This Statement of Work is issued by the Facility Engineering Division of the Massachusetts Army National Guard for Camp Edwards, located on Cape Cod, Massachusetts. The document outlines procurement, installation, and annual inspection/maintenance services for fire extinguishers across all Camp Edwards facilities. The contractor must furnish all necessary fire extinguishers, installation labor and supervision, and annual certification services for a three-year contract period. The project encompasses 89 buildings requiring between 1 and 13 fire extinguishers each, with specifications for 5-pound ABC, 10-pound ABC, 2A\K, and 10 BC extinguisher classes mounted on walls at heights between 4 inches and 5 feet above floor level. All work must be completed following receipt of the Notice to Proceed, with contractors required to coordinate schedules with building managers and the Project Manager at least three business days in advance of service dates. Camp Edwards operates during normal working hours from 7:00 a.m. to 3:00 p.m., Monday through Friday, excluding Federal and State holidays.

The contractor must possess at least five years of prior experience in fire extinguisher services and maintain all appropriate licenses and certifications required by Massachusetts State Building Codes and Federal regulations. All personnel, including subcontractors and employees, are subject to National Crime Information Center background checks and must provide Real IDs or Passports for security clearance prior to base access through the main entrance at 4000 Connery Ave, Buzzards Bay, Massachusetts. Work must comply with OSHA standards, Massachusetts environmental regulations, and JBCC Fire Prevention Standard 911-1, with hot work permits required for any welding or spark-producing operations. The contractor assumes full responsibility for any damage to facilities or finishes resulting from operations, including cleanup and restoration at no additional cost to the government. Upon completion, the contractor must provide an electronic list of all building numbers and installation locations and conduct a final inspection with the Project Manager.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FACILITY ENGINEERING

MASSACHUSETTS ARMY NATIONAL GUARD 2808

RICHARDSON ROAD

CAMP EDWARDS CAPE COD, MA 02542

PROJECT NUMBER 260686

STATEMENT OF WORK FOR

CONTRACT SERVICES TO

PERFORM

Procurement, Installation, and Annual

Inspection/Maintenance of Fire Extinguishers for Camp

Edwards

AT

MTA CAMP EDWARDS,

CAPE COD MASSACHUSETTS

June 2026

Procurement, Installation, and Annual

Inspection/Maintenance of Fire Extinguishers for

Camp Edwards

STATEMENT OF WORK

SECTION 01000

GENERAL REQUIREMENTS

This statement of work is hereby made part of the pre-printed forms of this contract.

1.1 SCOPE OF WORK: Furnish all necessary fire extinguishers, installation labor/supervision, and annual certification services for all the facilities listed in this document. All facilities listed are owned by MTA Camp Edwards, MA.

1.2 HOURS OF OPERATION: Normal working hours for Camp Edwards are 7:00 a.m. to 3:00 p.m.

Monday through Friday, excluding Federal & noted State Holidays. Any work requested outside these scheduled times, if approved by the Contracting Officer, will be performed at no additional cost to the government.

1.3 QUALIFICATIONS: The work as specified herein shall be performed by qualified personnel who are thoroughly familiar with specific fire extinguisher work in commercial facilities. The Contractor and/or Foreman and any sub-contractors must have been engaged in this type of business for at least five (5) years prior to the date of his/her bid and shall have all appropriate licenses and/or certifications necessary to perform the work as outlined. The contractor shall provide the Project Manager (PM) and/or the Contracting Officer (CO) with a copy of said licensing and certifications upon request.

1.4 INSPECTION BY THE GOVERNMENT: The Project Manager, as the designated field representative, will witness and/or inspect all aspects of the Contractors’ work. All work rejected because of these inspections will be re-accomplished by the Contractor at no additional cost to the Government.

1.5 ENVIRONMENTAL CONSIDERATIONS: Contractor shall take every precaution to protect both land and water resources within the Base proper, on Cape Cod and throughout Massachusetts in general. Under no circumstances will waste or recycling byproducts be disposed of at any other than the designated and/or an approved site for the specified byproduct. The contractor shall collect, transport, store, recycle, and dispose of all waste and recycling materials in strict compliance with these specifications and in accordance with all applicable laws and regulations of the Commonwealth of Massachusetts. Should spillage of any kind occur, the Contractor shall take immediate actions to contain the spillage and appropriately clean up or abate the area as necessary and notify the appropriate authorities 911. If clean up or abatement actions are necessary, the Contractor shall comply with the applicable Federal, State and local laws and regulations concerning environmental pollution control and abatement, in effect on the bid date for this contract. All necessary clean up and/or abatement and site restoration actions shall be at the direction of the Contracting Officer and at no additional cost to the Government.

1.6 SAFETY: All work shall be accomplished in accordance with applicable OSHA Standards. The contractor shall take all necessary precautions to ensure the work crew abides by industry safety standards in the performance of the work.

1.7 FIRE PROTECTION: The Contractor shall take all necessary precautions to ensure all operations are performed in a safe manner and that they are in strict compliance with current State and Federal Codes and Regulations. Additionally, he/she shall adhere to the requirements of JBCC Fire and Emergency Services Fire Prevention Standard 911-1 while performing work on Camp Edwards. HOT

WORK PERMITS ARE REQUIRED FOR ALL WELDING, CUTTING, AND/OR SPARK PRODUCING

OPERATIONS. Hot work permits are issued through the PM of the project.

1.8 SECURITY REQUIREMENTS: Camp Edwards is a "closed" facility located at Joint Base Cape Cod (JBCC). Entrance to JBCC and Camp Edwards is controlled, and security is strictly enforced. An NCIC (National Crime Information Center) background check will be accomplished on all contractor personnel prior to access to those facilities under jurisdiction of Provost Marshall and Security Forces Counsel of the JBCC. Contractor shall be required to provide the Real IDs or Passports of their personnel and that of any sub-contractors at the pre-performance meeting or no less than 3 business days prior to required access.

1.8.1 The Project Manager (PM), telephone (857) 360-5534, will provide the successful bidder with an electronic copy of the Security form, used to provide the necessary information. The personal information shall be filled in completely and submitted via email to the PM. Required information: Employers’ name, Employees name, Date of Birth and Citizenship, Country of Origin, Real ID and State of issue, Vehicle year, Make & Model, Vehicle Registration Plate (Tag) number and State of issue.

1.8.2 All access to the base must be through the main entrance located at 4000 Connery Ave, Buzzards Bay, MA 02542. The Security Forces Pass and ID office is located immediately after the main entrance on the lefthand side on Connery Ave. Their hours of operation are from 8:00am – 2:00pm, M - F. The contractor shall ensure that all employees, sub-contractors and their employees, and suppliers are registered for base entrance and that they shall remain within the designated "work site" as identified. The contractor is cautioned that the Government will not be held liable for any cost incurred due to delays encountered or for non-compliance or conformance with the security requirements and procedures.

1.9. CONTINUED USE OF FACILITIES: During this contract, the site will continue to be occupied.

Work will be performed in an orderly manner with minimum disturbance and inconvenience to the occupant. The contractor will confine their personnel to only those areas required in performing the work.

Agreement will be reached between the contractor and the Project Manager as to when the site will be available to perform the work. The contractor will inform the PM of these arrangements and confirm the appointment three (3) business days prior to the proposed schedule to ensure nothing has changed and ensure prompt access to the work areas.

1.10. DAMAGE TO APPURTENANCES OR FINISHES: Damaged property due to the contractor's operations will be cleaned, repaired, replaced, or restored without cost to the government. Misuse or abuse of government property will be a reason for default action under the terms of the contract.

1.11. SITE VISIT: Prospective bidders are not required to attend the site walk. The project site-walk date and time will be posted on COMMBUYS. Bidders are cautioned to submit an NCIC form to the PM to obtain pre-approval base access, 72 hours in advance to the site walk. Individual appointments will not be accommodated.

END OF SECTION

SECTION 02000

SPECIFIC WORK REQUIREMENTS

2.0 GENERAL: The contractor shall provide all equipment, labor, materials, parts, supervision and other support services necessary to perform the service. All these services are required to meet: all applicable Federal, State/Local Codes and Regulations. Equipment and tools will be operated strictly in accordance with the limitations established by the manufacturer and to the satisfaction of the Directorate of Facility Engineering Project Manager. All facilities identified herein are located within the confines of Camp Edwards.

2.1 SCHEDULE OF WORK: The contractor will schedule work to begin after the Notice to Proceed has been provided by the Project Manager. The contractor shall be responsible for coordinating with the building manager and the Project Manager to ensure available access and completion within the contract timelines. Once all parties agree to service dates, the Contractor will confirm three (3) days in advance with the PM.

2.2 SUPERVISION: The contractor will provide competent supervision when work is in progress.

He/she is responsible for scheduling and coordinating necessary trade activities through Camp Edward’s Project Management (857) 360-5534. The contractor’s job supervisor shall be held accountable for:

2.2.1 Ensuring that all work is accomplished, and materials used are in accordance with the contract and current code requirements. All materials shall be used strictly in conformance with manufacturer's directions and warnings.

2.2.2 Ensure employees’ conforming to all regulations, Federal, State, and local, governing the performance of all work and that they confine all activities to the specified work site.

2.3 CONTRACT CHANGES:

2.3.1 The Commonwealth Military Division through the National Guard Construction Facility Management Officer reserve the right to modify the original contract by adding, subtracting and/or substituting work elements which fall within the scope.

2.3.2 All changes to this contract shall be submitted through the PM and require processing and approval from the Contracting Officer before they can be considered a part of this contract and/or before any payments can be issued to the contractor.

2.4 SUBMITTALS: The contractor shall be responsible for providing the following document and material submittals to meet the requirements specified herein

SECTION 03000

TECHNICAL SCOPE

3.0 GENERAL: The Contractor shall provide all equipment, materials, labor, supervision and or other support services necessary to perform all the work to install fire extinguisher and perform a 3-year annual inspection service contract for all of the listed Camp Edwards facilities

3.1 SYSTEM DESCRIPTIONS: The table below will show what class extinguishers are required in each facility to meet MA state building code. Every fire extinguisher will be mounted on a wall and installed with a wall bracket.

3.2 SPECIFIC REQUIREMENTS: All work shall be performed in strict compliance with the parameters of the Statement of Work unless permitted otherwise by the PM. The contractor is cautioned that their supervisors and laborers shall be thoroughly familiar with the requirements as stated in these documents and this specification and will be required to have a copy of the contract documents with them at the time of service. The contractor service requirements include but are not limited to or by the minimal work elements noted herein and they shall complete the following in their efforts to meet compliance:

3.2.1 All inspection/maintenance/certifications as identified in the equipment’s manufacturers O&M manuals and service bulletins, and standard practices for the trade, and/or required by MA State Building Codes which are not specified or described herein shall be deemed part of this specification.

3.2.2 Minimum Requirements:

3.2.2.1 Procure all of the fire extinguishers with their required wall mounted brackets listed in the table.

3.2.2.2 Install all of the fire extinguishers in the specific facility listed with extinguishers.

3.2.2.3 All fire extinguishers must be installed on a wall and with a wall mount bracket provided by the contractor. Wall material includes but not limited to CMU, Concrete, drywall, and various types of lumber. Wall mounted brackets must be tied into a stud if the wall contains wood studs.

3.2.2.4 The fire extinguishers must be more than 4” above floor level measuring from the bottom of the extinguisher and less than 5’ max height measuring from the top of the extinguisher.

3.2.2.5 An electronic copy of a list that provides all the building numbers and locations in the building where the new fire extinguishers are installed provided to the PM.

3.2.2.6 Upon completion of all work, a complete final inspection with PM.

Building Fire Extinguisher

Building Number Building Area UoM 5lb ABC 10lb ABC 2A\K 10 BC

00102 15,822 SF 6 1

00110 2,304 SF 3

01031 3,195 SF 2

01200 6,035 SF 4 2

01201 3,731 SF 2

01206 6,707 SF 3 1

01213 7,670 SF 5

01221 1,296 SF 2

01224 1,968 SF 2

01225 1,968 SF 2

01226 1,968 SF 2

01227 1,968 SF 2

01228 1,968 SF 2

01229 1,968 SF 2

01232 3,528 SF 3

01233 3,528 SF 3

01243 1,056 SF 1

01244 2,112 SF 1

01245 1,056 SF 1

01246 2,064 SF 1

01247 1,056 SF 1

01248 2,112 SF 1

01249 1,056 SF 1

01250 2,208 SF 1

01251 1,144 SF 1

01253 1,144 SF 1

01254 2,256 SF 3

01255 1,144 SF 1

01257 1,144 SF 1

01259 1,144 SF 1

01261 1,144 SF 1

01262 2,208 SF 1

01263 1,144 SF 1

01265 1,144 SF 1

01267 1,144 SF 1

01269 1,056 SF 1

01805 3,590 SF 3

02806 5,063 SF 6

02807 2,400 SF 3

02808 21,600 SF 6

02810 3,200 SF 1

02812 4,004 SF 4

02814 9,000 SF 4

02816 77,432 SF 10

02822 28,080 SF 6

03139 8,518 SF 6 1 1

03140 2,400 SF 2 2

03461 18,235 SF 4

03468 8,501 SF 6 1

03469 1,676 SF 2

03493 4,800 SF 1

03494 6,000 SF 1

03495 6,400 SF 3

03496 1,400 SF 1

03497 2,400 SF 1

03498 4,970 SF 2

03499 1,750 SF 2

03506 1,500 SF 1

04005 1,144 SF 2

04010 400 SF 1

04012 1,800 SF 1

04017 324 SF 1

04020 3,472 SF 5

04021 780 SF 1

04030 1,144 SF 3

04031 543 SF 1

04032 960 SF 1

04202 368 SF 2

04220 836 SF 1

04350 1,500 SF 2

04679 7,000 SF 1

04680 875 SF 1

04682 49,044 SF 8

04690 180 SF 1

04691 117 SF 1

04699 40 SF 1

5212 1 1

05218 1,900 SF 3 1

05220 14,160 SF 6 2

05221 25,913 SF 2

05222 25,122 SF 9

05223 32,125 SF 9

05224 25,122 SF 9

05230 25,122 SF 9

05231 4,940 SF 6

05232 25,122 SF 9

05234 25,122 SF 9

05240 25,122 SF 9

05242 25,122 SF 9

05243 25,122 SF 9

05244 25,122 SF 9

05245 15,295 SF 6 2

05246 800 SF 3

05518 6,204 SF 9

05519 7,324 SF 9

05520 7,324 SF 9

05521 7,324 SF 9

05522 6,204 SF 9

05523 7,324 SF 9

05524 7,324 SF 9

05526 7,324 SF 9

5501 10,951 SF 13

5502 9,276 SF 13

5503 6,204 SF 9

5505 6,204 SF 9

5506 7,324 SF 9

5507 6,204 SF 9

5508 6,204 SF 9

5509 10,951 SF 9

5510 7,324 SF 9

5511 7,324 SF 9

5512 6,204 SF 9

5513 6,204 SF 9

5514 6,204 SF 9

5515 6,204 SF 9

5516 10,951 SF 13

5517 10,951 SF 13

05219 10,673 SF 6

531 0 7

File details come from the government source that posted it. Updated .