RFP 367827(RE) - Request for Clarifications_Responses.pdf

PDF 255 KB Posted

Attached to
Site-wide Crane Inspection & Troubleshooting Services
Solicitation number
267827(RE)
Issued by

About this file

This document is an Offeror's Request for Clarifications (Q&A document) for RFP No. SLAC_RFP_367827(RE) for Site-wide Crane Inspection & Troubleshooting services at SLAC National Accelerator Laboratory. The clarifications were submitted on 11/10/26 with responses issued on 11/13/26, with certain items requiring Statement of Work revisions and Section A/M revisions via amendment.

The clarification responses establish critical requirements for the hybrid Firm Fixed Price and Labor-Hour contract structure covering approximately 275 crane assets. Key scope details include: annual and quadrennial inspections subject to Cal/OSHA certification and ASME B30 standards; quadrennial inspections requiring 125% proof load tests with SLAC providing test weights and rigging; estimated quadrennial inspection crane counts of 4 units in Base Period (FY27), 134 in Option Year 1 (FY28), and 62 in Option Year 2 (FY29); all inspections must be performed by the subcontractor only (no lower-tier certifier delegation); quarterly and annual inspection schedules of two quarterly plus one annual in the 9-month Base Period (Jan 1–Sep 30, 2027), then three quarterly plus one annual per 12-month Option Period; and quarterly inspection applicability to 42 chain falls and 71 lever hoists at individual building locations. The maximum covered inventory is capped at 283 cranes without equitable adjustment. Preventative maintenance scope includes lubricants, gearbox oil changes, wire rope lubrication, brake/limit switch adjustments, and minor part replacements (fuses, contacts, buttons) as Firm Fixed Price inclusions. Emergency response requires 4-hour on-site capability during standard SLAC operating hours (Monday–Friday, 7:00 AM–5:00 PM, excluding holidays and shutdown). Item 02 (FFP inspections) invoices in equal monthly installments unless negotiated otherwise; Item 03 (troubleshooting labor hours) requires a single fully burdened hourly rate with all equipment, materials, and ODCs included. Inspection reports require 48-hour (or 24-hour for Exceeds ratings) delivery from conclusion of each day's work; prior inspection reports and deficiency records will be provided post-award. Personnel must be Cal/OSHA-qualified persons per Title 8 and ASME B30 standards; Cal/OSHA-accredited Crane Certifying Agencies perform required certifications. SCA wage classification 23430 (Heavy Equipment Mechanic) applies with flowdown to any lower-tier subcontractor. Maximum inspection access height is 60–80 feet; lift scheduling is coordinated with the SLAC Project Manager, and lifts may access via building roads and runways/catwalks subject to Environment, Safety, and Health approval. Radiological training (GERT/RWT) is required for restricted areas; beam-off/downtime access windows will be provided. Badging requires minimum one-week lead time; first quarterly inspections commence the week following January 4, 2027 (allowing pre-award onboarding if contract awards before the winter holiday shutdown).

View the file

Other files

File Type Posted
CRANE INVENTORY_MANUFACTURERS LIST.xlsx XLSX spreadsheet
Amd01_RFP 367827(RE)_11.16.26.pdf PDF
RFP_367827(RE)_Crane Inspection Services.zip ZIP file
RFP_367827(RE)_Crane Inspection.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 02

OFFEROR’S REQUEST FOR CLARIFICATIONS

Request for Proposal No: SLAC_RFP_367827(RE)

Site-wide Crane Inspection & Troubleshooting

ITEM DATE

SUBMITT

ED

RFP DOCUMENT

REFERENCE

QUESTION RESPONSE RESPONSE

DATE

RFP ACTIONS

1 11/10/26 SOW §3.1; Section B

Items 01–02 Equipment list. Please provide the asset list for the ~275 assets, including for each: asset ID, building/location, equipment type, rated capacity, span and lift/hook height, manufacturer/model, hoist type, control type (pendant/radio/cab, VFD, PLC), approximate height above floor for inspection access, and date of last annual and last quadrennial inspection. Firm fixed pricing cannot be accurately prepared from category counts alone.

Building numbers and specific locations cannot be provided prior to award; the selected Subcontractor will verify locations and building numbers post-award. SLAC will provide an equipment make and model breakout via solicitation amendment.

The maximum inspection access height above the floor is

60–80 feet.

The most recent annual inspections were completed in

Q4 FY2026 (July–September 2026). Approximately 200 cranes will require quadrennial inspections across

FY2027–FY2029.

11/13/26 N/A

2 11/10/26 SOW §3.2

(Quadrennial)

Quadrennial scope. Please identify which assets require a quadrennial inspection in the Base Period and in each Option

Period. Does SLAC intend the quadrennial inspection to include a proof load test? If so, please state the required test load (e.g., 125% of rated capacity) and whether SLAC will furnish test weights, rigging and handling equipment, or whether these are to be furnished by the Subcontractor.

Quadrennial inspections require a proof load test at

125% of rated capacity. SLAC will provide the test weights and rigging; any additional handling or testing equipment must be furnished by the Subcontractor.

The estimated quadrennial inspection crane counts by period are:

• Base Period (FY27): 4

• Option Year 1 (FY28): 134

• Option Year 2 (FY29): 62

11/13/26 N/A

3 11/10/26 SOW §3.2

(Annual/Quadrennial)

; SOW §1

Regulatory basis. Please identify which assets SLAC considers subject to Cal/OSHA crane certification under Title 8 CCR §5021

(annual certification and quadrennial load test by a Cal/OSHA-accredited certifier), and which assets are to receive annual/periodic inspections by a Qualified Person under ASME

B30 only.

All inventory items under this requirement are subject to

Cal/OSHA crane certification in addition to applicable

ASME B30 standards.

11/13/26 N/A

4 11/10/26 SOW §3.2; Section L

Factor 4 Use of a lower-tier certifier. Please confirm that the Offeror may perform the quarterly inspections with its own Qualified Persons and use a lower-tier subcontractor that is a Cal/OSHA-accredited crane certifier to perform the annual and quadrennial inspections/certifications. If permitted, please confirm (a) the lower-tier subcontractor should be identified in the proposal, (b) its certifier credentials and resumes may be submitted to satisfy

All inspections (PMs) must be performed by the sub-contractor ONLY.

11/13/26 N/A

Factor 4 for that portion of the work, and (c) whether FAR

52.219-14 (Limitations on Subcontracting) applies to this set-aside subcontract.

5 11/10/26 SOW §3.2; Section F Inspection count in Base Period. The SOW calls for three (3) quarterly and one (1) annual inspection per contract year, but the Base Period is nine (9) months (Jan 1 – Sep 30, 2027). Please state the number of quarterly and annual inspection events required in the Base Period, and confirm that the annual inspection takes the place of the fourth quarterly inspection (i.e., four inspection events per 12-month option year).

Because the Base Period spans nine (9) months (Jan 1 –

Sep 30, 2027), it requires two (2) quarterly inspections and one (1) annual inspection. The annual inspection takes the place of the final quarterly inspection and will be performed in the fourth quarter of the fiscal year (Jul–

Sep 2027). (Note: Each 12-month Option Period will consist of three [3] quarterly inspections and one [1] annual inspection.)G

11/13/26 N/A

6 11/10/26 SOW §3.1, §3.2 Portable hoists. Do the three quarterly inspections apply to the

42 chain falls and 71 lever hoists, or only to the annual inspection? Are these portable units stored at central tool cribs, and will SLAC collect them to one or more central locations for inspection, or must each be inspected where located?

Yes, the quarterly inspection requirements apply to the

42 chain falls and 71 lever hoists. These units are stored at the individual building locations where they are used and must be inspected at those locations.

ITEM DATE

SUBMITT ED

RFP DOCUMENT

REFERENCE

QUESTION RESPONSE RESPONS E

DATE

RFP ACTIONS

7 11/10/26 SOW §3.1 Equipment definitions. Please define "Lifting Point (LP)", "Fixed

Mount (FM)", "Floor Crane (FC)" and "Trolleys (T)". Please also confirm that slings, rigging hardware and below-the-hook lifting devices are excluded from this SOW.

Slings, rigging hardware, and below-the-hook lifting devices are excluded from the inspection scope of this

SOW, though SLAC will provide rigging hardware as needed for load-testing purposes

11/13/26 N/A

8 11/10/26 SOW §3.1 (MC, TMJ) Mobile crane and truck-mounted jibs. Please provide make, model and capacity for the Mobile Crane (MC) and the three

Truck Mounted Jibs (TMJ). Will SLAC provide a qualified/certified operator for operational and load testing of these units, and will they be presented at a single location?

SLAC will provide a qualified operator to operate the units during testing, and the equipment can be staged at a single location upon Subcontractor request.

11/13/26 N/A

9 11/10/26 SOW §3.2, §5 Crane operation during inspection. Will SLAC furnish qualified operators to operate cranes during operational tests, or are the

Subcontractor's inspectors permitted to operate SLAC cranes?

Who performs lockout/tagout of crane disconnects—SLAC personnel, or the Subcontractor under SLAC's LOTO program? If the latter, what SLAC LOTO/electrical safety training or authorization is required for Subcontractor personnel?

Subcontractor personnel are permitted to operate SLAC cranes during operational testing. SLAC-qualified personnel will perform all lockout/tagout (LOTO) of crane disconnects. Subcontractor personnel may be required to complete SLAC electrical safety training, but are strictly prohibited from performing any electrical work.

10 11/10/26 SOW §3.3 Preventative maintenance limits. Please define the extent of PM included in the FFP. Specifically: (a) are lubricants and consumables included; (b) is gearbox oil changing included; (c) is wire rope lubrication included; (d) are brake and limit switch adjustments included; and (e) is replacement of any parts (e.g., fuses, contacts, pendant buttons) included or treated as corrective repair outside this

SOW?

All preventative maintenance items listed in (a) through

(e)—including lubricants/consumables, gearbox oil changes, wire rope lubrication, brake and limit switch adjustments, and minor part replacements (e.g., fuses, contacts, pendant buttons)—shall be included in the Firm

Fixed Price offer.

11/13/26 Statement of

Work, Rev 04

11 11/10/26 SOW §3.6

(Equipment); Section B Item 01

Lift equipment duration. Item 01 is priced per month for nine (9) months. Does SLAC expect aerial lifts to remain on site continuously for the full period, or only during scheduled inspection events? Please identify which buildings/assets require

60-ft boom, 80-ft boom or scissor lift access.

Lift scheduling will be coordinated and agreed upon between the SLAC Project Manager and the

Subcontractor. As a standard practice, the Subcontractor may group and complete all buildings requiring the same lift type while that equipment is mobilized on site

11/13/26 N/A

12 11/10/26 SOW §3.6 (Equipment) Lift logistics and access. Please advise: (a) whether an on-site staging/storage location is available for lift equipment; (b) whether lifts may be driven between buildings on SLAC roads; (c) any door-size, floor-loading, or interior restrictions; and (d) whether runway walkways, catwalks or crane bridge walkways may be used for access in lieu of lifts where available.

(a) Yes, an on-site staging/storage location is available for lift equipment.

(b) Yes, lifts may be driven between buildings on SLAC roads.

(c) Most facility doors can accommodate standard aerial lifts.

(d) Yes, runway walkways, catwalks, or crane bridge walkways may be used for access in lieu of lifts, subject to prior approval from SLAC Environment, Safety, and Health

(ES&H).

11/13/26 N/A

13 11/10/26 SOW §3.6

(Equipment); Section B Item 01

Lifts for troubleshooting. If aerial lifts are required for a troubleshooting or emergency call, should that lift cost be included in Item 01, or billed under Item 03 (Labor Hour)? Item

03 is labor-only; please confirm how materials, equipment rental and ODCs for troubleshooting are to be priced and invoiced.

Any aerial lifts, equipment rentals, materials, or ODCs required for troubleshooting or emergency calls shall be priced under Section B, Line Item 03.

All associated costs must be built into a single, fully burdened hourly labor rate.

11/13/26 N/A

14 11/10/26 SOW §3.5; Section B Item 03; Non-Green Rider §4

Emergency response hours. Is the 4-hour on-site emergency response required 24 hours/7 days, including weekends, SLAC holidays and the holiday shutdown period? The Non-Green Rider limits work to 7am–5pm M–F unless authorized in advance by the

Procurement Specialist; please explain how afterhours emergency calls will be authorized.

The 4-hour on-site emergency response requirement applies during standard SLAC operating hours only:

Monday through Friday, 7:00 AM to 5:00 PM, excluding

SLAC holidays and shutdown periods. For emergency requests received outside of these hours, the 4-hour response window will carry over to the start of the next

SLAC business day.

11/13/26 Statement of

Work, Rev 04

15 11/10/26 Section B Item 03;

Cover Letter Labor-hour rates. For Item 03, may the Offeror propose separate rates for straight time, overtime and after-hours/holiday emergency response, and a minimum call-out charge (e.g., 2 or 4 hours)? Is travel/mobilization time billable? Please confirm the single unit price shown in Section B may be a weighted or blended rate if only one rate is permitted.

No. Offerors shall provide a single fully burdened labor rate. All costs associated with performing the required services shall be included in the proposed unit price.

Rates may be weighted or blended.

ITEM DATE

SUBMITT ED

RFP DOCUMENT

REFERENCE

QUESTION RESPONSE RESPONS E

DATE

RFP ACTIONS

16 11/10/26 Section B Item 02;

Cover Letter Billing of FFP inspections. Please confirm how Item 02 is to be invoiced: equal monthly installments over the period, or upon completion of each quarterly/annual inspection event.

The Subcontractor shall invoice Item 02 in equal monthly installments over the period of performance, unless otherwise negotiated prior to award.

11/13/26 N/A

17 11/10/26 SOW §3.1 Changes to asset count. SLAC reserves the right to add or remove equipment. How will the FFP be adjusted? Would SLAC like a per-asset unit price by equipment category included in the price breakdown for this purpose?

The maximum covered inventory will not exceed 283 cranes at any time without an adjustment. If the inventory increases beyond 283 assets, the Subcontractor may request an equitable adjustment based on agreed-upon per-asset unit pricing, which will be executed via a formal Subcontract Modification.

11/13/26 Statement of

Work, Rev 04

18 11/10/26 SOW §7; Non-Green

Rider Radiological and restricted areas. Please identify assets located in radiologically controlled areas, beamline housings, tunnels or other restricted areas, and the training (e.g., GERT, RWT), dosimetry and escort requirements for each. Are these assets accessible only during scheduled beam-off/downtime windows, and can SLAC provide the expected access windows for FY27?

SLAC General Employee Radiological Training (GERT) and

Radiological Worker Training (RWT) are required for personnel entering radiologically controlled areas. Assets in beamline housings, tunnels, and restricted areas are accessible only during scheduled beam-off/downtime windows. SLAC is unable to provide the FY2027 downtime schedule at this time.

11/13/26 N/A

19 11/10/26 SOW §7, §8; Section F

Onboarding and schedule. Performance begins January 1, 2027, during the SLAC holiday shutdown. What is the typical lead time for badging, ES&H Orientation and other required training? When does SLAC expect the first quarterly inspection to occur, and will SLAC provide a target inspection calendar?

Badging takes a minimum of one (1) week to complete. If the subcontract is awarded prior to the SLAC winter holiday shutdown, the Subcontractor may begin the badging and onboarding process before January 1, 2027;

otherwise, onboarding will begin on January 4, 2027. The first quarterly inspections will commence the week following January 4, 2027.

11/13/26 N/A

20 11/10/26 SOW §6.2; Section M

Factor 3 Report timing basis. With ~275 assets inspected over multiple days, please confirm whether the 48-hour (or 24-hour for

Exceeds) inspection report window runs from completion of each individual asset, each day's work, each building, or the complete inspection campaign.

The 48-hour (or 24-hour) reporting window begins at the conclusion of each day's inspection work for all assets inspected that day.

11/13/26 N/A

21 11/10/26 SOW §6 Report format and records. Does SLAC require a specific report template, checklist, or upload into a SLAC CMMS/database?

Should Cal/OSHA certificates and inspection tags/labels be posted on each crane? Please provide copies of the most recent annual and quadrennial reports and open-deficiency list for the covered assets.

The Subcontractor may use its own inspection report format, provided the checklist captures all minimum inspection requirements specified in the SOW. Copies of prior annual/quadrennial reports and open-deficiency records will be provided to the selected Subcontractor after award.

22 11/10/26 SOW §3.2, §5 Remove-from-service authority. Please confirm whether the

Subcontractor is authorized to tag an asset out of service, or whether the Subcontractor reports the condition and SLAC applies the out-of-service tag. Please also confirm the SLAC contact for immediate notifications (SOW §3.2) since the

Technical Representative is listed as TBD in Section H.

The Subcontractor is responsible for making the technical determination that an asset is unsafe and must be removed from service; however, SLAC will furnish and apply the physical out-of-service tag. Contact information for the SLAC Technical Representative will be provided at the time of award.

11/13/26 N/A

23 11/10/26 SOW §3.6 (Repair Work) Repair proposals. Will the inspection Subcontractor be eligible to propose corrective repairs identified during inspections (under a separate subcontract), or will SLAC treat that as a conflict of interest? Is the post-repair inspection/load test included in this

SOW or in the separate repair contract?

Yes, the Subcontractor may propose corrective actions and submit quotes for repair work, which will be procured separately from this subcontract without an

Organizational Conflict of Interest.

11/13/26 N/A

24 11/10/26 SOW §4; Section M

Factor 4 Required certifications. Section M Factor 4 evaluates personnel against "all required certifications as identified in the SOW", but

SOW §4 does not name specific certifications. Please list any specific certifications SLAC considers required (e.g., Cal/OSHA-accredited certifier, CMAA/NCCCO inspector, manufacturer training, licensed electrician for controls work).

Inspectors shall be qualified persons as defined by

Cal/OSHA and shall possess documented training and experience in crane inspection in accordance with applicable Cal/OSHA Title 8 and ASME B30 standards.

When crane certification is required by California regulations, inspections and certifications shall be performed by a Cal/OSHA-accredited Crane Certifying

Agency.

11/13/26 Section M

Revised

25 11/10/26 Section J Att. 04 (WD

2015-5637) SCA classification. Please identify the wage determination classification(s) SLAC considers applicable to crane inspectors and troubleshooting technicians (e.g., 23640 Millwright, 23160

Electrician, Maintenance) and confirm the SCA flows down to a lower-tier certifier performing the annual/quadrennial work.

The applicable SCLS wage determination classification is

23430 – Heavy Equipment Mechanic. SCLS requirements flow down to any lower-tier subcontractor performing annual or quadrennial inspection and certification work.

11/13/26 N/A

ITEM DATE

SUBMITT ED

RFP DOCUMENT

REFERENCE

QUESTION RESPONSE RESPONS E

DATE

RFP ACTIONS

26 11/10/26 Section A; Section G Contract type. Section A, Block 3 lists "Firm Fixed Price"; Section

B and the cover letter describe a combination FFP and Labor-Hour award. Please confirm both the Fixed Price and T&M/Labor-Hour

General Terms and Conditions apply to their respective line items.

Section A, Block 3 listing only "Firm Fixed Price" was a clerical error. SLAC will revise Section A via solicitation amendment to reflect the hybrid Firm Fixed Price (FFP) and Labor-Hour (LH) contract structure, with the respective General Terms and Conditions applying to each applicable line item.

11/13/26 Section A

Revised

27 11/10/26 Section L §7 Site walk. Will SLAC hold a site walk before the proposal due date, or provide representative photos/drawings of high-bay installations, so Offerors can evaluate access and lift equipment needs required under SOW §3.6?

SLAC will not conduct a site walk for this requirement. 11/13/26 N/A

28 11/10/26 Section L §11; Cover

Letter Clarifications in proposal. Because assumptions or clarifications in a proposal may be considered non-responsive, please confirm

SLAC's responses to these questions will be issued by amendment

Yes, all official responses to Offeror clarification requests will be issued via formal Solicitation Amendment, and any resulting changes or commitments will be incorporated

11/13/26 Amendment

01 Issued and incorporated into the subcontract, so Offerors may price on the basis of those responses.

into the Statement of Work (SOW) and resulting subcontract so Offerors may price their proposals accordingly.