26-0415 ASPHALT REPAIRS - PROJECT DESCRIPTION.pdf

PDF 139 KB Posted

Attached to
Asphalt Repairs Bldg 905, 916, PP201, LCH4930, AS211, & AS214
Solicitation number
N4008526R9071
Issued by

About this file

This is a Project Description document for pavement repair work at MCAS New River. The scope of work encompasses sawcutting, removal, and repaving of six utility repairs at multiple locations: building 905 at the intersection of Michael Road and Wilson Boulevard; building 916 on Mulberry Street; PP201 Parking lot off Brewster Boulevard; LCH4930 on Balducci Drive in Midway Park; and AS211 and AS214 Parking lots on Bancroft Street.

The contractor must maintain facility operations throughout the entire construction period, minimizing interference with normal operations. The project allows for a single qualified individual to serve in the combined roles of Superintendent, Quality Control Manager, and Safety & Health Officer, provided that person meets all qualifications as defined in the project specification.

View the file

Other files

File Type Posted
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
26-0415 ASPHALT REPAIRS - SOW.pdf PDF
RFP 260415.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
26-0415 ASPHALT REPAIRS - SUBMITTAL REGISTER.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DESCRIPTION

This scope of work will sawcut, remove, and repave six [6] utility repairs located at building 905, intersection of Michael Road and Wilson Blvd, building 916 on Mulberry Street, PP201 Parking lot off Brewster Blvd, LCH4930 Balducci Dr on Midway Park, AS211 and AS214 Parking lots, located on Bancroft Street, MCAS New River.

SPECIAL SCHEDULING

The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.

SUPERVISION

One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.