This is a bid schedule document for Collier County, Florida's SCWRF Electrical Service #1 Upgrades project (Bid No. 26-8628). The project involves a comprehensive electrical room upgrade at the South County Water Reclamation Facility located at 5600 Warren Street, Naples, Florida. Key work items include mobilization/de-mobilization, removal of existing switchgear and generators, provision of temporary power through multiple portable generators (500KW and 600KW units), furnishing and installation of new switchgear equipment, switchgear control panel equipment, two generators with associated day tanks and diesel piping systems, and a generators tap box. Sealed bids must be received by March 5, 2026 at 3:00 p.m. local time. A non-mandatory pre-bid meeting is scheduled for January 27, 2026 at 10:00 a.m., followed immediately by a non-mandatory site visit, both at the project location. Prospective bidders must register through the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl to obtain complete solicitation documents.

The bid schedule is structured as a lump sum (LS) contract with seven major work categories. All line items are currently listed with placeholder pricing of "$-0" pending contractor proposals. Collier County has allocated an Owner's Allowance of $400,000 for unforeseen conditions and work directed by the owner, which will be administered through formal change orders with supporting documentation of time and materials. The inclusion of the Owner's Allowance does not guarantee payment of any portion of these funds. Expenditures will be authorized only through change orders as conditions warrant or as directed by the County.

View the file

Other files for this state and local contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASE

COLLIER CO. SCWRF ELECTRICAL ROOM #1 UPGRADE PROJECT BID SCHEDULE
ITEMDESCRIPTIONUNITPRICE
1MOBILIZATION / DE-MOBILIZATIONLS$ - 0
2REMOVE EXISTING SWITCHGEAR, GENERATORS AND RELATED EQUIPMENT

A. Main Switchgear #1 B. Generator Switchgear #1 C. Switchgear #1 Battery Panel D. Electrical Room lighting E. Generator #1, Day Tank #1, and all ancillary equipment F. Generator #2, Day Tank #2, and all ancillary equipment G. Diesel piping from existing diesel storage tanks to generators

H. Cable tray, conduit, conductors and related hardware.LS$ - 0
3TEMPORARY POWER

A. Provide 500KW portable generator and fuel for temporary power to MCC-1 B. Provide 500KW portable generator and fuel for temporary power to MCC-2.

C. Provide 600KW portable generator and fuel for temporary power to MCC-5.

D. Provide 600KW portable generator and fuel for temporary power to MCC-6.

E. Provide 500KW spare portable generatorLS$ - 0
4FURNISH AND INSTALL SWITCHGEAR EQUIPMENT
A. Furnish Proposed Electrical Service #1 SwitchgearLS$ - 0
5FURNISH AND INSTALL SWITCHGEAR CONTROL PANEL EQUIPMENT
A. Furnish Proposed Electrical Service #1 Switchgear Control PanelLS$ - 0
6FURNISH AND INSTALL GENERATOR #1 AND GENERATOR #2 and ASSOCIATED DAY TANKS, 304SS DIESEL PIPING, EXHAUST, RADIATORS AND ALL ANCILLARY EQUIPMENT

A. Furnish Proposed Generator #1 and associated Day Tanks, 304SS Diesel Piping, Exhaust System, Startup Services, etc.

B. Furnish Proposed Generator #2 and associated Day Tanks, 304SS Diesel Piping, Exhaust System, Startup Services, etc.LS$ - 0
7FURNISH AND INSTALL GENERATORS TAP BOX EQUIPMENT
A. Furnish Proposed Generators Tap BoxLS$ - 0
TOTAL BID AMOUNT:LS$ - 0
Staff has allocated $400,000 in Owner's Allowance for Owner's use as directed. The Owner's Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Owner's Allowance as part of the contract price is not a guarantee that the Contractor will be paid any portion or the full amount of the Owner's Allowance. Expenditures of Owner's Allowance will be made through change order with proper documentation of time and materials supporting the change.

REV 260106 SCWRF ELECTRICAL ROOM #1 UPGRADE