This is a Bid Schedule document for Collier County, Florida's Construction ITB #26-8638 for Goodland Pump Station Improvements. The project involves 17 line items, all quoted on a lump sum basis, including mobilization/demobilization, general requirements, restoration, demolition, asphalt driveway work, yard piping, recirculation pump assembly, pump building interior piping assembly, vertical turbine pumps, sodium hypochlorite pump skid and chemical storage, caustic pump skid and chemical storage, generator, fuel system improvements, mechanical HVAC improvements, electrical improvements, structural improvements, and bypass operations. Sealed bids were due no later than March 5, 2026 at 3:00 p.m. local time. A non-mandatory pre-bid meeting was held on January 28, 2026 at 10:00 a.m. at the South County Regional Water Treatment Plant in Naples, Florida, with a non-mandatory site visit immediately following at the project site located at 2559 San Marco Road, Marco Island, Florida 34145.
The bid schedule shows a total base bid amount of $0.00, indicating this is a blank template for bidder submission. Collier County has allocated a $500,000 Owner's Allowance designated for the Owner's use as directed to address unforeseen conditions. This allowance is not guaranteed to be expended in full and will only be utilized through Change Order with proper documentation of time and materials supporting any changes. Prospective bidders were required to register on the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl to obtain the complete project documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25-XXXXXX Bid Schedule Construction ITB #26-8638 Goodland Pump Station Improvements Bid Schedule
| ITEM NO | DESCRIPTION | QUANTITY | UNITS | TOTAL |
| BASE BID: Includes all items described as the Base BId in the Summary of Work as shown on the attached Drawings and Exhibits with no substitutions or limitations. | ||||
| 1 | Mobilization/Demobilization | 1 | Lump Sum | |
| 2 | General Requirements | 1 | Lump Sum | |
| 3 | Restoration | 1 | Lump Sum | |
| 4 | Demolition | 1 | Lump Sum | |
| 5 | Asphalt Driveway | 1 | Lump Sum | |
| 6 | Yard Piping | 1 | Lump Sum | |
| 7 | Recirculation Pump Assembly | 1 | Lump Sum | |
| 8 | Pump Building Interior Piping Assembly | 1 | Lump Sum | |
| 9 | Vertical Turbine Pumps | 1 | Lump Sum | |
| 10 | Sodium Hypochlorite Pump Skid and Chemical Storage | 1 | Lump Sum | |
| 11 | Caustic Pump Skid and Chemical Storage | 1 | Lump Sum | |
| 12 | Generator | 1 | Lump Sum | |
| 13 | Fuel System Improvements | 1 | Lump Sum | |
| 14 | Mechanical HVAC Improvements | 1 | Lump Sum | |
| 15 | Electrical Improvements | 1 | Lump Sum | |
| 16 | Structural Improvements | 1 | Lump Sum | |
| 17 | Bypass Operations | 1 | Lump Sum | |
| TOTAL BID FOR ITEMS 1 THROUGH 17 | $0.00 | |||
| *Staff has allocated $500,000 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change |