This is a Statement of Work (SOW) for Commercial Industrial Services (CIS) Scaffolding Services on USS John P. Murtha (LPD-26). The contract requires the contractor to provide all labor, services, equipment, and materials for on-load, assembly, certification, modification, disassembly, and offload of scaffolding and fall protection materials onboard the vessel. The contractor must supply all cranes necessary for the work, including floating cranes when required, with boom capacity sufficient to reach ships berthed second ship out. The contractor is responsible for providing all management, administrative services, rigging services, transportation, testing, utilities coordination, waste disposal, and environmental controls. Work must be completed within specified Milestone Events and Dates, including weekends and holidays, with normal working hours defined as 0600-1800 daily. The contractor must submit a Condition Found Report (CFR) within 24 hours of the milestone start date, pier laydown requests within 24 hours of Purchase Order receipt, and properly completed Work Authorization Forms (WAF) prior to work commencement.

The SOW requires extensive compliance with safety, environmental, and quality standards including OSHA 1915 (shipyard employment), Navy safety manuals (OPNAVINST 5100.23G), NAVSEA Standard Items (NSI 009-05, 009-11, 009-26, 009-32), and hazardous waste regulations. The contractor must conduct preliminary inspections, daily inspections of scaffolding and fall protection with certification by 0900 daily, and final contamination/damage inspections with zero allowable defects. The contractor is responsible for all waste disposal (hazardous and non-hazardous), cleanup, gas-freeing of spaces, and compliance with air emissions and solid waste regulations. Security requirements include submitting personnel information to the Security Management Office within five days of award, issuing employee identification cards, and for aircraft carrier work, verifying U.S. citizenship and RADCON training. The contractor must submit weekly progress reports, participate in daily/weekly progress meetings, provide critical lift plans for heavy crane operations, and submit invoice packages within 14 days of work completion including all supporting documentation.

View the file

Other files

File Type Posted
Amendment_0001.pdf PDF
26Q0045_SOW_PRN.pdf PDF
RFQ_26Q0045_rev1.pdf PDF
26Q0045_Itemized_Pricing_Sheet_rev1.xlsx XLSX spreadsheet
26Q0045_SOW_JPM.pdf PDF
26Q0045_RFC_rev1.docx DOCX document
26Q0045_RFC.docx DOCX document
26Q0045_Itemized_Pricing_Sheet.xlsx XLSX spreadsheet
26Q0045_SF18.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C: DESCRIPTIONS AND SPECIFICATIONS

STATEMENT OF WORK: COMMERCIAL INDUSTRIAL SERVICES (CIS)

SCAFFOLDING SERVICES CONTRACT FOR THE ON-LOAD, ASSEMBLY,

CERTIFICATION, MODIFICATION, DISASSEMBLY, AND OFFLOAD OF SCAFFOLDING

AND FALL PROTECTION MATERIALS ONBOARD

USS JOHN P. MURTHA (LPD-26)

PURPOSE:

The primary purpose of the Commercial Industrial Services (CIS) Scaffolding Services contract is to provide labor, services, equipment, and materials for the on-load, assembly, certification, modification, disassembly, and offload of scaffolding and fall protection materials onboard USS

John P. Murgha (LPD-26).

The effort required hereunder shall be performed in accordance with the Statement of Work (SOW contained in Section C herein, attachments, and references and in accordance with all other terms and conditions set forth herein.

C.1. REFERENCES:

C.1.1 The requirements of the following references and attachments shall be utilized in the execution of this contract unless otherwise stated herein. Whenever specifications, Naval Sea

Systems Command (NAVSEA) Standard Items (NSI), standards, drawings, publications or other documents undergo subsequent revisions, the Contractor shall use the latest revised version during contract execution. If future revisions result in a change to the Contractor’s price, the Contractor shall promptly notify the contract administration office of the revision details and the anticipated impact. The Administrative Contracting Officer (ACO) or Contracting Officer (KO) shall negotiate and incorporate the necessary changes via bilateral modification to the contract. When future revisions result in no change to the Contractor’s price, the Contractor shall utilize the latest version as soon as the change becomes known without a need for a contract modification.

(a) NAVSEA Standard Items

1. Category I NAVSEA STANDARD ITEMS (NSI) may be viewed on the internet at http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/. Category I NSI are automatically be invoked without further reference in the contract, the Statement of Work (SOW), the awarded Purchase Order(s), and modification(s) to the awarded Purchase Order.

2. Category II NAVSEA STANDARD ITEMS (NSI) may be viewed on the internet at http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/. The below listed

Category II NSI shall be invoked without further reference in the contract, the SOW, the awarded

Purchase Order(s), and modification(s) to the awarded Purchase Order. Other Category II NSI not http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/ http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/ listed below shall be specifically invoked in the individual awarded Purchase Order(s) and modification(s) to the awarded Purchase Order.

009-05 Temporary Access; accomplish

009-11 Insulation and Lagging Requirements; accomplish

009-26 Deck Covering; accomplish

009-32 Cleaning and Painting Requirements; accomplish

(b) OPNAVINST 5100.23G; Navy Safety and Occupational Health Program Manual

(c) Occupational Safety and Health Act (OSHA) of 1970

(d) Code of Federal Regulations (CFR) Title 29 Labor, Chapter XVII Occupational Safety and

Health Administration, Department of Labor, Part 1910 Occupational Safety and Health Standards

(e) CFR Title 29 Labor, Chapter XVII Occupational Safety and Health Administration, Department of Labor, Part 1915 Occupational Safety and Health Standards for Shipyard

Employment

(f) CFR Title 40 Protection of Environment, Chapter 1 Environmental Protection Agency, Subchapter C Air Programs, Part 63 National Emission Standards for Hazardous Air Pollutants for

Source Categories, Subpart II National Emission Standards for Shipbuilding and Ship Repair

(Surface Coating)

(g) CFR Title 40 Protection of Environment, Chapter 1 Environmental Protection Agency, Subchapter I Solid Wastes, Parts 260 through 273

(h) CFR Title 49 Transportation, Chapter 1 Pipeline and Hazardous Materials Safety, Administration, Department of Transportation, Parts 105 through 177

(i) United States Code (USC) Title 10 Armed Forces, Subtitle C, Part IV, Chapter 633, Section

7311, Repair or Maintenance of Naval Vessels: Handling of Hazardous Waste

(j) California Code of Regulations (CCR), Title 22, Div. 4.5, Environmental Health Standards

For the Management of Hazardous Waste. Online at https://oal.ca.gov/publications/ccr/

(k) National Fire Protection Association (NFPA) Standard 312, Standards for Fire Protection of

Vessels during Construction, Conversion, Repair and Lay-up. Online at https://www.nfpa.org/

(m) Resource Conservation and Recovery Act (RCRA) Laws and Regulations. Online at https://www.epa.gov/rcra

(n) Commander Fleet Forces Command Instruction (COMFLTFORCOMINST) 4790.3, Work

Authorization Form (WAF) https://www.epa.gov/rcra

(p) NAVSEA Standard Work Template 077-001, Hazardous Waste Produced on Naval Vessels;

control

(q) Naval Base San Diego Instruction 3170.1 Policy Governing Port Operations and Laydowns

(r) NAVFAC P-307, Management of Weight Handling Equipment.

(s) Base Support Vehicles and Equipment (BSVE) Standard Operating Procedure (SOP) # 11-2, Naval Base Coronado Contractor Crane Oversight Plan.

(t) BSVE SOP # 11-2, Naval Base San Diego Contractor Crane Oversight Plan

(u) BSVE SOP # 11-2, Naval Base Point Loma Contractor Crane Oversight Plan

(v) Current Southwest Region Maintenance Center (SWRMC) approved adhesive, paint and solvent lists.

(w) Systems and Specifications, SSPC Painting Manual Volume 1 and Volume 2

(x) S9086-CH-STM-010, Naval Ship’s Technical Manual (NSTM) Chapter 074 Volume 3; Gas

Free Engineering

(y) S9086-T8-STM-010, Naval Ship’s Technical Manual (NSTM) Chapter 593 Pollution Control

(z) Safe Work Practices for Marine Hanging Staging: an OSHA Guidance Document

C.1.2 If the contractor does not have copies of the referenced documents, technical manuals, military standards, procedures, and regulations etc., the Shipbuilding Specialist (SBS) must be notified so that copies can be disseminated.

C.1.3 Other documents not listed above may also be invoked, as required, for individual Purchase

Orders. Specific references for individual Purchase Orders shall be identified on each Purchase

Order and associated referenced technical documentation.

C.2 GENERAL REQUIREMENTS:

C.2.1 The quality of all services rendered shall conform to the highest standard in the relevant profession, trade or field of endeavor. Without additional expense to the Government, the

Contractor shall be responsible for obtaining any necessary insurance, licenses and permits, and for complying with all applicable laws, codes and regulations, in connection with the performance of the work. The Contractor is responsible for ensuring that proper safety and health precautions are taken to protect the workers and the property of others.

C.2.2 All work being performed in the Scaffolding Services contract shall be accomplished within the Milestone Events and Dates provided and in accordance with (IAW) the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase

Order, and references C.1.1.(a) through C.1.1.(z).

C.2.3 The Contractor shall provide all management, administrative services, materials, tools, equipment, labor, scaffolding services, rigging services, crane services, transportation, testing, utilities (i.e. air, water and electricity, etc.), and required services and support to accomplish the work under the Scaffolding Services contract IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and references

C.1.1.(a) through C.1.1.(z).

C.2.4 The Contractor shall provide all cranes necessary to accomplish the work under this contract, including floating cranes when required and cranes with a boom capacity great enough to reach ships berthed second ship out IAW the requirements of the contract, the SOW, the awarded

Purchase Order(s), modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z).

C.2.5 The Contractor may utilize government utilities (i.e. air, water, and electricity, etc.) available at the pier to accomplish the work specified in this contract. It is the Contractor’s responsibility to arrange for, coordinate with, meet the requirements of, and pay Naval Facilities Engineering

Command-Southwest (NAVFAC-SW) for use of government utilities.

C.2.6 The Contractor shall comply with the Occupational Safety and Health Standard for Shipyard

Employment (CFR, Title 29, Part 1915) promulgated under Public Law A85-742, Amended

Section 41 of the Longshoremen’s and Harbor Workers Compensation Act (33 U.S.C.942) and adopted by the Department of Labor as Occupational Safety and Regulations, for all work being performed under this contract on the navigable waters of the United States including any dry-dock or marine railway. Nothing contained in this contract or any Purchase Order there under shall be construed as relieving the Contractor from any obligation, which it may have for compliance with the aforesaid regulations IAW the requirements of the contract, the SOW, the awarded Purchase

Order(s) and awarded Purchase Order modification(s), and references C.1.1.(a) through C.1.1.(z).

C.2.7 The Contractor shall immediately notify the ACO and SBS verbally and in a submitted

Conditions Found report (CFR), written and electronic, of difficulties that may jeopardize the execution of work stated within the Milestone Events and Dates of the contract, the SOW, the awarded Purchase Order(s) and awarded Purchase Order modification(s), and references C.1.1.(a)

C.2.7.1 FALSE TRIP: The Contractor shall immediately notify the ACO and SBS verbally and in a submitted CFR, written and electronic, when the Maintenance Team and/or the SAR had delayed or stopped or cancelled or rescheduled the delivery, assembly, modifications, dismantle, and offload of the scaffolding and fall protection materials IAW the requirements of the contract, the SOW, the awarded Purchase Order(s) and awarded Purchase Order modification(s), and references C.1.1.(a) through C.1.1.(z)..

C.2.7.2 FALSE TRIP: The SBS shall verify that the Contractor has on-site the scaffolding and fall protection materials and personnel to perform the delivery, assembly, modifications, dismantle, and offload of the scaffolding and fall protection materials

C.2.8 The Government shall not be responsible for work delays or stoppages caused by the

Contractor’s failure to comply with registration, security, and access requirements. Similarly, the

Government shall monitor and take appropriate action against contractors who repeatedly or egregiously violate access control requirements.

C.2.9 The Contractor shall complete the work requirement specified in this contract within the

Milestone Events and Dates provided in the SOW, the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order which includes weekends and holidays. Work may be required outside normal working hours. Normal working hours are defined as between 0600 and 1800, Sunday through Saturday.

C.2.10 Prior to staring any work in this contract and the awarded Purchase Order and modification(s) to the awarded Purchase Order, the Contractor shall notify the Ship’s Authorized

Representative (SAR) of the equipment and systems that require isolation so that tag outs can be accomplished as required.

C.2.11 The Contractor shall accomplish a complete tag-out of the equipment and the affected systems prior to the execution of work stated IAW the requirements of the contract, the SOW, the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order, and references

C.1.1.(a) through C.1.1.(z).

C.2.11.1 The Contractor shall follow procedures for system tag-out IAW the requirements of the

Order, and references C.1.1.(a) through C.1.1.(z), including NSI 009-24.

C.2.12 The Contractor shall notify the SAR immediately when all work stated in the contract, the

SOW, the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order is completed and the system is ready for activation and removal of tags.

C.2.13 The Contractor shall coordinate schedules of work-affected areas with the other contractors and the SAR daily at the beginning of each shift.

C.2.14 The Contractor shall submit a Test and Inspection Plan (TIP), Production Schedule Status

Report, and a Quality Control Inspector (QCI) listing customized to the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order IAW the requirements of the contract, the

SOW, the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z).

C.2.14.1 The TIP, Production Schedule Status Report, and QCI listing and shall be submitted to the SBS and Quality Assurance Specialist (QAS) no later than 1 day prior to the start of productive work under the awarded Purchase Order and modification(s) to the awarded Purchase Order under this contract.

C.2.15 The Contractor is encouraged to attend ship checks as specified by the SBS to identify the work requirement, Milestone Events and Dates, and other pertinent information. The Contractor shall immediately notify the SBS if the Contractor shall be delayed or shall be unable to attend the ship check.

C.2.16 The Contractor shall be responsible for the removal of all interferences necessary to accomplish the work specified in the contract IAW the requirements of the contract, the SOW, awarded Purchase Order(s) and modification(s) to the awarded Purchase Order, and references

C.1.1.(a) through C.1.1.(z) including NSI 009-23.

C.2.16.1 The Contractor shall reinstall all previously removed interferences/equipment upon completion of the work specified in the in the contract IAW the requirements of the contract, the

SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z) including NSI 009-23.

C.2.17 The Contractor shall ensure required engineering controls are installed to prevent environmental pollutant discharges from work areas and safety boundaries are in place prior to the start of productive work IAW the requirements of the contract, the SOW, the awarded Purchase

Order(s) modification(s) to the awarded Purchase Order, and references C.1.1.(a) through

C.1.1.(z).

C.2.18 Nothing in this contract shall relieve the Contractor from complying with applicable federal, state and local laws, codes, ordinances and regulations, including, but not limited to obtaining of licenses and permits, in connection with the use of hazardous material and the generation of hazardous waste in the performance of this contract.

C.2.19 The Contractor shall comply with applicable federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

C.3 SCOPE OF WORK:

C.3.1 Within 24 hours of the Milestone Events and Dates provided, the Contractor shall submit one legible copy, in hard copy or electronic media, a Condition Found Report (CFR) to the SBS identifying discrepancies associated with the equipment/areas specified in the awarded Purchase

Order(s) and modification(s) to the awarded Purchase Order. The Contractor shall be responsible for discrepancies or damages not noted in the initial CFR.

C.3.2 The Contractor shall submit one legible copy, in hard copy or electronic media, of subsequent CFR’s identifying discrepancies or damages associated with the description of work to the SBS within 4 hours of discovering such discrepancies or damages.

C.3.3 Within 24 hours after receipt of the awarded Purchase Order(s) and/or modification(s) to the awarded Purchase Order, the Contractor shall submit Pier Laydown request to the CIS SBS IAW the requirements of the contract, the SOW, the awarded Purchase Orders, modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z), specifically reference (q).

C.3.4 Prior to the start of work under each awarded Purchase Order and/or modification(s) to the awarded Purchase Order, the Contractor shall ensure that the required Work Authorization Form

(WAF) is properly filled out and authorized IAW the ships WAF Program and specifically reference C.1.1.(n). The authorized WAF shall be posted at the primary and secondary entrances to the location of work. In the event the ship does not have an established WAF program, the

Contractor shall provide the necessary documents to the SAR.

C.3.5 For work on Aircraft Carriers, the Contractor shall submit WAFs in sufficient detail so that the ship can provide proper work area isolation. The Contractor shall initiate WAFs in the

Information Management System (IMS). Computer terminals shall be made available by Newport

News Shipbuilding (NNS) for maintenance providers to enter WAFs directly into this system.

Once the WAF is entered in IMS, the Contractor shall print the WAF, sign the WAF and submit the WAF to the Work Test Control/Maintenance Support Center (WTC/MSC) on the ship for processing and authorization. The Contractor shall be responsible for updating status of the WAF in IMS as work is authorized and completed.

C.3.5.1 The Contractor shall establish an account in Electronic-Systems Operations Management

System (E-SOMS) in order to produce an Electronic Work Authorization Form (E-WAF) to obtain ship force departmental concurrences via routing on the vessel. Typical routing for ship’s force departmental concurrences requires at least 3 days.

C.3.6 The Contractor shall be responsible for the cleanup of any spills and/or mitigation of hazards associated with the work being performed hereunder, from the ship and from the Naval Facility

IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z).

C.3.7 The Contractor shall be responsible for the disposal of all liquid wastes, solid waste, hazardous wastes, and non-hazardous wastes, dust, and debris generated in the performance of the

Scaffolding Services contract IAW the requirements of the contract, the SOW, the awarded

C.3.8 The Contractor shall be responsible for the cleanliness of the locations listed in the awarded

Purchase Order(s) modification(s) to the awarded Purchase Order to include adjacent locations that may be affected by the Scaffolding Services contract. All waste generated by the Contractor shall be removed from the ship as required and at the end of each shift.

C.3.9 The Contractor shall be responsible to gas free the space(s) IAW the requirements of the contract, the SOW, the awarded Purchase Orders, modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z). The Contractor shall provide gas-free certification and maintain certification IAW 29 Code of Federal Regulations Part 1915. The Contractor shall post the gas free certificate on the job site during the entire performance period.

C.4 INSPECTION PROCEDURES:

C.4.1 (I) Inspections require verification and documentation by a separate individual, other than the person who has accomplished the work, who is qualified as an inspector and currently certified where required by the technical documents (e.g., NAVSEA Basic Paint Inspector {NBPI}, National Association of Corrosion Engineers {NACE}, non-destructive testing, electrical cableway inspections, etc.).

C.4.2 (V) Inspections require verification and documentation by the qualified tradesperson, trade supervisor, or inspector.

C.4.3 (G) A symbol inserted in a work item to establish a point in the sequence of accomplishment of work at which time the SBS shall be notified by the prime contractor in all cases to permit observation of a specific test or inspection (I) (V) by the government.

C.4.4 For (G) checkpoints scheduled during normal working hours, the Contractor shall notify the

SBS of checkpoints via electronic method. Notification shall be at least two hours, but not more than one working day, prior to commencing the specific checkpoint requirements annotated with the symbol (G). Normal working hours are defined as between 0600 and 1800, Sunday through

Saturday.

C.4.4 1 For cancellation of (G) checkpoints scheduled during normal working hours, the

Contractor shall notify the SBS for cancellation of the scheduled test or inspection as soon as known, but no later than one hour prior to the scheduled check point.

C.4.5 For (G) checkpoints scheduled after normal working hours, on a weekend, or on a federal holiday, the Contractor shall notify the SBS of checkpoints via electronic method. Notification shall be no later than four hours before the end of the last preceding day shift prior to commencing the specific checkpoint requirements annotated with the symbol (G). Normal working hours are defined as between 0600 and 1800, Sunday through Saturday.

C.4.5.1 For cancellation of (G) checkpoints scheduled after normal working hours, on a weekend, or a federal holiday, the Contractor shall notify the SBS to cancel a scheduled test or inspection as soon as known, but no later than two hours prior to the scheduled check point.

C.5 SCAFFOLDING/FALL PROTECTION: ON-LOAD AND ASSEMBLY, DAILY

INSPECTION, AND CERTIFICATION:

(I)(V) CHECKPOINT: Preliminary Inspection

C.5.1 The Contractor shall conduct a preliminary inspection of the locations listed in the Purchase

Order and modification(s) to the awarded Purchase Order to include adjacent compartments to determine readiness for on-load and assembly of scaffolding and fall protection materials IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z).

C.5.1.1 The preliminary inspection shall include adjacent locations that may be affected by the on-load and assembly of scaffolding and fall protection materials IAW the requirements of the

C.5.2 Prior to the assembly of scaffolding and fall protection, the Contractor shall inspect the mast, antennas, yardarms, decks, bulkheads, and other equipment in and around the areas were scaffolding and fall protection shall be assembled for existing damages and defects.

C.5.3 The Contractor shall submit one legible copy, in hard copy or approved transferrable media, of a CFR detailing the results of the requirement of paragraphs C.5.1, C.5.1.1, and C.5.2 to the

SBS. The Contractor shall be responsible for discrepancies or damages not noted in the CFR submitted.

C.5.4 The Contractor shall complete the on-load and assemble the scaffolding and fall protection materials at the locations listed in the awarded Purchase Order(s) IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase

Order, and references C.1.1.(a) through C.1.1.(z) and within the Milestone Events and Dates provided in the awarded Purchase Order(s) or ), modification(s) to the awarded Purchase Order.

C.5.5 The contractor shall install shrink wrap, when required, at the locations listed in the awarded

Purchase Order IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and references C.1.1.(a) through C.1.1.(z).

C.5.6 The Contractor shall remove from the ship any and all scaffolding and fall protection materials and accessories not used in the assembly of the scaffolding and fall protection called out in the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order.

(I)(V) CHECK POINT (On-load and assembly, inspection, and certification)

C.5.7 The Contractor, after the assembly of the scaffolding and fall protection materials and/or shrink wrap at the locations listed in the awarded Purchase Order, shall perform an inspection and certification that the assembled scaffolding and fall protection and/or shrink wrap is complete and ready to use IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), C.5.8 The inspection and certification of the assembled scaffolding and fall protection materials shall be documented on the “Scaffolding/Fall Protection Inspection Tag(s)”. The

“Scaffolding/Fall Protection Inspection Tag(s)” shall be affixed within the vicinity of all access locations.

NOTE: The “Scaffolding/Fall Protection Inspection Tag(s)” shall be legibly completed including the date and time of the inspection and certification.

C.5.9 The Contractor shall submit one legible copy, in hard copy or approved transferrable media, of a CFR detailing the results of the requirement of paragraphs C.5.4, C.5.5, C.5.6, C.5.7, and

C.5.8 to the SBS. The Contractor shall be responsible for discrepancies or damages not noted in the CFR submitted.

(I)(V) CHECK POINT (Daily Inspection)

C.5.10 The Contractor shall perform a daily inspection of the assembled scaffolding and fall protection and/or shrink wrap at the locations listed in the Purchase Order and modification(s) to the awarded Purchase Order certifying that the assembled scaffolding and fall protection and/or shrink wrap is complete, in satisfactory condition, and ready for use IAW the requirements of the

C.5.10.1 The daily certification and inspection of the assembled scaffolding and fall protection and/or shrink wrap at the locations listed in the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order shall be completed daily no later than 0900.

C.5.10.2 The date and time of the inspection and certification of the assembled scaffolding and fall protection materials shall be documented on the “Scaffolding Inspection Tag(s)”. The

Scaffolding/Fall Protection Inspection Tag(s) shall be affixed within the vicinity of all access locations.

the date and time of the inspection and certification.

C.5.11 The Contractor shall maintain the assembled scaffolding and fall protection and/or shrink wrap at the locations listed in the awarded Purchase Order(s) and modification(s) to the awarded

Purchase Order in a safe, serviceable, and secured condition. The Contractor shall replace any defective component of the assembled scaffolding and fall protection and/or shrink wrap.

C.6 SCAFFOLDING/FALL PROTECTION: MODIFICATION, DAILY INSPECTION

AND CERTIFICATION:

C.6.1 When the assembled scaffolding and fall protection and/or shrink wrap at the locations listed in the awarded Purchase Order(s) is altered or modified, the Contractor, shall perform an inspection of the altered or modified scaffolding and fall protection and shrink wrap, certifying that the altered or modified assembled scaffolding and fall protection and/or shrink wrap is complete, in a satisfactory condition, and ready for use IAW the requirements of the contract, the

C.6.1.1 The Contractor shall remove from the ship any and all scaffolding and fall protection materials and accessories not used in the alteration or modification of the assembled scaffolding and fall protection called out in the awarded Purchase Order(s) or modification(s) to the awarded

Purchase Order.

C.6.2 The inspection and certification of the altered or modified scaffolding and fall protection materials at the locations listed in the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order shall be completed no later than 2 hours after the modification or alteration was completed.

C.6.2.1 The date and time of the inspection and certification of the altered or modified scaffolding and fall protection materials shall be documented on the “Scaffolding/Fall Protection Inspection

Tag(s)”. The “Scaffolding/Fall Protection Inspection Tag(s)” shall be affixed within the vicinity of all access locations.

the date and time of the inspection and certification

(I)(V) CHECK POINT (Daily Inspection)

C.6.3 The Contractor shall perform a daily inspection of the assembled, altered, or modified scaffolding and fall protection and/or shrink wrap at the locations listed in the Purchase Order, certifying that the assembled scaffolding and fall protection and/or shrink wrap is complete, in a satisfactory condition, and ready for use IAW the requirements of the contract, the SOW, the awarded Purchase Orders, modification(s) to the awarded Purchase Order, and references C.1.1.(a)

C.6.3.1 The daily certification and inspection of the assembled, altered or modified scaffolding and fall protection and/or shrink wrap at the locations listed in the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order shall be completed daily no later than 0900.

C.6.3.2 The date and time of the inspection and certification of the assembled, altered or modified scaffolding and fall protection materials shall be documented on the “Scaffolding/Fall Protection

Inspection Tag(s)”. The “Scaffolding/Fall Protection Inspection Tag(s)” shall be affixed within the vicinity of all access locations.

C.6.4 The Contractor shall submit one legible copy, in hard copy or approved transferrable media, of a CFR detailing the results of the requirement of paragraphs C.6.1, C.6.2, C.6.3, 6.3.1, and

C.6.3.2 to the SBS. The Contractor shall be responsible for discrepancies or damages not noted in the CFR submitted.

C.6.5 The Contractor shall maintain the assembled, altered, or modified scaffolding and fall protection and/or shrink wrap at the locations listed in the awarded Purchase Order(s) and modification(s) to the awarded Purchase Order in a safe, serviceable, and secured condition. The

Contractor shall replace any defective component of the assembled, altered, or modified scaffolding and fall protection and/or shrink wrap.

C.7 SCAFFOLDING/FALL PROTECTION: DISASSEMBLY AND OFFLOAD:

C.7.1 Prior to the disassembly of scaffolding and fall protection at the locations listed in the

Purchase Order and modification(s) to the awarded Purchase Order the Contractor shall inspect the mast, antennas, yardarms, decks, and bulkheads, and other equipment and adjacent areas were scaffolding and fall protection was assembled. The Contractor shall inspect for new damages and defects not identified under C.5.3.

C.7.2 The Contractor shall complete the disassembly and offload of the scaffolding and fall protection materials at the locations listed in the Purchase Order IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase

Order, and references C.1.1.(a) through C.1.1.(z) and within the Milestone Events and Dates provided in the Purchase Order or as directed by the Government.

C.8 COMPLETION OF WORK:

(V)(G) CHECK POINT: Final Contamination/Damage Inspection

C.8.1 The Contractor shall accomplish an inspection of the locations listed in the Purchase Order and modification(s) to the awarded Purchase Order ensuring the disassembly and offload of all scaffolding and fall protection materials IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and references

C.1.1.(a) through C.1.1.(z). The Contractor shall be responsible for discrepancies or damages not noted in the CFR submitted in C.5.3. Allowable defects: NONE

C.8.2 The Contractor shall accomplish an inspection of the adjacent compartments that maybe by the on-load and assembly of scaffolding and fall protection materials IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase

Order, and references C.1.1.(a) through C.1.1.(z). The Contractor shall be responsible for discrepancies or damages not noted in the CFR submitted in C.5.3. Allowable defects: NONE

C.8.3 The Contractor shall submit one legible copy, in hard copy or approved transferrable media, of a CFR detailing the results of the requirement of paragraphs C.8.1 and C.8.2 to the SBS.

C.9 DELAYS AND DISRUPTIONS:

C.9.1 The Contractor shall coordinate his work efforts on a daily basis with the SAR to schedule his work to avoid delays and disruptions. More than one Contractor working in the same area is a normal condition encountered during ship repair periods. Delays caused by these events shall be at no cost to the Government.

C.9.2 Drills, shifting of berths and piers, repositioning of the ship, inspections, serving of meals, official ceremonies, additional security requirements, operation of equipment and scheduled meetings are to be considered normal evolutions to be encountered when working on board naval installations and vessels rather than unusual occurrences. Delays caused by these events shall be at no cost to the Government.

C9.3 The Contractor shall be responsible for relocation of all Contractor Furnished Equipment

(CFE) in the event of berth shifts, pier shifts, repositioning of the ship and outboard another vessel.

C.10 PROGRESS MEETINGS/REPORTS:

C.10.1 The Contractor shall participate in daily or weekly progress meeting(s) as required by the

SAR, Maintenance Team, and the SBS. The Contractor shall provide a weekly progress report of all active and completed Purchase Orders (completed within 30 days of the date of report) to the

SBS, on Monday or the first business day of each week, no later than 0800.

C.10.2 For work on Aircraft Carriers, the Contractor shall also submit all initial production schedules to Newport News Shipbuilding (NNS) via SWRMC Code 350, for integration into the topside schedule. Initial schedules shall be submitted no later than 3 business days prior to the start of the Period of Performance. Production schedules shall be developed in Microsoft Project

2000 (minimum). The production schedules shall be revised/updated on a weekly basis. Weekly updates shall be submitted to NNS no later than 1200 Thursday. On the occasion that a Federal

Holiday lands on a Thursday the weekly updates shall be submitted to NNS no later than 1200 on the Wednesday preceding the Thursday Holiday.

C.10.3 The Contractor shall be prepared to address all facets of the work including but not limited to schedule and/or problems with the ongoing work and the proposed actions to be taken to resolve these problems.

C.11 DELIVERY OF SERVICE:

C.11.1 The Contractor shall commence work on this contract, within the Milestone Events and

Dates provided. The Contractor shall complete the work requirement within the Milestone Events and Dates provided, which includes weekends and holidays IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), modification(s) to the awarded Purchase Order, and

C.11.2 The Contractor shall provide a weekly progress report of all active and completed Purchase

Order (completed within 30 days of the date of report) to the SBS, on Monday or the first business day of each week, no later than 0800.

C.11.3 The Scaffolding Services to be performed for the on-load, assembly, certification, modification, disassembly, and offload of scaffolding and fall protection materials shall be completed within the Milestone Events and Dates provided in the awarded Purchase Order(s) and/or modification(s) to the awarded Purchase Order, except that when the need of the

Government permits, the Purchase Order may provide a longer time of delivery.

C.12 SECURITY REQUIREMENTS:

C.12.1 The Contractor shall submit a list providing security information to the SWRMC Security

Management Office via e-mail at swrmc.security.var.fct@navy.mil no later than five days after the contract award date. The data shall include a listing of all Contractor personnel supporting the contract effort, employee numbers, addresses, citizenship, level of clearance and radiological controls indoctrination (RADCON) training documents (for CVN contracted work only). The

Contractor shall submit a new list whenever there is any change in the security information listing.

C.12.2 The Contractor shall issue each employee an identification card containing the employee's picture, which shall be utilized for positive identification. The card shall be worn in a visible location when employee is on Government property. For additional identification, the Contractor’s employee shall also display visible representation of the company name or logo.

C.12.3 For work on aircraft carriers, access to the ship shall only be granted to Contractor employees who are United States citizens and have received RADCON training prior to the start of work on the Purchase Order or modification(s) to the awarded Purchase Order.

C.12.4 The contractor shall submit the DBIDS documents to the SWRMC Security Management

Office via e-mail at swrmc.security.var.fct@navy.mil for review and forwarding to the Naval Base

San Diego Pass and ID for processing and approval. The Contractor shall submit new DBIDS documents whenever there is any change in the information submitted.

https://www.cnic.navy.mil/om/dbids.html

C.13 HAZARDOUS WASTE:

https://www.cnic.navy.mil/om/dbids.html

C.13.1 The Contractor shall be responsible for the disposal of all liquid wastes, solid waste, hazardous wastes, and non-hazardous wastes, dust, and debris generated in the performance of the

Scaffolding Services contract IAW the requirements of the contract, the SOW, the awarded

C.13.1.1 All waste generated that is deemed non-hazardous or non-hazardous after laboratory testing shall be removed from the pier daily and shall not be allowed to accumulate. All waste generated, hazardous or non-hazardous, shall be removed from the pier later than the last day of the specified Milestone Events and Dates.

C.13.2 The Contractor shall submit a copy of all reports of chemical analysis or other documents evidencing identification of the hazardous waste to SWRMC Environmental Department Code

106B no later than 2 business days after completion work in the awarded Purchase Order(s) or

C.13.3 The analysis of any waste requiring the services of a testing laboratory (e.g., liquids, used cleaning solvent material) shall be performed by a laboratory certified by National Voluntary

Laboratory Accreditation Program (NVLAP) or by a laboratory certified by the California State

Department of Health Services to be competent and equipped to conduct the specific type of analysis to be performed.

C.13.4 The Contractor shall comply with the requirements of NAVSEA Standard Work Template

077-001 Hazardous Waste Produced on Naval Vessels; control IAW the requirements of the

C.13.5 The Contractor shall be responsible for the disposal of all liquid wastes, solid waste, hazardous wastes, and non-hazardous wastes, dust, and debris generated in the Scaffolding

Services contract IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), C.13.6 All waste generated shall be properly and legally disposed of in accordance with all applicable State, Local, and Federal Regulations and IAW the requirements of the contract, the

C.13.7 The Contractor shall provide covered containers, offload, transportation, and disposal of solids waste, liquid waste, hazardous waste, non-hazardous waste, dust and debris generated in the performance of this contract, to meet Clean Air Act, Clean Water Act and Hazardous Waste

Regulations.

C.13.7.1 Trucks intended for hauling hazardous waste shall be state certified and licensed for transporting hazardous waste. Contractor shall manifest all hazardous waste using site specific

Environmental Protection Agency (EPA) generated Identification (ID) number.

C.13.8 The Contractor shall submit one legible copy, in hard copy or approved transferrable media of the hazardous waste manifest form signed by the owner or operator of the disposal facility to the supervisor within 48 hours of receipt from owner or operator of disposal facility IAW the

C.13.9 The Contractor shall submit emission inventory, Hazardous Waste Manifest Form to

SWRMC Code 106-B Environmental Dept. upon completion of this contract.

C.13.10 The Contractor shall comply with Federal Emergency Planning Community Right to know Act (EPCRA) and permit conditions for all APCD permitted equipment during all cleaning evolutions. Submit one completed copy of each report to SWRMC Code 106-B, Environmental

Department IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), C.13.11 The Contractor shall comply with the San Diego County Air Pollution Control District

(APCD) rules or the most current APCD asbestos regulations, 40CFR61, Subpart M and the EPA

Clean Air Act Applicability Determination Index. Provide one copy of each original written notification, all revised notifications and all written and electronic communications submitted to the APCD to the Supervisor Code 106 Environmental Manager prior to the start of work.

C.14 STANDARDS OF WORKMANSHIP:

C.14.1 The quality of all services rendered hereunder shall conform to the highest standards in the relevant profession, trade or field of endeavor. All services shall be rendered by or supervised directly by individuals fully qualified in the relevant profession, trade, or field, and holding any licenses required by law.

C.14.2 None of the services required by this contract shall be subcontracted to or performed by persons other than the Contractor or the Contractor’s employees without the prior approval of the

Contracting Officer.

C.15 BILLING/INVOICING:

C.15.1 At the time of billing/invoicing, the Contractor shall submit one hard copy and one electronic copy of the invoice package containing all of the information, documents, and reports compiled during the performance of the work required on the awarded Purchase Order(s) or

C.15.2 The invoice package shall include the awarded Purchase Order, modification(s) to the awarded Purchase Order, CFR, TIP, Production Schedule, WAF, check points, Laboratory test results, Gas Free certificates, chemical analysis report, Hazardous Waste Manifest Forms, and other information, documents, and reports compiled during the performance of the work IAW the

C.15.3 The Contractor shall submit the hard copy and electronic copy of the invoice package to the Government no later than 14 days after completion of the work required under each awarded

Purchase Order(s) and modification(s) to the awarded Purchase Order.

C.16 GOVERNMENT FURNISHED MATERIAL (GFM):

NONE.

C.17 CONTRACTOR FURNISHED EQUIPMENT (CFE):

C.17.1 The Contractor shall furnish all necessary materials, tools, and equipment to perform work required by this contract IAW the requirements of the contract, the SOW, the awarded Purchase

Order(s), modification(s) to the awarded Purchase Order, and references C.1.1.(a) through

C.1.1.(z).

C.17.2 The Contractor shall be responsible for maintaining all Contractor Furnished Equipment

(CFE). The CFE shall be properly calibrated, tested and in an optimal condition of readiness to perform the work required by this contract and avoid impacting the performance requirements of this contract IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), C.17.3 The Contractor shall ensure all CFE are located neatly out of walk ways and shall not pose a trip hazard IAW the requirements of the contract, the SOW, the awarded Purchase Order(s), C.17.4 All Contractor personnel and equipment must be licensed/registered/certified to operate/maintain/service all equipment involved in the performance of the requirements of this contract.

C.17.5 The Contractor shall submit all required permits to SWRMC Code 106-B for all Contractor owned or rental equipment prior to start of work.

C.18 NON-NAVY OWNED CRANES:

C.18.1 The Contractor shall adhere to and follow the requirements of references C.1.1.(a), C.1.1.(r), C.1.1.(s), C.1.1.(t), and C.1.1.(u). The following is a list of minimum requirements that

Contractors shall comply with for all awarded Purchase Order(s) and modification(s) to the awarded Purchase Order that may result in the use of a crane for the accomplishment of work.

C.18.2 The Contractor shall notify the Contracting officer, in advance, of the intent of bringing a non-Navy owned crane onto a Navy shore installation. All entries shall be through a prearranged entry point IAW references C.1.1.(a), C.1.1.(r), C.1.1.(s), C.1.1.(t), and C.1.1.(u) as applicable.

C.18.3 The Contractor shall comply with the applicable American Society of Mechanical

Engineers (ASME) standards (e.g., B30.5 for mobile cranes, B30.22 for articulating boom cranes, B30.3 for construction tower cranes, and B30.8 for floating cranes). For barge mounted mobile cranes, a load indicating device, a wind indicating device, and a marine type list indicator readable in one-half degree increments are required. In addition, the Contractor shall comply with specific naval crane safety and operation regulations/standards specifically required by the Navy shore installation and state or local Government.

C.18.4 The Contractor shall certify that the crane and rigging gear meets the requirements of

OSHA 29 CFR Part 1915 – Occupational Safety and Health Standards for Shipyard Employment by providing a Certificate of Compliance. The Certificate of Compliance shall comply with can be downloaded from the NAVFAC Naval Crane Center website, https://www.navfac.navy.mil/navfac_worldwide/specialty_centers/ncc/about_us/resources/p307/ p307_forms.html.

C.18.5 The Contractor shall also certify that all of its crane operators working in the naval activity have been trained not to bypass safety devices (e.g., anti-two block devices) during lifting operations. The Certification of Compliance form shall be posted on the crane. For mobile cranes with original equipment manufacturer (OEM) rated capacities of 50,000 pounds or greater, the crane operators shall be designated as qualified by a source that qualifies crane operators (i.e., union, a Government agency, or an organization that tests and qualifies crane operators). Proof of current qualification shall be provided. The Contractor shall certify that the crane operator is qualified and trained for the operation of the crane to be used.

C.18.6 The Contractor shall provide a critical lift plan to NAVFAC for concurrence prior to the lift IAW references C.1.1.(a), C.1.1.(r), C.1.1.(s), C.1.1.(t), and C.1.1.(u). For each of the following lifts: lifts over 75 percent of the capacity of the crane or hoist (lifts over 50 percent of the capacity of a barge mounted mobile crane’s hoists) at any radius of lift; lifts involving more than one crane or hoist; lifts of personnel; and lifts involving non-routine rigging or operation, sensitive equipment, or unusual safety risks. The plan shall include the following as applicable:

C.18.6.1 The size and weight of the load to be lifted, including crane and rigging components that add to the weight. The OEM's maximum load capacities for the entire range of the lift shall also be provided. The lift geometry, including the crane position, boom length and angle, height of lift, and radius for the entire range of the lift. This applies to both single and tandem crane lifts. A rigging plan, showing the lift points, rigging gear, and rigging procedures. The environmental conditions under which lift operations are to be stopped.

C.18.7 For barge mounted mobile cranes, barge stability calculations identifying barge list and trim based on anticipated loading; and load charts based on calculated lists and trim. The amount https://www.navfac.navy.mil/navfac_worldwide/specialty_centers/ncc/about_us/resources/p307/p307_forms.html https://www.navfac.navy.mil/navfac_worldwide/specialty_centers/ncc/about_us/resources/p307/p307_forms.html of list and trim shall be within the crane manufacturer’s requirements.

C.18.8 The Contractor shall notify the Contracting officer as soon as practicable, but no later than four hours after any weight handling equipment (WHE) accident. The Contractor shall investigate and report all accidents IAW reference C.1.1.(k), Section 12.

C.19 CONTRACTING ADDITIONAL WORK:

C.19.1 The following procedure shall be used to order additional work (any work related to the

Scaffolding Services that is not covered by a fixed price line item) which is necessary to satisfactorily complete any Scaffolding services under this contract. Such over and above work may be called for by the issuance of a Purchase Order modification, by the Contracting Officer

(KO), during the term of the contract. Any work not covered in the basic scope of work shall be solicited and competed as a new requirement.

C.19.2 During the course of work under other fixed price contract line items, the contractor shall promptly recommend to the KO, in writing, additional work as the contractor discovers the need for such work. Concurrently, the contractor shall quote a price and delivery time for the additional work. The KO shall promptly review the recommendation and may, after reaching agreement with the contractor, issue a Purchase Order modification. The Government has no obligation under this paragraph to issue any Purchase Order modification.

C.19.3 Government requirements for the additional work shall be issued as Purchase Order modifications under this contract by the KO. The KO shall negotiate a firm fixed amount of man-hours and material dollars with the contractor. The price of the Purchase Order modification for the additional work shall be based on negotiated man hours multiplied by the hourly rate bid for the additional work in Section B, plus negotiated material dollars and handling fee.

C.19.3.1 In negotiating the fixed price for materials, the contractor shall submit quotes or invoices for the material required. The negotiated price for materials on undisclosed work shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government shall not pay any material handling charges under material items. Any material handling charges incurred by the contractor should be included as a factor in the hourly rate for additional work.

C.19.3.2. In negotiating a fixed number of man hours for additional work, the contractor’s proposal shall include quality assurance, engineering and supervision…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .