26-2166 Air Monitoring Shelter- Schedule A - Statement of Work.docx

DOCX document 252 KB Posted

Attached to
Shelter - Air Monitoring site
Solicitation number
RFP 761 260000002166 1
Issued by
Michigan

About this file

This is a Statement of Work (Schedule A) for RFP 260000002166 issued by the Michigan Department of Environment, Great Lakes, and Energy (EGLE). EGLE seeks to purchase one air monitoring shelter to expand its ambient air monitoring network in compliance with federal Clean Air Act requirements. The shelter must house climate-controlled instruments and shield equipment from moisture while maintaining operating temperatures between 20-30 degrees Celsius. The shelter specifications include dimensions of 8 feet wide by 10 feet long by 8 feet high with integrated metal-studded modular construction, aluminum or steel base with forklift and jack lifting points, aluminum or fiberglass skin, R-11 or better insulation, and a rubber non-leak membrane roof. The shelter must include a 100 AMP electrical service panel with industrial controlled heating and cooling (12,000 BTU Bard or equivalent), internal and external electrical outlets, LED lighting, solid nickel-raised rubber flooring, a 6-foot countertop at 29 inches height, preinstalled ceiling port for monitoring equipment, gas cylinder mounts for three tanks, aluminum or galvanized metal removable non-slip roof with grating, OSHA-approved roof railing system, and a shelter tie-down system with four anchor points. Delivery is required within six months from the receipt of order to 815 Filley Street, Lansing, Michigan, during business hours (Monday-Friday, 8:00 a.m. to 4:00 p.m.).

Bidders must provide detailed pricing in Schedule B, confirm acceptance of all product specifications and general requirements, and disclose any exceptions to stated specifications. The contractor must offer warranties with details on coverage, repair procedures, timing, and confirmation that manufacturer warranties pass through to the State. Additional requirements include Quality Assurance programs, recall procedures, technical support available 24 hours with issue resolution or on-site service within 72 hours, on-site maintenance per manufacturer recommendations, appointment of a dedicated Contractor Program Manager available during 8:00 a.m. to 5:00 p.m. Eastern time, and compliance with Americans with Disabilities Act standards for all digital deliverables. The State will make payment via Electronic Funds Transfer (EFT), and pricing is firm for the entire contract term. Bidders must disclose any subcontractors, including their legal business names, addresses, percentage of work performed, and GDBE status. The contractor must comply with federal provisions related to funding requirements, provide Material Safety Data Sheets for any hazardous chemicals, confirm products are mercury-free and do not contain brominated flame retardants or intentionally added PFAS, and identify any energy-efficient or environmentally friendly products with relevant certifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enter your company name Schedule A – Statement of Work

RFP 260000002166

Air Monitoring Shelter This schedule identifies the anticipated requirements of any Contract resulting from this RFP. The term “Contractor” in this document refers to a bidder responding to this RFP, as well as the Contractor who is awarded the contract. The term “bidder” is used to identify where specific responses to the RFP are required. Yellow fields are also used to identify areas where a bidder response is required.

The Contractor must respond to each requirement or question and explain how it will fulfill each requirement. Attach any supplemental information and reference it appropriately within your response.

Background EGLE operates an ambient air monitoring network in accordance with federal Clean Air Act requirements. As a part of this network, EGLE deploys many instruments that can only be operated within climate-controlled (shielded from moisture and having operating temperatures between 20-30 degrees Celsius) shelters. EGLE is expanding these air monitoring sites and needs to purchase one (1) air monitoring shelter.

Scope EGLE intends to purchase one (1) air monitoring shelter according to the product specifications below.

General Requirements Air monitoring shelter to house instruments that can only be operated within climate-controlled conditions. The shelter must be able to shield from moisture and temperature fluctuations between 20-30 degrees Celsius.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Product Specifications The Contractor must provide the following:

Dimensions:

8’W X 10’L X 8’H Construction:

Integrated metal studded modular air monitoring shelter Aluminum or steel base with fork truck and jack lifting points Aluminum or fiberglass skin Rubber non-leak membrane roof R-11 or better insulation in walls, ceiling and floors Paneled interior walls and ceiling 36” insulted metal door with closer and commercial grade lever lockset keyed to our key Utilities:

100 AMP electrical service panel Industrial controlled heating and cooling HVAC (12,000 BTU Bard or equivalent) Internal (8) and external (2) electrical outlets as specified on attached SOW Appendix 1 Ample interior LED lighting with wall switch Interior:

Solid nickel- raised rubber flooring- black 6’ Countertop ~ 29” height Preinstalled ceiling port for T640 or Met One BAM per attached SOW Appendix 1 Gas cylinder mounts for 3 tanks Exterior:

Aluminum or galvanized metal removable non-slip roof with grating or equivalent Aluminum roof railing system, OSHA approved with kick plate with 28” gap for stairs Shelter tie-down system including four tie-down points/brackets for installation in shelter base and anchoring to concrete pads Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Warranties Bidder Response

Bidder must describe any warranties included in the bid and provide the length of the warranty. Explain the process for reporting warranty issues and how the Contractor how any repairs or replacements are made, including timing. If the warranty is provided through a third-party or manufacturer, the Contractor must confirm that the manufacturer’s warranty passes through to the State. Provide the name, address, contact name, phone number and email address of the party responsible for the warranty.

Describe how you will comply with the requirement(s)

The State reserves the right to require additional warranties other than those identified by the Contractor in its response to this RFP.

Recall Requirements and Procedures Bidder Response

Bidder must describe any recall procedures.

Describe how you will comply with the requirement(s)

Quality Assurance Program Bidder Response

Explain your Quality Assurance Program(s).

Describe how you will comply with the requirement(s)

Incentives Bidder Response

Explain any special incentives or services including, but not limited to, return policies, trade-in programs, quantity discounts, etc.

Describe how you will comply with the requirement(s)

ADA Compliance The State is required to comply with the Americans with Disabilities Act of 1990 (ADA), including its accessibility standard for websites, applications, content and documents. All Contract Activities created, provided, or made available by Contractor under this Contract in a digital format, including but not limited to, websites, applications, software, mobile applications, text, images, sounds, videos, controls, animations, links, and documents (including files in the following formats: PDF, word processing, presentation, and spreadsheet) must comply with the accessibility standards provided in the Digital Accessibility Standards, located at SOM Digital Standards.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Timeframes All Contract Activities must be delivered within 6 months from the receipt of order or other timeframe agreed upon by vendor. The receipt of order date is pursuant to the Notices section of the Standard Contract Terms.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Delivery Delivery will be expected within 6 months, or another timeframe agreed upon by vendor, upon date of order Monday-Friday 8:00am-4:00pm. Delivery will be made at 815 Filley Street, Lansing, MI, 48906.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Technical Support and Repairs When providing technical support, the Call Center must resolve the caller’s issue within 24 hours. If the caller’s issue cannot be resolved within 24 hours, on-site service must be scheduled. The on-site service must be performed within 72 hours of the time the issue was scheduled for service.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Maintenance On-site maintenance must be performed according to the recommended manufacturer maintenance schedule.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Training Bidder Response

Explain any training that is included in your proposal, as well as any additional training capabilities available. Any costs associated with training must be detailed in Schedule B – Pricing.

Explain your proposed training program

Contractor Program Manager The Contractor must appoint a Service Manager, an individual specifically assigned to State of Michigan accounts who will respond to State inquiries regarding the Contract Activities, answer questions related to ordering and delivery, etc. (the “Contractor Program Manager”).

The Contractor must notify the Contract Administrator at least 10 calendar days before removing or assigning a new Contractor Program Manager.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Customer Service Number Bidder Response

The Contractor must specify its customer service number for the State to contact the Contractor Program Manager who must be available for calls during the hours of 8:00am-5:00pm Eastern, Monday-Friday, at a minimum. Identify customer service availability for this proposal by hours and days of the week.

Insert customer service number

Technical Support, Repairs and Maintenance The Contractor must be available for calls and service during the hours of 8:00am-5:00pm Eastern at a minimum. Identify availability for this proposal by hours and days of the week.

Bidder Response

The Contractor must specify its technical support number for the State to contact the Contractor for technical support, repairs and maintenance.

Insert technical support number and availability

Disclosure of Subcontractors If the Contractor intends to utilize subcontractors, the Contractor must disclose the following:

The legal business name; address; telephone number; a description of subcontractor’s organization and the services it will provide; and information concerning subcontractor’s ability to provide the Contract Activities.

The relationship of the subcontractor to the Contractor.

Of the total bid, the price of the subcontractor’s work.

Whether the Contractor has a previous working experience with the subcontractor. If yes, provide the details of that previous relationship.

A complete description of the Contract Activities that will be performed or provided by the subcontractor.

Required Subcontractor information. Bidders must complete the table below for each anticipated subcontractor. Copy the table as many times as needed for each subcontractor. Complete the second table with the percentage of work that will be completed by all subcontractors involved.

Requested Information
Bidder Response

The legal business name, address, telephone number of the subcontractor(s).

A description of subcontractor’s organization and the services it will provide and information concerning subcontractor’s ability to provide the Contract Activities.

The relationship of the subcontractor to the Bidder.

Is the subcontractor a GDBE?

Whether the Bidder has a previous working experience with the subcontractor.

A complete description of the Contract Activities that will be performed or provided by the subcontractor.

Of the total bid, the price of the subcontractor’s work.

Work performed by subcontractors

Total percentage of work that will be performed by subcontractors: Insert %

Total percentage of subcontracted work that will be performed by GDBE subcontractors: Insert %

Security The Contractor will be subject the following security procedures:

The Contractor’s staff may be required to make deliveries to or enter State facilities. The State may require the Contractor’s personnel to wear State issues identification badges.

Bidder Response

The Contractor must explain any security measures in place to ensure the security of State facilities.

Explain your security measures.

Funding Requirements The Contractor must accept and follow the provisions laid out in the Schedule F- Federal Provisions Addendum. The Contractor must follow all requirements necessary to receive federal funds.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Price Term Pricing is firm for the entire length of the Contract.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Authorizing Document The appropriate authorizing document for the Contract will be a Purchase Order (PO).

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Delivery Programs Bidder Response

The Contractor must explain in detail its delivery program(s) (e.g., standard delivery and quick-ship), including any limitations such as quantity.

Explain delivery program(s)

The Contractor must explain the transportation method(s) (e.g., UPS, FedEx, Contractor fleet, or other third-party carrier) it intends on utilizing in delivery of the Contract Activities.

Explain transportation method(s)

Packaging and Palletizing Packaging must be optimized to permit the lowest freight rate. Shipments must be palletized whenever possible using manufacturer's standard 4-way shipping pallets.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Acceptance, Inspection and Testing The State will use the following criteria to determine acceptance of the Contract Activities:

EGLE will inspect the shelter for damages when it is delivered.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Invoice Requirements All invoices submitted to the State must include: (a) date; (b) delivery order; (c) quantity; (d) description of the Contract Activities; (e) unit price; (f) shipping cost (if any); (g) vendor-generated invoice number and (h) total price.

Bidder Response

☐ I confirm the above requirement(s) and agree with no exception(s)

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Payment Methods The State will make payment for Contract Activities via EFT (Electronic Funds Transfer).

Bidder Response

Explain your process for ordering and accepting this payment method. If an account needs to be created on your purchasing platform, please submit documentation that shows the steps for completing this process.

Explain your process.

Required Functionality Relating to Data Retention, Disposal, and Retrieval The State has legal obligations to retain, dispose, and retrieve State Data along with obligations to manage and secure State Data. To meet these obligations, the Solution must allow the State to:

retain all data for the entire length of the Contract.

delete its data or request the deletion of its data, even data that may be stored offline or in backups.

transfer its data back to the State or to a new vendor or new solution.

transfer its data to the Archives of Michigan as may be required by a retention and disposal schedule.

retrieve data, even data that may be stored offline or in backups.

Except as otherwise stated in the Contract, Contractor will not dispose of, delete, or destroy State Data without the prior written approval of the State.

Bidder Response

☐ I have reviewed the above requirement(s) and agree with no exceptions.

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

Exceptions: List all exceptions here

Bidder must review and explain how the data retention, disposal, and retrieval requirements will be met by the solution and describe its data management capabilities (storage limitations, duration, etc.). If the Solution does not allow the State to perform these activities itself, the bidder must explain how it will support the State’s compliance with these requirements.

Describe how you will comply with the requirement(s)

Environmental and Energy Efficiency Product Standards The Contractor must identify any energy efficient, bio-based, or otherwise environmentally friendly products used in the products. Contractor must include any relevant third-party certification, including the verification of a United States Department of Agriculture certified bio-based product label. Contractor must describe how products that meet these requirements are identified or otherwise labelled and list any exceptions to this requirement.

Bidder Response

☐ I have reviewed the above requirement(s) and agree with no exceptions.

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

List all exceptions – either in the Exceptions List table below or identified here as an attachment to this RFP:

Bidder must provide detailed information as required above – either in this response box or identified here as an attachment to this RFP.

Describe how you will comply with the requirements or indicate the filename of the attachment.

Exceptions List

Item #
Response

Hazardous Chemical Identification In accordance with the federal Emergency Planning and Community Right-to-Know Act, 42 USC 11001, et seq., as amended, the Contractor must provide a Material Safety Data Sheet listing any hazardous chemicals as defined in 40 CFR §370.2, to be delivered. Each hazardous chemical must be properly identified, including any applicable identification number, such as a National Stock Number or Special Item Number.

The Contractor must identify any hazardous chemicals that will be provided under any resulting contract.

Bidder Response

☐ I confirm the above requirement and agree with no exception

Mercury Content Pursuant to MCL 18.1261d, mercury-free products must be procured when possible. The Contractor must explain if it intends to provide products containing mercury, the amount or concentration of mercury, and whether cost competitive alternatives exist. If a cost competitive alternative does exist, the Contractor must provide justification as to why the particular product is essential. All products containing mercury must be labeled as containing mercury.

Bidder Response

☐ I confirm the above requirement and agree with no exception

Brominated Flame Retardants The State prefers to purchase products that do not contain brominated flame retardants (BFRs) whenever possible. The Contractor must disclose whether the products contain BFRs and describe how the products are identified or otherwise labelled.

Bidder Response

☐ I have reviewed the above requirement(s) and agree with no exceptions.

☐ I have reviewed the above requirement(s) and have noted any exceptions below.

List all exceptions – either in the Exceptions List table below or identified here as an attachment to this RFP:

Exceptions List

Item #
Response

Perfluoroalkyl and Polyfluoroalkyl Substances (PFAS) The Contractor must confirm that the provided products do not intentionally contain PFAS. This consists of all components of the provided products, including product packaging.

Bidder Response

☐ I confirm the above requirement and agree with no exception

(OR)

The Contractor must disclose whether a product or its components contain intentionally added PFAS. If the product or its components contain intentionally added PFAS the Contractor must:

provide an explanation with respect to the intentionally added PFAS contents, including the purpose for which PFAS are used in the product or its components, the types of PFAS used in the product or its components, and the amount of each PFAS used in the product or its components.

indicate whether the product will be labeled or packaged with information about the intentionally added PFAS contents.

identify any alternative products that do not contain intentionally added PFAS.

provide any additional information that would further the Department’s implementation of ED 2021-08.

Bidder Response

☐ I have reviewed the above requirement and have listed all PFAS containing products in the table below or as an attachment:

Bidder must provide detailed information as required above – either in this response box or identified here as an attachment to this RFP.

Describe how you will comply with the requirements or indicate the filename of the attachment.

PFAS List

Item #
Response

Enter your company name

RFP 260000002166 Air Monitoring Shelter 1 SOW Appendix 1- Shelter Diagram

RFP 260000002166 Air Monitoring Shelter 1 image2.png image3.png image1.png

File details come from the government source that posted it. Updated .