).

9. PERFORMANCE AND LABOR & MATERIALS BONDS

9.1 Description:

If the winning bid is in excess of Fifty Thousand Dollars ($50,000), the Contractor shall obtain a performance bond equal to one hundred percent (100%) of contract amount and shall be provided within ten (10) days of Notice of Award.

If the winning bid is in excess of Fifty Thousand Dollars ($50,000), the Contractor shall obtain a Labor & Materials Payment Bond equal to but not less than fifty percent (50%) of contract amount and shall be provided within ten (10) days of Notice of Award. The bond shall include payment of reasonable attorney’s fees incurred by successful claimants in civil actions.

9.2 Basis of Payment:

All costs connected with obtaining performance and labor and materials bonds for the work will be paid for at the Contract Lump Sum Price for Performance and Labor and Materials Bonds (Line Item 002-A). The CONTRACTOR may apply for one hundred percent (100%) payment of this item following written approval by the OWNER of the Schedule of Prices.

10. CLEARING AND GRUBBING

10.1 Description:

Per Section 201 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

10.2 Special Provisions:

Clearing and grubbing shall include the removal of pavement and base layers as needed to complete the Project.

Equipment employed for the clearing and grubbing work shall be in satisfactory operating condition, capable of safely and efficiently performing the work as indicated.

Equipment and machinery shall be kept in good condition at all times.

The CONTRACTOR may encounter obstructions or other debris that are not identified and may pose a hazard during construction, or that which may cause a major delay to the construction schedule. The CONTRACTOR shall advise the OWNER immediately of any obstructions or other debris of this nature that are encountered within any areas to be cleared and grubbed.

10.3 Additional Submittals:

In addition to the requirements stated in the Section 201.03(d), prior to commencing any work at the Project Construction Site the CONTRACTOR shall submit the following:

10.3.1 Pre-construction Submittals:

The CONTRACTOR shall submit a clearing and grubbing plan to the OWNER, which shall include the following:

a. Clearly identifies any no-work areas or structures as delineated by the

OWNER;

b. Clearly identifies anticipated areas where clearing and grubbing will be required to complete the work;

c. Lists equipment to be used during clearing and grubbing; and

d. Details a plan for disposal of all cleared and grubbed material.

10.3.2 Post-Construction Submittals:

Within fourteen (14) days after completion of work, the CONTRACTOR shall provide post-construction submittal to the OWNER documenting that all the areas have been cleared and grubbed in accordance to the Plans and Specifications and that all cleared and grubbed material has been appropriately disposed of at the approved disposal facilities.

10.4 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per acre of clearing and grubbing upon submittal of the required documentation (Section 10.3) and acceptance by the OWNER. Price and payment for this item shall constitute full compensation for all materials, labor, supplies and equipment required for clearing and grubbing. This work is considered complete when the areas have been cleared and grubbed to an acceptable level as determined by the OWNER and documentation of disposal of all cleared and grubbed material has been provided by the CONTRACTOR to the OWNER. All costs connected with clearing and grubbing will be paid for at the Contract Unit Price for Clearing and Grubbing (Line Item 201-A).

11. CLEANING EXISTING DRAINAGE STRUCTURES

11.1 Description:

Per Section 534 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

11.2 Special Provisions:

None.

11.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per linear foot of cleaning existing culvert upon acceptance by the OWNER. This work is considered complete when the existing structures have been cleaned to an acceptable level as determined by the OWNER. All costs connected with cleaning existing drainage structures will be paid for at the Contract Unit Price for Cleaning Existing Culverts (less than or equal to 48” horizontal opening) (Line Item 534-E).

12. PARTIAL REMOVAL OF EXISTING DRAINAGE STRUCTURES

12.1 Description:

Per Section 206 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

12.2 Special Provisions:

None.

12.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per linear foot of removing pipe upon acceptance by the OWNER. This work is considered complete when the existing structures have been cut flush with the new headwall to an acceptable level as determined by the OWNER. All costs connected with the partial removal of existing drainage structures will be paid for at the Contract Unit Price for Removing Pipe (Line Item 206-D).

13. EMBANKMENT

13.1 Description:

Per Section 210 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

13.2 Special Provisions:

None.

13.3 Basis of Payment:

Embankment will not be measured for payment. A quantity of three hundred and fifty cubic yards (350 CY) has been estimated for this project. All of the operations required for embankment formation described herein shall be considered necessary work incidental to and for which compensation is included in the contract unit prices for the pay items of the materials composing the embankment.

14. STRUCTURE EXCAVATION AND BACKFILL FOR DRAINAGE AND MINOR

STRUCTURES

14.1 Description:

Per Section 214 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

14.2 Special Provisions:

Foundation Back Fill, Commercial (Line Item 214-B) shall be deposited uniformly for the full width of the excavation twelve inches (12”) thick. Backfill shall be deposited in horizontal layers not to exceed six inches (6”) in thickness with each layer being compacted to 98% Modified Proctor.

14.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per cubic yard of structure excavation or foundation backfill upon acceptance by the OWNER. This work is considered complete when the material is reasonably close to conformity with the lines and grades shown on the plans as determined by the OWNER.

All costs connected with the structure excavation will be paid for at the Contract Unit Price for Structure Excavation (Line Item 214-A).

All costs connected with the foundation backfill will be paid for at the Contract Unit Price for Foundation Back Fill, Commercial (Line Item 214-B).

15. REINFORCED CONCRETE BOX CULVERTS

15.1 Description:

Per Section 524 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

15.2 Special Provisions:

Required steel reinforcement shall be considered a subsidiary of reinforced concrete box culverts. The geotextile shall meet Section 502 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition” for Steel Reinforcement.

Required geotextile shall be considered a subsidiary of reinforced concrete box culverts.

The geotextile shall meet Section 243 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition” for Geosynthetic Reinforcement for Soft Soil Stabilization, Type 2. A quantity of one thousand square yards (1,000 SY) has been estimated for this project.

15.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per linear foot of culvert concrete (precast) upon acceptance by the OWNER. This work is considered complete when the box culverts have been installed in accordance with the plans as determined by the OWNER. All costs connected with the reinforced concrete box culverts will be paid for at the Contract Unit Price for Culvert Concrete (Precast) (Line Item 524-A).

16. MINOR STRUCTURE CONCRETE

16.1 Description:

Per Section 620 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

16.2 Special Provisions:

The required straight headwalls, concrete barrier rail and concrete pads are included in the Minor Structure Concrete line item.

16.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per cubic yard upon acceptance by the OWNER. This work is considered complete when the culvert end treatments and other minor structure concrete have been constructed in accordance with the plans as determined by the OWNER. All costs connected with the minor structure concrete will be paid for at the Contract Unit Price for Minor Structure Concrete (Line Item 620-A).

17. STABILIZED ROADBED

17.1 Description:

Per Section 231 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

17.2 Special Provisions:

None.

17.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per cubic yard of roadbed stabilization upon acceptance by the OWNER. This work is considered complete when a satisfactory roadbed for receiving a base or pavement structure layer as determined by the OWNER is provided. All costs connected with the stabilized roadbed will be paid for at the Contract Unit Price for Roadbed Stabilizing Material, LBR 40 (Line Item 231-A).

18. AGGREGATE BASE

18.1 Description:

Per Section 301 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

18.2 Special Provisions:

None.

18.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per square yard of aggregate base upon acceptance by the OWNER. This work is considered complete when the base aggregate complete in place on the roadbed in accordance with the plans as determined by the OWNER. All costs connected with the aggregate base will be paid for at the Contract Unit Price for Aggregate Base Course, Type A Plant Mixed, 8 inches (Line Item 301-A).

19. BITUMINOUS SURFACE TREATMENT

19.1 Description:

Per Section 401 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018Edition”.

19.2 Special Provisions:

None.

19.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per square yard of bituminous treatments upon acceptance by the OWNER. This work is considered complete when the bituminous surface treatment is complete in place on the roadbed in accordance with the plans as determined by the OWNER. All costs connected with the bituminous surface treatment will be paid for at the Contract Unit Price for Bituminous Treatment, Type A (Prime Coat) (Line Item 401-A).

20. TACK COAT

20.1 Description:

Per Section 405 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

20.2 Special Provisions:

None.

20.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per gallon of tack coat upon acceptance by the OWNER. This work is considered complete when the tack coat is placed on the surface to be covered by the bituminous plat mix material in accordance with the plans as determined by the OWNER. All costs connected with the tack coat will be paid for at the Contract Unit Price for Tack Coat (Line Item 405-A).

21. ASPHALT SURFACE

21.1 Description:

Per Section 410 and Section 424 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

21.2 Special Provisions:

None.

21.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per square yard of asphalt upon acceptance by the OWNER. This work is considered complete when the asphalt is placed on the surface in accordance with the plans as determined by the OWNER. All costs connected with the asphalt surface will be paid for at the Contract Unit Price for Superpave Bituminous Concrete Wearing Surface, 3/8" Maximum Aggregate Size Mix, ESAL Range C/D (3 inches) (Line Item 424-A).

22. TRAFFIC STRIPE

22.1 Description:

Per Section 701 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

22.2 Special Provisions:

None.

22.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price per mile upon acceptance by the OWNER. This work is considered complete when the traffic stripe is placed on the asphalt surface in accordance with the plans as determined by the OWNER.

All costs connected with the traffic stripe will be paid for at the Contract Unit Price for Broken Yellow, Class 2, Type A Traffic Stripe (Line Item 701-A).

23. GUARDRAIL AND BARRIER RAIL

23.1 Description:

Per Section 630 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, Current Edition”.

23.2 Special Provisions:

None.

23.3 Basis of Payment:

The CONTRACTOR may request payment for the Contract Unit Price upon acceptance by the OWNER. This work is considered complete when the guardrail is in place in accordance with the plans as determined by the OWNER.

Costs connected with the guardrail will be paid for at the Contract Unit Price per linear foot for Aluminum Beam Guardrail, Class A (Line Item 630-B).

Costs connected with the end anchor assemblies will be paid for at the Contract Unit Price per each for Guardrail End Anchor, Type 13 Series (Line Item 630-C (003)).

Costs connected with the end anchor assemblies will be paid for at the Contract Unit Price per each for Guardrail End Anchor, Type 20 Series (Line Item 630-C (080)).

24. TEMPORARY SOIL EROSION AND SEDIMENT CONTROL

24.1 Description:

Per Section 665 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

24.2 Special Provisions:

None.

24.3 Submittals:

Prior to commencing any work at the Project Construction Site the CONTRACTOR shall submit a Stormwater Management Plan (SWMP) as described in Section 108.04(b)3 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, Current Edition”.

24.4 Basis of Payment:

Once the CONTRACTOR has mobilized, the CONTRACTOR shall be paid thirty percent (30%) of the Contract Lump Sum Price for temporary soil erosion and sediment control. Once the CONTRACTOR has completed the work activities, the CONTRACTOR shall be paid fifty percent (50%) of the Contract Lump Sum Price for temporary soil erosion and sediment control. Once the CONTRACTOR has removed all temporary controls and completed site stabilization as approved by the OWNER, the

CONTRACTOR shall be paid twenty percent (20%) of the Contract Lump Sum Price for temporary soil erosion and sediment control. Costs connected with temporary soil erosion and sediment control will be paid for at the Contract Lump Sum Price for Temporary Soil Erosion and Sediment Control (Line Item 665).

25. TRAFFIC CONTROL DEVICES FOR CONSTRUCTION ZONES

25.1 Description:

Per Section 740 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

25.2 Special Provisions:

None.

25.3 Basis of Payment:

All costs connected with handling traffic safely for the construction work zone for the work will be paid for at the Contract Lump Sum Price for Traffic Control Devices for Construction Zones (Line Item 740). Once the CONTRACTOR has mobilized, the CONTRACTOR shall be paid fifty percent (50%) of the Contract Lump Sum Price. Once the CONTRACTOR has completed the work activities, the CONTRACTOR shall be paid thirty percent (30%) of the Contract Lump Sum Price. Once the CONTRACTOR has removed all temporary traffic control devices as approved by the OWNER, the CONTRACTOR shall be paid twenty percent (20%) of the Contract Lump Sum Price.

This work is considered complete upon approval by the OWNER and removal of temporary traffic control devices.

26. MINOR UTILITY ADJUSTMENTS

26.1 Description:

Per Section 640 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

26.2 Special Provisions:

None.

26.3 Submittals:

In the event a utility shall be relocated to complete the work and prior to commencing utility adjustment work at the Project Construction Site, the CONTRACTOR shall submit the following:

26.3.1 Pre-construction Submittals:

The CONTRACTOR shall submit a utility adjustment plan to the OWNER, which shall include the following:

Clearly identifies the utility in conflict and identified the utility owner;

Clearly identifies anticipated areas where utility adjustment will be required to complete the work;

Clearly identifies the construction details of the proposed utility adjustment (proposed location, depth, etc.);

Lists equipment to be used during utility adjustment; and

Details a plan for coordination with utility owner including approval of plan and acceptance of the utility adjustment.

26.3.2 Post-Construction Submittals:

Within fourteen (14) days after completion of work, the CONTRACTOR shall provide post-construction submittal to the OWNER documenting that the utility has been relocated accordance to the Utility Adjustment Plan and acceptance by the utility owner.

26.4 Basis of Payment:

Payment for the utility adjustment will be made at the contract unit price per linear foot per type utility which shall be payment in full for adjustments as described in Section

640.05 of the “Alabama Department of Transportation Standard Specifications for Highway Construction, 2018 Edition”.

All costs connected with the minor utility adjustments will be paid for at the Contract Unit Price for Underground Utility Adjustment (Communication) (Line Item 640-A).

27. RECORD DOCUMENTS

27.1 Description:

27.1.1 Purpose:

The CONTRACTOR shall not use record documents for construction purposes;

these documents shall be protected from deterioration and loss in a secure, fire-resistive location.

This is the start of the file's text. The full file is on GovTribe.