26365 MSHP Day Use Restroom - Addendum 1.pdf

PDF 2 MB Posted

Attached to
751/26365. ABG; MSHP Day Use Restroom Renovations
Solicitation number
RFQ 171 260000000468 2
Issued by
Livingston County, Mcbride Village, Michigan

About this file

This is Addendum No. 1 to a construction contract issued by the Michigan Department of Natural Resources (DNR) for the Colonial Michilimackinac MSHP Day Use Restroom renovation project located in Mackinac City, Michigan. The addendum, issued October 6, 2026, clarifies and modifies the original plans and specifications prepared by UP Engineers and Architects, Inc. Key modifications include the addition of Section 10 28 00 covering toilet, bath, and laundry accessories to the specifications; replacement of drawings A101 and A201 with revised versions; and the addition of a new Site Plan (C101). The addendum also establishes responsibility for snow removal, with MSHP responsible for parking lot clearance and the contractor responsible for site access and work area clearing. A mandatory pre-bid walkthrough was conducted with an attached sign-in sheet and pre-bid meeting agenda provided. Material testing results for lead, cadmium, and asbestos are included, with paint analysis from samples taken at the exterior soffit location showing cadmium levels of 31.7 mg/kg.

The addendum specifies four additional light fixture options for the project, including models from Metalux, HALO, Luminaire LED, and EVENLITE manufacturers. The project file number is 751/26365.ABG with UP Engineers and Architects order number 713454. Material testing was performed by Schneider Laboratories Global, Inc. in Richmond, Virginia, with analysis completed on September 28, 2026. Bidders were required to acknowledge receipt of Addendum No. 1 on their bid forms and include the addendum with their bid packages.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

707 Ashmun Street Sault Ste. Marie, MI 49783

906-635-0511 • 800-867-0511 • Fax: 906-635-0612

Offices also in:

Houghton

Iron Mountain Ishpeming Marinette

U.P. Engineers & Architects, Inc. www.UPEA.com

[M12-06362]

ADDENDUM NO. 1

TO THE

DNR/Colonial Michilimackinac MSHP Day Use Restroom Mackinac City, MI

ADDENDUM NO. 1 is issued October 6, 2026, to clarify, modify, and/or change the original plans and specifications issued by UP Engineers and Architects. This ADDENDUM NO. 1 is hereby made part of the Contract Documents for the contract noted below.

File No. 751/26365.ABG DNR/Colonial Michilimackinac MSHP Day Use Restroom

Please acknowledge receipt of this ADDENDUM NO. 1 on the appropriate blank on the Bid Form and also include this addendum with the bid package.

GENERAL

1. See attached mandatory pre-bid walkthrough sign-in sheet.

2. See the attached pre-bid meeting agenda.

3. See the attached paint and material testing results for lead, cadmium and asbestos.

SPECIFICATIONS

4. Add the attached SECTION 10 28 00 TOILET, BATH, AND LAUNDRY ACCESSORIES to the specifications.

PLANS

5. Add the attached C101 SITE PLAN to the drawings

6. Replace A101 and A201 with the attached revised drawings.

7. AD100 – Add GENERAL NOTE: MSHP WILL BE RESPONSIBLE FOR SNOW

REMOVAL FOR THE PARKING LOT. CONTRACTOR WILL BE

RESPONSIBLE FOR SNOW REMOVAL FOR ACCESS FROM THE PARKING

LOT AND AROUND THE SITE AS NECESSARY FOR THE WORK.

8. AD101 – Add GENERAL NOTE: EXISTING CEILING IS LATH AND PLASTER

9. E505 LIGHT FIXTURE SCHEDULE – Add the following as additional light fixtures

Type A: Metalux model # 4PWM-2060C5 Type B: HALO model # SMX8SLSFS010 Type C: Luminaire LED model # SWP1212-NODIM-25W-40K-MVOLT-

OP-BRZ

Type EM: EVENLITE model # WW-EM-BZ-CT

END OF ADDENDUM NO. 1

Prepared by:

U.P. Engineers & Architects, Inc

Attn:

Address: 424 South Pine Street Order #: 713454

Ishpeming, MI 49849

Project: MSHP Day Use Restroom Reno

UP Engineers & Architects, Inc. (2716)Customer:

M12-06362Number: PO Number:

Received 09/28/26

Schneider Laboratories Global, Inc 2512 W. Cary Street • Richmond, Virginia • 23220-5117 804-353-6778 • 800-785-LABS (5227) • Fax 804-359-1475

Location: Mackinac Restroom

09/28/26Reported

Analysis Report

Cust. Sample ID

Parameter

Sample ID Location

UnitsRL* AnalystAnalysis DateResultMethod

Matrix Paint

713454-001 100 Ext Soffit Tan

Metals Analysis

Cadmium mg/kg DM09/28/2631.7<31.8EPA 6010D / ME-003

Lead mg/kg DM09/28/2631.7977EPA 6010D / ME-003

713454-002 101 Ext Win Tan

Metals Analysis

Cadmium mg/kg DM09/28/266.3718.4EPA 6010D / ME-003

Lead mg/kg DM09/28/2663735800EPA 6010D / ME-003

713454-003 102 Storage Ceiling White

Metals Analysis

Cadmium mg/kg DM09/28/266.6490.9EPA 6010D / ME-003

Lead mg/kg DM09/28/2666.43280EPA 6010D / ME-003

713454-09/28/26 04:57 PM

Analyst

Reviewed By: Ahmed Elnasseh

Method Parameter Michigan Virginia

State Certifications

Cadmium No state cert. necessary VELAP CertifiedEPA 6010D

Lead No state cert. necessary VELAP CertifiedEPA 6010D

State Certificate Number

Virginia VELAP 14319

All internal QC parameters were met. Unusual sample conditions, if any, are described. Surrogate Spike results designated with "D" indicate that the analyte was diluted out. "MI" indicates matrix interference. Concentration and *Reporting Limit (RL) based on areas provided by client. Values are reported to three significant figures. Solid PPM = mg/kg | PPB = µg/kg and Water PPM = mg/L | PPB = µg/L. The test results apply to the sample as received.

Attn:

Address: 424 South Pine Street Order #: 713453

Ishpeming, MI 49849

UP Engineers & Architects, Inc. (2716)Customer:

Received 09/28/26

Schneider Laboratories Global, Inc 2512 W. Cary Street • Richmond, Virginia • 23220-5117 804-353-6778 • 800-785-LABS (5227) • Fax 804-359-1475

10/04/26Analyzed

10/05/26Reported

Analysis Report

PLM Analysis

Cust. IDSample ID LocationCollected Asbestos Fibers Other Materials

EPA 600/R-93/116 & 40 CFR App. E Sub. E Pt. 763Method:

Project: MSHP Day Use Restroom

M12-06362Number:

Location: Mackinac Restroom

Mackinac Restroom09/23/26 1A713453-001

Tan/Black, Bituminous

ShingleLayer 1: No Asbestos Detected

Sample was inhomogenous, subsamples of each component were analyzed separately.

MINERAL/GLASS WOOL20%

NON FIBROUS MATERIAL80%

Black, Bituminous/Fibrous

UnderlaymentLayer 2: No Asbestos Detected MINERAL/GLASS WOOL55%

NON FIBROUS MATERIAL45%

West Side09/23/26 2A713453-002

Gray, Granular

Window GlazingLayer 1: NON FIBROUS MATERIAL98%2% CHRYSOTILE

Mens Bath09/23/26 3A713453-003

Gray, Granular

Ceiling PlasterLayer 1: No Asbestos Detected NON FIBROUS MATERIAL100%

Mens Bath09/23/26 4A713453-004

Gray, Granular

GroutLayer 1: No Asbestos Detected NON FIBROUS MATERIAL100%

Storage Ceiling Room09/23/26 5A713453-005

Gray, Granular

Ceiling PlasterLayer 1: No Asbestos Detected NON FIBROUS MATERIAL100%

Mackinac Restroom09/23/26 6A713453-006

Gray, Granular

MortarLayer 1: No Asbestos Detected NON FIBROUS MATERIAL100%

Reporting Limit: 1% Gravimetrically Reduced Reporting Limit: 0.01% PLM analysis is based on Visual Estimation and NESHAP recommends that any friable sample with an asbestos content less than 10 percent be verified by Point Count or TEM Analysis. The EPA recommends that any attic loose fill vermiculite should be treated as asbestos containing material. This report must not be reproduced except in full with the approval of the laboratory. Laboratory estimated asbestos error rates available upon request. The test results apply to the sample as received.

PLM Analysis

Cust. IDSample ID LocationCollected Asbestos Fibers Other Materials

EPA 600/R-93/116 & 40 CFR App. E Sub. E Pt. 763Method:

Project: MSHP Day Use Restroom

M12-06362Number:

Location: Mackinac Restroom

Laboratory Director

Reviewed By: Ben Wood

Total layers analyzed on order: 7 713453-10/05/26 03:09 PM

EPA Regulatory Limit: 1%

Analyst Elsamani Abdelfadiel

Reporting Limit: 1% Gravimetrically Reduced Reporting Limit: 0.01% PLM analysis is based on Visual Estimation and NESHAP recommends that any friable sample with an asbestos content less than 10 percent be verified by Point Count or TEM Analysis. The EPA recommends that any attic loose fill vermiculite should be treated as asbestos containing material. This report must not be reproduced except in full with the approval of the laboratory. Laboratory estimated asbestos error rates available upon request. The test results apply to the sample as received.

DTMB Day Use Restroom Renovations 102800 - 1 Toilet, Bath, And Laundry

Accessories

SECTION 102800

TOILET, BATH, AND LAUNDRY ACCESSORIES

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:

1. Toilet and Shower Room accessories.

B. Related Requirements:

1. Section 061000 - Rough Carpentry: Concealed wood framing and blocking for support of accessories.

2. Section 260503 – Equipment Wiring

1.2 REFERENCE STANDARDS

A. ASTM International:

1. ASTM A123 - Standard Specification for Zinc (Hot Dip Galvanized) Coatings on Iron and

Steel Products.

2. ASTM A153 - Standard Specification for Zinc Coating (Hot Dip) on Iron and Steel

Hardware.

3. ASTM A269 - Standard Specification for Seamless and Welded Austenitic Stainless Steel

Tubing for General Service.

4. ASTM A653 - Standard Specification for Steel Sheet, Zinc Coated (Galvanized) or Zinc

Iron Alloy Coated (Galvannealed) by the Hot Dip Process.

5. ASTM A666 - Standard Specification for Annealed or Cold Worked Austenitic Stainless

Steel Sheet, Strip, Plate, and Flat Bar.

6. ASTM B456 - Standard Specification for Electrodeposited Coatings of Copper Plus

Nickel Plus Chromium and Nickel Plus Chromium.

7. ASTM C1036 - Standard Specification for Flat Glass.

1.3 COORDINATION

A. Coordinate Work of this Section with placement of reinforcement of toilet partitions to receive anchor attachments.

1.4 SUBMITTALS

A. Product Data: Submit data on accessories, describing size, finish, details of function, and attachment methods.

B. Manufacturer's Instructions: Submit special installation procedures, conditions requiring special attention, and maintenance requirements.

1.5 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum ten years' experience.

1.6 WARRANTY

A. Furnish ten-year manufacturer's warranty for electric hand dryers.

Renovations 102800 - 2 Toilet, Bath, And Laundry

Accessories

B. Furnish fifteen-year manufacturer's warranty for mirror glass and stainless steel mirror frames.

PART 2 PRODUCTS

2.1 TOILET AND SHOWER ROOM ACCESSORIES

A. Manufacturers:

1. American Specialties, Inc.

2. Bobrick Washroom Equipment

3. Bradley Corporation

4. Koala Kare

5. Grab Bar Specialist

6. Georgia Pacific

7. GOJO

8. Global Industries.

9. World Dryer

10. Substitutions: Section 016000 - Product Requirements.

B. Performance and Design Criteria:

1. Design grab bars and attachments to resist minimum 250 lb concentrated load applied at any point in any direction.

2.2 MATERIALS

A. Accessories: Shop assembled, free of dents and scratches, and packaged complete with anchors and fittings, steel anchor plates, adapters, and anchor components for installation.

1. Grind weld joints smooth.

2. Fabricate units made of metal sheet of seamless sheets with flat surfaces.

3. Install 2x blocking in wall at grab bars, shower seats and shelves.

B. Keys: Furnish two keys for each keyed accessory to Owner.

C. Stainless Steel Sheet: ASTM A666, Type 304.

D. Stainless Steel Tubing: ASTM A269, Type 304 stainless steel.

E. Galvanized Sheet Steel: ASTM A653, G90 zinc coating.

F. Mirror Glass (Type MR-F): ASTM C1036, Type 1 transparent flat, Class 1 clear, Quality Q2 mirror; type with copper and silver coating, and organic overcoating.

G. Adhesive: Two-component epoxy type, waterproof.

H. Fasteners, Screws, and Bolts: Hot-dip galvanized, tamper-proof.

I. Expansion Shields: Fiber, lead, or rubber as recommended by accessory manufacturer for component and substrate.

2.3 FINISHES

A. Stainless Steel: No. 4 satin brushed finish, unless otherwise indicated.

B. Chrome/Nickel Plating: ASTM B456, satin finish.

C. Baked Enamel: Pretreat to clean condition, apply one coat primer and minimum two coats baked enamel.

Renovations 102800 - 3 Toilet, Bath, And Laundry

Accessories

D. Galvanizing: ASTM A123; hot-dip galvanize after fabrication.

E. Galvanizing for Nuts, Bolts, and Washers: ASTM A153.

F. Shop-Primed Ferrous Metals: Pretreat and clean, spray apply one coat primer and bake.

G. Back paint components where contact is made with building finishes to prevent electrolysis.

2.4 TOILET ROOM AND SHOWER ROOM ACCESSORIES

A. All model numbers and manufacturers listed are the Basis of Design. Substitutions may be permitted according to Section 016000 of the specifications.

B. Mirrors:

1. Size: 24”x36” or as indicated on Drawings.

2. Frame: 0.05 inch channel shapes, with mitered, welded, and ground corners, and tamper-proof hanging system; bright annealed finish.

3. Backing: Full mirror sized, minimum 0.03 inch galvanized steel sheet and nonabsorptive filler material.

C. Toilet Paper Dispensers: Double roll dispenser with shelf standard core roll; basis for design:

Bradley.

D. Soap Dispensers: Basis for design: GOJO manual 2,000 ml foam, model #5271-06, color black/chrome

E. Sanitary Napkin Dispenser: Basis for Design: Bobrick B-270, Contura Series

1. 18-8 S, type 304, 22 gauge, stainless steel, all welded construction.

2. Include minimum 12 additional liners, equal to part number Bobrick 270-12.

F. Diaper-Changing Station: Basis for Design: Koala Kare KB208 Baby Changing Station

1. Mounting: Surface mounted.

2. Operation: By pneumatic shock-absorbing mechanism.

G. Grab bars: Stainless steel, 1-1/2” outside diameter, minimum 0.05” wall thickness, nonslip grasping surface, concealed flange mounting; 1-1/2” clear between wall and inside of grab bar.

1. Length and configuration: As indicated on Drawings.

2. Model: 812 Series, manufactured by Bradley.

2.5 CUSTODIAL ACCESSORIES

A. Provide and install (1) each at new janitor sinks.

1. Utility shelf with mop/broom holders and rag hooks; basis for design: Bobrick B-239.

2. Single hose bracket; basis for design: Ferguson’s Proflo Model PF296.

3. Service sink hose; basis for design: Ferguson’s Proflo PFSSHE, 5/8” x 30”.

4. Stainless steel wall shelf; basis for design: Regency Model 600WS1224HD.

5. Stainless steel wall guard; basis for design: Ferguson’s Proflo Model PFWG24S, 12” high.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify exact location of accessories for installation.

B. Verify field measurements and rough-in dimensions for recessed accessories are as instructed by manufacturer.

Renovations 102800 - 4 Toilet, Bath, And Laundry

Accessories

3.2 PREPARATION

A. Deliver inserts and rough-in frames to Site for timely installation.

B. Provide templates and rough-in measurements as required.

3.3 INSTALLATION

A. Do not install accessories until after completion of all finishes to adjacent wall and ceiling surfaces.

B. Install plumb and level, securely and rigidly anchored to substrate.

C. Turn over to Owner all keys and special tools required for lockable or secured accessories.

D. Mounting Heights and Locations: As required by accessibility regulations.

E. Hand dryers: provide dedicated circuit with GFI protection.

3.4 CLEANING

A. Clean mirrors and exposed surfaces using procedures as recommended by accessory manufacturer.

3.5 SCHEDULE

A. Reference Toilet Accessory Schedule on Drawing Sheet A401.

END OF SECTION

V.

I.F

5' - 0"

5' - 6"

DOWEL INTO EXISTING CONCRETE

#5 18" BARS @ 16" O.C. EMBEDDED 8" INTO EXISTING CONCRETE

4' - 6"

CLEARANCE

5' - 0" MIN.

C

LE

AR

AN

C E

5'

0" M

IN

C101

DOWEL INTO EXISTING CONCRETE

#5 18" BARS @ 16" O.C. EMBEDDED 8" INTO EXISTING CONCRETE

DEMO CONCRETE FOR

INSTALLATION OF NEW RAMPS

AND EXTENDED WALK-WAY

COMPACTED SUBGRADE OR EMBANKMENT FILL

C O

N C

R

ET

E W

AL

K

4" C

LA

SS

II

, C

.I.

P.

" M

D O

T

MEDIUM BROOM FINISH

PERPENDICULAR TO

WALK DIRECTION

1/2" EXPANSION JOINT MATERIAL TO BE PLACED

BETWEEN NEW EXTERIOR SLAB AND EXISTING

CONCRETE APRON

CONTROL JOINT FOR SIDEWALK TO BE PLACED EVERY 6'

6" x 6" #10 MESH

STAINLESS STEEL SET SCREWS

1 1/4" ALUMINUM PEG

2" GALVANIZED POST

1 2 3 4 5

1 2 3 4 5

D

C

B

A

D

C

B

A

© U.P. Engineers & Architects, Inc.

PR

OJ

EC

T N

O:

DR

AW

N

BY

CH

EC

KE

D:

AP

PR

OV

ED

DE

SI

GN

ED

B Y:

w w w .u pe a.

co m

IS

SU

ED

F

O R

D

A

TE

P:

\M

-0

D

TM

B- M

SH

P

D ay

U se

R es tro om

R en ov at io ns

\D es ig n\

D ra w in gs \M

-0

.rv t

/6

/2

9:

:4

AM

C101

SITE PLAN

ST

A

TE

O

F M

IC

H

IG

A

N M

A C

K

IN

A C

S

TA

TE

H

IS

TO

R

IC

P A

R K

M

SH

P D

A Y

U

SE

R

ES

TR

O

O M

S R

EM

O

D

EL

N H ur on

A ve

, M ac ki na w C ity , M

I 4

M

-0

G S

JGG

S

ST

A

TE

O

F M

IC

H

IG

A

N M

A C

K

IN

A C

S

TA

TE

H

IS

TO

R

IC

P A

R K

M

SH

P D

A Y

U

SE

R

ES

TR

O

O M

S R

EM

O

D

EL

AD

D

EM

D

U M

-5

-2

1/4" = 1'-0"2 PROPOSED SITE PLAN

1/4" = 1'-0"1 DEMOLITION SITE PLAN

1" = 1'-0"3 SIDEWALK DETAIL

1" = 1'-0"4 RAILING CONNECTION DETAIL

RAILING DETAILS PER "CHAPTER 4: RAMPS AND CURB RAMPS - HANDRAILS"

OF THE US ACCESS BOARD ADA TECHNICAL GUIDE

A201

A201

A2016

MENS

WOMENS

FAMILY RESTROOM

N

EW

L

AN

D

IN

G W

ID

TH

5'

6" N

EW

R

AM

P

LE

N

G

TH

7'

9" N

EW

R

AM

P

AN

D

L

AN

D

IN

G W

ID

TH

5'

6"

BABY CHANGING

STATION

NEW WINDOWS IN

EXISTING MASONRY

OPENINGS (TYP.)

NEW FLUID APPLIED EPOXY

FLOORING

NEW FLUID APPLIED EPOXY

FLOORING

NEW TOILETES

MOP

SINK

JANITOR CLO.

NEW WINDOWS IN

EXISTING MASONRY

OPENINGS (TYP.)

NEW TOILET STALL

PARTITIONS (TYP.)

NEW TOILET STALL

PARTITIONS (TYP.)

A201 5

A202

2A

2C

2B 2D

A202

1A

1C

1D 1B

A202 3A

3D

3C

3B

A301

A301

A201 1 A2012

A201

A201

B2 ø 5' - 7

A1A1A1

NEW WALL TILE ON

FIBER CEMENT BACKER

BOARD ON ALL

PERIMETER WALLS

SEE SHEET A601 FOR

WALL SCHEDULE

NEW WALL TILE ON

FIBER CEMENT BACKER

BOARD ON ALL

PERIMETER WALLS

SEE SHEET A601 FOR

WALL SCHEDULE

104A

NEW LANDING

4' - 11"

NEW RAMP

7' - 9"

12' - 8"

NEW RAMP WIDTH

5' - 6"

NEW LANDING LENGTH

18' - 2"

1"

1' -0

1" / 1'-0"

SL

OP

E

SLOPE

A301

A501

A301

A501

NEW URINALS NEW LAVS

NEW LAVS

NEW 2'x 3' MIRROR

ABOVE EACH SINK

NEW 2'x 3' MIRROR

ABOVE EACH SINK

NEW 2'x 3' MIRROR

ABOVE EACH SINK

NEW 2'x 3' MIRROR

ABOVE EACH SINK

NEW HANDRYER

NEW HAND DRYER

NEW HANDRYER

3' - 4" 3' - 4" 3' - 4" 3' - 4"

6' - 6" 3' - 4" 3' - 4" 3' - 4" 3' - 4"

A1 A1 A1 A1 A1 A1

A1 A1 A1

CONTROL JOINTS

ADA STALL

ADA STALL

7" 7"

7"

5'

1"

6' - 6"

DUAL STAINLESS STEEL TOILET

PAPER DISPENSERS MOUNTED

O.C. 7" FORM FACE OF TOILET

DUAL STAINLESS STEEL TOILET

PAPER DISPENSERS MOUNTED

O.C. 7" FROM FACE OF TOILET

DUAL STAINLESS STEEL TOILET

PAPER DISPENSERS MOUNTED

O.C. 7" FROM FACE OF TOILET

(1) SAMITARY NAPKIN

DISPOSAL PER STALL IN

WOMEN'S RESTROOM

ADA GRAB BARS MOUNTED

PER SHEET A001

5'

1"

1'

6"

EXISTING POST

EXISTING POST

5 1/2" 3' - 0" 5 1/2" 3' - 0" 3' - 3 1/4" 3' - 0" 5 1/2" 3' - 0" 3' - 3 1/4" 3' - 0" 5 1/2" 3' - 0" 5 1/2"

5 1/2" 3' - 0" 5 1/2" 3' - 0" 3' - 3 1/4" 3' - 0" 5 1/2" 3' - 0" 3' - 3 1/4" 3' - 0" 5 1/2" 3' - 0" 5 1/2"

SOFFIT ABOVE

FUR OUT WALL FOR PLUMBING

TO DRINKING FOUNTAINS

SEE PLUMBING PLANS FOR

DRINKING FOUNTAIN DETAILS

PIPES TO BE SLOPED AS SHOWN

IN PLUMBING DETAILS FOR

DRAINING AND WINTERIZING

A301

6x6/6 WWF

6x6/6 WWF

A301

C101

2" GALVANIZED RAIL SYSTEM

SEE ELEVATIONS ON SHEET A201

AND DETAILS ON SHEET C101

2" GALVANIZED RAIL SYSTEM

SEE ELEVATIONS ON SHEET A201

AND DETAILS ON SHEET C101

1 2 3 4 5

1 2 3 4 5

D

C

B

A

D

C

B

A

© U.P. Engineers & Architects, Inc.

PR

OJ

EC

T N

O:

DR

AW

N

BY

CH

EC

KE

D:

AP

PR

OV

ED

DE

SI

GN

ED

B Y:

w w w .u pe a.

co m

IS

SU

ED

F

O R

D

A

TE

P:

\M

-0

D

TM

B- M

SH

P

D ay

U se

R es tro om

R en ov at io ns

\D es ig n\

D ra w in gs \M

-0

.rv t

/6

/2

9:

:4

AM

A101

PROPOSED

FLOOR PLAN

ST

A

TE

O

F M

IC

H

IG

A

N M

A C

K

IN

A C

S

TA

TE

H

IS

TO

R

IC

P A

R K

M

SH

P D

A Y

U

SE

R

ES

TR

O

O M

S R

EM

O

D

EL

N H ur on

A ve

, M ac ki na w C ity , M

I 4

M

-0

D C

/G S

JA JGD

C

/G S

ST

A

TE

O

F M

IC

H

IG

A

N M

A C

K

IN

A C

S

TA

TE

H

IS

TO

R

IC

P A

R K

M

SH

P D

A Y

U

SE

R

ES

TR

O

O M

S R

EM

O

D

EL

1/2" = 1'-0"A1 PROPOSED FLOOR PLAN

TYP.

O W

N

ER

R

EV

IE

W

6-

-2

O W

N

ER

R

EV

IE

W

7-

-2

PR

O

G R

ES

S

SE

T

8-

-2

R

EV

IE

W

8-

-2

R

EV

IE

W

8-

-2

R

EV

IE

W

9- 9-

BI

D

SE

T 9-

-2

AD

D

EM

D U

M

-5 -2

PAINT EXISTING WOOD PANELS IN GABLE ENDS

B2

M

AX

2'

3"

MIN

1' - 0"

MAX

6' - 0"

2'

6" 6"

A1 A1 A1 A1 A1 A1

2'

6" 6"

MAX

6' - 0"

A301

INFILL W/ CERTAINTEED COMPOSITE

PANEL IN NATURAL CLAY

SEE DETAIL 5 ON SHEET 301

A1 A1 A1A1 A1 A1

A301

MIN

1' - 0"

M

AX

2'

3"

6" 2'

6"

MAX

6' - 0"

1 2 3 4 5

1 2 3 4 5

D

C

B

A

D

C

B

A

© U.P. Engineers & Architects, Inc.

PR

OJ

EC

T N

O:

DR

AW

N

BY

CH

EC

KE

D:

AP

PR

OV

ED

DE

SI

GN

ED

B Y:

w w w .u pe a.

co m

IS

SU

ED

F

O R

D

A

TE

P:

\M

-0

D

TM

B- M

SH

P

D ay

U se

R es tro om

R en ov at io ns

\D es ig n\

D ra w in gs \M

-0

.rv t

/6

/2

9:

:5

AM

A201

EXTERIOR

ELEVATIONS

ST

A

TE

O

F M

IC

H

IG

A

N M

A C

K

IN

A C

S

TA

TE

H

IS

TO

R

IC

P A

R K

M

SH

P D

A Y

U

SE

R

ES

TR

O

O M

S R

EM

O

D

EL

N H ur on

A ve

, M ac ki na w C ity , M

I 4

M

-0

G S

JA JGG

S

ST

A

TE

O

F M

IC

H

IG

A

N M

A C

K

IN

A C

S

TA

TE

H

IS

TO

R

IC

P A

R K

M

SH

P D

A Y

U

SE

R

ES

TR

O

O M

S R

EM

O

D

EL

1/4" = 1'-0"5 EAST ELEVATION

1/4" = 1'-0"6 WEST ELEVATION

1/4" = 1'-0"7 NORTH ELEVATION

1/4" = 1'-0"8 SOUTH ELEVATION

1/4" = 1'-0"1 EAST ELEVATION DEMO

1/4" = 1'-0"2 WEST ELEVATION DEMO

1/4" = 1'-0"4 SOUTH ELEVATION DEMO

1/4" = 1'-0"3 NORTH ELEVATION DEMO

DEMO LOUVERS AND EXTERIOR PANELLING

PREP FOR NEW WINDOWS

DEMO ALL EXISTING EXTERIOR DOORS, FRAMES, AND WINDOWS

DEMO WOOD AND CONCRETE RAMPS AND LANDINGS BOTH SIDES

DEMO ALL EXISTING SOFFIT AND FASCIA, TYP.

NEW VENTED SOFFIT AND FASCIA

WRAP COLUMNS IN NEW COMPOSITE FINISH TYP.

NEW CONCRETE RAMP AND LANDING TO ACCOMMODATE FAMILY RESTROOM NEW CONCRETE RAMP AND LANDING

INSTALL NEW DOORS, WINDOWS, AND FRAMES

NEW VENTED SOFFIT AND FASCIA

WRAP COLUMNS IN NEW FINISH TYP.

NEW CONCRETE RAMPS AND LANDINGS

NEW WINDOWS

DEMO EXISTING SHINGLES,

UNDERLAYMENT, AND DRIP EDGE

NEW RIDGE VENT

DEMO ALL EXISTING EXTERIOR

DOORS, FRAMES, AND WINDOWS

DEMO WOOD AND CONCRETE RAMPS AND LANDINGS BOTH SIDES

DEMO ALL EXISTING SOFFIT AND FASCIA,

TYP.

DEMO EXISTING SHINGLES,

UNDERLAYMENT, AND DRIP EDGES

DEMO FOR NEW MECH LOUVERS

COORDINATE WITH MECHANICAL

NEW MECHANICAL LOUVERS

COORDINATE WITH MECHANICAL

NEW MECHANICAL LOUVERS

COORDINATE WITH MECHANICAL

NEW MECHANICAL LOUVERS

COORDINATE WITH MECHANICAL

PAINT EXISTING WOOD PANELS IN GABLE ENDS

NEW SHINGLES AND UNDERLAYMENT

NEW PLUMBING VENT NEW PLUMBING VENT

NEW PLUMBING VENTNEW PLUMBING VENT

POSTS TO REMAIN, TYP.

NEW CERTAINTEED COMPOSITE PANEL

SIDING AND TRIM IN NATURAL CLAY

NEW CERTAINTEED COMPOSITE PANEL SIDING

AND TRIM IN NATURAL CLAY @ AREAS OF

INFILL TYP.

SEE PLUMBING SHEETS FOR NEW DRINKING FOUNTAIN DETAILS

SEE PLUMBING SHEETS FOR NEW

DRINKING FOUNTAIN DETAILS

PREP AND APPLY BRICK WATER

REPELANT SEALANT PER SPECS

PREP AND APPLY BRICK WATER

REPELANT SEALANT PER SPECS

PREP AND APPLY BRICK WATER

REPELANT SEALANT PER SPECS

PREP AND APPLY BRICK WATER REPLANT

SEALANT PER SPECS

O W

N

ER

R

EV

IE

W

6-

-2

O W

N

ER

R

EV

IE

W

7-

-2

PR

O

G R

ES

S

SE

T

8-

-2

R

EV

IE

W

8-

-2

R

EV

IE

W

8-

-2

R

EV

IE

W

9- 9-

BI

D

SE

T 9-

-2

AD

D

EM

D U

M

-5 -2

NEW RAILINGS

Addendum No. 1.pdf
Meeting Attendance.pdf
Pre-bid Meeting Agenda.pdf
713454 Attachment 09-29-26 0857AM.pdf
102800-Toilet, Bath, And Laundry Accessories.pdf
M12-06362_MSHP RESRTROOM RENOVATIONS_ADDENDUM 01_10.8.26.pdf

File details come from the government source that posted it. Updated .