This Invitation for Bid (IFB) details a cemetery expansion and improvement construction project for the Snake River Canyon National Cemetery in Buhl, Idaho. The base bid includes gravesite expansion of PPCs and columbaria walls, concrete panel repairs, tree removal and landscaping, installation of a new storage facility with an electronic gravesite locator kiosk, water quality pond improvements, and various site infrastructure enhancements. The project is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with an estimated construction value between $5-10 million under NAICS code 238190.

The project has a 12-month (365 calendar day) completion timeline after receipt of Notice to Proceed. Key requirements include securing necessary permits, investigating on-site conditions, maintaining site drainage, providing daily progress reports with electronic photos, offering a one-year warranty on materials and workmanship, and coordinating with the Cemetery Director for logistics. A pre-bid site visit is scheduled for 7/22/2025 at 10:00 AM PST, and all Requests for Information must be submitted by 7/28/2025 at 3:00 PM EST. A Bid Bond is mandatory at the time of bid opening.

View the file

Other files

File Type Posted
36C78625B0038 0003.pdf PDF
941002 SRCNC Gravesite Expansion - Project Manual Spec Book R2.1.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 6 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 8 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 5 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 7 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 4 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 3 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 2 of 8.pdf PDF
941002 SRCNC Gravesite Expansion Bid Set - Plans 1 of 8.pdf PDF
36C78625B0038 0002_rev.pdf PDF
36C78625B0038 0002.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans Cover Sheet.pdf PDF
Brand Name Material List.pdf PDF
941002 SRCNC Gravesite Expansion - Project Manual Spec Book R1.pdf PDF
36C78625B0038 0001_Amendment.pdf PDF
36C78625B0038_Solicitation_rev2.pdf PDF
36C78625B0038_Solicitation_rev.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Specifications 1 of 1.pdf PDF
Wage Determination_Twin Falls County ID_Building.txt TXT text file
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 6 of 8.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 4 of 8.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 2 of 8.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 1 of 8.pdf PDF
IFB Lump Sum Division Spreadsheet_RNC Site Improvements.xlsx XLSX spreadsheet
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 7 of 8.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 8 of 8.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 3 of 8.pdf PDF
250520 Snake River Canyon ID 941-002 Expansion Design Bid Set Plans 5 of 8.pdf PDF
36C78625B0038_Solicitation.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION FOR BID

SCOPE OF WORK

FOR

SNAKE RIVER CANYON ID 941-002 EXPANSION

A. PART I – PROJECT OBJECTIVES

A1. Statement of Work

STATEMENT OF BID ITEM(S)

1. BASE BID:

a. Gravesite expansion of PPCs, IGCs, columbaria walls, and memorial walls and all associated walks, roads, landscaping, drainage, site furnishings, and automated irrigation.

b. Repair and replace concrete panels in front of columbarium wall and within committal shelter.

c. Remove and replace approximately 135 trees (contractor to site verify). Add landscape fabric, groundcover, and edger to existing landscape berm along south edge of property as shown on drawings.

d. Add concrete block sprinkler protectors to existing sprinkler heads.

e. Reset locations of all seals and add Space Force service seal to committal shelter.

f. Add a Storage Facility (approximately 22’x 22’), with electronic gravesite locator kiosk, walkways, and extended pavement. Remove existing gravesite locator and patch concrete.

g. Insulate Sanitary service lines and sanitary septic tank.

h. Water quality improvements at the east end pond including replacement of the pond liner, add concrete overflow weir, add landscape berm, add concrete channel, regrade around the pond.

This work includes the relocated pump intake structure, pump intake pipe, and backwash pipe.

A.2 General Conditions

1. All work will be accomplished during normal business hours (8:00 am to 4:30 pm) Monday through Friday, except Federal Holidays.

2. Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and review the scope of work to determine the extent of the work. The Contractor shall take the necessary precautions to avoid damages to existing items to remain in place, to be reused or to remain the property of the Cemetery. Any damaged items shall be repaired or replaced at the Contractors expense as directed by the Contracting Officer’s Representative

(COR).

3. Establish construction limits, install safety controls, and install construction fencing as approved by the COR.

4. SITE SURVEY: Locate and stake/flag all underground utilities.

5. SITE CLEARING: Remove grass and other vegetation or obstructions as required to permit grading of the site within the project limits. Dispose/haul away and dump trash, debris and waste to an approved disposal site.

6. EROSION CONTROL AND SITE DRAINAGE: Contractor shall provide erosion control measures to prevent erosion or displacement of soils and discharge of soil bearing water runoff or airborne dust.

7. SITE GRADING AND FINISHING: Perform grading within the limits of the project to the lines, grades, and elevations indicated and as specified. Thoroughly clean up the work area at the end of each day’s work and at completion of the project. Leave premises clean and free of waste, scrap, used equipment or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.

8. LANDSCAPING: Provide turf grass sod. The Contractor shall protect from damage all existing improvements, equipment, structures, facilities, grounds and utilities at or near the work site or adjacent property. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work.

9. Upon completion of contract, deliver work complete and undamaged. Existing materials, equipment, structures, facilities, grounds and disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in good condition as existed before commencing work.

10. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.

Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Contracting Officer and the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

11. Thoroughly clean up the work area at the end of each day’s work and at the completion of the project. Leave premises clean and free of waste, scraps, used equipment or other material intentionally or accidentally delivered to the site by the Contractor or Contractor’s personnel.

12. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs and grass) on or adjacent to the work site not to be removed and do not reasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

13. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be made known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

14. The Contractor shall coordinate with the Cemetery Director for parking, material storage, temporary portable restroom facilities and any other needs for the work.

A3. Other Requirements:

1. Contractor shall secure all necessary permits including any environmental permit required to meet compliance.

2. Contractor shall investigate all on-site conditions including all utilities prior to construction.

3. Contractor shall grade the site to maintain proper site drainage.

4. Contractor shall provide daily progress summary and electronic photos to show construction progress through e-mail to the COR.

5. Contractor shall provide a certificate of warranty for material supplied and workmanship for a minimum of one year from the date of acceptance.

6. Contractor shall provide two copies of Operation and Maintenance Manuals, if required, at the final inspection.

7. Contractor shall perform daily clean up and final clean up.

8. Contractor shall dispose of all waste materials properly off site.

9. Seal concrete.

10. Protect existing roads and undisturbed infrastructures and environments.

11. Repair and restore all damages to be as good as the original conditions or better due to construction activities.

12. Prior to submitting any bid, a site meeting will be held and participants would include but not limited to the contractor, contracting officer and/or COR, District Engineer, and the Cemetery Director. The purpose of the meeting would be to visit site locations, clarification of scope, and to thoroughly investigate the site to ensure a clear understanding of the project.

A4. Schedule

1. The anticipated completion of this project is 12 months or 365 calendar days after receipt of

Notice to Proceed.

A5. Definitions

1. Construction contract as defined by the Department of Veterans Affairs (VA) is the procurement by the Government, under one contract, with one firm or joint venture (JV) for construction services for a specific project.

2. Contracting Officer: The services to be performed under this contract are subject to the general supervision, direction, control and approval of the Contracting Officer. The Contracting Officer is the only person authorized to obligate the government, interpret or change the contract.

3. Project Manager / Contracting Officer’s Representative (COR): The COR is the Contracting Officer's authorized representative. The COR is responsible for protecting the Government's interest in the execution of the construction contract work. His duties include surveillance of all construction work to assure compliance with the contract documents, approval of all submittals, samples, shop drawings, etc.

4. Contract: This term, as used herein, refers to the Contract(s) to perform the construction of the project.

5. Contractor: This term, as used herein, refers to the contractor under this contract.

A6. Location

1. Snake River Canyon ID

B. PART II – RESPONSIBILITIES OF THE DESIGN-BUILD TEAM

1. The section is not applicable for this IFB.

C. PART III - PROPOSAL REQUIREMENTS

1. The section is not applicable for this IFB.

D. PART IV - POST AWARD REQUIREMENTS

1. Construction Period Submittals

• Shop drawings and submittals - The Contractor shall be responsible to ensure that the VA COR reviews shop drawings, detail drawings, schedules, descriptive literature and samples, and review the color, texture and suitability of materials for conformity with the contract documents. The COR shall recommend approval, disapproval, or other suitable disposition. The VA COR will have final approval authority.

• Other submittals – The Contractor shall submit test results, certificates, manufacturer’s instructions, manufacturer’s field reports, etc. as required by the VA IFB specifications, to the VA COR.

• Project record drawings - The Contractor will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the IFB specifications. The project record drawings will be available for review by the VA COR at all times.

2. Project Close-Out. The Contractor shall comply with the requirements in the “General Conditions”, and “General Requirements”, for submission of final IFB as-built drawings, manuals, and other documents as noted. Required as-built drawings and specifications will be submitted in the same format required for the construction documents.

3. Site Visits and Inspections. At the behest of the Contractor, the VA COR/inspector shall observe the construction, advise the contractor of any deviations or deficiencies or solutions to issues discussed.

- E N D OF SOW -

B. PART II – RESPONSIBILITIES OF THE DESIGN-BUILD TEAM

File details come from the government source that posted it. Updated .