PROJECT LABOR AGREEMENT (PLA) REQUEST FOR DBB P222 MQ-25 AIRCRAFT LAYDOWN FACILITIES, NSN, VA
Solicitation number
Not on record
Issued by

About this file

This document is a Project Labor Agreement (PLA) Request for Information (RFI) questionnaire for the MQ-25 Aircraft Laydown Facilities project at Naval Station Norfolk in Virginia. The project involves constructing a hangar and supporting facilities with a total estimated construction cost between $100M-$250M and an anticipated performance period of 1,100 calendar days. The construction scope includes site preparation, utility demolition and relocation, excavation, special foundation features with pile systems, environmental mitigation, storm water management, security fencing, and site improvements.

The Navy is seeking industry input on the potential implementation of a Project Labor Agreement (PLA) through a detailed questionnaire addressing labor availability, contractor interest, wage comparisons, and potential cost implications. Responses are requested via email to catharine.a.keeling.civ@us.navy.mil by 2:00 P.M. local time on 19 June 2025. The survey is for planning purposes only, follows Executive Order 14063 requirements for large-scale federal construction projects over $35M, and will be conducted by the Naval Facilities Engineering Command (NAVFAC) Mid-Atlantic using a design-bid-build project delivery method.

View the file

Other files

File Type Posted
25R2639 P222 - PLA Request for Information.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Labor Agreement (PLA) Request for Information (RFI) for DBB P22 MQ-25 Aircraft Laydown Facilities, Naval Station Norfolk (NSN) in the State of Virginia

Project Labor Agreement (PLA) Questionnaire

Questions
Responses

1) Are you responding as a representative of a government entity, union, contractor (union or non-union) and/or qualified small business?

2) Would the work involve specialized construction that is available from only a limited number of contractors or subcontractors? Explain in detail.

3) What is your understanding of the availability of union labor and non-union labor in this area for this type of project? Are you otherwise aware of national, regional, or local interest in participating in this project by union or non-union contractors. Explain in detail.

4) As a qualified contractor for a project of this type, would you be interested in participating in this project?

Would the requirement of a PLA under this project impact your interest in any way? Explain in detail.

5) Are you aware of PLAs having been used on other similar construction projects in the area and/or other nearby areas? Explain in detail.

6) How do union wage rates compare to prevailing wage rates for this type of project and in this area, i.e., prevailing wage rates under the Construction Wage Rates Requirements statute (formerly known as the Davis-Bacon Act). Explain in detail.

7) Are there any ways in which the requirement of a PLA might increase costs on a project of this type in this area? Explain in detail.