About this file

This Addendum 2 document, issued November 16, 2026, by the City of Lake Oswego, Oregon, provides clarifications and responses to 45 proposer inquiries regarding the Design Services RFP for the Lake Oswego Public Library Project. The proposal scope encompasses architectural and engineering design services including structural, civil, mechanical, electrical, plumbing, and landscape architecture, along with community engagement, sustainability consulting, and furniture procurement. The RFP comprises two phases: Phase 1 (February 2027 through July 2028) covering site selection, programming, and concept design to support a May 2029 bond measure, and Phase 2 (June 2029 through December 2032) covering schematic design through construction administration. Proposals were originally due November 20, 2026, with fee proposals required from shortlisted firms by December 18, 2026 at 10:00 a.m. The contract will be awarded as a single contract with an initial one-year term and options to renew for six additional one-year terms. All proposal copies must include attachments; covers, tabs, and section dividers are excluded from the page limit; and ink signatures are required only on the original copy.

The addendum establishes key assumptions for consistent fee proposal evaluation, including 60 owner-architect meetings during Phase 1, 10 candidate properties for site visits with 5 receiving test fits, 4 renderings, 16 community engagement events, and specified numbers of presentations to City Council (3), Library Staff (6), Advisory Boards (2), and Citizen Groups (4). Proposers must assume a 60,000 square-foot project size and identify the construction value basis for their fees. The fee proposal should provide detailed breakdowns by project phase (Pre-Bond Work, Schematic Design, Design Development, Construction Documents, Permitting, and Construction Administration/Project Closeout) and by service line (Architectural Services, Civil Engineering, Structural Engineering, Mechanical Engineering, Electrical Engineering, Plumbing Engineering, Landscape Architecture, Furniture Procurement, Community Engagement, and other services as needed). No COBID utilization target has been established; however, COBID certification or documented subcontractor utilization is scored at 10 points as an evaluation criterion. Environmental assessments will be provided by the owner and are not in scope for the architect's fee. The City plans to procure a general contractor for preconstruction services and cost estimating, with the successful preconstruction contractor eligible to respond to the future Construction Manager/General Contractor (CMGC) RFP.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lake Oswego Public Library Project– Design Services RFP

Addenda 02

Issued: November 16, 2026

Response

1 I see that only Attachment H is listed as being within the proposal requirements. Does

Attachment H need to be signed?

Attachment H does not need to be signed

2 Alternatively, would it be acceptable to provide all Attachments as a separate package from the proposal? This would aid in the ease of the printing process and signing these documents by hand.

Every proposal copy submitted should include all attachments as part of the proposal package.

3 Attachments C and E just have the word "reserved" on it. Is there a complete attachment C and E?

Attachments C and E are not applicable at this time. If either attachment becomes necessary, the applicable documents will be issued through a formal addendum.

4 Do you anticipate using a community engagement consultant in Phase 1 at all? Community engagement will be an important component of phase 1. We will look to the selected team to develop a community engagement plan that will be used starting as early as Q2 2027 taking into consideration task force findings. If you anticipate engaging a consultant, please identify your preferred consultant(s) or firm(s).

5 Is it acceptable to give the land use scope of work to a consultant? Yes, a land use consultant is acceptable; please include as an additional service.

6 The proposal requirements in section 4, items 2 and 3 are questions often answered by a Contractor. Could you further clarify what content you would like to see as it relates to the services an architect provides?

For clarification -- where a contractor might provide information from subcontractors, an architect might provide information from subconsultants or others performing a subtask in their scope.

7 Are covers and/or tab pages permitted, and if so, are they exempt from the page limit?

Yes, covers and tabs are permitted and will be excluded from the page limit.

8 Would it be acceptable to use a simple spiral binding on the printed copies? Yes, spiral binding is acceptable.

9 Are ink signatures required on all printed copies (including the original and the copies)?

No, ink signatures are not required on all printed copies; they are only required on the original.

10 Is it required to provide copies of the Attachments with all copies of the proposal, or would a single set of Attachments with the marked original be sufficient?

Please refer to the response to Question #2.

11 RFP section 3.1-b (pg. 15) notes that Attachment C is required among the forms in our proposals, however it appears Attachment C is not included / marked as "Reserved."

Can you provide this form to us or clarify the expectation for proposers to address

Attachment C?

Please refer to the response to Question #3.

12 At what point in the process will proposer's need to provide the Price Proposal noted on page 19 - would this piece be required prior to the interviews, after interviews, or post-award?

The fee proposal is due December 18th, 2026 at 10:00am

13 Does this City have a COBID utilization target for this project? No utilization target has been established.

14 How will the 10 points max in Section 4 be allocated? Is it possible to get full points if the prime firm is not COBID certified? Would proposers be eligible for partial points depending on what percentage of our team or estimated fee would comprise COBID certified subs?

The 10 points max in Section 4 will be allocated as determined by the scoring committee.

15 Is there a page size requirement? 8 1/2" x 11"

16 Do section dividers count toward the page limit? Please refer to the response to Question #7.

17 For Price Proposal Criteria – Proposal Phase 2 (If Shortlisted): Is this for all phases of work – both pre-bond and post bond? Site Selection/Programming, Concept Design and Schematic Design Through Construction?

Yes, fee proposal is requested for all phases.

18 For Price Proposal Criteria – Proposal Phase 2 (If Shortlisted): Do you require the hourly rates of the full consultant team or just the architectural team?

Provide hourly rates for full consultant team.

19 For Price Proposal Criteria – Proposal Phase 2 (If Shortlisted): Do you require the estimate of all hours by each consultant or just the architectural team?

No, just the architectural team

Question

Issued: November 16, 2026

Response

21 For Price Proposal Criteria – Proposal Phase 2 (If Shortlisted): For the purposes of developing a fee for Schematic Design through Construction which will occur in 2029, could the city provide a specific total gross building area and construction cost to base the fee on? Establishing common assumptions for the fee proposals will be helpful for them to be evaluated consistently, with adjustments made later if the size and cost varies significantly.

Assume a project size of 60,000 square feet. The architect shall identify the construction value used as the basis for their fee proposal and explain how their proposed fee may be adjusted if the construction value changes.

22 Item 2.1 a, i - Notes “weekly” owner architect meetings during all design phases as applicable. For the 18 month site verification / program / concept phase, could the city provide an assumed number of Owner architect meetings during this timeframe for the purpose of developing a fee?

Assume 60 meetings.

23 Will Short List Finalists have an opportunity to ask additional clarifying questions pertaining to the fee proposal after the short list notification?

Additional questions will be accepted within 48 hours of shortlist notification and responses will be shared with all responders.

24 Item 2.2 a, x - Notes environmental assessment may be included. Given this could be extensive and or vary depending on the site, can this be considered “not in scope” for purpose of developing a fee?

Environment assessments will be by owner.

25 Item 2.2 a, xx We understand the community engagement strategy will be developed collaboratively with Library and City staff and the selected consultant team. To establish a consistent basis for fee proposals, could the City provide assumptions regarding the number of community events and other anticipated tasks?

Phase 1: Assume a total of 16 community engagement events. Include preparation of a community engagement strategy, development of materials for each event, distribution of outreach materials, and preparation of content for online project updates.

26 Item 2.2 a, xvii - The scope notes presentations to City Council, Library Staff, Advisory

Boards and citizen groups as needed. We assume a detailed stakeholder engagement plan will be developed with the selected team. For fee purposes, could the City provide an assumed number of meetings or presentations for each audience group to ensure proposals are based on a consistent scope?

For Phase 1 assuming the following number of meetings:

City Council - 3

Library Staff - 6

Advisory Board - 2

Citizen Groups / Task Force - 4

27 Will the cover sheet, table of contents, and section dividers be excluded from the total page count?

Please refer to the response to Question #7.

28 Given the typical length of a design and construction project, in lieu of "the dollar value of goods purchased from COBID-certified suppliers during the past six months"

(Section 4: 3), would a helpful alternative be to include examples of successful COBID partner fee distribution on a complete project?

No, however, examples of successful COBID partner fee distribution on a complete project could be an example of something included under a utilization plan.

29 Will the selected architect participate in the CMGC selection process? If timing allows the selected architect may be asked to participate in the selection process.

20 Please provide a detailed fee breakdown for each of the following project phases and format fee breakdown as described below:

Columns

Pre-Bond Work

Schematic Design

Design Development

Construction Documents

Permitting

Construction Administration/Project Closeout

For each project phase, provide separate fee line items for the following services:

Rows

Architectural Services

Civil Engineering

Structural Engineering

Mechanical Engineering

Electrical Engineering

Plumbing Engineering

Landscape Architecture

Furniture Procurement

Community Engagement

Other as needed

Consultant Markup

Reimbursable Expenses

Please clearly identify the fee associated with each service within each project phase and provide a total fee for each phase, as well as a grand total for all services.

For Price Proposal Criteria – Proposal Phase 2 (If Shortlisted): The second note asks to provide a description of each “task” that the proposing firm understands as comprising the services under this RFP. Please define what level of task you are referencing with examples if possible. Also is this for each consultant or just the architectural team/general project approach?

Issued: November 16, 2026

Response

30 To better refine the design team's scope, please provide the CMGC's expected responsibilities in each phase.

Still to be determined.

31 Which LEED program (e.g., 4,4.1, or 5) is expected for LEED Gold equivalency? Still to be determined.

32 Do project examples included in Section 1: Firm Qualifications c. need to be completed?

No

33 The RFP mentions that the proposals should be stapled, not bound. What is the expectation for stapling the document – a single corner staple, or staples down the left edge (staple bound)?

Please refer to the response to Question #8. Proposers may staple documents as they deem appropriate.

34 For teams that move on to the interview/fee proposal phase, are fee proposals sought from subconsultants in addition to the prime? And can you please confirm in the addendum whether fee proposals are for Phase 1 and Phase 2 or just Phase 1?

Please refer to the response to Question #17.

35 Addendum 01 indicates that the City intends to retain a general contractor for preconstruction services early in Phase 1 to assist with site evaluation and cost estimating. Please clarify the anticipated procurement method and whether the Phase

1 preconstruction contractor will be eligible to compete for or continue into the Phase

2 construction contract.

The contractor procurement method is TBD. Yes the successful pre-construction contractor is eligible to respond to the future CMGC RFP.

36 For Section 4, 2 : can you describe what information you want for the “Utilization

Plan” to employ COBID-certified subcontractors?

Please refer to question #6 and #28.

37 Program baseline and sustainability. Should proposers treat the recently completed pre-building program study as the baseline to validate under 2.2(a)(ii)? Separately, is

LEED certification required, or is the goal LEED-equivalent performance without certification?

Yes proposers should treat the recently completed pre-building program study as the baseline to validate under 2.2(a)(ii).

Sustainability standards for this project have not been confirmed yet.

38 Cost estimating consultant. It was stated during the pre-proposal conference that the

City would hire a cost estimating consultant. Is this still the intention? If, so when will the RFP for cost estimating services be issued and at point will the City bring the consultant into Phase 1 project schedule?

The City plans to hire a general contractor to provide cost estimate services. If a second cost estimate is needed, it will be outside the architect’s scope of services.

39 Assumed quantities. For planning purposes, what should proposers assume for each of the following? The number of candidate properties to visit and evaluate under

2.2(a)(v)–(vi)

Assume 20 hours for site visits as described in section 2.2(a)(vi). Assume 10 candidate properties to visit and evaluate 5 with test fits.

40 Assumed quantities. For planning purposes, what should proposers assume for each of the following? The number of renderings under 2.2(a)(xiv)

Assume 4 renderings for the phase 1 fee proposal.

41 Assumed quantities. For planning purposes, what should proposers assume for each of the following? The number of Council, advisory board, and citizen-group presentations under 2.2(a)(xvii) and (xix)

Please refer to the response to Question #26.

42 Which subconsultant disciplines are assumed for Phase 1 fee proposal? Please refer to the response to Question #20.

43 2.1, a, i: Confirm that the coordination meetings noted in 2.1, a, i are the same meetings noted in 2.2, a, iv. If not, please provide a frequency assumption for the 2.2, a, iv meetings.

The coordination meetings noted in 2.1, a, i are covered by the meetings noted in

2.2, a, iv and 2.2 a, xvii. Please refer to the responses to Question #22 and #26.

44 2.2, a, vii: Will the architect be expected to attend the monthly city council meetings?

If not, what meeting frequency should be assumed per phase? Similarly, how many library staff, advisory boards, and citizen groups' presentations should be assumed during Phases 1 and 2?

Please refer to the response to Question #26.

45 2.3, e, iv: 'Administering compliance with labor standards' and 'providing testing and inspection administration' are typically administered by the contractor and owner, not the architect. Please clarify the function(s) the architect is expected to perform for these items.

Administering compliance with labor standards: The Architect will not be required to administer labor standard, but may assist with reviewing construction documentation and reporting observed contract noncompliance.

Testing and Inspection Administration: The Architect responsibilities include review inspection and testing requirements, coordinate with the contractor and consultants as needed, review reports, observe construction for general conformance, and track outstanding issues.