3-2101-058 Earthwork For Bidding Specs.pdf
PDF 3 MB Posted
- Solicitation number
- RA26-65
- Issued by
- Davis County, Utah
About this file
Roosevelt City Rough Rider Shooting Complex Earthwork Project Summary
This is a bidding specification and contract document package for the Roosevelt City Rough Rider Shooting Complex Earthwork project managed by Roosevelt City in Roosevelt, Utah, with Jones and DeMille Engineering serving as the engineer of record. The project involves earthwork construction to build shooting ranges, including approximately 28,000 cubic yards of berm fill and 5,000 cubic yards of additional excavation. The work encompasses clearing and grubbing, excavation of topsoil and existing materials, placement and compaction of fill materials using on-site soil sources, temporary erosion and sediment control measures, and final grading. An optional pre-bid conference is scheduled for December 8, 2025 at 1:00 PM at Jones and DeMille Engineering's office (520 West Highway 40, Roosevelt, Utah 84066). Written questions must be submitted to Karissa Wilson-Musich at karissa.m@jonesanddemille.com by December 11, 2025 at 4:00 PM. Sealed bids are due at Jones and DeMille Engineering on December 16, 2025 at 1:00 PM local time, at which time bids will be publicly opened and read. Bid results will be posted on the Utah Bonfire purchasing website. The anticipated project budget is approximately $225,000 with an expected duration of 30 days and completion by June 1, 2026.
Award will be made to the lowest responsive bidder from a responsible contractor demonstrating successful completion of at least three similar-sized earthwork projects within the past five years. The bid consists of three unit price items: Mobilization (lump sum), Berm Fill at plan quantity of 28,000 cubic yards, and Excavation at plan quantity of 5,000 cubic yards. Payment terms include 5 percent retainage until substantial completion, monthly progress payments based on actual quantities accepted by the engineer, and unit prices that include all labor, equipment, overhead, and profit. The contractor must provide performance and payment bonds equal to the contract price, workers' compensation insurance, commercial general liability of $2,000,000, automobile liability of $1,000,000, and pollution liability of $1,000,000. Liquidated damages of $500 per day apply for delays beyond the 30-day substantial completion deadline. The contract is governed by Utah law and includes standard EJCDC construction contract terms with provisions for change orders, differing site conditions, and dispute resolution through negotiation or court proceedings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-2101-058 Earthwork For Bidding Plans.pdf | ||
| 1-001113 00 Advertisement for Bids C111 2018 (17).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROOSEVELT CITY
ROUGH RIDER SHOOTING
COMPLEX EARTHWORK
PROJECT MANUAL
NOVEMBER 28, 2025
FOR BIDDING ONLY
Project #: 2101-058
Roosevelt City 00 01 10 Table of Contents Rough Rider Shooting Complex Earthwork (2101-058)Page 1 of 2
DOCUMENT 00 01 10
TABLE OF CONTENTS
NUMBER TITLE
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
Division 00 - Procurement and Contracting Requirements
Introductory Information 00 01 10 Table of Contents
Procurement Requirements 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 15 Bid Form
Contracting Requirements 00 51 00 Notice of Award 00 52 15 Contract for Construction of a Small Project 00 55 00 Notice to Proceed 00 61 13.13 Performance Bond Form 00 61 13.16 Payment Bond Form 00 63 36 Field Order Form 00 63 49 Work Change Directive Form 00 63 63 Change Order Form 00 65 16 Certificate of Substantial Completion Form 00 65 19.21 Notice of Acceptability of Work
SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP (Division 01)
Division 01 - General Requirements 01 10 00 Summary 01 20 00 Price and Payment Procedures 01 30 00 Administrative Requirements 01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 57 13 Temporary Erosion and Sediment Control 01 70 00 Execution and Closeout Requirements 01 71 13 Mobilization
FACILITY CONSTRUCTION SUBGROUP (Division 02 to 19) – Not Used
FACILITY SERVICES SUBGROUP (Division 20 to 29) – Not Used
SITE AND INFRASTRUCTURE SUBGROUP (Division 34 to 39)
Division 30 – Not Used
Division 31 - Earthwork
12/02/2025
Roosevelt City 00 01 10 Table of Contents Rough Rider Shooting Complex Earthwork (2101-058)Page 2 of 2
31 11 00 Clearing and Grubbing 31 23 16 Excavation 31 23 23 Fill
Division 32 to 39 – Not Used
PROCESS EQUIPMENT SUBGROUP (Division 40 to 49) – Not Used
Roosevelt City 00 11 13 Advertisement for Bids Rough Rider Shooting Complex Earthwork (2101-058)Page 1 of 1
DOCUMENT 00 11 13
ADVERTISEMENT FOR BIDS
ROOSEVELT CITY, 255 SOUTH STATE STREET, ROOSEVELT, UTAH 84066
General Notice:
Roosevelt City is requesting Bids for the construction of the following Project: Rough Rider Shooting
Complex Earthwork.
Bids for the construction of the Project will be received at the offices of Jones and DeMille Engineering located at 520 West Highway 40, Roosevelt, Utah 84066, until December 16th, 2025 at 1:00 PM local time. At that time, the Bids received will be publicly opened and read. Bid results will be posted on the
State Purchasing website, Bonfire, at https://utah.bonfirehub.com/projects.
The Project includes the following Work: earthwork to build shooting ranges including approximately
28,000 cubic yards of berm fill and 5,000 cubic yards of additional excavation. Bids will be received for a single contract.
Owner anticipates that the Project’s total bid price will be approximately $225,000. The Project has an expected duration of 30 days and is expected to be completed by June 1, 2026.
Obtaining Bidding Documents:
Information and Bidding Documents for the Project can be found at the Bonfire website. For first time users, follow the “Register” button at the top right-hand corner of the Utah Public Procurement Place
(U3P) portal provided by Utah State Purchasing at utah.bonfirehub.com/portal/?tab=openOpportunities. Any responses received through the U3P Jaggaer courtesy posting will not be considered responsive, nor will they be evaluated. Questions or needed assistance can be directed to the online knowledge base, the FAQs page, or the Bonfire Support Team at support@gobonfire.com.
The designated website will be updated with addenda, plan holders list, reports, and other information relevant to submitting a Bid for the Project. Official notifications, addenda, and other Bidding
Documents will be offered through the designated website.
The Issuing Office for the Bidding Documents is: Jones & DeMille Engineering, Inc., 520 West Highway
40, Roosevelt, Utah 84066
Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including addenda, if any, obtained from sources other than the designated website and the Issuing Office.
Questions are due in writing to Karissa Wilson-Musich, at karissa.m@jonesanddemille.com on or before
December 11, 2025 at 4:00 P.M.
Pre-bid Conference:
A pre-bid conference for the project will be held on December 8, 2025 at 1 P.M. at 520 West Highway 40
Roosevelt, Utah, 84066. Attendance at the pre-bid is encouraged but not required.
Instructions to Bidders:
For further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents. The Owner may reject any or all bids submitted.
Issued by:
Owner: Roosevelt City
By: JR Bird
Title: Mayor
Date: December 1, 2025
Roosevelt City 00 21 13 Instructions to Bidders Rough Rider Shooting Complex Earthwork (2101-058) Page 1 of 5
DOCUMENT 00 21 13
INSTRUCTIONS TO BIDDERS
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the Contract
Documents. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – The office from which the Bidding Documents are to be issued.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the advertisement or invitation to bid.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within 5 days of Owner’s request, Bidder shall submit (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) additional information as requested by Owner.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE
4.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
4.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions:
1. No reports of explorations or tests of subsurface conditions at or adjacent to the Site, or drawings of physical conditions relating to existing surface or subsurface structures at the Site, are known to Owner.
2. No reports or drawings related to Hazardous Environmental Conditions at the Site are known to Owner.
Rough Rider Shooting Complex Earthwork (2101-058) Page 2 of 5
B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and
Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Site Visit and Testing by Bidders
A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.
B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
C. On request, and to the extent Owner has control over the Site, and schedule permitting, the
Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on
Owner’s authority regarding the Site.
D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
ARTICLE 5 – PRE-BID CONFERENCE
5.02 An optional pre-bid conference will be held on Monday, December 8th at 1:00 PM local time at
Jones and DeMille Engineering, 520 West Highway 40, Roosevelt, Utah, 84066. Attendance at the pre-bid conference is encouraged but not required. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.
5.03 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner or Engineer will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 6 – INTERPRETATIONS AND ADDENDA
6.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of
Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
6.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
Rough Rider Shooting Complex Earthwork (2101-058) Page 3 of 5
ARTICLE 7 – BID SECURITY
7.01 A Bid does not need to be accompanied by a Bid security for this project.
ARTICLE 8 – SUBSTITUTE AND “OR-EQUAL” ITEMS
8.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by
Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer at least 15 days prior to the date for receipt of Bids. Each such request shall include sufficient information to allow Engineer to determine if proposed material or equipment is acceptable. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders.
Bidders shall not rely upon approvals made in any other manner.
8.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of
“or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 9 – BASIS OF BID
9.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Contract
Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Contract Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract
Price will be determined based on actual quantities used for the Work.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
ARTICLE 10 – SUBMITTAL OF BID
10.01 An unbound copy of the Bid Form is to be completed and submitted with the other documents required to be submitted under the terms of the Bid Form.
10.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the
Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the other required documents.
A. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID
Rough Rider Shooting Complex Earthwork (2101-058) Page 4 of 5
ENCLOSED.” A mailed Bid shall be addressed to Roosevelt City, c/o Jones and DeMille
Engineering, at the following address: 520 West Highway 40, Roosevelt, Utah 84066.
10.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the
Bidder unopened.
ARTICLE 11 – MODIFICATION AND WITHDRAWAL OF BID
11.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a
Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
11.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in the Paragraph above and submit a new Bid prior to the date and time for the opening of Bids.
11.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned, if submitted. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.
ARTICLE 12 – OPENING OF BIDS
12.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 13 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
13.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 14 – EVALUATION OF BIDS AND AWARD OF CONTRACT
14.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that
Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.
14.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.
14.03 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the
Contract Form or prior to the Notice of Award.
Rough Rider Shooting Complex Earthwork (2101-058) Page 5 of 5
B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
14.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
A. In order to be considered qualified for the Project, the Bidder shall have successfully constructed at least three similar sized earthwork projects within the past five years.
14.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 15 – SIGNING OF CONTRACT
15.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted Contract Documents. Within 14 days thereafter, Successful Bidder shall execute and deliver the required bonds, insurance and other required documentation to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Contract to Successful
Bidder, together with four printed and one portable document format (PDF) electronic copies of the Contract Documents.
15.02 The effective date of the Contract will be the date indicated on the Contract.
15.03 It is intended that the Contract Time will commence to run as soon as possible after the Contract
Documents have been executed. The Contractor, Owner and Engineer will determine a mutually agreed upon date for the Contract Times to commence to run and that date will be indicated on the Notice to Proceed issued by the Owner.
END OF DOCUMENT
Roosevelt City 00 41 15 Bid Form Rough Rider Shooting Complex Earthwork (2101-058) Page 1 of 4
DOCUMENT 00 41 15
BID FORM
Roosevelt City
Rough Rider Shooting Complex Earthwork
2101-058
ARTICLE 1 – BID RECIPIENT
1.01 This Bid is submitted to: Roosevelt City c/o Jones & DeMille Engineering, 520 West Highway 40, Roosevelt, Utah 84066.
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS
2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 – BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, and any data and reference items identified in the Bidding Documents, and hereby acknowledges receipt of the following Addenda:
Addendum No. Addendum, Date
B. Bidder has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfied itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and has satisfied itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Bidding Documents.
Rough Rider Shooting Complex Earthwork (2101-058) Page 2 of 4
E. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and any Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs.
F. Bidder agrees, based on the information and observations referred to in the preceding paragraph, that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the
Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by Owner and others at the
Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and confirms that the written resolution thereof by Engineer is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work.
J. The submission of this Bid constitutes an incontrovertible representation by Bidder that
Bidder has complied with every requirement of this Article, and that without exception the
Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
ARTICLE 4 – BIDDER’S CERTIFICATION
4.01 Bidder certifies that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
Rough Rider Shooting Complex Earthwork (2101-058) Page 3 of 4
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
ARTICLE 5 – BASIS OF BID
5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
UNIT PRICE BID
Bid Form
Item Item Description Unit
Estimated Bid Unit Bid Price
No. Quantity Price
1-1 Mobilization L.S. 1
1-2 Berm Fill (Plan Quantity) C.Y. 28,000
1-3 Excavation (Plan Quantity) C.Y. 5,000
Total
Bidder acknowledges that (1) each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and (2) estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents.
ARTICLE 6 – TIME OF COMPLETION
6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment on or before the dates or within the number of calendar days indicated in the
Agreement.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 7 – ATTACHMENTS TO THIS BID
7.01 The following documents are submitted with and made a condition of this Bid:
A. List of Proposed Subcontractors.
B. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids.
C. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids.
D. Required Bidder qualification information as indicated in Article 3 of the Instructions to
Bidders.
Rough Rider Shooting Complex Earthwork (2101-058) Page 4 of 4
ARTICLE 8 – DEFINED TERMS
8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders and the Contract.
ARTICLE 9 – BID SUBMITTAL
BIDDER: [Indicate correct name of bidding entity]
By:
[Signature]
[Printed name]
(If Bidder is a corporation, a limited liability company, a partnership, or a joint venture, attach evidence of authority to sign.)
Attest:
[Signature]
[Printed name]
Title:
Submittal Date:
Address for giving notices:
Telephone Number:
Fax Number:
Contact Name and e-mail address:
Bidder’s License No.:
Roosevelt City 00 51 00 Notice of Award Rough Rider Shooting Complex Earthwork (2101-058) Page 1 of 1
DOCUMENT 00 51 00
NOTICE OF AWARD
Date of Issuance:
Owner: Roosevelt City Owner's Contract No.:
Engineer: Jones & DeMille Engineering Engineer's Project No.: 2101-058
Project: Rough Rider Shooting Complex
Earthwork
Contract Name:
Bidder:
Bidder’s Address:
TO BIDDER:
You are notified that Owner has accepted your Bid for the above Contract, and that you are the Successful
Bidder and are awarded a Contract for the following: earthwork to build shooting ranges including approximately
28,000 cubic yards of berm fill and 5,000 cubic yards of additional excavation.
The Contract Price of the awarded Contract is: $ _______ [Note if subject to unit prices, or cost-plus.]
Contract Documents will be made available to Bidder.
You must comply with the following conditions precedent within 14 days of the date of receipt of this Notice of Award:
1. Deliver performance and payment bonds.
2. Deliver insurance documentation.
Failure to comply with these conditions within the time specified will entitle Owner to consider you in default, annul this Notice of Award, and declare your Bid security forfeited.
Within ten days after you comply with the above conditions, Owner will return to you one fully executed counterpart of the Contract, together with any additional copies of the Contract Documents.
Owner: Roosevelt City
Authorized Signature
By: ____________________________
Title: ____________________________
EJCDC® C-522, Contract for Construction of a Small Project.
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
DOCUMENT 00 52 15
CONTRACT FOR CONSTRUCTION OF A SMALL PROJECT
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1 of 18
CONTRACT FOR CONSTRUCTION OF A SMALL PROJECT
This Contract is by and between Roosevelt City (Owner) and
(Contractor).
Owner and Contractor hereby agree as follows:
ARTICLE 1 - THE WORK
1.01 Work
A. Work includes all labor, materials, equipment, services, and documentation necessary to construct the Project defined herein. The Work may include related services such as testing, start-up, and commissioning, all as required by the Contract Documents.
B. The Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Project is generally described as follows:
1. Rough Rider Shooting Complex Earthwork, which includes earthwork to build shooting ranges including approximately 28,000 cubic yards of berm fill and 5,000 cubic yards of additional excavation.
2. The Site of the Work includes property, easements, and designated work areas described in greater detail in the Contract Documents but generally located on
Roosevelt City property east of the sewer lagoons, south of Ballard and southeast of
Roosevelt City.
ARTICLE 2 - CONTRACT DOCUMENTS
2.01 Intent of Contract Documents
A. It is the intent of the Contract Documents to describe a functionally complete project. The
Contract Documents do not indicate or describe all of the Work required to complete the
Project. Additional details required for the correct installation of selected products are to be provided by the Contractor and coordinated with the Owner and Engineer. This Contract supersedes prior negotiations, representations, and agreements, whether written or oral.
The Contract Documents are complementary; what is required by one part of the Contract
Documents is as binding as if required by other parts of the Contract Documents.
B. During the performance of the Work and until final payment, Contractor and Owner shall submit all matters in question concerning the requirements of the Contract Documents, or relating to the acceptability of the Work under the Contract Documents to the Engineer.
Engineer will be the initial interpreter of the requirements of the Contract Documents, and judge of the acceptability of the Work thereunder.
C. Engineer will render a written clarification, interpretation, or decision on the issue submitted, or initiate a modification to the Contract Documents.
D. Contractor, and its subcontractors and suppliers, shall not have or acquire any title to or ownership rights to any of the Drawings, Specifications, or other documents (including copies or electronic media editions) prepared by Engineer or its consultants.
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2 of 18
2.02 Contract Documents Defined
A. The Contract Documents consist of the following documents:
1. This Contract.
2. Performance bond.
3. Payment bond.
4. Specifications listed in the Table of Contents.
5. Drawings as listed on the Drawing Sheet Index.
6. Addenda.
7. Exhibits to this Contract (enumerated as follows):
a. Exhibit 1 – Contractor’s Bid.
8. The following which may be delivered or issued on or after the Effective Date of the
Contract:
a. Work Change Directives (EJCDC C-940).
b. Change Orders (EJCDC C-941).
c. Field Orders.
ARTICLE 3 - ENGINEER
3.01 Engineer
A. The Engineer for this Project is Jones & DeMille Engineering, Inc.
ARTICLE 4 - CONTRACT TIMES
4.01 Contract Times
A. The Work will be substantially completed within 30 days of the first day of work with all work being completed on or before June 1, 2026.
4.02 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence in the performance of the
Contract, and that Owner will incur damages if Contractor does not complete the Work according to the requirements of Paragraph 4.01. Because such damages for delay would be difficult and costly to determine, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):
1. Substantial Completion: Contractor shall pay Owner $500 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial
Completion, until the Work is substantially complete.
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $500 for each day that expires after such time until the Work is completed and ready for final payment.
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3 of 18
4.03 Delays in Contractor’s Progress
A. If Owner, Engineer, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an equitable adjustment in the Contract Times and Contract Price. Contractor’s entitlement to an adjustment of the Contract Times is conditioned on such adjustment being essential to
Contractor’s ability to complete the Work within the Contract Times.
B. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for delay, disruption, or interference caused by or within the control of Contractor or their subcontractors or suppliers.
C. If Contractor’s performance or progress is delayed, disrupted, or interfered with by unanticipated causes not the fault of and beyond the control of Owner, Contractor, and those for which they are responsible, then Contractor shall be entitled to an equitable adjustment in Contract Times.
D. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for any delay, disruption, or interference if such delay is concurrent with a delay, disruption, or interference caused by or within the control of Contractor or Contractor’s subcontractors or suppliers.
4.04 Progress Schedules
A. Contractor shall develop a progress schedule and submit to the Engineer for review and comment before starting Work on the Site. The Contractor shall modify the schedule in accordance with the comments provided by the Engineer.
B. The Contractor shall update and submit the progress schedule to the Engineer each month.
The Owner may withhold payment if the Contractor fails to submit the schedule.
ARTICLE 5 - CONTRACT PRICE
5.01 Payment
A. Owner shall pay Contractor in accordance with the Contract Documents, the lump sum amount of (words)
________________________ (numbers) ($ ) for all Work.
B. Owner shall pay Contractor in accordance with the Contract Documents at the unit prices for each unit of Work completed at the unit prices stated in the Contractor’s Bid, attached here to as an exhibit. Payment will be made in an amount equal to the total of all extended prices for actual Work completed. The extended price is determined by multiplying the unit price times the actual quantity of that Work item completed. Actual quantities installed will be determined by the Engineer.
ARTICLE 6 - BONDS AND INSURANCE
6.01 Bonds
A. Before starting Work, Contractor shall furnish a performance bond and a payment bond from surety companies that are duly licensed or authorized to issue bonds in the required amounts in the jurisdiction in which the Project is located. Each bond shall be in an amount equal to the Contract Price, as security for the faithful performance and payment of all of Contractor’s
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4 of 18 obligations under the Contract. These bonds shall remain in effect until the completion of the correction period specified in Paragraph 7.12 but, in any case, not less than one year after the date when final payment becomes due.
6.02 Insurance
A. Before starting Work, Contractor shall furnish evidence of insurance from companies that are duly licensed or authorized in the jurisdiction in which the Project is located with a minimum AM Best rating of A-VII or better. Contractor shall provide insurance in accordance with the following:
1. Contractor shall provide coverage for not less than the following amounts, or greater where required by Laws and Regulations:
a. Workers’ Compensation:
State: Statutory
Employer’s Liability:
Bodily Injury, each Accident $ 500,000
Bodily Injury By Disease, each Employee $ 500,000
Bodily Injury/Disease Aggregate $ 500,000
b. Commercial General Liability:
General Aggregate $ 2,000,000
Products - Completed Operations Aggregate $ 1,000,000
Personal and Advertising Injury $ 1,000,000
Each Occurrence (Bodily Injury and Property
Damage) $ 1,000,000
c. Automobile Liability herein:
Bodily Injury:
Each Person $ 1,000,000
Each Accident $ 1,000,000
Property Damage:
Each Accident $ 1,000,000
d. Excess or Umbrella Liability:
Per Occurrence $ 1,000,000
General Aggregate $ 1,000,000
e. Contractor’s Pollution Liability:
Each Occurrence $ 1,000,000
General Aggregate $ 1,000,000
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5 of 18
B. All insurance policies required to be purchased and maintained will contain a provision or endorsement that the coverage afforded will not be canceled or materially changed or renewal refused until at least 10 days prior written notice has been given to the insured and additional insured.
C. Automobile liability insurance provided by Contractor shall provide coverage against claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance, or use of any motor vehicle. The automobile liability policy shall be written on an occurrence basis.
D. Contractor’s commercial general liability policy shall be written on a 1996 or later ISO commercial general liability occurrence form and include the following coverages and endorsements:
1. Products and completed operations coverage maintained for three years after final payment;
2. Blanket contractual liability coverage to the extent permitted by law;
3. Broad form property damage coverage; and
4. Severability of interest; underground, explosion, and collapse coverage; personal injury coverage.
E. The Contractor’s commercial general liability and automobile liability, umbrella or excess, and pollution liability policies shall include and list Owner and Engineer and the respective officers, directors, members, partners, employees, agents, consultants, and subcontractors of each as additional insureds; and the insurance afforded to these additional insureds shall provide primary coverage for all claims covered thereby (including as applicable those arising from both ongoing and completed operations) on a non-contributory basis.
1. Additional insured endorsements will include both ongoing operations and products and completed operations coverage through ISO Endorsements CG 20 10 10 01 and CG
20 37 10 01 (together). If Contractor demonstrates to Owner that the specified ISO endorsements are not commercially available, then Contractor may satisfy this requirement by providing equivalent endorsements.
2. Contractor shall provide ISO Endorsement CG 20 32 07 04, “Additional Insured— Engineers, Architects or Surveyors Not Engaged by the Named Insured” or its equivalent for design professional additional insureds.
F. Umbrella or excess liability insurance shall be written over the underlying employer’s liability, commercial general liability, and automobile liability insurance. Subject to industry-standard exclusions, the coverage afforded shall be procured on a “follow the form” basis as to each of the underlying policies. Contractor may demonstrate to Owner that Contractor has met the combined limits of insurance (underlying policy plus applicable umbrella) specified for employer’s liability, commercial general liability, and automobile liability through the primary policies alone, or through combinations of the primary insurance policies and an umbrella or excess liability policy.
G. The Contractor shall provide property insurance covering physical loss or damage during construction to structures, materials, fixtures, and equipment, including those materials, fixtures, or equipment in storage or transit.
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6 of 18
H. If Contractor has failed to obtain and maintain required insurance, Owner may exclude the
Contractor from the Site, impose an appropriate set-off against payment, and exercise
Owner’s termination rights under Article 15.
ARTICLE 7 - CONTRACTOR’S RESPONSIBILITIES
7.01 Supervision and Superintendence
A. Contractor shall supervise and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, safety, and procedures of construction.
B. Contractor shall assign a competent resident superintendent who is to be present at all times during the execution of the Work. This resident superintendent shall not be replaced without written notice to and approval by the Owner and Engineer except under extraordinary circumstances.
C. Contractor shall at all times maintain good discipline and order at the Site.
D. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during regular working hours, Monday through Friday.
7.02 Other Work at the Site
A. In addition to and apart from the Work of the Contractor, other work may occur at or adjacent to the Site. Contractor shall take reasonable and customary measures to avoid damaging, delaying, disrupting, or interfering with the work of Owner, any other contractor, or any utility owner performing other work at or adjacent to the Site.
7.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, testing, start up, and completion of the Work, whether or not such items are specifically called for in the Contract Documents.
B. All materials and equipment incorporated into the Work shall be new, of good quality and shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable supplier, except as otherwise may be provided in the Contract Documents.
7.04 Subcontractors and Suppliers
A. Contractor may retain subcontractors and suppliers for the performance of parts of the
Work. Such subcontractors and suppliers must be acceptable to Owner.
B. The Contractor shall not award work valued more than 50 percent of the Contract Price to
Subcontractor(s), without prior written approval of the Owner.
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7 of 18
7.05 Quality Management
A. Contractor is fully responsible for the managing quality to ensure Work is completed in accordance with the Contract Documents.
7.06 Licenses, Fees and Permits
A. Contractor shall pay all license fees and royalties and assume all costs incident to performing the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others.
B. Contractor shall obtain and pay for all construction permits and licenses unless otherwise provided in the Contract Documents.
7.07 Laws and Regulations; Taxes
A. Contractor shall give all notices required by and shall comply with all local, state, and federal
Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither Owner nor Engineer shall be responsible for monitoring Contractor’s compliance with any Laws or Regulations.
B. Contractor shall bear all resulting costs and losses, and shall indemnify and hold harmless
Owner and Engineer, and the officers, directors, members, partners, employees, agents, consultants, and subcontractors of each and any of them from and against all claims, costs, losses, and damages if Contractor performs any Work or takes any other action knowing or having reason to know that it is contrary to Laws or Regulations.
C. Contractor shall pay all applicable sales, consumer, use, and other similar taxes Contractor is required to pay in accordance with Laws and Regulations.
7.08 Record Documents
A. Contractor shall maintain one printed record copy of all Drawings, Specifications, Addenda, Change Orders, Work Change Directives, Field Orders, written interpretations and clarifications, and approved shop drawings in a safe place at the Site. Contractor shall annotate them to show changes made during construction. Contractor shall deliver these record documents to Engineer upon completion of the Work.
7.09 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the Work.
B. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury, or loss to:
1. All persons on the Site or who may be affected by the Work;
2. All the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and
3. Other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, other work in progress, utilities, and underground facilities not designated for removal, relocation, or replacement in the course of construction.
Copyright © 2016 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 8 of 18
C. All damage, injury, or loss to any property caused, directly or indirectly, in whole or in part, by Contractor, or anyone for whose acts the Contractor may be liable, shall be remedied by
Contractor at its expense (except damage or loss attributable to the fault of Contract
Documents or to the acts or omissions of Owner or Engineer and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of Contractor).
D. Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the Site in accordance with Laws or Regulations.
E. In emergencies affecting the safety or protection of persons or the Work or property at the
Site or adjacent thereto, Contractor shall act to prevent threatened damage, injury, or loss.
Contractor shall give Engineer prompt written notice if Contractor believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby or are required as a result thereof. If Engineer determines that a change in the
Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Work Change Directive or Change Order will be issued.
7.10 Shop Drawings, Samples, and Other Submittals
A. Contractor shall review and coordinate the shop drawing and samples with the requirements of the Work and the Contract Documents and shall verify all related field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information.
B. Each submittal shall bear a stamp or specific written certification that Contractor has satisfied
Contractor’s obligations under the Contract Documents with respect to Contractor’s review of that submittal, and that Contractor approves the submittal.
C. With each submittal, Contractor shall give Engineer specific written notice, in a communication separate from the submittal, of any variations that the shop drawing or sample may have from the requirements of the Contract Documents.
D. Engineer will provide timely review of shop drawings and samples.
E. Engineer’s review and approval will not extend to means, methods, techniques, sequences, or procedures of construction or to safety precautions or programs.
This is the start of the file's text. The full file is on GovTribe.