This is a Project Labor Agreement (PLA) Request for Information (RFI) for a naval construction project at Naval Station Norfolk in Virginia. The project involves constructing a hangar and supporting facilities with an estimated construction magnitude of $100M-$250M and a performance period of approximately 1,100 calendar days. Specific project scope includes site preparation, utility demolition and relocation, excavation, grading, deep foundation system installation, paving, security fence modifications, environmental mitigation (including soil and groundwater contamination treatment), and site improvements. The project will be design-bid-build, with NAICS Code 236220, and aims to incorporate energy-efficient life cycle cost solutions.

The RFI seeks public input on potential Project Labor Agreement implementation, as required by Executive Order 14063 for large-scale federal construction projects over $35M. Interested parties are invited to complete an attached questionnaire addressing topics such as labor availability, contractor interest, union versus non-union labor rates, and potential PLA cost implications. Responses must be submitted via email to catharine.a.keeling.civ@us.navy.mil by 2:00 P.M. local time on 19 June 2025. This is explicitly not a solicitation or proposal request, but a market survey for planning purposes, with all submitted information to be held confidentially.

View the file

Other files

File Type Posted
25R2639 P222 - PLA Questionnaire .docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Labor Agreement (PLA) Request for Information (RFI) for

DBB P22 MQ-25 Aircraft Laydown Facilities, Naval Station Norfolk (NSN) in the State of Virginia

This is a request for information/market survey. This is not a request for proposal, request for quote, or an invitation for bid. There will be no solicitation, specification, or drawings available at this time.

Naval Facilities Engineering System Command (NAVFAC) Mid-Atlantic is soliciting comments from the public addressing the potential use of Project Labor Agreements (PLA) for the following construction project. The construction project is for a hangar and supporting facilities/building.

Construction includes site preparation, utility demolition and relocation, excavation cut and fill and grading. The site is an area of manmade land and releases of contaminants to the soil and groundwater as a result of historical airfield and industrial operations. Special foundation features include deep foundation system with piles. Paving and site improvements include storm water management Low

Impact Development (LID) facilities and items, security fence relocation and expansion with lockable pedestrian gates, vehicular circulation areas, parking restriping, expanded security fencing, site cleanup and landscaping. Environmental Mitigation includes sampling, staging, and offsite disposal of contaminated soil, treatment (including sampling, licensed operator, and treatment system) of contaminated groundwater and runoff during dewatering activities, disposal of groundwater treatment media, and disposal of AFFF concentrate/solution contained within the existing fire protection system of

Building LP48. Facilities will incorporate features that provide the lowest practical life cycle cost solutions satisfying the facility requirements with the goal of maximizing energy efficiency. The project will be design-bid-build. NAICS Code: 236220. The magnitude of construction is anticipated to be

$100M – $250M. General period of performance is anticipated to be approximately 1,100 calendar days.

A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement as described in 29 U.S.C. 158 (f). Federal Acquisition Regulation (FAR) policy states:

Executive Order (E.O.) 14063, Use of Project Labor Agreements for Federal Construction Projects, requires agencies to use PLAs in large-scale construction projects (defined as a construction projects with a total estimated cost at or above $35M) to promote economy and efficiency in the administration and completion of Federal construction projects. When awarding a contract in connection with a large-scale construction project, agencies shall require use of a PLA for contractors and subcontractors engaged in construction on the project, unless an exception(s) at FAR 22.504(d) applies. Reference is made to: FAR Subpart 22.5 Use of Project Labor Agreements for Federal Construction Projects;

provision, FAR 52.222-33 Notice of Requirement for Project Labor Agreement; and to clause, FAR

52.222-34 Project Labor Agreement.

In consideration of the above factors, and any others which may be deemed appropriate, the public is invited to provide responses on the use of a PLA for this construction project utilizing the attached questionnaire.

This is not an announcement of the availability of a solicitation nor is it a means of generating a plan holder’s list. This survey is for planning purposes only and shall not be construed as a Request for

Proposal or as an obligation on the part of the Government. The Government does not intend to award a contract on the basis of this market survey or otherwise pay for the requested information. The

Government will not provide a debriefing on the results of this survey. All information will be held in a confidential manner and will only be used for the purposes intended.

Responses shall be submitted on the attached questionnaire via email to catharine.a.keeling.civ@us.navy.mil no later than 2:00 P.M. local time on 19 June 2025.

Project Labor Agreement (PLA) Questionnaire

Questions Responses

1) Are you responding as a representative of a government entity, union, contractor (union or non-union) and/or qualified small business?

2) Would the work involve specialized construction that is available from only a limited number of contractors or subcontractors? Explain in detail.

3) What is your understanding of the availability of union labor and non-union labor in this area for this type of project? Are you otherwise aware of national, regional, or local interest in participating in this project by union or non-union contractors.

Explain in detail.

4) As a qualified contractor for a project of this type, would you be interested in participating in this project?

Would the requirement of a PLA under this project impact your interest in any way? Explain in detail.

5) Are you aware of PLAs having been used on other similar construction projects in the area and/or other nearby areas?

Explain in detail.

6) How do union wage rates compare to prevailing wage rates for this type of project and in this area, i.e., prevailing wage rates under the Construction Wage Rates Requirements statute (formerly known as the Davis-Bacon Act). Explain in detail.

7) Are there any ways in which the requirement of a PLA might increase costs on a project of this type in this area? Explain in detail.