26_016_LH PavingThe Way Project_6_IFB.pdf

PDF 426 KB Posted

Attached to
26-016-LH Paving The Way Project 6 (10/23/25)
Solicitation number
PE-61100-NONST-2026-000000093
Issued by
Bibb County, Georgia

About this file

This is an Invitation for Bids (IFB) issued by Macon-Bibb County, Georgia for the Paving the Way Project-6, a roadway repair and resurfacing initiative for various streets within the county. The project involves milling, asphalt paving, roadway patching, and related infrastructure work on approximately 9.23 miles of roads, including streets in areas such as Ashford Chase, Country Oaks, Kimmeridge, Providence Boulevard, and others. The bid is scheduled to be opened on October 23, 2025, with a pre-bid conference set for September 24, 2025. The contract period is 120 days from the notice to proceed, with the contractor required to commence work within 10 calendar days of receiving the notice and complete all work requirements within 150 calendar days of obtaining necessary railroad permits.

The bid includes comprehensive quantities for various items such as 12,277.9 tons of milling, 8,929.36 gallons of bituminous tack, 14,882.27 square yards of roadway patching, and 12,277.9 tons of 12.5 mm Superpave Asphalt. The project also involves installing and adjusting 262 sewer and storm manholes, 189 water valve risers, and performing striping and painting work. Minority, Women Owned, and Disadvantaged Business Enterprises are encouraged to participate, with small businesses able to seek assistance from the county's Small Business Affairs office. The bid requires a 5% bid bond, and the successful bidder will need to provide performance and payment bonds for 100% of the contract price, with liquidated damages of $75 per day for project delays.

View the file

Other files

File Type Posted
26_016_LH Atachment C_Frequently Asked Questi.pdf PDF
26_016_LH Attachment B_Project Quantity Sheet.xlsx XLSX spreadsheet
26_016_LH Attachment A.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Macon-Bibb County, Georgia

INVITATION FOR BIDS

FOR

PAVING THE WAY PROJECT-6

745-02 745-21 745-65 755-35 755-30

BID NUMBER: 26-016-LH

ISSUED: 9/18/25

BIDS DUE NO LATER THAN 12:00 NOON ON THURSDAY, OCTOBER 23, 2025

Macon-Bibb County Procurement Department 700 Poplar Street

Suite 308 City Hall

Macon, Georgia 31201

TABLE OF CONTENTS

I. GENERAL

A. INVITATION

B. BID DOCUMENTS

C. PRE-BID

D. BID BOND

E. SEALED BIDS

F. VALIDITY

G. CONTRACT AWARD

H. SURETY

I. PAYMENT CONDITIONS

J. EXCISE TAXES

K. INSURANCE

II. INSTRUCTIONS TO BIDDERS

A. DEFINITIONS

B. RELATED DOCUMENTS

C. BIDDER’S REPRESENTATION

D. DOCUMENT DISCREPANCIES

E. SUBMITTALS

F. RESERVATIONS

G. SURETY AND INSURANCE COMPANIES

III. SPECIAL CONDITIONS

A. GENERAL

B. PERMITS AND LICENSES

C. LAYOUT OF WORK

D. WORK AREA

E. UNDERGROUND UTILITIES

F. TRAFFIC CONTROL

G. EROSION CONTROL

H. VANDALISM

I. MATERIAL DISPOSAL

J. EXTENSION OF TIME

K. LIQUIDATED DAMAGES

L. INSPECTION

IV. EXECUTION

A. GENERAL

B. SPECIFICATIONS

C. SCHEDULE

V. WARRANTY

VI. OPEN RECORDS….…………………………………………………………………………...………….….. 8

FORMS PROVIDED:

BID FORM

BIDDER QUALIFICATION FORM

FINANCIAL & LEGAL STABILITY STATEMENT

LIST OF SUB-CONTRACTORS

BIDDER MINORITY PARTICIPATION GOAL

GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT (E-VERIFY) AFFIDAVIT

ATTACHMENTS:

A – REQUIRED SUBMITTAL DOCUMENTS W/ BID SCHEDULE & BID PRICE FORM

B – QUANTITY WORKSHEET

C – FREQUENTLY ASKED QUESTIONS

END OF TABLE OF CONTENTS

PAVING THE WAY PROJECT-6

I. GENERAL

A. Invitation

1. Notice is hereby given that the Macon-Bibb County Board of Commissioners will receive sealed bids (1 original and Flash Drive) in the Procurement Department, Suite

308, Macon-Bibb City Hall, 700 Poplar Street, Macon, Georgia 31201, until

12:00 o’clock NOON at the time legally prevailing in Macon, Georgia on Thursday, October 23, 2025, for Paving The Way Project-6 for the Macon-Bibb County

Engineering Department, Macon, Bibb County, Georgia.

2. NO BIDS WILL BE ACCEPTED AFTER THIS DESIGNATED TIME.

3. Bids will be publicly opened in the Macon-Bibb County Board of Commissioners

Chamber on Thursday October 23, 2025, at 2:00 pm.

4. Minority, Women Owned, and other Disadvantaged Business Enterprises are encouraged to participate in the solicitation process. Additionally, respondents are encouraged to use M/W/DBE subcontractors where possible. Small and other disadvantaged businesses requiring assistance with the competitive process can contact

Charise Stephens, Director of Small Business Affairs at (478) 300-2297 or

Cstephens2@maconbibb.us .

B. Bid Documents

1. Bid documents may be examined and obtained at the Macon-Bibb County Procurement

Department, Suite 308, City Hall, 700 Poplar Street, Macon, Georgia 31201, by calling

(478) 803-0550, or may be viewed and downloaded from one of the links included below:

Georgia Procurement Registry website http://ssl.doas.state.ga.us/PRSapp/PR_custom_index.jsp?agency=61100

Macon-Bibb County Procurement Page www.maconbibb.us/purchasing

C. Pre-Bid

A Pre-bid conference is scheduled for 10:00 o’clock a.m., Wednesday, September 24, 2025, in the Macon-Bibb Board of Commissioners Chambers located at 700 Poplar Street, Macon, GA 31201. This Pre-bid is not mandatory. Deadline for submission of questions is Friday, September 26, 2025, at 3:00 p.m. standard eastern time. Questions must be submitted via email to Lhardwick@maconbibb.us.

D. Bid Bond

1. Bids, in order to be considered, shall be accompanied by a bid bond, payable to the

Owner, in amount not less than five percent (5%) of the total base bid.

a) This bid security shall become payable to the Owner only if the bidder, to whom award is made, should fail to execute a contract with the Owner and furnish bond and insurance in accordance with terms of the contract within ten

(10) days after notification of award.

E. Sealed Bids

1. Envelopes shall be identified on the outside as

“Bid 26-016-LH – “Paving the Way Project-6”

And delivered by hand or mailed to:

Macon-Bibb County Procurement Department

700 Poplar Street, Suite 308 mailto:Cstephens2@maconbibb.us http://ssl.doas.state.ga.us/PRSapp/PR_custom_index.jsp?agency=61100 http://www.maconbibb.us/purchasing

F. Validity

1. No bid may be withdrawn for a period of sixty (60) days after time has been called on date of bid opening.

G. Contract Award

1. The contract, if awarded, will be based on Total Bid Price.

2. Guidelines in the award of this contract will be Section 36-10-2.2, Official Code of

Georgia Annotated.

3. Upon award of the Contract, a pre-construction meeting will be held to discuss the project and to establish a schedule of work.

H. Surety

1. Whereas the anticipated contracted price exceeds $5,000, the bidder to whom award is made shall submit a Payment Bond and a Performance Bond, both in amount of one hundred percent (100%) of the contract price.

a) Bonding company/Surety shall be:

(1) Rated B+ or better in current Key Rating Guide as issued by A.M.

Best Company, Oldwick, NJ.

(2) Licensed to do business in the State of Georgia.

I. Payment Conditions

1. The County Inspector will collect material tickets, measure and inspect work completed to date on said job and report to the Project Manager for payment.

2. A 10% retainage will be withheld from each payment until final payment is made.

The Owner will only pay for items used and actual work performed.

3. Change orders are issued for any variance from contract or plan sheets.

4. Any unauthorized work or material change will not be paid for unless a change order has been issued.

J. Excise Taxes

1. Any material that is to be incorporated into the work of this project may be consigned to

Macon-Bibb County in care of the contractor. If the shipping papers show clearly that any such materials are consigned, the shipment shall be exempt from the tax on transportation of property under the provisions of Section 3478(b) of the Internal

Revenue Code, as amended by Public Law 180-78th Congress.

2. The Contractor shall pay all transportation charges.

3. Each bidder shall take this exemption into account in calculating his bid.

K. Insurance

1. Insurance coverage shall be carried with an insurance company licensed to do business in the State of Georgia.

2. Insurance shall be obtained prior to commencement of work and shall remain in force throughout the period of the contract.

3. Macon-Bibb County shall be named as additional insured on the policy.

4. Coverage shall include water damage.

5. Contractor is responsible for any and all deductibles.

6. Required coverage:

a) Worker’s Compensation: Statutory

b) General Liability:

(1) $1,000,000.00 combined single limit for B.I., P.D.

(2) Maximum deductible: $5,000.00

(3) To include:

(a) Premises – Operations

(b) Products & Completed Operations

(c) Broad form Contractual

(d) Independent Contractor and Subcontractor

(e) Underground explosion and collapse

c) Automobile Liability:

(1) $1,000,000.00 combined single limit for B.I. and P.D.

(2) Maximum deductible: $5,000.00

(3) To include:

(a) Owned Automobiles

(b) Hired Automobiles

(c) Non-Owned Automobiles

II. INSTRUCTIONS TO BIDDERS

A. Definitions

1. Wherever the term “Owner”, “County”, or “Macon-Bibb County” occur in these specifications, it shall mean Macon-Bibb County, a political subdivision of the State of

Georgia acting through the Macon-Bibb County Board of Commissioners.

2. Wherever the term “Engineer” occurs in these specifications, it shall mean the engineer of the Owner, the County Engineer, or his representative.

3. Wherever the term “work” occurs in these specifications, it shall mean the work as defined herein, including, all labor, materials, equipment, transportation, and supervision necessary to complete the contract.

4. Wherever the term “D.O.T.” occurs in these specifications, it shall mean the Georgia

Department of Transportation.

B. Related Documents

1. Quantity Worksheet (Attachment “B”)

2. Bid Form

3. Bidder’s Qualification Form

4. Financial & Legal Stability Statement

5. Bidder MBE Plan Form

6. List of Sub-contractors

7. Bond Forms

8. E-Verify Affidavit

9. Title VI non-discrimination Notice

C. Bidder’s Representation

1. Each bidder, by making his bid, represents that he has:

a) Read and understand the bidding documents; and,

b) Visited the site and became familiar with the local conditions under which the work is to be performed.

(1) Bidders shall examine the areas wherein work of this project is to be carried out and shall take into consideration all conditions that might affect his work.

(a) Failure of the bidder to inspect firsthand the areas affected by work in this project shall not relieve him of the obligation to comply fully with the scope of the work as defined herein.

(b) No consideration will be given any claim based on lack of knowledge of existing conditions, except where the Contract

Documents make definite provisions for adjustment of cost or extension of time due to existing conditions that cannot be readily ascertained.

D. Document Discrepancies

1. Should the bidder find discrepancies in, or omissions from the documents, he shall at once notify the Macon-Bibb County Procurement Department.

2. Requests for Interpretations of Drawings and Specifications shall be submitted via email to Lhardwick@maconbibb.us no later than September 26, 2025, by 3:00 pm.

3. Any subsequent instructions to bidders will be issued in the form of addenda to the specifications and sent to the bidder. All addenda shall be enumerated in the Bid Form.

4. All definitions set forth in the specifications are applicable to this Instruction to Bidders, the Bid Form and the proposed Contract Documents including, but not limited to, drawings, project manual, and any addenda issued prior to receipt of bids.

a) Addenda are written or graphic instruments issued prior to the execution of the

Contract that may modify or interpret the bidding documents by deletion, additions, clarifications or corrections.

b) Addenda will become part of the Contract Documents when the Construction

Contract is executed.

E. Submittals

1. In order for bids to be considered, the complete bid document package should be submitted including each of the following completed documents.

a) Bid Form

b) Bidder’s Qualification Form

c) Financial & Legal Stability Statement

d) List of Sub-Contractors

e) Minority Participation Goal

f) Bid Bond in amount of 5% of the total base bid

g) E-Verify Affidavit

h) Disbarment Form

F. Reservations

1. The bidder acknowledges that Macon-Bibb County reserves full freedom (in addition to the right to reject any and all bids) in awarding bids to consider all available factors including, but not limited to, price, the provision of needed and unneeded features, usefulness to the using department and prior County experience. In addition, the bidder recognizes the right of the Owner to reject a bid if the bidder failed to furnish any required submittals on the date required by the bidding documents, or if the bid is in any way incomplete or irregular. Hence the County may award bids to other than the lowest bidder if in the judgment of the Board of Commissioners the interest of the County will be best served by award to another.

mailto:Lhardwick@maconbibb.us

G. Surety and Insurance Companies

1. The Contract provides that the surety and insurance companies must be acceptable to the

Owner. The bidder shall require the attorney in fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of his power of attorney indicating the monetary limit of such power.

III. SPECIAL CONDITIONS

A. General

1. All work to be performed as part of this specification shall comply with all codes, ordinances and regulations applicable to the contract, including, but not limited to:

a) International Building Code

b) State and Local Building Code

c) Georgia Department of Transportation (D.O.T.)

d) Occupational Safety and Health Administration (OSHA)

e) Other Federal, State, or Local Codes

B. Permits and Licenses

1. Contractor shall obtain all permits and licenses, paying all fees as required, for execution of the Contract. In addition, the Contractor shall arrange for necessary inspections required by the City, County, State and other authorities having jurisdiction, and submit certificates of approval to the Owner or his designated representative.

C. Layout of Work

1. The Contractor shall verify all existing conditions and contiguous work and lay out his work there from, providing for himself all other necessary measurements, lines and levels, and shall assume the responsibility for the correctness of the layout of the work.

D. Work Area

1. The Contractor shall confine his operations to as small an area as possible, using only the areas designated for on-site storage.

2. The Contractor shall protect all surrounding adjoining private and public property, taking every precaution to prevent damage or injury to trees, shrubs, curbs, sidewalks, driveways and fences along or adjacent to the work. Should damage occur, the

Contractor shall restore, at his expense, any such property damage or injuries by his operations to a condition equal to that existing before such damage or injury was done, by repairing, rebuilding or otherwise restoring as may be directed by, and to the satisfaction of the Owner.

3. In case of failure on the part of the Contractor to restore such property, or make good such damages or injury, the Owner may, after forty-eight (48) hours written notice, proceed to repair, rebuild, or otherwise restore such property as may be deemed necessary, and the cost thereof shall be deducted from any monies due or which may become due the contractor under this contract.

E. Underground Utilities

1. The Contractor shall verify all underground utilities and their locations prior to commencing any work under this contract. Damage to underground utilities, and costs to repair same, shall be the responsibility of the Contractor.

F. Traffic Control

1. It shall be the responsibility of the Contractor to maintain traffic by utilizing adequate construction signs and flagmen at all times.

2. The Contractor shall furnish, install, maintain and eventually remove all traffic control devises necessary to properly protect and divert traffic. Such barricades and detour signs shall be illuminated at night.

3. All costs associated with traffic control shall be the responsibility of the Contractor.

4. The Contractor shall assume all responsibility for damages resulting from the failure of the signs and/or barricades to properly protect the work from traffic.

G. Erosion Control

1. The Contractor shall control all erosion by incorporating temporary grassing, mulch, baled straw, or silt fencing wherever required.

H. Vandalism

1. The Contractor shall take every precaution not to leave equipment and materials where they can be reached and used for defacing new or existing work at any time.

I. Material Disposal

1. The Contractor shall allow no trash, dirt, stumps, tree trunks, or excess material to accumulate and shall be responsible for removing same from the premises.

a) Such items shall be disposed of off the premises.

b) Burning of material on the site will not be permitted.

c) All costs of removing trash shall be the responsibility of the Contractor.

d) Place and method of disposal shall be the responsibility of the Contractor.

J. Extension of Time

1. In the event the work under this project is delayed by neglect, delay, or default of any other Contractor or the Owner, or by any damage which is the result of an Act of God, or by a general strike of the employees, the Contractor shall have reason to claim for delay and request an extension of time to complete the contract.

K. Liquidated Damages

1. Liquidated damages in the amount of $75 shall be charged to the contractor for each day that the project is delayed beyond the completion date of the contract. These charges are to defray the cost of inspection by Macon-Bibb employees assigned to the project.

L. Inspection

1. The Engineer may appoint inspectors to inspect all materials used and all work performed. Such inspection may extend to all or any part of the work and to the preparation of manufacture of the materials to be used. The inspectors will not be authorized to revoke, alter, enlarge or relax the provisions of this specification, nor will they be authorized to approve or accept any portion of the completed work or to issue instruction contrary to the plans and specifications. The inspector shall have authority to reject defective material and to suspend work that is being improperly done, subject to the final decision of the Engineer.

2. It is mutually agreed between the parties to the contract that to prevent all disputes and misunderstandings between them in relation to any of the provisions contained in these specifications, or their performance by either of said parties, the Engineer shall serve as the referee to decide all matters of construction of the specifications and of the terms of the contract, and as to all matters arising or growing out of said contract and his decision shall be final and binding upon both parties.

3. The Engineer and his inspectors shall have free access to all parts of the work, and to all material intended for use in the work. The work will be inspected as it progresses, but failure to reject or condemn defective work at the time it is done will in no way prevent its rejection whenever it is discovered before the work is finally accepted and approved, nor will final acceptance and approval constitute waiver by the County of any right of action for defective work or the failure to perform the contract according to its terms.

IV. EXECUTION

A. General

1. It is the intent of this specification to provide for the Paving the Way Project-6, for the

Macon-Bibb County Engineering Department, Macon, Georgia.

B. Specifications

1. The Contractor shall provide all services as outlined in this solicitation, See

Attachment “B” for Quantity Worksheet, attached hereto and incorporated herein

C. Schedule

1. The contractor shall commence work including applying for all needed railroad permits within 10 calendar days following issuance of notice to proceed, shall execute the work diligently, and shall complete all work requirements within 150 calendar days following the receipt of all necessary railroad permits. This time shall include all clean up, demobilization, and other necessary work to return the project area to its final state.

V. WARRANTY

A. The Contractor shall guarantee all labor and workmanship for minimum of one (1) year(s) from date of completion.

VII. SUBCONTRACTOR REPORTING REQUIREMENTS

A. Contractor shall submit a “Subcontractor/Supplier Participation Report” on this contract quarterly to the Macon-Bibb County Office of Small Business Affairs which shall include the following:

1. The name of each subcontractor or supplier participating in the contract.

2. A description of the work to be performed, materials, supplies, and services provided by each subcontractor or supplier.

3. Whether each subcontractor or supplier is a minority owned, woman owned, LGBTQIA+ owned, veteran owned, disabled person owned, Certified Disadvantaged Business Entity, non-profit, or local business.

4. Whether each subcontractor is a supplier, subcontractor, or other.

5. The dollar value of each subcontract or supply agreement.

6. The actual payment to date of each subcontractor or supplier participating in the contract.

B. The report shall be updated during the applicable quarter by the Contractor whenever any of the approved subcontractors or suppliers have completed the portion of the work they were contracted to perform. Copies of this report should be transmitted promptly to the Macon-

Bibb County Office of Small Business Affairs.

C. The County may withhold any payment due to the Contractor on any project for failure to submit the Subcontractor/Supplier Report within thirty (30) days following the end of the calendar quarter or for the failure to submit updates to the quarterly report within thirty (30) days of any subcontractor or supplier having completed the portion of work they were contracted to perform.

BID FORM

Macon-Bibb County Board of Commissioners

Laura Hardwick, Procurement Director

Macon-Bibb County, Procurement Dept.

700 Poplar Street, Suite 308

DATE: ___________________________________

Re: Paving The Way Project-6

Macon-Bibb County Engineering Department

Bibb County, Georgia

1. We have examined the Specifications, related documents and the site of the proposed Work, and are familiar with all the conditions surrounding this project, including the availability of materials and labor, and hereby bid to furnish all materials and labor, and to complete the project in accordance with the

Contract Documents, within the time set forth herein, and at the prices stated below. These prices are to cover all expenses incurred in performing the Work required under these Specifications, of which this bid is part.

2. ADDENDUM RECEIPT:

a. We acknowledge our responsibility to ensure that all addenda have been received prior to the submission of a bid.

b. Bidder acknowledges receipt of the following addenda:

Addendum No. Dated _________________________

Addendum No. Dated__________________________

Addendum No. Dated__________________________

3. We agree to commence actual physical work on site, with adequate force and equipment within the timeframe presented in the specifications and to complete fully all work within the stated timeframe following notice to proceed.

4. We agree that this bid may not be revoked or withdrawn after the time set for the opening of bids and shall remain open for acceptance for a period of sixty (60) days following such time.

5. In case of written notification by mail, telegraph, or delivery of the acceptance of this bid within sixty (60) days after the time set for the opening of bids, the undersigned agrees to execute within ten (10) days a

Contract for the Work for the below stated compensation and at the same time to furnish and deliver to the

Owner a Performance Bond and a Payment Bond, both in an amount equal to one-hundred-percent (100%) of the Contract Sum.

5. Enclosed herewith is a Bid Bond in the amount of five percent (5%) of the total base bid. We agree that the above stated amount is the proper measure of liquidated damages that the Owner will sustain by the failure of the undersigned to execute the Contract and to furnish the Performance Bond and the Payment

Bond.

6. If this bid is accepted within sixty (60) days after the date set for the opening of bids and we fail to execute the Contract within ten (10) days after written notice of such acceptance or if we fail to furnish both a

Performance Bond and a Payment Bond, the obligation of the bond will remain in full force and affect and the money payable thereon shall be paid into the funds of the Owner as liquidated damages for such failure; otherwise, the obligation of the bond will be null and void.

7. We hereby certify that we have not, nor have any member of the firm(s) or corporation(s), either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with this submitted bid.

8. We understand the total bid price listed below to be inclusive of all materials, labor, equipment, and other provisions necessary to provide the services in accordance with the associated specification.

Pave the Way Package 6 for Macon-Bibb County (Roadway Repair and Resurfacing)

Bid Schedule – Pave the Way Package 6

The quantities listed are an approximate estimate of the materials required to complete the roadway repair and resurfacing projects, for the Main Streets list. The “Total Bid Price” is the bid amount which shall be used to award Pave the Way Package 6 paving contract to the successful bidder.

Prior to beginning contract paving work on the main streets, the successful bidder shall be required to contact

Mike Beard with the Macon Water Authority, at (478) 256-9382, regarding coordination with MWA on locating /marking paved over sanitary manholes. Contact Willie Sidney with the Macon Water Authority, at

(478) 256-9400, to locate / mark paved over water valves.

Also, the successful bidder shall contact Monte Tolleson with the Macon Water Authority Storm Water Office, at (478) 738-6520, regarding locating / marking paved over storm manholes.

The 120-day contract period shall proceed upon the successful bidder receiving the “Notice to Proceed” from our Procurement Office.

Road Name From To Miles

Ashford Chase Ct Peake Road Ashford Trace Lane 0.17

Ashford Chase Ct Ashford Trace Ln cul-de-sac 0.07

Ashford Trace Lane Ashford Chase Ashford Court 0.11

Ashford Trace Lane Ashford Court cul-de-sac 0.07

Autumn Trace Ct Peake Road Autumn Trace Ct 0.04

Autumn Trace Ct Autumn Trace Ct North cul-de-sac 0.07

Autumn Trace Ct Autumn Trace Ct South cul-de-sac 0.14

Country Oaks Dr Lamar Road Adams Way 0.05

Country Oaks Dr Adams Way Old Oak Court 0.05

Country Oaks Dr Old Oak Ct Kimmeridge Dr 0.25

Country Oaks Dr Kimmeridge Dr cul-de-sac 0.04

Adams Way Country Oaks Dr cul-de-sac 0.11

Kimmeridge Dr Country Oaks Dr Candlewick Ct 0.11

Kimmeridge Dr Candlewick Ct cul-de-sac 0.10

Kimmeridge Dr Country Oaks Dr Van Dyke Cove 0.08

Kimmeridge Dr Van Dykke Cove Dorchester Ct 0.11

Kimmeridge Dr Dorchester Ct Montrose Dr 0.08

Kimmeridge Dr Montrose Dr cul-de-sac 0.13

Old Oak Ct Country Oaks Dr cul-de-sac 0.03

Candlewick Ct Kimmeridge Dr cul-de-sac 0.07

Van Dyke Cove Kimmeridge Dr cul-de-sac 0.05

Montrose Dr Lamar Road end of divided median

0.03

Montrose Dr

Lamar Road end of divided median

0.03

Montrose Dr End of divided median Amalie Dr 0.06

Montrose Dr Amalie Dr Kimmeridge Dr 0.08

Montrose Dr Kimmeridge Dr cul-de-sac 0.16

Amalie Dr Montrose Dr south cul-de-sac 0.05

Amalie Dr Montrose Dr Charlotte Court 0.08

Amalie Dr Charlotte Court cul-de-sac 0.15

Amalie Dr Amalie Dr cul-de-sac 0.04

Underwood Dr cul-de-sac east Camden Road 0.22

Underwood Dr Camden Road cul-de-sac 0.21

Ousley Place Forest Hill Road Camden Road 0.23

Ousley Place Camden Road Newport Place 0.21

Ousley Place Newport Place cul-de-sac 0.15

Azalea Dr Ayers Rd Barrington Pl 0.18

Azalea Dr Barrington PL Club Trace 0.06

Azalea Dr Club Trace Greenfield Rd 0.03

Greenfield Rd Azalea Dr Napier Ave 0.06

Club Trace Azalea Dr cul-de-sac 0.04

Barrington Pl Ayers Rd Azalea Dr 0.20

Shadow Lawn Dr Ayers Rd Lakewood Ave 0.14

Brooklawn St Ayers Rd Lakewood Ave 0.09

Brooklawn St Lakewood Ave Brooklawn Pl 0.06

Brooklawn Pl Brooklawn St cul-de-sac 0.04

Lakewood Ave Brooklawn St Shadow Lawn Dr 0.17

Lakewood Ave Shadow Lawn Dr cul-de-sac 0.10

Park St Napier Ave Ayers Blvd 0.05

Park St Ayers Blvd Alexander Ave 0.04

Park St Alexander Ave Parkwood Ave 0.04

Park St Parkwood Ave Berkley Dr 0.03

Park St Berkley Dr Forsyth Rd 0.15

Dexter Ave Columbus Rd Winifred Way 0.27

Wellworth Ave Columbus Rd Winifred Way 0.24

Winifred Way Burton Ave Dexter Ave 0.06

Winifred Way Dexter Ave Welllworth Ave 0.05

Winifred Way Wellworth Ave Florence Ave 0.06

Winifred Way Florence Ave Saint Claire St 0.08

Saint Claire St Winifred Way Florence Ave 0.10

Florence Ave Winifred Way Saint Claire St 0.06

Florence Ave Atherton St Mercer University Dr 0.07

Atherton St Florence Ave cul-de-sac 0.07

Pierce Dr N Gwinette Dr unnamed side street 0.18

Pierce Dr N unnamed side street Gwinette Dr 0.18

Pierce Dr W Gwinette Dr Pierce Dr S 0.12

Pierce Dr S Pierce Dr W Janice Pl 0.07

Pierce Dr S Janice Pl Gwinette Dr 0.16

Janice Pl Pierce Dr S Gwinette Dr 0.09

Providence Blvd Bass Road Waverly Lane 0.27

Providence Blvd Waverly Lane Carillon Lane 0.06

Providence Blvd Carillon Lane Waverly Pt 0.07

Waverly Lane Providence Blvd Waverly Park Dr 0.03

Waverly Lane Waverly Park Dr Waverly Ct 0.15

Waverly Lane Waverly Ct Waverly Point 0.09

Waverly Park Dr Waverly Lane Waverly Pt 0.15

Waverly Point Providence Blvd Waverly Park Dr 0.04

Waverly Point Waverly Park Dr Waverly Lane 0.07

Waverly Point Waverly Ln cul-de-sac 0.10

Waverly Ct Waverly Ln cul-de-sac 0.05

Carillon Ln Providence Blvd Carillon Ct 0.06

Mary Dr Mary Dr West Mary Dr 0.15

Mary Dr West Mary Dr Hardy Place 0.12

Mary Dr Hardy Pl Shaw Dr 0.04

Mary Dr Shaw Dr Austin Ave 0.19

West Mary Dr Mary Dr Mary Dr 0.13

Hardy Place Mary Dr Guthrie Dr 0.02

Hardy Place Guthrie Dr Atkins Dr 0.07

Guthrie Dr Hardy Pl Austin Ave 0.21

Austin Ave Shaw Dr Guthrie Dr 0.06

Austin Ave Guthrie Dr Austin Pl 0.01

Austin Ave Austin Pl Glynn Ave 0.06

Austin Ave Glynn Ave Atkins Dr 0.04

Austin Ave Atkins Dr Hillcrest Ave 0.02

Total 9.23

Package 6 Bid Quantity Sheet

Item Unit Quantity Unit Price Total

Milling TONS 12277.9

Bituminous Tack GAL 8929.36

Roadway Patching SY 14882.27

12.5 mm Superpave Asphalt TONS 12277.9

9.5 mm Superpave Asphalt TONS 0

Install Furnished Sewer

Manhole, Storm

Manholes, EA 262

Install Furnished Water

Valve Riser

EA 189

Manhole (Adjustment) EA 262

Water Valve (Adjustment) EA 189

Traffic Signal Loop Install EA

Striping (Center Lines, Edge Lines, Lane Lines)

LF 16337

Painted Arrows EA 6

Bike Symbols EA 0

Painted Messages EA 0

Painted Crosswalks LF 506

Painted Stop Bars LF 1002

Painted RR Symbols EA 0

Painted Hatching LF 140

Rumble Stripe SET 0

RPMs MILE 0.31

Clipping Grassed Shoulders MILE 0.25

Total Bid $ _____________

Firm Name: _________________________

Print Name: _________________________

Title: _______________________________

Signature: ___________________________

File details come from the government source that posted it. Updated .