25125 Addendum 1 with attachments 20250813.pdf

PDF 1 MB Posted

Attached to
271/25125. GSA; Treasury/Operations Center HR Suite
Solicitation number
RFQ-171-250000000589-2
Issued by
Eaton County, Detroit City, Michigan

About this file

This document is a Construction Bid Addendum No. 1 issued by the Michigan Department of Technology, Management and Budget (DTMB) for the Michigan Department of Treasury Operations Center HR Suite project. The project, with file number 271/25125.GSA and Hobbs+Black project number 25308, is scheduled for bidding with key dates including: bid issuance on August 5, 2025, pre-bid meeting on August 11, 2025, last day for pre-bid RFIs on August 13, 2025, bid due date of August 20, 2025, and anticipated construction commencement by September 16, 2025. The project timeline targets substantial completion by October 14, 2025, with HR move-in planned for October 16, 2025, and final project close-out by November 2, 2025.

The addendum includes several attachments: pre-bid meeting conference notes, a pre-bid sign-in sheet, and electrical panel photographs. The document provides an anticipated project schedule and indicates that all work shall be performed in accordance with original drawings and specifications, with this addendum taking precedence. The addendum was distributed to all plan holders via the Sigma system and requires bidders to acknowledge receipt on their proposal forms. No specific pricing details or funding sources are explicitly outlined in this document, which primarily serves to provide additional context, clarifications, and schedule information for potential bidders.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 6/25)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND

BUDGET

State Facilities Administration Design & Construction Division

CONSTRUCTION BID ADDENDUM NO. 1

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

8/14/2025

PROJECT NAME

Michigan Department of Treasury Operations Center – HR Suite

FILE NUMBER

271/25125.GSA

PROFESSIONAL

Hobbs+Black

PROJECT DIRECTOR

George Ananich

BID OPENING DATE:

8/20/2025

ADDENDUM ITEMS: (6 pages attached)

Pre-bid meeting Conference Notes – Attached Pre-bid Sign-in Sheet – Attached Electrical Panel Photos - Attached

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

John Mortimore. Hobbs+Black

PROFESSIONAL: DATE: 8/14/2025

APPROVED BY:

George Ananich, DTMB/DCD

PROJECT DIRECTOR: DATE: 8/14/2025

http://www.michigan.gov/SIGMAVSS

117 E. Allegan Street, Lansing, Michigan 48933 | 517.484.4870

ANN ARBOR | DETROIT | GRAND RAPIDS | LANSING | PHOENIX | WWW.HOBBS-BLACK.COM

ADDENDUM 1

DATE: August 13, 2025

PROJECT: DTMB/Department of Treasury

Operations Center HR Suite

DTMB File: 271/25125.GSA

H+B PROJECT: 25308

This Addendum is issued for the purpose of modifying and/or clarifying the original drawings and specifications and shall take precedence over them.

All work included herein shall be in accordance with the original drawings and specifications except as specifically noted herein. All incidental items required to provide the following modifications shall be included even though not specifically described.

This Addendum is being sent to all bidders receiving plans and specifications. Receipt of this Addendum shall be noted on Proposal Form in appropriate locations.

GENERAL

1. ANTICIPATED PROJECT SCHEDULE

Issued for Bids August 5, 2025

Submit for Building Plan Review(s) July 31, 2025

Pre-Bid Meeting 2:00 p.m. August 11, 2025

Last Day for Pre-Bid RFI’s August 13, 2025

Last Addenda Issued August 14, 2025

Bids Due 2:00 p.m. August 20, 2025

Post-Bid Interview(s) August 21, 2025

Recommendation to DTMB August 22, 2025

Pre-Construction Kick-Off Meeting – (no later than) September 3, 2025

Construction Commences – (no later than) September 16, 2025

Substantial Completion (ready to use – punch list complete) October 14, 2025

HR Move-in October 16, 2025

Contractor Project Close-Out

(As-built Drawings, Operations & Maintenance Manuals) November 2, 2025

2. Pre-Bid Sign-In sheet is attached as part of this addendum.

3. Photos of existing electrical panels for contractor reference attached.

END OF ADDENDUM

JDM/ame

Enclosure

Cc: All Plan Holders (via Sigma)

Operations Center HR Sutie

271/25125.GSA, H+B 25308

Addendum 1 August 13, 2025

Figure 1 Electrical Panels

Figure 2 Panel IRA Figure 3 Panel IRA

Addendum 1

Figure 4 Panel IRA1

Figure 5 Panel IRA1

Addendum 1

Figure 6 Panel IRA2

Figure 7 Panel IRA2

Addendum 1

Figure 8 Panel IRA3

Figure 9 Panel IRA3

File details come from the government source that posted it. Updated .