3) 70Z08826B0030252-Station Vallejo SPECS_12Jun26.pdf

PDF 697 KB Posted

Attached to
DREDGING AND SEDIMENT DISPOSAL AT SAN FRANCISCO BAY AREA; THREE (3) LOCATIONS - FY 2026
Solicitation number
70Z08826B0030252
Issued by

About this file

This is a Specifications document for maintenance dredging services at Coast Guard Station Vallejo in Solano County, California (PSN 28979950).

The project requires removal and disposal of approximately 10,386 cubic yards of sediment from a 1.66-acre dredge footprint to a design depth of -10 feet MLLW with 2 feet of overdepth allowance, using mechanical clamshell dredging equipment. Dredged material must be permanently disposed of via bottom dump barge, with distribution constraints: in-Bay disposal limited to 20% of total volume (Carquinez Straight Disposal Site SF-9), approved upland beneficial reuse sites receiving minimum 62% (Cullinan Ranch or Montezuma Wetlands), and remaining material at approved ocean or upland sites. All in-water work must occur within the in-water work window of August 1 to November 30 per ESA requirements. The contractor must submit a detailed Dredge Operations Plan (DOP) within 30 days of award for Corps approval, with dredging scheduled to commence 60 days after DOP submission. Key submittals include pre-dredge and post-dredge hydrographic surveys performed by certified hydrographers, solid debris management plan, and post-dredge project report within 30 days of completion. An Option Bid Item includes temporary removal and reinstallation of four Jet Docks (15' x 30' each) and one concrete floating dock (9' x 70'). Payment is unit-priced per cubic yard based on the difference between pre- and post-dredge surveys, with no compensation for dredging beyond authorized depths or outside authorized areas. The contract requires compliance with multiple environmental permits including USACE (SPN-2008-00049), BCDC (C2007.005.07), Section 401 Water Quality Certification (WDID 2 CW455657), and conditions of the 2015 Biological Opinion for Long-Term Management Strategy.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

CIVIL ENGINEERING UNIT OAKLAND

OAKLAND, CALIFORNIA 94612-5203

PSN 28979950

SPECIFICATIONS

FOR

MAINTENANCE DREDGE

AT

COAST GUARD STATION VALLEJO

SALANO COUNTY, CALIFORNIA

Civil Engineering Unit Oakland Signature Date Gabriel Posluszny

PROJECT MANAGER

Joel Tomco

SUPERVISOR, RE DESIGN TEAM B

Steven F. Osgood

TECHNICAL DIRECTOR

TABLE OF CONTENTS

SECTION TITLE PAGE

DIVISION 01 - GENERAL REQUIREMENTS 3

01 10 00 - GENERAL PARAGRAPHS 3

01 33 00 – SUBMITTALS PROCEDURES 12

01 35 29 – HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES 16

01 35 43 – ENVIRONMENTAL PROCEDURES 19

DIVISION 2 – EXISTING CONDITIONS 23

02 41 00 – FLOATING DOCK REMOVAL AND REINSTALLATION 23

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION 27

35 20 23 - DREDGING 27

28979950 01 10 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 - GENERAL PARAGRAPHS

PART 1 GENERAL

1.01 BASE WORK - SCOPE OF WORK: Provide all labor, materials, and equipment necessary to dredge and dispose of approximately 10,386 cubic yards (cy) of sediment from the authorized dredge footprint at U.S. Coast Guard (USCG) Station Vallejo, located within Vallejo, California. Dredged material shall be removed using a mechanical clamshell dredge and transported by barge to be permanently disposed of at an appropriate placement site. Suitable dredged material may be placed at an in- Bay site such as Alcatraz Island Dredged Material Disposal Site (SF-9), at a permitted beneficial reuse site, or at an appropriate authorized upland location.

The contractor is expected to mobilize for pre-dredge hydrographic survey as soon as possible and produce a Dredge Operations Plan (DOP) within 30 days of award (to include the surveys). The contractor shall begin dredging as soon as a notice to proceed is received following approval of the DOP, while implementing requirements and best practices identified in the attached permits to minimize impacts to federally listed species and protected habitat.

A. All in-water work must be completed during the in-water work window (IWWW) of August 1 to November 30 to minimize impacts on Environmental Safety Act (ESA) protected fish species per BCDC Permit No. C2007.005.07, (BCDC Permit) Special Condition II-I.

B. Dredged sediment shall be permanently disposed of using a bottom dump barge. As part of the Long Term Management Strategy (LTMS) for placement of dredged material in the San Francisco Bay Region, the volume disposed of for the work described herein shall be limited by site per the Clean Water Act Section 401 Water Quality Certification and Order WDID # 2 CW455657 (Section 401). In-Bay disposal shall not exceed 20% of total dredged material.

Approved upland beneficial reuse sites shall receive no less than 62% of the total dredged material so long as the material dredged is suitable for upland placement.

The remaining dredged material shall be disposed of at approved ocean or upland sites.

28979950 01 10 00 Page 4

1) Approved In-Bay Disposal Sites: Limited to 20% of the total volume dredged.

(a) Unconfined disposal at Carquinez Straight Disposal Site (SF-9).

(b) When utilizing the SF-9, the permittee shall dispose all dredged material within a rectangular area, 1000 feet by 2000 feet, long axis bearing 050 true, and center at latitude 38°03'50"N; longitude 122°15'55"W. The specific location within the disposal area will be determined by the District Engineer upon approval of the Dredge Operation Plan

(DOP).

2) Approved Beneficial Reuse Sites: Minimum of 62% of the total volume dredged.

(a) Placement of material at any permitted beneficial reuse site, such as Cullinan Ranch Restoration Project (Cullinan) or Montezuma Wetlands Restoration Project (Montezuma), shall be overseen by the operator in compliance with site permit.

3) Deep Ocean Disposal (SF-DODS)or Approved Upland Disposal: Remaining volume dredged.

C. Dredge approximately 10,386 cy of sediment from the approximately 1.66-acre dredge footprint to a design depths of -10 feet MLLW with two (2) feet of overdepth allowance throughout. No dredging in other areas is authorized.

1.02 OPTION BID ITEMS: Provide all labor, material equipment, tools, transportation, supervision, field verification, and test services necessary to do the same work as described in paragraph 1.01 of 01 10 00 and contract drawings for the following option bid items. The work shall also conform to the applicable requirements of the project specifications (including Division 1).

A. Option Bid Item #1: Temporary removal and re-installation of floating docks in accordance with Division 2.

1) Remove the four Jet Docks, measuring approximately 15 ft by 30 ft each and the concrete floating dock, tugging them away temporarily and reinstalling them in the same configuration once dredge work is complete.

28979950 01 10 00 Page 5

1.03 BASIS FOR BIDS: Mobilize and demobilize personnel and

equipment including the dredge, barge, scow, trucks, and other equipment necessary to complete the work. Conduct pre-dredge surveys to prepare a Dredge Operations Plan (DOP). Once notified, remove no more than the authorized volume of sediment and permanently dispose of sediment in accordance with all specification and permit conditions.

Once operations are complete, conduct post- dredge surveys to complete the final report. Include all direct costs not associated with the dredging operation.

A. Dredge Operations Plan (DOP): Utilize the data collected from the pre-dredge surveys to finalize and submit a detailed dredge and disposal operations plan for the entire sediment disposal event. For more information on the DOP, see Section 3 20 23 Part 1.02A. The DOP shall include at a minimum:

1) A list of equipment, personnel, environmental controls, means of transport, and means and locations of intermediate storage or handling of dredge sediment.

2) The volumes to be disposed of in total and at each intended disposal location. Include proof of acceptance for beneficial reuse of sediment at the authorized facilities. The Contractor is solely responsible for coordinating the scheduling, offloading logistics, and tipping fees associated with the authorized beneficial reuse sediment placement facilities (Montezuma and Cullinan) with the facility owners.

3) Contractor shall coordinate the usage of the dredge footprint and adjacent navigable waters with the USCG Station Vallejo Command and all appropriate CG personnel. Operational plan must demonstrate how the Contractor will prevent navigational obstructions and maintain 34/7 emergency access for USCG Search and Rescue vessels.

4) Details of the mobilization effort including preparation of the dredging plant and all site controls. Note that mobilization shall not proceed after the DOP has been approved and dredge operations have been authorized.

5) Demobilization including the dredging plant, site

28979950 01 10 00 Page 6 controls, and any other sign of the work described herein.

6) Dredging shall be scheduled to start 60 days after the USCG receives, reviews, and resubmits the DOP.

B. Dredging Event: Dredge and dispose of approximately 10,386 cy of sediment from the approved dredge footprint.

Dredging material shall be removed using a mechanical clamshell dredge to the permitted design depths.

Transport the dredged sediment by barge to the approved disposal site(s). For more information see Section 35 20 23.

1) The removal, transport and disposal of dredged sediment shall be paid for at the established unit prices per cubic yard (cy) and based on the difference in volume between the pre- and post- dredge hydrographic surveys of the dredge prism. Payment for dredging, including disposal fees, shall not be made for dredging deeper than the allowable over-depth, dredging outside the authorized areas, or dredging and/or disposing of sediment in an unauthorized manner.

C. Pre-Dredge and Post-Dredge Hydrographic Surveys and Computations: Submit results of hydrographic surveys taken by a certified third-party surveyor before and after dredging per Section 401. The hydrographic surveys and related drawings must include the dredged prism. For more information see Section 35 20 23 Part 1.06 through 1.09.

1) The pre-dredge and post-dredge survey comparison will be utilized as a formal drawing for the record and payment and will be included in the post-dredge report to be submitted to the regulatory agencies.

D. Post-Dredge Project Report: This report will be submitted to the regulatory agencies to satisfy permit requirements. For more information see Section 35 20 23 Part 1.02E.

1) Contractor shall submit the post-dredge report within 30 days after the completion of the dredging activities authorized.

1.04 LOCATION: The project site is located at USCG Station

28979950 01 10 00 Page 7

Vallejo at 2 Habor Way, Vallejo, California.

1.05 SITE INVESTIGATION: Investigate the site per FAR 52.236-3 to ascertain the general and local conditions, which can affect the work or its cost. Since the site is secured, prior arrangements for site visits should be made by contacting the Contracting Officer.

1.06 KICK OFF MEETING: Within 10 days after award, the

Contractor shall be available for a project kick-off meeting.

1.07 NOTIFICATION OF START AND COMPLETION OF WORK: The

Contractor shall notify the Contracting Officer in writing five (5) business days in advance of intended date of commencement of work, and five (5) business days prior to the date that work will be ready for final inspection.

1.08 CONTRACTOR'S DAILY REPORT: Complete Form 17-148

"Contractor's Daily Report to Construction Manager" every day there is any type of contractor or subcontractor activity (including equipment or material delivery) at the construction site. The contractor shall include daily calculations of estimated quantity of material dredged and disposed. The daily reports shall be compiled during the week and e-mailed to the USCG Project Manager at the close of business each Friday.

1.09 FINAL INSPECTION AND ACCEPTANCE: When work is complete

and ready for final inspection, submit a written request for final inspection to the Contracting Officer at least 10 working days in advance of the date of final inspection. Final inspection will not be scheduled until all submittals have been approved. Note inspection and acceptance will be required separately for both dredging and disposal.

1.10 CONTRACTOR SECURITY REQUIREMENTS: The Contractor shall

provide a list of all on-site personnel, including sub-contractors (including second and third-tier subcontractors) and suppliers, to the Contracting Officer. The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the USCG facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the USCG facility. Contractor personnel shall have photo

28979950 01 10 00 Page 8 identification at all times while working on Coast Guard facilities.

Contractor and delivery personnel may be required to present personal photo identification to gain access to a USCG installation. If identification does not indicate United States citizenship, USCG Security may require proof of the legal right to work in the United States.

Contractor and delivery personnel also may be subjected to an immigration status and outstanding criminal warrants check.

The Real ID Act of 2005 established minimum security standards for license issuance and production and prohibits Federal agencies from accepting, for certain purposes, driver's licenses and identification cards from states not meeting the Act's minimum standards. Anyone requiring access to a military facility under this contract, to include subcontractors, who holds a driver's license from any state without approved licenses will be required to provide identification other than that driver's license to gain access. Government IDs annotated with “Federal Limits Apply” will not be accepted for access purposes. It is the responsibility of the Contractor to ensure that their personnel have federally acceptable personal photo identification and comply with any other requirements for base access.

Contractors shall provide the Contracting Officer's Representative with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, parts, etc.) and provide the company name, delivery person, and phone number of the firm(s) making deliveries. All vehicle access to government property requires vehicle registration and proof of liability insurance, otherwise access to the USCG facility may be denied.

At least 7 days prior to commencing work the Contractor shall verify and ensure the USCG Security Office knows of the date and time the work will commence.

1.11 CONTINUITY OF FACILITIES OPERATION: The Contractor will

be working on a military installation. Become familiar with and obey fire, traffic, and security regulations.

Personnel shall not stray from the immediate area of work nor direct avenues of ingress and egress unless authorized in advance by the Contracting Officer.

28979950 01 10 00 Page 9

A. Scheduling: Provide clear timelines for project work to minimize interference with the facility’s normal operations. Notify the Contracting Officer and site contact 2 weeks in advance of any mobilization effort or potential obstruction. Confirm arrival at the site within 48 hours with site POC and COR. Perform all on-site work, including deliveries, between the hours of 7:00 AM and 5:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Contracting Officer and the Unit Commanding Officer.

B. Coordination: USCG Station Golden Gate is home to five search and rescue boats that support its mission.

Maintain constant communication with the Officer in Charge (OIC) and the COR to establish and maintain clear safety zones around equipment and vessels. Contractor equipment and personnel shall not impede access for USCG vessels nor hinder vessel access to and from their moorings and the navigational channel.

C. Emergency Response: The Contractor shall be capable of moving all equipment within approximately 15 minutes including dredge, barge, and support vessels to accommodate emergent USCG operations.

D. Upon completion of the work, the Contractor shall promptly remove all equipment, temporary navigational aids, survey markers, and materials from the site.

1.12 HAZARDOUS MATERIAL IDENTIFICATION: Submit Safety Data

Sheets (SDS) for any materials defined as hazardous under the most current revision of Federal Standard 313. One copy of each MSDS shall be submitted to the Contracting Officer’s Representative no later than the delivery date of the product. Two copies shall be submitted to the Contracting Officer.

1.13 SAFETY: During the execution of this contract, the

Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. When the standards differ, the more restrictive standard shall apply. The contractor shall provide barriers, temporary fencing, trench covers, etc.

wherever work could cause injury to workers, visitors, USCG personnel, or dependents. An Accident Prevention Plan shall be submitted in accordance with Section 01 35 29, paragraph 1.05.

28979950 01 10 00 Page 10

1.14 CLEANUP: The Contractor shall keep the work area, including storage area, free from accumulations of waste materials daily and comply with all federal, state, and local regulations pertaining to storage, transport and disposal of wastes.

A. All incidental daily refuse generated by the Contractor’s crew and vessels shall be contained onboard and disposed of legally at an off-site facility. The Contractor shall not use the USCG waste disposal facilities including garbage cans, trash piles, or dumpsters.

B. Any artificial debris (e.g., submerged timber, wires, tires) incidentally recovered by the clamshell bucket during dredging operations shall be segregated from the dredged sediment. This debris becomes the property of the Contractor and must be disposed of at a licensed, upland disposal facility. For more information see Section 35 20 23 Part 1.03.

1.15 TEMPORARY FACILITIES:

A. Storage: If needed, the Contractor may be provided a storage area in a location determined by the Contracting Officer. The Contractor shall be responsible for restoring the area to its original condition at the completion of work. The Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risks of loss. The USCG assumes no responsibility for material or equipment left in the storage area.

B. Sanitary Facilities: There may not be toilet facilities available for Contractor use at the job site. The Contractor shall provide their own facilities, including hand washing facilities, in accordance with 29 CFR 1926, Subpart D, paragraph 1926.51 (c)(1) and (f)(1).

C. Availability of Utility Services: No commercial utilities are available.

1.16 EXISTING UTILITIES: The existence of any other utility

locations and cable crossings is unknown. The authorized dredge footprint and disposal site are not anticipated to contain underground utilities. The Contractor shall verify all utility and cable crossing locations prior to dredging.

28979950 01 10 00 Page 11

1.17 ATTACHMENTS: Documents and drawings to be used in

conjunction with these specifications are listed below.

The files are the property of the Government and shall not be used for any purpose other than that considered by the specification. The work shall conform to the documents and drawings listed below which form a part of these specifications.

Number Title

No.1 NMFS Biological Opinion No.2 BCDC Permit, C2007.005.007 No.3 Section 401 WQC, 2 CW455657 No.4 Integrated Alternatives Analysis No.5 USACE Permit, SPN-2008-00049 No.6 Sampling Analysis Report

1.18 ENVIRONMENTAL REGULATORY PERMITS: The contractor shall

comply with all permits received by the USCG to perform the work as detailed in this specification and in accordance with the attached project documents. More details about permit requirements can be found in Section 01 35 43.

1.19 SEDIMENT ANALYSIS: The material to be removed is material carried along the shoreline by natural currents, wind, and waves. Sampling was completed for this site in December 2023 and analyzed according to the procedures specified by the Dredged Material Management Office (DMMO). Sediment analysis results indicated that the proposed dredged materials are suitable for placement at SF-09, Cullinan Ranch, or the Montezuma Wetlands. DMMO concurred that Cullinan Ranch is a suitable placement site.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

28979950 01 33 00 Page 12

01 33 00 – SUBMITTALS PROCEDURES

PART 1 GENERAL

1.01 GENERAL

A. Forward all submittals, except as stated elsewhere, to the Contracting Officer by email within 10 business days from date of award, unless indicated otherwise in this specification. Submittals shall be accompanied with the USCG furnished material submittal form in PDF Format.

Unless noted otherwise, all submittals shall be provided in legible, high quality electronic image format. Provide these submittal images to the Contracting Officer, the Construction Manager, and the Contracting Officer's Representative (COR) simultaneously. The Contracting Officer will e-mail approval or disapproval of submittals, within 10 calendar days after receipt.

B. The COR, Construction Manager, and Project Manager will review all submittals for compliance with these specifications. The Contracting Officer shall approve submittals before acceptance.

C. Approval of submittals, and corrections or comments made during the review, do not relieve the Contractor from compliance with the requirements of the plans and specifications or permit coordination.

D. The schedule of submittals listed in the submittal register (Table 1) and in the individual sections are the submittals required for this contract. Unsolicited submittals may be returned to the Contractor without review.

1.02 CERTIFICATES OF COMPLIANCE: Certificates of compliance

shall be signed by an authorized officer of the manufacturing company furnishing the material which states that the material being furnished meets all requirements of these specifications and referenced specifications.

1.03 DESIGN DRAWINGS: Design drawings shall be provided in

AutoCAD drawing file and PDF formats. When saving the AutoCAD drawing file the drawing shall be saved in AutoCAD 2020 drawing (*.dwg) format if an AutoCAD program is newer than AutoCAD 2020 is used by the contractor.

Design drawings shall be prepared, completed, and

28979950 01 33 00 Page 13 accurate. All plan views, elevations, sections, details, profiles, schedules, etc. shall be as complete as necessary to carry out the purpose of the drawing.

Drawings (including Drawing Files provided by the USCG for use in design development) shall comply with the most current USCG CAD standards (i.e. Job Guide for Drawing Format and Handling, SILC-JG-36-51 73 15-02) and templates before the Drawing Files will be accepted by the USCG. Drawings shall be submitted by email.

A. Files to be provided upon the request:

1) Job Guide for Drawing Format and Handling, SILC-JG-36- 51 73 15-02;

2) USCG CEU Oakland Title Block Templates (e.g. G-001 & G-002).

B. General Compliance of Drawing Format and Handling: See Sections 1.8.1 to 1.8.3 of the Job Guide for more requirements.

1) All drawing sets shall have a cover sheet and sheet index.

2) All unattached External references (XREFs) shall be deleted. All used XREFs shall be bound to each Drawing Sheet File using the “Insert” option, so that no external files will be required to view the drawings.

3) Each Drawing Sheet File shall contain no more than one layout tab. The layout tab shall be named to match the Sheet Identification (ID) (e.g. “G-001”).

4) Confirm only USCG CAD Standard Dimension and Text Styles are being used.

5) Confirm only USCG CAD Standard Multileader and Table Style are being used.

6) Purge the drawings of un-used block definitions, layers, line types, etc. to keep file size to a minimum and simplify product for future users.

C. Final Plan Review: Upon review by the Coast Guard of the final plans, CAD files shall be provided in conjunction with PDF’s. All XREFS shall be bound to each sheet file.

Cover sheet drawing (e.g. G-001) shall be stamped by

28979950 01 33 00 Page 14 either a Professional Engineer or Registered Surveyor of the respective discipline indicated by the drawing and who is registered in the state where the work will be constructed.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

28979950 01 33 00 Page 15

TABLE 1

CEU OAKLAND SUBMITTAL REGISTER

PSN:

28979950

CONTRACT NO.:

TBD

PROJECT TITLE AND LOCATION :

Maintenance Dredging at Station Vallejo Vallejo , California

Submittal Reference Location ACTION DATE

NO.

SPEC.

SECTION

SECTION PAGE DESCRIPTION OF SUBMITTAL DATE REQUIRED DISAPPROVED APPROVED

01 01 10 00 1.06 7 Kick Off Meeting 10 days after award 02 01 10 00 1.08 7 Contractor’s Daily Report Daily 03 01 10 00 1.10 7 Contractor Security Requirements 10 days after award 04 02 41 00 1.03 23 Temporary Removal Plan NLT 30 days after award 05 35 20 23 1.02(A) 27 Dredge Operations Plan NLT 30 days after award 06 35 20 23 1.02(B) 29 Solid Debris Management Plan NLT 30 days after award 07 35 20 23 1.02(C) 29 Hydrographic Survey: Pre-dredge NLT 30 days after award 08 35 20 23 1.02(C) 29 Hydrographic Survey: Post-dredge NLT 5 days post dredge 09 35 20 23 1.02(D) 30 Dredge Quantity Calculations NLT 30 days post-dredge 10 35 20 23 1.02(E) 30 Post Dredge Project Report NLT 30 days post-dredge

28979950 01 35 29 Page 16

01 35 29 – HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES: This section applies to steps taken by the contractor to comply with the health and safety requirements listed herein. The Contractor shall comply with all applicable federal, state, and local laws and regulations. The ultimate responsibility for identifying applicable requirements and protecting contractor employees or sub-contractors rests with the primary contractor.

1.02 APPLICABLE PUBLICATIONS: The publications listed below

form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

A. American National Standards Institute (ANSI):

Z359 Series Fall Protection Code, Version 2 (Z359.0-2007, Z359.1-2007, Z359.2- 2007, Z359.3-2007, Z359.4-2007, Z359.6-2009, Z359.12-2009, Z359.13-2009, Z359.14-2012, and historical Z359.1-1992 (R1999)

B. Environmental Protection Agency (EPA) Regulations:

40 CFR 204 Noise Abatement Program for Construction Equipment

40 CFR 302.4 Designation of Hazardous Substances

C. U.S. Army Corps of Engineers (USACE):

EM 385-1-1 Safety and Health Requirements Manual

D. U.S. Department of Labor Occupation Safety and Health Administration (OSHA) Regulations:

29 CFR 1910.1200 Hazard Communication

29 CFR 1926.106 Working Over or Near Water

29 CFR 1926.453 Aerial Lifts (Construction Specific)

28979950 01 35 29 Page 17

29 CFR 1926 Subpart M Fall Protection

29 CFR 1926 Subpart P Excavations

1.03 REFERENCE STATUTES: The statutes listed below form a part of this specification to the extent referenced.

Noise Control Act (NCA) (42 U.S.C. §§ 4901 to 4918)

1.04 DEFINITIONS

A. Sediment: Soil and other debris that has been eroded and transported by runoff water.

B. Solid Waste: Rubbish, debris, and other discarded solid materials resulting from industrial, commercial, and agricultural operations, and from community activities.

Solid waste may also include non-sewage liquids.

C. Rubbish: A variety of combustible and noncombustible wastes such as paper, boxes, glass, crockery, metal, lumber, cans, and bones.

D. Debris: Includes combustible and noncombustible wastes, such as ashes, waste materials that result from construction or maintenance and repair work, leaves, and tree trimmings.

E. Chemical Wastes: Includes salts, acids, alkalines, herbicides, pesticides, and organic chemicals.

F. Sewage: Wastes characterized as domestic sanitary sewage.

G. Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

H. Oily Waste: Includes petroleum products and bituminous materials.

I. Hazardous Material (HM): Chemicals defined by OSHA 29 CFR

1910.1200 and under the U.S. Department of Transportation (DOT) regulations (Title 49 CFR Parts 100 through 199) which are determined by the Secretary of Transportation to present risks to safety, health, and property during transportation. The DOT regulations include requirements for shipping papers, package marking, labeling, transport vehicle placarding, and training of personnel handling hazardous materials.

28979950 01 35 29 Page 18

1.05 Accident Prevention: Submit a copy of your “Accident

prevention” or “Injury and Illness Prevention” in the dredge operations plan.

1.06 Mobile Equipment Operator List: A list of qualified

operators for all mobile equipment that will be brought onto the job site with employee name(s), qualifications, and specific equipment to be operated shall be provided to the Contracting Officer prior to equipment operation.

(This includes forklifts, cranes, motorized lifting device, etc.). This is also to be included in the dredge operations plan.

1.07 NOISE: Make the maximum use of "low-noise-emission

products" as certified by EPA and described at 40 CFR Part 204. No blasting or use of explosives is permitted.

Comply with applicable portions of the Noise Control Act (NCA). The Contractor is responsible for complying with all other federal, state, and local noise control laws and regulations.

1.08 WORKING OVER OR NEAR WATER: When working over or near

water, comply with 29 CFR 1926.106.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

28979950 01 35 43 Page 19

01 35 43 – ENVIRONMENTAL PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES: This section applies to all necessary

steps taken by the Contractor to comply with the environmental protection requirements listed herein.

1.02 APPLICABLE PUBLICATIONS: The publications listed below

form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

A. Environmental Protection Agency (EPA) Regulations:

40 CFR 122 National Pollution Discharge Elimination System

40 CFR 261 Identification and Listing of Hazardous Waste

1.03 REFERENCE STATUTES: The statutes listed below form a part of this specification to the extent referenced.

Clean Air Act (CAA) (42 U.S.C. §§ 7401 to 7642)

Clean Water Act (CWA) (33 U.S.C. §§ 1251 to 1387)

Coastal Zone Management Act (CZMA) (16 U.S.C §§ 1456)

Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (42 U.S.C. §§ 9601 to 9675)

Endangered Species Act (ESA) (16 U.S.C. §§ 1531)

Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA) (7 U.S.C. §§ 136 to 139y)

Federal Water Pollution Control Act (CWA) (33 U.S.C. §§ 1251)

National Environmental Policy Act (NEPA) (42 U.S.C. §§ 4321-4347)

Toxic Substance Control Act (TSCA) (15 U.S.C. §§ 2601 to 2654)

Resource Conservation and Recovery Act (RCRA) (42 U.S.C.

§§ 6901 to 6991i)

28979950 01 35 43 Page 20

1.04 ENVIRONMENTAL PROTECTION REQUIREMENTS: Provide and

maintain environmental protection during the life of the Contract to control pollution or to correct conditions that develop during construction. Comply with all Federal, State, and local laws and regulations pertaining to water, air, soil, and noise pollution.

1.05 PROTECTION OF NATURAL RESOURCES

A. Permits: The Government has received permits and concurrences from the U.S. Army Corps of Engineers for compliance with Section 404 of the Clean Water Act, Section 10 of the Rivers and Harbor Act, Section 103 of the Marine Protection, Research, and Sanctuaries Act (SPN-2008-00049), and the San Francisco Bay Regional Water Quality Certification and Order for compliance with Section 401 of the Clean Water Act (WDID # 2 CW455657), the San Francisco Bay Conservation and Development Commission with the Coastal Zone Management Act (C2007.005.07)The project shall adhere to Section 307 of the Coastal Zone Management Act, the U.S. Fish and Wildlife Service and National Marine Fisheries Service, Section 7 of the Endangered Species Act, Marine Mammal Protection Act, and Magnuson-Stevens Fisheries Conservation and Management Act. Copies of the environmental permits provided as an Attachment.

The terms and conditions, best management practices, and avoid measures include, but are not limited to, turbidity monitoring, solid debris management, spill prevention plans, etc.

The Contractor shall comply with all requirements under terms and conditions set forth in the environmental permits and authorizations issued for this project.

Copies of these environmental permits are provided with these specifications as attachments. The Contractor shall familiarize personnel with these, and any other permits issued for this project and comply with all requirements under the terms and conditions set forth therein. The contractor will be responsible for payment of fines resulting from violations of conditions set forth in the above permits.

B. Preserve the natural resources within the project boundaries and within the vicinity of performed under this Contract in their existing condition or restore to an equivalent or improved condition upon completion of

28979950 01 35 43 Page 21 the work. Repair or restore to original condition landscape features scarred or damaged by equipment or operations. Obtain Contracting Officer's approval before repair or restoration. Confine construction activities to areas defined by the work schedule, drawings, and specifications. Federal Acquisition Regulation clause 52.236-9 applies.

All project activities must be executed in compliance with the 2015 Biological Opinion (BiOp) for the Long Term Management Strategy for the Placement of Dredged Material in the SF Bay Region. These conservation measures include:

1) Compliance with environmental work windows.

2) Best practices for all dredgers (minimize dredging and disposal, minimize impacts of dredging, minimize impacts of disposal)

3) Best practices for hydraulic dredging if used. See BiOp, Section 1.3.4 at San Francisco District > Missions > Dredging Work Permits > LTMS.

C. Except in areas indicated to be cleared, do not remove, cut, deface, injure, or destroy vegetation without special written permission from the Contracting Officer.

D. Construction equipment is to be kept in good repair, without leaks of hydraulic or lubricating fluids. If such leaks or drips do occur, they shall be cleaned up immediately. Drip pans shall be utilized when vehicles are parked. Confine equipment maintenance and/or repair to one location. Control runoff in this area to prevent contamination of soils and water.

E. At or before Contract completion, temporary construction facilities such as stockpiles of excess or waste materials and all other vestiges of construction. Restore all disturbed areas to their original condition.

F. For all work in or over water habitats, provide a debris boom. Take precautions to prevent construction materials from entering the water and immediately remove any material that enters the water in the work area. Report spills of any liquids into the water habitat and take steps to preclude spread or dissipation of spilled liquids.

https://www.spn.usace.army.mil/missions/dredging-work-permits/ltms/ https://www.spn.usace.army.mil/missions/dredging-work-permits/ltms/

28979950 01 35 43 Page 22

G. The Contractor shall maintain an adequate spill response kit (including absorbent pads and floating oil containment booms) on the primary dredge vessel and support tugboat. All hydraulic hoses must be maintained to prevent leaks. In the event of a petroleum spill, the Contractor must immediately deploy containment booms, notify the USCG COR, and contact the National Response Center (NRC).

1.06 EROSION AND SEDIMENT CONTROL MEASURES:

A. Borrow pits are not permitted on Government property.

B. Provide necessary controls to prevent visible or measurable erosion from leaving the construction site.

C. Provide temporary protection for erodible soils.

Immediately protect side slopes and back slopes upon completion of rough grading. Plan and conduct all earthwork to minimize duration of exposure of unprotected soils.

1.07 CONTROL AND DISPOSAL OF WASTES: With the exception of

materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials become the contractor's property and shall be removed from the job site daily.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

28979950 02 41 00 Page 23

DIVISION 2 – EXISTING CONDITIONS

02 41 00 – FLOATING DOCK REMOVAL AND REINSTALLATION

PART 1 GENERAL

1.01 SECTION INCLUDES: This section applies to all work

required for temporary removal and reinstallation of the existing Jet Docks (four segments, each 15 ft x 30 ft) and concrete floating dock (9 ft by 70 ft). The scope of work includes disconnecting the existing floating docks, tugging them away temporarily, and reinstalling them in the same original configuration once dredging work is completed.

1.02 APPLICABLE PUBLICATIONS: The publications listed below

form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only:

A. American National Standards Institute (ANSI): ANSI A10.6- 2006 (R2016) Safety Requirements for Demolition Operations.

B. U.S. Army Corps of Engineers (USACE): EM 385-1-1 (2014) U.S. Army Corps of Engineers Safety and Health Requirements Manual.

1.03 TEMPORARY REMOVAL PLAN: The contractor shall submit a

removal plan in accordance with Section 01 33 00 SUBMITTAL PROCEDURES within 10 days after award. Do not begin any work until authorization is received from the Contracting Officer.

A. Removal plan shall include procedures for coordination with other work in progress, description of methods and equipment to be used for each operation and of the sequence of operations. The plan shall address the schedule for removing the existing floating docks and the stowaway location and re-installation plans as coordinated with the COR and Station Command.

B. If removal is scheduled to occur during a period that vessels would normally utilize the floating docks, alternative berthing shall be provided by the Contractor.

1.04 REGULATORY AND SAFETY REQUIREMENTS: Comply with federal, state, and local hauling and disposal regulations. In

28979950 02 41 00 Page 24 addition to the requirements of the "Contract Clauses," safety requirements shall conform to ANSI A10.6.

1.05 DUST AND DEBRIS CONTROL: Prevent the spread of dust and

debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.

1.06 PROTECTION:

A. Existing Work: Before beginning any removal work, the contractor shall survey the site and examine the reference drawings and specifications to determine the extent of the work and verify current conditions. The Contractor shall take all necessary precautions to avoid damage to existing items remaining in place; any damaged items shall be repaired or replaced as approved by the Contracting Officer. The Contractor shall coordinate the work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Provide new supports and reinforcement for existing construction weakened by demolition or removal work. Repairs, reinforcement, or structural replacement must have Contracting Officer approval.

B. Facilities: the Contractor shall isolate all electrical power or other stored energy systems and disconnect them from the dock to be removed. The Contractor is required to isolate and lock out any energized lines feeding to the dock. The Contractor shall work with assigned station personnel to identify isolation points and to notify station personnel that the systems have been locked out.

Where removal of existing utilities is required, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. The Contractor shall ensure that no elements determined to be unstable are left unsupported and shall be responsible for placing and securing bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, or demolition work performed under this contract.

28979950 02 41 00 Page 25

C. Relocations: Perform the removal and reinstallation of relocated items (floating docks) with workmen craftsmanship skilled in the trades involved. Any damages to items during relocation process shall be repaired or replaced with new undamaged items as approved by the Contracting Officer at the Contractor’s expense.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.01 EXISTING FACILITIES TO BE REMOVED: Items A through F

below shall be executed in sequence. All tugging activity shall be by pulling on the floats with the proper size chains/cables/ropes attachments and at connections properly fit for the action (i.e. cleats) care shall be taken not to damage any components of the floats.

A. Jet Docks: The contractor is responsible for removing and reinstalling the Jet Docks in the existing configuration.

The Jet Docks are currently tied to the concrete floating dock via chains and include electrical utilities.

Temporary storage and protection are the responsibility of the contractor. The Contractor shall contact the COR prior to removal and re-installation to conduct a joint inspection and document any existing damages or deficiencies. Any damages caused by the Contractor is the Contractor shall be corrected prior to installation. The Contractor is responsible for any hardware and parts directly related to removal and reinstallation.

B. Disconnect all utilities and lock out all energy sources to the existing floating docks.

C. Cap utilities and ensure all feed lines are closed and temporarily isolated and non-operable.

D. Disconnect the concrete floating dock sections from the

(7) guide piles by removing the guide pile framing and rollers. Docks shall be moved to the floater boat that will tug them away.

E. Tug the float to a nearby pre-approved temporary stationing location, inside the bay, and maintain in this position until time for re-installation. All existing guide piles shall remain in place.

28979950 02 41 00 Page 26

F. The existing gangways shall be removed and stored on site in a safe place away from work area at a location to be designated by the Contracting Officer or facility local contact personnel. The gangway shall be reinstalled after work completion.

3.02 RE-INSTALLATION OF FACILITIES: After dredge completion.

A. Tug the floating dock back into original functioning position and secure to existing guide piles, use same framing, re-install rollers.

B. Re-install gangway, as it was originally configured and attached to the float.

28979950 02 41 00 Page 27

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 23 - DREDGING

PART 1 GENERAL

1.01 SECTION INCLUDES: This section applies to all work

required for dredging and disposal of sediment. Perform all operations necessary for the removal of all sediments to the required dimensions, the disposal thereof, and all operations thereto.

1.02 SUBMITTALS:

A. Dredge Operations Plan (DOP): This submittal is required within 30 days of award and must be approved by the Corps prior to initiating the work. The dredging work shall be scheduled to begin 60 days after submittal of the DOP.

The detailed plan shall cover the entire dredging and dredge sediment disposal operation. The document shall explain in writing the exact procedures to be followed and which materials and equipment shall be used by the Contractor to accomplish the required work. It shall include a list of equipment, environmental controls, means of transport, and means and locations of intermediate storage or handling of dredge sediment.

The DOP shall adhere to the permit requirements from the U.S. Army Corps of Engineers and shall include, at a minimum:

1) Corps permit number and dredge episode number.

2) Copy of the dredging contract and description of the scope of working including identification of the work as maintenance dredging.

3) Name and contact information of Contractor’s representative on site.

4) Mobile equipment operator list.

5) Dredging start and completion dates.

6) Names of vessels, dump scow identifications, bin or barge capacities

7) Detailed discussion of the Contractor’s proposed

28979950 02 41 00 Page 28 dredging method as governed under BCDC Permit Special Conditions II, including drawings of the areas authorized to be dredged, procedures and dredging equipment, cross-sections, volume to be dredged, and design depths including overdepth based on MLLW.

8) Controls being established to ensure that dredging operations occur within authorized area and at the authorized depths.

9) Controls being established to ensure that disposal of the dredged material at the disposal sites is at the assigned location and depth.

10) Method of determining electronic positions of dredge or dump scow during entire operation at dredge site, disposal site, and enroute to and from disposal site.

11) Discussion of the sediment quality, explaining why the sediment is suitable for the proposed disposal and/or beneficial reuse placement sites.

12) Procedures for conducting the pre- and post-dredge hydrographic surveys.

13) The pre- dredge hydrographic survey with volume calculations.

14) Procedures for monitoring the progress and quantity of dredging during the execution of the work.

15) Identification of the disposal location(s) including associated dates and quantities of each sediment disposal proposed.

16) Discussion as to how the proposed disposal volumes are consistent with the LTMS.

17) Procedures for transporting the sediment to the disposal location.

18) Notice to Mariners.

19) Solid debris management plan.

20) Accident/spill prevention and control plan.

21) Any specific conditions listed on attached permits.

28979950 02 41 00 Page 29

Provide plans and procedures should gale force winds or higher be forecast. Precautions shall include, but not be limited to, closing all openings, removing all loose materials, tools and equipment from exposed locations, anchoring and tying down barge, dredge, and/or pipeline.

The Contractor must acknowledge that the BCDC staff shall be allowed to board any vessel under way associated with dredging or disposal and subject to reasonable safety and operational considerations (PCDC Permit, Amendment No.

One).

Results of any barge overflow, effluent water quality or other testing required by the Water Board shall be submitted in writing to Commission staff at the same time such testing is submitted to the Water Board (PCDC Permit, Amendment No. One).

Submit weekly Disposal Site Verification Logs (DSVL) by noon Monday via e. The DSVL enumerates work accomplished during the preceding week.

B. Solid Debris Management Plan: Submit proposed measures to ensure that solid debris generated during any authorized dredging, demolition or construction operation is retained and properly disposed.

1) Mechanically dredged material shall be passed through a debris grid with a maximum opening size of 12 inches by 12 inches that will cover the entire loading area of the dump cow. Everything that does not pass through the grid will be considered solid debris and shall be promptly removed from the grid and disposed of at an upland disposal site suitable for the material.

C. Hydrographic Surveys: Submit results of hydrographic surveys taken before (pre) and after (post) dredging performed by a third-party licensed surveyor to certify their accuracy. The hydrographic surveys and related drawings must include the dredged prism. More information provided in Section 1.06, below.

1) The pre-dredge survey submittal is required no later than 30 days after award.

2) The post-survey submittal is required prior to final acceptance of the dredging work and 30 days after the last disposal activity.

28979950 02 41 00 Page 30

3) A copy of the Post-Dredge survey shall be sent to the National Ocean Service for chart updating.

D. Dredge Volume Calculations: Submit results of actual gross volume of dredged sediment. Cover sheet shall be signed, dated, and sealed by licensed surveyor.

E. Post-Dredge Project Report: The Contractor shall provide the COR, construction manager, and project manager with a notice of completion within 24 hours of the last sediment deposit. Within 30 days after the completion of the dredging, the Contractor shall submit a post-dredge report to document the project’s execution. This report will be submitted to the regulatory agencies to satisfy permit requirements. At a minimum, the report will include:

1) Corps permit number and dredge episode number.

2) Dates of commencement and completion of work.

3) Post-dredge survey maps of the dredge footprint.

4) Calculated final dredging volume (in cubic yards) based on the pre- and post-dredge surveys. Explain any variation in quantities greater than 15% beyond estimated quantities or dredging deeper than is permitted (design plus overdepth allowance).

5) Disposal locations and volume of dredged sediment placed at each placement location.

6) As appropriate, a discussion of the actions and/or measures implemented to prevent exposure of the contaminated z-layer to aquatic life post dredging.

7) Should testing and analysis of the z-layer from the project area show elevated levels of contaminants that may pose a threat to aquatic life, coordinate with COR and DMMO on a suitable plan, with a timeline, on actions and/or measures the Contractor shall implement to prevent exposure of the contaminated z-layer to aquatic life post dredging. This plan must be coordinated before the episode approval request package is submitted to the Water Board.

8) Copies of all hydrographic surveys.

28979950 02 41 00 Page 31

9) Required monitoring logs and any noncompliance issues.

10) Environmental permitting compliance documentation.

1.03 DEBRIS SCREENING: The Contractor shall employ a rigid

debris screen (commonly referred to as a “grizzly”) over the receiving scows or barges during all mechanical dredging operations to catch and separate oversized artificial obstructions. The USCG anticipates debris such as, but not limited to, metal bands, pallets, pieces of broken cable, rope, hose, and broken piles.

A. The Government has no knowledge of existing wrecks or wreckages.

B. The Contractor shall ensure that the debris screen is safely and regularly cleared of accumulation.

C. The Contractor is strictly prohibited from using USCG uplands, piers, or shorelines for stockpiling, sorting, or dewatering of recovered debris. All recovered debris must be temporarily stored in a secure, designated debris bin or containment area located directly on the Contractor’s support vessels or barges.

D. Under no circumstances shall artificial debris be placed into the scows destined for the unconfined aquatic disposal site.

1.04 QUANTITY OF MATERIAL: The total estimated amount of

material to be removed from within the specified limits, including side slopes, is 10,386 cubic yards. The quantity listed is an estimate only.

A. Maximum Event: The total dredge volume, per environmental authorizations, is not to exceed 10,386 cy for this event.

B. Over-depth Dredging: Due to unavoidable inaccuracies in the dredging processes, different types of equipment, operator skill, and material composition, it is possible that material originating beyond the specified limits will be inadvertently removed.