26Q0027 - Attachment A SOW.pdf

PDF 612 KB Posted

Attached to
NEC-HVAC System Preventive Maintenance (PMSC)
Solicitation number
19PM0726Q0027
Issued by

About this file

This is a Statement of Work (SOW) for preventive maintenance services for Non-CAA Screw Chiller, Air Handler Units, and Cooling Towers at the United States Embassy in Panama City.

The contractor must maintain all specified HVAC systems in safe, reliable, and efficient operating condition. The contract is firm fixed price, payable entirely in US dollars, with no adjustment for material, equipment, labor cost escalations or currency exchange rate fluctuations. The contractor shall provide trained and qualified technicians, all necessary tools, consumable materials, and supplies including filters, belts, hoses, oils, chemicals, coolant, grease, sealant, thermostats, fuses, personal protective equipment, and MSDS documentation. Preventive maintenance tasks are defined in Exhibit A and include quarterly and annual procedures for two YORK 410-ton chillers, two EVAPCO 500-ton cooling towers, three centrifugal pumps, a water treatment control system, and eleven air handling units ranging from 3 to 40 horsepower. The contractor must inventory expendable parts on-site and maintain manufacturer O&M binders at the post. Hardware replacements and repairs of electronic/electrical components require Contracting Officer's Representative (COR) approval prior to installation. The contract excludes major equipment repairs and component replacements such as bearings, pistons, gears, and crankshafts, which will be separately priced. Contractor personnel require security clearance and pre-approval, with names and biographic data submitted within 30 days of award. Public liability insurance must include minimum coverage of $100,000 per occurrence and $150,000 cumulative for both property damage and bodily injury, plus worker's compensation insurance as required under local law. The performance standard permits no more than one customer complaint per month. Deliverables include personnel security information within 30 days of award, certificate of insurance, signed PM checklists after each maintenance service, and invoices following completion of services.

View the file

Other files

File Type Posted
26Q0027 - Cover page.pdf PDF
26Q0027 - Invitation letter.pdf PDF
26Q0027 - Attachment to SF1449.pdf PDF
26Q0027 - Attachment B C-SCRM Questionnaire.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR

PREVENTIVE MAINTENANCE SERVICE CONTRACT

NEC-HVAC System Preventive Maintenance (PMSC)

United States Embassy at Panama City

American Embassy Panama UNCLASSIFIED

U.S. Department of State

TABLE OF CONTENTS

Section Page

1. DESCRIPTION

2. EQUIPMENT AND PERFORMANCE REQUIREMENTS

3. ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT

4. SCHEDULED PREVENTIVE MAINTENANCE

5. PERSONNEL, TOOLS, CONSUMABLE MATERIALS AND SUPPLIES

6. SOFTWARE, LICENSES AND PASSWORDS

7. DELIVERABLES

8. INSURANCE REQUIREMENTS

9. LOCAL LAW REGISTRATION

10. QUALITY ASSURANCE PLAN (QAP)

11. TRANSITIONS/CONTACTS

Attachments:

Exhibit A – Equipment and Checklist.

1. DESCRIPTION

The American Embassy Panama City requires preventive maintenance services for Non-CAA

Screw Chiller, Air Handler Units and Cooling towers. These services shall result in all systems being serviced under this agreement being in good operational condition when activated.

1.1. Type of Contract

This is a firm fixed price contract payable entirely in US Dollar. Prices for all Contract Line-Item

Numbers (CLIN) shall include proper disposal of toxic substances as per Item 8.4 where applicable. No additional sums will be payable for any escalation in the cost of materials, equipment, or labor, or because of the contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results required. The contract price will not be adjusted due to fluctuations in currency exchange rates.

2. EQUIPMENT AND PERFORMANCE REQUIREMENTS

4.1. The U.S Embassy in Panama requires the Contractor to maintain the following equipment in a safe, reliable, and efficient operating condition. Please see equipment list included in Exhibit A for a more detailed description.

1. Equipment Description

See Attachment Exhibit A

4.2. The Contractor shall provide all necessary managerial, administrative and direct labor personnel, as well as all transportation, equipment, tools, supplies and materials required to perform inspection, maintenance, and component replacement as required to maintain the systems in accordance with this work statement. Under this Contract the Contractor shall provide:

• The services of trained and qualified technicians to inspect, adjust, and perform scheduled preventive maintenance.

4.3. Performance Standards

The air handling units shall be clean and in good operating condition upon completion of the service. The preventive maintenance service shall result in the parts of the system serviced being in a condition to operate efficiently and effectively.

3. ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT

3.1 General. The Contractor shall designate a representative who shall supervise the Contractor’s technicians and be the Contractor’s liaison with the American Embassy Panama City. The

Contractor’s employees shall be on-site only for contractual duties and not for any other business or purpose. Contractor employees will be given access to the equipment and equipment areas and will be escorted by Embassy personnel.

3.2 Personnel Security. The Government reserves the right to deny access to U.S.-owned and

U.S.-operated facilities to any individual. The Contractor shall provide the names, biographic data and police clearance on all Contractor personnel who to be used on this Contract prior to their utilization. Submission of information shall be made within 30 days of award of contract. No technician will be allowed on site without prior authorization. Note: this may include cleared personnel if advance notice of visit is not given at least one week before the scheduled visit.

3.2.1 Vehicles. Contractor vehicles will not be permitted inside the embassy compound without prior approval. If vehicle access is necessary, submit contractor vehicle information (Make, Model, License Plate #) along with a written justification as to why access is necessary. This shall be submitted to the Facility Manager at least one (1) week prior to the visit.

3.2.2 Government shall issue identity cards to Contractor personnel, after they are approved.

Contractor personnel shall display identity card(s) on the uniform at all times while providing services under this contract. These identity cards are the property of the US Government. The

Contractor is responsible for their return at the end of the contract, when an employee leaves

Contractor service, or at the request of the Government. The Government reserves the right to deny access to U.S.-owned and U.S.-operated facilities to any individual.

Choose Red for non-CAA.

4. SCHEDULED PREVENTIVE MAINTENANCE

4.1. General

4.1.1. The Contractor shall perform preventive maintenance as outlined in Exhibit A -

STATEMENT OF WORK. The objective of scheduled preventive maintenance is to eliminate system malfunction, breakdown and deterioration when units are activated/running.

4.1.2. The Contractor shall inventory, supply and replace expendable parts (e.g., filters, belts, hoses, gaskets) that have become worn due to wear and tear. The Contractor shall maintain a supply of expendable and common parts on site so that these are readily available for normal maintenance to include: hoses, belts, oil, chemicals, coolant, filters (Air, Fuel, Oil), grease, sealant, thermostat, fuses; in addition to the appropriate tools, testing equipment, safety shoes and apparel for technicians, personal protective equipment (hands, hearing, eye protection), MSDS, cleaning material and oil spill containment kits. The contractor shall inventory the supply after each visit and order replacement supplies and have them delivered on site. Maintenance materials shall be unused and are to be industry standard and intended for the task to be performed. Parts shall be

OEM approved. Refrigerants shall meet the AHRI Standard 700-2015 or most recent AHRI

Standards.

4.1.3. Exclusion. This contract does NOT include repair of equipment and replacement of hardware (e.g. bearings, pistons, piston rings, crankshaft, gears.) Hardware replacements will be separately priced out by the Contractor for the Government’s approval and acceptance.

The Government has the option to accept or reject the Contractor’s quote for parts and reserves the right to obtain similar spare parts from other competitive sources. If required by the

Government, the Contractor shall utilize Government-purchased spare parts, if awarded the work.

Such repairs/replacements will be accomplished by a separate purchase order. However, this exclusion does not apply if the repair is to correct damage caused by Contractor negligence.

4.1.4. Replacement/repair of any electronic or electrical parts shall be approved by the COR prior to installation of the part. If the Contractor proceeds to replace any electronic or electrical parts without COR approval, the Contractor shall de-install the parts at no cost to the Government.

4.1.5. Stocking of recommended repair parts is at the discretion of the Facility Manager and is dependent upon the nearest location of the Equipment manufacturer, distributor or dealer. A recommended spare parts list shall be obtained by the contractor from the manufacturer or distributor and provided to the Facility Manager to procure.

4.2 Checklist Approval. The Contractor shall submit to the COR a schedule and description of preventive maintenance tasks which the Contractor plans to perform. The Contractor shall prepare this schedule and task description in a checklist format for the COR’s approval prior to contract work commencement.

4.2.1. The Contractor shall provide trained technicians to perform the service at frequencies stated in Exhibit A and on the equipment called out in this SOW.

4.2.2. It is the responsibility of the Contractor to perform all manufacturers’ recommended preventive maintenance including preventive maintenance recommended by the manufacturers’ technical manuals for the respective equipment.

4.2.3 Additionally, the maintenance contractor shall obtain and keep at the post O&M binders provided by the manufacturers. These binders shall be placed in a location accessible to post personnel to review as needed.

5. PERSONNEL, TOOLS, CONSUMABLE MATERIALS AND SUPPLIES

The Contractor shall provide trained technicians with the appropriate tools and testing equipment for scheduled maintenance, safety inspection, and safety testing as required by this Contract. The

Contractor shall provide all of the necessary materials and supplies to maintain, service, inspect and test all the systems to be maintained.

Contractor shall not provide less than 2 technicians to ensure the accomplishment of safety standards and procedures included in the contract such as mechanic work. The Embassy personal will provide only escort support.

5.1 Contractor furnished materials include but are not limited to appropriate tools, testing equipment, safety shoes and apparel for technicians, hands, hearing, and eye protection, MSDS, cleaning material and oil spill containment kit. Expendable/consumable items (e.g. hoses, belts, oil, chemicals, coolant, filters (Air, Fuel, Oil), generator starting batteries, grease, sealant, thermostat, fuse), shall be maintained in the onsite inventory. See 7.1.2.

5.2 Repairs are not included in this contract. See 7.1.3. Exclusions.

5.3 Disposal of used oil, fuel, battery and other toxic substances. The Contractor is responsible for proper disposal of toxic/hazardous substances. All material shall be disposed of according to

Government and Local law. After proper disposal the contractor must show proof of authorized disposal of these toxic/hazardous substances.

6. SOFTWARE, LICENSES AND PASSWORDS

Copies of any and all software and licenses needed to control or to adjust the communications module shall be given to the post upon completion of the work.

7. DELIVERABLES

Provide a typewritten report to Post Facilities Manager containing following:

System information (make, model, all devices types)

a) Pass/Fail of each feature and type of component tested. If a device fails, note device type, address and location within Post

b) Any comments on system (or device) condition pertaining to service life and dependability.

c) Full printout of test from system printer

d) Testing of exhaust gas by Gas Analyzer

The following items shall be delivered under this contract:

Description QTY Delivery Date Deliver to

Names, biographic data, police clearance on Contractor personnel (#6.2)

1 30 days after contract award COR

Certificate of Insurance (#11.2) 1 30 days after contract award CO

PM Checklist signed by Contractor’s employee (#7.2.1)

1 After completion of each maintenance service

COR

Invoice (#15) 1 After completion of each maintenance service

COR

8. INSURANCE REQUIREMENTS

8.1 Personal Injury, Property Loss or Damage (Liability). The Contractor assumes absolute responsibility and liability for any and all personal injuries or death and property damage or losses suffered due to negligence of the Contractor’s personnel in the performance of this Contract.

The Contractor’s assumption of absolute liability is independent of any insurance policies.

8.2 Insurance. The Contractor, at its own expense, shall provide and maintain during the entire period of performance of this Contract, whatever insurance is legally necessary. The Contractor shall carry the following minimum insurance:

Public Liability Insurance

Property damage: $ 100,000 per occurrence: $150,000Cumulative

Bodily Injury: $100.000 per occurrence: $150,000 Cumulative

Workers’ Compensation and Employer’s Liability

8.3 Worker's Compensation Insurance. The Contractor agrees to provide all employees with worker's compensation benefits as required under local laws (see FAR 52.228-4 “Worker’s

Compensation and War-Hazard Insurance Overseas”).

9. LOCAL LAW REGISTRATION

If the local law or decree requires that one or both parties to the contract register the contract with the designated authorities to insure compliance with this law or decree, the entire burden of this registration shall rest upon the Contractor. Any local or other taxes which may be assessed against the Contract shall be payable by the Contractor without Government reimbursement.

10. QUALITY ASSURANCE PLAN (QAP).

10.1 Plan. This plan is designed to provide an effective surveillance method to promote effective

Contractor performance. The QAP provides a method for the Contracting Officer's Representative

(COR) to monitor Contractor performance, advise the Contractor of unsatisfactory performance, and notify the Contracting Officer of continued unsatisfactory performance. The Contractor, not the Government, is responsible for management and quality control to meet the terms of the

Contract. The role of the Government is to conduct quality assurance to ensure that Contract standards are achieved.

Performance Objective SOW Para Performance Threshold

Services.

Performs all services set forth in the

Statement of Work (SOW)

1 thru 14 &

Exhibit A

All required services are performed and no more than one

(1) customer complaint is received per month

10.2 Surveillance. The COR will receive and document all complaints from Government personnel regarding the services provided. If appropriate, the COR will send the complaints to the

Contractor for corrective action.

10.3 Standard. The performance standard is that the Government receives no more than one (1) customer complaint per month. The COR shall notify the Contracting Officer of the complaints so that the Contracting Officer may take appropriate action to enforce the inspection clause (FAR

52.212-4, Contract Terms and Conditions-Commercial Items), if any of the services exceed the standard.

10.4. Procedures.

10.4.1 If any Government personnel observe unacceptable services, either incomplete work or required services not being performed, they will immediately contact the COR.

10.4.2 The COR will complete appropriate documentation to record the complaint.

10.4.3 If the COR determines the complaint is invalid, the COR will advise the complainant. The

COR will retain the annotated copy of the written complaint for his/her files.

10.4.4 If the COR determines the complaint is valid, the COR will inform the Contractor and give the Contractor additional time to correct the defect, if additional time is available. The COR shall determine how much time is reasonable.

10.4.5 The COR shall, as a minimum, orally notify the Contractor of any valid complaints.

10.4.6 If the Contractor disagrees with the complaint after investigation of the site and challenges the validity of the complaint, the Contractor shall notify the COR. The COR will review the matter to determine the validity of the complaint.

10.4.7 The COR will consider complaints as resolved unless notified otherwise by the complainant.

10.4.8. Repeat customer complaints are not permitted for any services. If a repeat customer complaint is received for the same deficiency during the service period, the COR will contact the

Contracting Officer for appropriate action under the Inspection clause.

11. TRANSITIONS/CONTACTS

Within 30 days after contract award, the Contracting Officer may ask the contractor to develop a plan for preparing the contractor to assume all responsibilities for preventive maintenance services.

The plan shall establish the projected period for completion of all clearances of contractor personnel, and the projected start date for performance of all services required under this contract.

The plan shall assign priority to the selection of all supervisors to be used under the contract.

14.1 On site contact. The following are the designated contact personnel between the US Embassy and the Contractor

COR

BAS TECHNICIAN

The Post Control Officer (PCO) will be the contractor’s point of contact at the U.S. Embassy in

Panama All questions concerning coordination of service activities while at post shall be directed to the Post Control Officer, with weekly reporting to the COR:

PCO: _____________________________________

EXHIBIT A

Statement of Work

GENERAL INFORMATION:

The United States Embassy in Panama City requires professional services and contractor cost proposals to perform preventive maintenance services of the facility’s Air Handling Units, Chiller

Systems .

PROJECT REQUIREMENTS:

DESCRIPTION OF EQUIPMENT

L/I Component Manufacture Model# Serial# Capacity Location

Chillers

1 Chiller, commissioned in 2007

YORK YRXCXDT346CS SMPM989530 410 ton UTLY

Building

2 Chiller, commissioned in 2014

YORK YRXCXDT346CS SMPM989410 410 ton UTLY

Building

3 Primary

Chiller Pump

Bell &

Gossett

CO12172-02-

M50

25HP UTLY

Building

4 Secondary

Chiller Pump

Bell &

Gossett

CO11484-01-

A60

50HP UTLY

Building

Cooling

Towers

5 Cooling Tower commissioned in 2007

EVAPCO USS-112-612 5-1306-9 500 ton WHS Roof

6 Cooling Tower commissioned in 2007

EVAPCO USS-112-612 5-1306-50 500 ton WHS Roof

7 Condenser

Pump

Bell &

Gossett

CO12171-01-

M50

10HP UTLY

Building

8 Water

Treatment

Control

Microtron Micro-C UTLY

Building

Component Manufacturer Model# Serial# Capacity Location

AHUs

1 TAG#

AHU-0-01

Commissioned

In 2007

YORK P91-33 -CL3 05-83828-01

25 HP

Chancery

Building

(Basement)

2 TAG#

AHU-0-02

Commissioned

In 2007

YORK P91-33 -CL3 05-83828-02

40 HP

Chancery

Building

(Basement)

3 TAG#

AHU-0-03

Commissioned

In 2007

YORK P91-33 -CL3 05-83828-03

40 HP

Chancery

Building

(First

Floor)

4 TAG#

AHU-0-04

Commissioned

In 2007

YORK P91-33 -CL3 05-83828-04

40 HP

Chancery

Building

(Second

Floor)

5 TAG#

AHU-0-05

Commissioned

In 2007

YORK P91-33 -CL3 05-83828-05

40 HP

Chancery

Building

(Third

Floor)

6 TAG#

AHU-0-07

Commissioned

In 2007

YORK P91-30- CL2 05-83828-06

40 HP

Chancery

Building

(Fourth

Floor)

7 TAG#

AHU-0-14

Commissioned

In 2007

YORK XT1-

102X084-

FANA046A

CFRMXT0069

25 HP

Chancery

Building

(Fourth

Floor)

8 TAG#

AHU-5-01

Commissioned

In 2007

YORK P91-27-CL2 05-83823-11

10 HP

Annex

Building

9 TAG#

AHU-5-02

Commissioned

In 2007

YORK XTI-

051X081-

FAJA046A

CLPMXT0361

7.5 HP

GSO

Annex

Building

10 TAG#

AHU-1-01

Commissioned

In 2007

YORK P91-18-CL3

05-83828-10

10 HP

MSGQ

Building

11 TAG#

AHU-4-01

YORK 3 HP WHSE

GENERAL REQUIREMENTS:

The Contractor under this SOW shall be responsible for labor, tools, and materials(oil tester and expendable Material) required to carry out all preventive maintenance as outlined in this SOW.

Embassy staff has service Manuals for all.

CHILLER PREVENTIVE MAINTENANCE

Contractor shall provide all materials, supervision, labor, tools and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use safety protection while all work is performed. Any questions or injuries shall be brought to the attention of the Post Occupation Safety and Health Officer (POSHO) immediately. The SDS copies will be provided to the COR for approval. If any discrepancies are found with the Air Handling Units that are not covered under this scope of work the contractor shall provide the following:

1. Detailed report noting the discrepancy found.

2. Bill of Materials (BOM) to include component name, quantity, part #, and price for any repair material required and material lead time.

3. Price quote for repair labor.

MAINTENANCE PROCEDURES: CHILLER YORK 410 Ton

SAFETY AND SPECIAL INSTRUCTIONS:

1. Follow site safety procedures and supervisor’s instructions.

2. Schedule outage with operating personnel.

3. Use extreme caution when climbing access ladders.

4. Perform applicable lockout/tag out steps of site safety procedures.

5. Lockout and disconnect the main power before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.

6. Record and report equipment damage or deficiencies.

7. Review and follow the manufacturer’s O&M instructions.

8. Record results in the equipment history log.

9. Allow only qualified personnel to do maintenance work on this equipment.

10. Record results in the equipment history log.

11. Check manufacturer’s specifications for the maximum number of plugged tubes.

12. Allow only qualified personnel to do maintenance work on this equipment.

CHILLER QUARTERLY

1. Check oil return system operation.

2. Check operation of motor starter.

3. Check oil heater operation.

4. Check three-phase voltage and current balance.

5. Verify proper operation/setting/calibration of safety controls

6. Verify condenser and evaporator water flows.

7. Leak check and repair leaks as needed.

8. Perform oil analysis on compressor oil.( contractor Provide test.)

9. Megohm Motor windings

10. Replace Oil and Filter as Needed (GFM Provide)

11. Wipe down the unit.

12. Lock out and tag out equipment.

13. Verified chiller water treatment Value Range

14. Remove tags and place equipment back into operation.

CHILLER ANNUAL

1. Lock out and tag out equipment.

2. Check and tighten electrical connections.

3. Mega-ohm motor windings.

4. Replace oil filter and oil return filter/driers.

5. Clean or backflush heat exchanger (SSS Applications)

6. Perform oil analysis on compressor lube oil. ( contractor Provide test.)

7. Perform refrigeration analysis.

8. Perform Compressor vibration analysis. (Price Included Clin 004)

9. Service the motor starter: Check connections.

10. Perform Eddy current testing and inspect tubes. (Price Included Clin 004)

11. Remove tags and place equipment back into operation.

PROCEDURES FOR INSPECTING THE CENTRIFUGAL PUMP

1. Shutdown and tag out unit.

2. Clean and inspect centrifugal pump.

a. Clean accumulated dirt and grime from pump casing, shaft coupling, and motor.

b. Check motor ventilation ports for soil accumulation, clean if necessary.

c. Clean exterior of motor surfaces of soil accumulation.

d. Check motor hold down bolts and grounding straps for tightness.

3. Check that base bolts are securely fastened.

4. Drain pump housing, check suction, discharge and check valve for holding.

5. Remove corrosion and repaint.

6. On pumps with oil ring lubricated bearings, drain oil, flush, and fill to proper oil level with new approved type oil.

7. Check motor and pump alignment.

8. Check drive shaft coupling.

10. Cycle valves two times.

11. Remove tags and start the pump.

12. Ensure unit rotates in the proper direction.

13. Start and stop pump, noting vibration, pressure, and action of check valve.

14. Adjust packing.

15. Lubricate centrifugal pump.

16. Lubricate motor bearings.

a. Remove filler and drain plugs (use zerk fittings if installed).

b. Free drain hole of any hard grease (use piece of wire if necessary).

c. Add grease - use good grade lithium base grease unless otherwise noted.

NOTE: Complete CM-0002 (Qualitative Infrared Thermography) and CM-0003

(Motor Insulation Test) on units over 7.5 horsepower.

17. Operational test of the centrifugal pump.

a. Check flanges and fittings for leaks.

b. Measure motor phase voltages and current and record results. Compare against motor nameplate data.

c. Record inlet and outlet pressures.

18. Return the unit to service

COOLING TOWERS

Contractor shall provide all materials, supervision, labor, tools and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use safety protection while all work is performed. Any questions or injuries shall be brought to the attention of the Post Occupation Safety and Health Officer (POSHO) immediately. Material Safety Data

Sheets (MSDS) shall be provided by the Contractor for all HAZMAT materials. Copies shall be provided to the COR for approval.

If any discrepancies are found with the Cooling Towers that are not covered under this scope of work then the contractor shall provide the following:

1. Detailed report noting the discrepancy found.

2. Bill of Materials (BOM) to include component name, quantity, part #, and price for any repair material required and material lead time.

2. Schedule outage with operating personnel.

3. Use extreme caution when climbing access ladders.

4. Perform applicable lockout/tag out steps of site safety procedures.

5. Lockout and disconnect the main power before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.

6. Record and report equipment damage or deficiencies.

7. Review and follow the manufacturer’s O&M instructions.

8. Record results in the equipment history log.

9. Allow only qualified personnel to do maintenance work on this equipment.

10. The recirculating water system may contain chemicals or biological contaminants, including

Legionella, which could be harmful if inhaled or ingested. Personnel exposed directly to the discharge airstream and the associated drift mists, generated during operation of the water distribution system and/or fans, or mists produced by high pressure water jets or compressed air (if used to clean components of the recirculating water system), must wear respiratory protection equipment approved for such use by governmental occupational safety and health authorities.

COOLING TOWERS

MAINTENANCE PROCEDURES:

Note to Statement of Work writer: The frequencies and tasks shown in this template SOW are for reference only. The actual maintenance procedures will be determined by the manufacturer’s

O&M recommendations. These O&M recommendations may be obtained from the manufacturer or may already be within the post files. The manufacturer’s maintenance recommendations are to be considered the minimum tasks to be provided and these tasks may be altered or increased depending upon the location of the post.

Additionally, it may be required the maintenance contractor shall obtain and keep at the post O&M binders provided by the manufacturers. These binders will be placed in a location accessible to post personnel to review as needed.

COOLING TOWER

MAINTENANCE TASK DESCRIPTION: (QUARTELY) First and Third Visit.

1. Observe cooling tower for proper operation.

2. Clean and inspect the cooling tower.

3. Drain the unit and associated piping.

4. Test and adjust cooling tower, check motor, Lubricate motor.

5. Clean pan strainer.

6. Check bleed-off valve for proper operation.

7. Check water distribution system and spray pattern.

8. Check and adjust belt tension and replace belt if cracked or frayed.

9. Check fan screens, inlet louvers and fans. Remove any dirt or debris

10. Check and Clean drift eliminators.

11. Lubricate shaft bearings.

12. Inspect and repair metal structure corrosion. Remove rust and apply protective coatings.

13. Check Level Control Sensor.

14. Clean all strainers.

15. Inspect spray nozzles at the unit.

16. Clean outside of fan motor.

17. Test the electronic vibration cutout switch.

18. Measure motor voltage and current. Compare to nameplate values.

19. Report and clean unusual dirt accumulation, formation of scale or algae.

20. Inspect and clean water basin and fill area.

21. Check condition of drive system.

22. Verified condense water treatment value range.

23. Star system and perform an operational check

24. Check operation of make-up valve.

SPECIAL INSTRUCTIONS:

1. Review manufacturer's instructions.

2. De-energize, tag, and lock electrical circuits.

3. Review the Standard Operating Procedure for "Selection, Care, and Use of Respiratory

Protection".

4. Ensure that there are safe and sturdy ladders and platforms to perform the lifting and cleaning required.

5. If biological growth is excessive, have a qualified water treatment specialist review your treatment program.

6. Refer to Table A for information on chlorine use.

7. Properly dispose of any debris, excess oil, and grease.

8. Record and report to your supervisor any equipment damage or deficiencies found while performing this maintenance task.

9 Schedule performance of this PM activity prior to seasonal start-up.

10 Consider the time needed to affect any required repairs.

11 Review the Standard Operating Procedure for Controlling Hazardous

12 Energy Sources.

13 All tests shall conform to the manufacturer's test procedures and

14 Standard values.

15 Record all test results in the component maintenance log.

WARNING: DO NOT USE THE TOP HORIZONTAL SURFACE OF THE TOWER AS A

WORKING PLATFORM. THE TOWER IS DESIGNED SO THAT ALL MAINTENANCE

CAN BE PERFORMED FROM THE EXTERIOR AND INTERIOR OF THE TOWER. DO

NOT USE THE UPPER BASIN COVERS AS A WALKING SURFACE OR WORKING

PLATFORM. REMOVE BASIN COVERS AND USE PORTABLE LADDERS

WHENEVER PERFORMING SERVICE ON THE HOT WATER BASIN. USE OF

LADDER SHOULD BE IN ACCORDANCE WIGTH MANUFACTURER'S

RECOMMENDATIONS.

TOOLS, MATERIALS, AND EQUIPMENT

1. Mechanic's toolset.

2. Hose, ladder, and cleaning materials.

1. .

TOOLS, MATERIALS, AND EQUIPMENT (QUARTERLY ):

1. Hose, ladder, and cleaning materials.

2. Lubricants. (Use Mobil Oil SHC 100 or equal for fan bearings.)

3. Cleaning materials.

4. Protective coatings.

5. Multimeter.

PROCEDURES (SEMI-ANNUAL/ANNUAL)

1. Perform a structural inspection.

2. Inspect and repair corrosion. Remove rust and apply protective coatings

3. Clean the unit:

a. Drain the cold water basin.

b. Clean and flush the cold water basin with the basin strainers in place.

c. Clean all strainers and install.

d. Inspect the metal components of the tower. Clean and refinish as required.

e. Clean air inlet louvers.

f. Clean and inspect drift eliminators.

g. Inspect spray nozzles

4. Verify fan rotates freely by hand.

5. Check all mounting bolts properly tightened.

6. Check drive alignment.

7. Treat the unit with biocide. (Apply shock treatment if the sump was not completely drained.)

8. Check water level sensor .

9. Set bleed rate.

10. Check that flow is balanced.

11. Inspect and clean protective finish.

12. Inspect and grease sliding motor base.

13. Lubricate fan shaft bearings .

14. Inspect electrical connections for tightness.

15. Measure motor voltage and current. Compare to nameplate values.

16. Perform a megger check of the motor.

17. Remove tags and start unit.

18. Check for proper operation.

19. Verified condense water treatment value.

20. Test the electronic vibration cutout switch.

21. Check for unusual noise and vibration.

22. Monitor and test corrosion coupons as applicable

23. Check operation of make- up valve.

TOOLS, MATERIALS, AND EQUIPMENT ( SSEMI ANNUAL /ANNUAL):

1. Mechanic's/electrician's tool sets.

2. Hose, ladder, and cleaning materials.

3. Cleaning materials.

4. Protective coatings.

5. Biocide.

6. Meggar.

7. Multimeter.

PROCEDURES FOR INSPECTING THE CENTRIFUGAL PUMP

1. Shutdown and tag out unit.

2. Clean and inspect centrifugal pump.

a. Clean accumulated dirt and grime from pump casing, shaft coupling, and motor.

b. Check motor ventilation ports for soil accumulation, clean if necessary.

c. Clean exterior of motor surfaces of soil accumulation.

d. Check motor hold down bolts and grounding straps for tightness.

3. Check that base bolts are securely fastened.

4. Drain pump housing, check suction, discharge and check valve for holding.

5. Remove corrosion and repaint.

6. On pumps with oil ring lubricated bearings, drain oil, flush, and fill to proper oil level with new approved type oil.

7. Check motor and pump alignment.

8. Check drive shaft coupling.

10. Cycle valves two times.

11. Remove tags and start the pump.

12. Ensure unit rotates in the proper direction.

13. Start and stop pump, noting vibration, pressure, and action of check valve.

14. Adjust packing.

15. Lubricate centrifugal pump.

16. Lubricate motor bearings.

a. Remove filler and drain plugs (use zerk fittings if installed).

b. Free drain hole of any hard grease (use piece of wire if necessary).

c. Add grease - use good grade lithium base grease unless otherwise noted.

NOTE: Complete CM-0002 (Qualitative Infrared Thermography) and CM-0003

(Motor Insulation Test) on units over 7.5 horsepower.

17. Operational test of the centrifugal pump.

a. Check flanges and fittings for leaks.

b. Measure motor phase voltages and current and record results. Compare against motor nameplate data.

c. Record inlet and outlet pressures.

18. Return the unit to service.

Condenser Water Treatment Report

Follow site safety procedures and supervisor’s instructions.

Schedule outage with operating personnel.

Use extreme caution when climbing access ladders.

Perform applicable lockout/tag out steps of site safety procedures.

Lockout and disconnect the main power before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.

Record and report equipment damage or deficiencies.

Review and follow the manufacturer’s O&M instructions.

Record results in the equipment history log.

Allow only qualified personnel to do maintenance work on this equipment.

Record results in the equipment history log.

Check manufacturer’s specifications for the maximum number of plugged tubes.

Allow only qualified personnel to do maintenance work on this equipment.

Test system for proper pH, total amount of dissolved solids, conductivity, scale and corrosion inhibitors.

Test supply water for base conditions.

Monitor and test corrosion coupons as applicable.

MAINTENANCE TASK DESCRIPTION:

1. Water treatment for the condenser water system.

SPECIAL INSTRUCTIONS:

1. Chemicals must comply with the Environmental Protection Agency

(EPA) regulations and handled in accordance with occupational safety requirements. Employ personal protection against corrosive or hazardous treatment chemicals as appropriate.

2. Be familiar with the Material Safety Data Sheets of any chemicals used in the water treatment program.

3. Water treatment specialists must be properly trained.

4. Water treatment must be based on proven standard engineering practices.

5. Follow treatment as directed by manufacturer or water treatment company.

6. Maintenance includes chemicals, chemical feeding, maintaining proper water conditions, controlling bleed off, protecting idle equipment, and record-keeping.

7. Select water treatment methods which protect the life of equipment, maximize heat transfer, and minimize scale, corrosion, solid matter buildup, algae, fungi, biological growth, and water usage. Alternate biocides. Changes to higher dosage levels may be required to control growth.

8. Ensure chemicals are properly stored, test equipment clean, and that chemicals have not passed expiration date.

9. Special attention must be paid to wooden towers and solar heating systems which can be more difficult to properly maintain.

10. Physical inspections of towers and piping systems are to be made to determine water treatment effectiveness.

11. Maintain records and test results.

12. All tests shall conform to the manufacturer's test procedures and standard values.

REPORT OF WATER ANALYSIS:

DATE:

SOURCE:

DATE ANALYZED:

TOTAL DISSOLVED

SOLIDS

ppm CALCIUM ppm

ORGANIC MATTER ppm MAGNESIUM ppm

SUSPENDED MATTER ppm MATTER SODIUM ppm

CHLOROFORM (Oil, etc.)

ppm POTASSIUM ppm pH BICARBONATE ppm

PHENOLPHTHALEIN

ALK.

ppm CARBONATE ppm

METHYL ORANGE

ALK.

ppm HYDROXIDE

HYDROXIDE ALK. ppm (as OH) ppm

HARDNESS ppm SULPHATE ppm

SPECIFIC

CONDUCTANCE

ppm NITRATE ppm

SILICA ppm CARBON DIOXIDE ppm

IRON ppm TURGIDITY ppm

OTHER ppm OTHER ppm

AIR HANDLING UNITS

Contractor shall supervision, labor, tools and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use safety protection while all work is performed. Any questions or injuries shall be brought to the attention of the Post Occupation Safety and Health Officer (POSHO) immediately. Material Safety Data Sheets (MSDS) shall be provided by the Contractor for all HAZMAT materials. Copies shall be provided to the COR for approval.

If any discrepancies are found with the Air Handling Units that are not covered under this scope of work the contractor shall provide the following:

1. Detailed report noting the discrepancy found.

2. Bill of Materials (BOM) to include component name, quantity, part #, and price for any repair material required and material lead time.

2. Schedule outage with operating personnel.

3. Use extreme caution when climbing access ladders.

4. Perform applicable lockout/tag out steps of site safety procedures.

5. Lockout and disconnect the main power before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.

6. Record and report equipment damage or deficiencies.

7. Review and follow the manufacturer’s O&M instructions.

8. Record results in the equipment history log.

9. Allow only qualified personnel to do maintenance work on this equipment.

10. Record results in the equipment history log.

11. Check manufacturer’s specifications for the maximum number of plugged tubes.

12. Allow only qualified personnel to do maintenance work on this equipment.

AIR HANDLING UNITS

MAINTENANCE PROCEDURES:

Note to Statement of Work Writer: The frequencies and tasks shown in this template SOW are for reference only. The actual maintenance procedures will be determined by the manufacturer’s

O&M recommendations. These O&M recommendations may be obtained from the manufacturer or may already be within the post files. The manufacturer’s maintenance recommendations are to be considered the minimum tasks to be provided and these tasks may be altered or increased depending upon the location of the post.

Additionally, it may be required that the maintenance contractor shall obtain and keep at the post

O&M binders provided by the manufacturers. These binders will be placed in a location accessible to post personnel to review as needed.

Quarterly /Annually

1. Perform semi-annual tasks.

2. Clean exterior of air handler cabinet.

3. Inspect doors, handles, latches and hinges for proper operation.

4. Inspect door gaskets for damage and proper seal.

5. Inspect panels for damage.

6. Clean fan segment and fan assembly (supply, return, exhaust).

7. Check fan housing, wheel, shaft, frame, inlet vanes and bearings for damage, wear, loose parts, dirt and debris.

8. Check fan base, vibration isolators and thrust restraints for damage, wear, loose parts, dirt and debris.

9. Check flex connector for damage and wear.

10. Lubricate fan bearings.

11. Clean variable inlet vanes.

12. Check adjustable fan motor base and mounting hardware for loose parts.

13. Check adjustable fan motor base for damage.

14. Check fan motor for leaky bearing seals.

15. Check fan for motor damage.

16. Check for dirt, dust & debris in air vents on fan motor housing.

17. Clean dehumidification coils.

18. Clean condensate drain pan, trap, drain line and adjacent wetted surfaces.

19. Check Energy Recovery Wheel, clean media, adjust seals, replace belt.

20. Energize circuit and check operation of starter and any pilot lights. Replace as required.

21 Check contacts of drum controller for arcing and overheating. Apply a thin film of lubricant to drum controller contacts and to rotating surfaces.

END OF STATEMENT OF WORK