Questions and Answers for Middle Island and Plainview.pdf
PDF 122 KB Posted
- Solicitation number
- 25-001811
About this file
This document is a Questions and Answers file for an FBI antenna removal project at two tower sites: Middle Island and Plainview/Melville. The Q&A provides critical details for potential contractors, including site-specific information such as FCC ASR numbers, equipment to be removed, and project logistics. Key answers clarify that the project involves removing Gabriel HP six and four-foot diameter dishes, waveguide and Heliax hangers, coaxial lines, and other transmission equipment from outside tower locations. Contractors interested in bidding can schedule site visits by contacting NYFO LET Tom Suhey via email or phone, with typical work hours set from 9am-6pm. The document specifies that no broadcast equipment needs to be turned down, there is no operational elevator, and all removed equipment should be disposed of, not kept by the FBI.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ques�ons and Answers for Middle Island and Plainview/Melville Antenna Removals
1. Can you provide coordinates to each tower site?
1. Plainview FCC ASR 88152
2. Middle Island FCC ASR
2. Can you provide the model numbers of all the dishes that are to be removed
1. No, Gabriel HP six foot and four foot diameter
3. Can you provide site photos of each tower?
1. No, available pictures, Google maps
5. Are we removing all of the exis�ng coax/waveguide securements or will they stay?
1. Wave guide and Heliax hangers
5. If the securements are to be removed, can you please provide photos of the securements going up the tower or confirm whether they are secured using buterflies or not
1. The industry term for these is Heliax hangers or Waveguide hangers. I guess some call them buterflies. Our License Agreement requires that we remove antennas and transmission lines and anything else when we leave an antenna site.
6. Is the FBI wan�ng to keep any of the removed equipment
1. No, it should be disposed
7. Is this a prevailing wage job? If so, can you please provide the correct wage order
1. No.
8. Are we able to schedule a site visit prior to quo�ng?
1. Yes, interested vendors would need to contact NYFO LET Tom Suhey via email at trsuhey@�i.gov or via cellphone at 917-504-7476.
9. Can the Government provide informa�on on the area surrounding the tower and compound? Is the space confined by vegeta�on and/or housing or any other obstruc�ons?
1. No. Google maps
10. Are the lines that are to be removed located on the inside or outside of the tower?
1. Outside
11. What are the hours of opera�on for the contractor workday?
1. Typical 9am-6pm mailto:trsuhey@fbi.gov
13. Is there broadcast equipment that needs to be turned down during work hours(Middle Island Tower)?
1. N/A
13. Is there an opera�onal elevator on the tower?
1. No