26Q7901_ Equipment Removal.pdf

PDF 181 KB Posted

Attached to
CNC HORIZONTAL MACHINING CENTER (SOLE SOURCE)
Solicitation number
SPMYM226Q7901
Issued by

About this file

This is an Existing Equipment Removal Requirements attachment for a federal contract involving the Trident Refit Facility (TRF) at Naval Base Kitsap – Bangor in Silverdale, Washington. The document specifies requirements for removing a HAAS EC-1600 CNC Horizontal Machining Center (NID# 68438C0017) from Building 7000, Room W138 to make space for new equipment installation under Project #412-320.

The contractor is responsible for coordinating equipment removal with the Prime Contractor installing the replacement equipment, scheduling work to minimize production downtime, and completing removal in accordance with site-specific requirements detailed in Attachment A. Contractor responsibilities include removing the machine and all associated electrical gear and disconnects, managing waste as designated by the Government, disassembling the machine as necessary for transport, and transporting the machine to scrap. The contractor must also clean any residual fluids, dirt, and debris that leak from the removed equipment for 15 calendar days following removal. The Government will disconnect utilities and bring the machine to a Zero-Energy State by removing stored energy sources, provide a laydown area for contractor equipment, and remove bulk fluids. All work requires submission and approval of a Plan of Action and Milestones (POA&M) prior to execution.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Trident Refit Facility

pg. 1

TRF Bangor – Project #412-320 – CNC Horizontal Machining Center

Attachment B

Existing Equipment Removal Requirements

LOCATION:

TRF Bangor, B7000 Rm W138

7000 Finback Circle, Silverdale, WA 98315

Naval Base Kitsap – Bangor, in Silverdale, Washington

1. REQUIREMENTS

1.1. Scope. The Government’s installation site for the equipment specified herein is currently occupied by a

HAAS EC-1600 CNC Horizontal Machining Center (NID# 68438C0017). The machine with all associated equipment and electrical gear, including disconnects, shall be removed. The contractor shall coordinate/schedule the removal and disposition of the machine as follows:

1.1.1. Coordinate equipment removal with Prime Contractor for the new equipment being installed in conjunction with this contract document.

1.1.2. Schedule and conduct work in such a manner that minimizes, to the greatest extent possible, any downtime and/or disruption to shop production operations as a result of the collective effort required to remove and install the new equipment.

1.1.3. All work shall be conducted IAW the site-specific requirements as detailed in Project Document

Attachment A.

1.2. Equipment Removal. Upon receipt of an approved Plan of Action and Milestones (POA&M) per contract, the contractor shall be responsible for completion of the following:

1.2.1. The machine with all associated equipment and electrical gear, including disconnects, shall be removed.

1.2.2. Manage waste as designated by the Government in Attachment A.

1.2.3. The machine shall be disassembled as necessary for transport.

1.2.4. Transport machine to scrap.

2. GOVERNMENT RESPONSIBILITIES:

2.1. Disconnect utilities and bring the machine to a Zero-Energy State.

2.1.1. Remove or relieve any sources of stored energy (gravitational, mechanical, electrical, etc.) that remain within the equipment.

2.2. Provide laydown area for contractor equipment.

2.3. Remove bulk fluids.

2.4. The contractor shall be responsible for cleaning any residual fluids, dirt, and debris found to have leaked from the removed equipment for a period of 15 calendar days after removal.

File details come from the government source that posted it. Updated .