26 05 11 Requirements for Electrical Installations.pdf
PDF 77 KB Posted
- Attached to
- Z1DA--Installation of Additional Environmental Monitors Federal contract opportunity
- Solicitation number
- 36C25621R0131
About this file
This solicitation notice is for installation of additional environmental monitors at the Southeast Louisiana Veterans Health Care System facilities located in New Orleans, Louisiana. The project involves providing all labor, materials, tools, equipment and expertise to install additional environmental monitors with a construction cost estimated between $500,000 to $1,000,000. This is a 100% set-aside for Service-Disabled Veteran Owned Small Businesses. Interested SDVOSB contractors must be verified in the Vendor Information Pages database and System for Award Management to be considered for award. The solicitation will be issued on June 4, 2021 on beta.SAM.gov and questions regarding the solicitation should be directed to the Contracting Officer, Bill Geary.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01-01-16
26 05 11 - 1
SECTION 26 05 11
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section applies to all sections of Division 26.
B. Furnish and install electrical materials and accessories in accordance with the specifications and drawings. Capacities and ratings of transformers, conductors and cable, and other items and arrangements for the specified items are shown on the drawings.
C. Conductor ampacities specified or shown on the drawings are based on copper conductors, with the conduit and raceways sized per NEC.
Aluminum conductors are prohibited.
1.2 MINIMUM REQUIREMENTS
A. The latest International Building Code (IBC), Underwriters
Laboratories, Inc. (UL), Institute of Electrical and Electronics
Engineers (IEEE), and National Fire Protection Association (NFPA) codes and standards are the minimum requirements for materials and installation.
B. The drawings and specifications shall govern in those instances where requirements are greater than those stated in the above codes and standards.
1.3 TEST STANDARDS
A. All materials and equipment shall be listed, labeled, or certified by a
Nationally Recognized Testing Laboratory (NRTL) to meet Underwriters
Laboratories, Inc. (UL), standards where test standards have been established. Materials and equipment which are not covered by UL standards will be accepted, providing that materials and equipment are listed, labeled, certified or otherwise determined to meet the safety requirements of a NRTL. Materials and equipment which no NRTL accepts, certifies, lists, labels, or determines to be safe, will be considered if inspected or tested in accordance with national industrial standards, such as ANSI, NEMA, and NETA. Evidence of compliance shall include certified test reports and definitive shop drawings.
B. Definitions:
1. Listed: Materials and equipment included in a list published by an organization that is acceptable to the Authority Having Jurisdiction and concerned with evaluation of products or services, that maintains periodic inspection of production or listed materials and
26 05 11 - 2 equipment or periodic evaluation of services, and whose listing states that the materials and equipment either meets appropriate designated standards or has been tested and found suitable for a specified purpose.
2. Labeled: Materials and equipment to which has been attached a label, symbol, or other identifying mark of an organization that is acceptable to the Authority Having Jurisdiction and concerned with product evaluation, that maintains periodic inspection of production of labeled materials and equipment, and by whose labeling the manufacturer indicates compliance with appropriate standards or performance in a specified manner.
3. Certified: Materials and equipment which:
a. Have been tested and found by a NRTL to meet nationally recognized standards or to be safe for use in a specified manner.
b. Are periodically inspected by a NRTL.
c. Bear a label, tag, or other record of certification.
4. Nationally Recognized Testing Laboratory: Testing laboratory which is recognized and approved by the Secretary of Labor in accordance with OSHA regulations.
1.4 QUALIFICATIONS (PRODUCTS)
A. Manufacturer’s Qualifications: The manufacturer shall regularly and currently produce, as one of the manufacturer's principal products, the materials and equipment specified for this project, and shall have manufactured the materials and equipment for at least three years.
B. Product Qualification:
1. Manufacturer's materials and equipment shall have been in satisfactory operation, on three installations of similar size and type as this project, for at least three years.
2. The Government reserves the right to require the Contractor to submit a list of installations where the materials and equipment have been in operation before approval.
1.5 APPLICABLE PUBLICATIONS
A. Applicable publications listed in all Sections of Division 26 shall be the latest issue, unless otherwise noted.
B. Products specified in all sections of Division 26 shall comply with the applicable publications listed in each section.
26 05 11 - 3
1.6 MANUFACTURED PRODUCTS
A. Materials and equipment furnished shall be of current production by manufacturers regularly engaged in the manufacture of such items, and for which replacement parts shall be available. Materials and equipment furnished shall be new, and shall have superior quality and freshness.
B. When more than one unit of the same class or type of materials and equipment is required, such units shall be the product of a single manufacturer.
C. Factory wiring and terminals shall be identified on the equipment being furnished and on all wiring diagrams.
1.7 WORK PERFORMANCE
A. All electrical work shall comply with requirements of the latest NFPA
70 (NEC), NFPA 70B, NFPA 70E, NFPA 99, NFPA 110, OSHA Part 1910 subpart
J – General Environmental Controls, OSHA Part 1910 subpart K – Medical and First Aid, and OSHA Part 1910 subpart S – Electrical, in addition to other references required by contract.
B. Job site safety and worker safety is the responsibility of the
Contractor.
C. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
D. For work that affects existing electrical systems, arrange, phase and perform work to assure minimal interference with normal functioning of the facility.
E. New work shall be installed and connected to existing work neatly, safely and professionally. Disturbed or damaged work shall be replaced or repaired to its prior conditions, as required by Section 01 00 00, GENERAL REQUIREMENTS.
F. Coordinate location of equipment and conduit with other trades to minimize interference.
1.8 EQUIPMENT INSTALLATION AND REQUIREMENTS
A. Equipment location shall be as close as practical to locations shown on the drawings.
B. Working clearances shall not be less than specified in the NEC.
C. Inaccessible Equipment:
1. Where the Government determines that the Contractor has installed equipment not readily accessible for operation and maintenance, the
26 05 11 - 4 equipment shall be removed and reinstalled as directed at no additional cost to the Government.
2. "Readily accessible” is defined as being capable of being reached quickly for operation, maintenance, or inspections without the use of ladders, or without climbing or crawling under or over obstacles such as, but not limited to, motors, pumps, belt guards, transformers, piping, ductwork, conduit and raceways.
1.9 SUBMITTALS
A. Submit to the COR in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. The Government's approval shall be obtained for all materials and equipment before delivery to the job site. Delivery, storage or installation of materials and equipment which has not had prior approval will not be permitted.
1.10 ACCEPTANCE CHECKS AND TESTS
A. The Contractor shall furnish the instruments, materials, and labor for tests.
B. When test results indicate any defects, the Contractor shall repair or replace the defective materials and repeat the tests for the equipment.
Repair, replacement, and re-testing shall be accomplished at no additional cost to the Government.
1.11 WARRANTY
A. All work performed and all equipment and material furnished under this
Division shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the
Contracting Officer for the Government.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)