About this file

This is an Environmental, Health and Safety (EHS) Contractor Requirements document issued by Collier County, Florida for all construction projects undertaken by Collier County. The document establishes mandatory compliance standards for contractors performing work on county property, requiring adherence to applicable federal, state, and local regulations from agencies including OSHA, DOT, EPA, DHS, ANSI, FDEP, and NFPA, as well as county-specific Environmental Health and Safety Standard Operating Procedures and Job Safety Analysis protocols. Contractors must comply with specific requirements including vendor badge requirements, powered industrial vehicle certifications, hazardous materials handling and storage procedures, daily incident and OSHA inspection reporting, weekly internal safety inspections, fall protection devices for work above six feet, electrical safety practices, proper PPE usage, equipment maintenance standards, and guarding of floor and wall openings. When working within rights-of-way such as roads, sidewalks, and bike paths, contractors must follow all applicable FDOT and MUTCD requirements, including ANSI/ISEA 107-2010 compliant Class 2 or 3 hi-visibility safety garments and maintenance of traffic plans. The document requires submission of eight site-specific safety plans addressing general safety, security, hurricane preparedness, pandemic safety, respirable crystalline silica hazards, confined space entry, asbestos management, mold remediation, and environmental protection, with applicability determined by project scope. Risk management must be incorporated into all pre-activity, activity, and post-activity construction meetings, and contractors are responsible for safeguarding construction sites by protecting hazardous locations with appropriate barricading, signage, and closure measures to prevent public access.

Contractors must ensure all work meets or exceeds the standards set forth in Collier County Vertical Construction Standards and IT Construction Standards unless specifically exempted in writing by the Facilities Management Division Director and Risk Management Director. The requirements apply to all contractors performing work on Collier County properties and are mandatory conditions of contract performance; there is no incumbent vendor referenced in this standards document as it establishes baseline requirements applicable to all bidders on county construction projects.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Environmental, Health and Safety

Contractor Requirements for all BCC Construction Projects

1. Contractors will be required to understand and comply with all applicable laws and regulations of any governmental entity (OSHA, DOT, EPA, DHS, ANSI, FDEP. NFPA, etc.) and

Collier County CMA’s, EHS Standard Operating Procedures (SOP’s) or Job Safety Analysis

(JSA’s) that that pertain to environmental, health and safety standards and/or work practices applicable to the activities they perform for Collier County. These include but are not limited to:

• Must wear a BCC provided Vendor Badge at all times while on BCC property.

• Powered Industrial Vehicle Certifications (Heavy Equipment, Cranes, etc.)

• Storage, handling, and use of flammable liquids and hazardous materials, including fuels and compressed gas cylinders.

• Daily reporting of any incidents/accidents or any OSHA safety inspections of equipment and worksites.

• Weekly reporting of at least one internal safety inspection of equipment and worksite.

• Use of Personal Fall Protection Devices while working at heights above 6 feet.

• Following Electrical Safety Practices, Arc Flash and Lockout/Tagout procedures.

• Proper use of Personal Protective Equipment. (PPE)

• Proper maintenance and use of ladders and other equipment.

• Guarding of wall and floor openings, open trenches, and excavations.

• Environmental Requirements (Permitting, Tanks, etc.)

2. Required Site EHS Plans for:

• Site Specific Safety Plan

• Site Specific Security Plan

• Site Specific Hurricane Plan

• Site Specific Pandemic Safety Plan (COVID-19) (If Applicable)

• Site Specific Respirable Crystalline Silica Plan (If Applicable)

• Site Specific Confined Space Entry Plan (If Applicable)

• Site Specific Asbestos Management Plan (If Applicable)

• Site Specific Mold Testing and Remediation Management Plan (If Applicable)

• Site Specific Environmental Protection Plan (Spill Cleanup, SPCC, etc.) (If

Applicable)

3. When working within a right-of-way (i.e. roads, sidewalks, bike paths, etc) – All applicable

FDOT and/or MUTCD requirements are to be followed at all times. Specifics include but are not limited to:

• ANSI/ISEA 107-2010 Compliant Class 2 or 3 Hi-Visibility Safety Garments.

• Applicable work zone signage, cones, barricades or barrels, arrow panels, flagging personnel and Stop/Slow Paddles, where necessary, required by law or the BCC.

• An applicable work zone (Maintenance of traffic) plan based on FDOT and/or

MUTCD designs on site.

4. Risk Management is included in all Pre-Activity/Construction, Activity/Construction and

Post Activity/Construction Meetings.

5. Safeguarding construction sites – Protecting the jobsite and preventing or inhibiting public access after activities are finished for the day is equally important. Therefore, all hazardous locations within construction sites and rights-of-ways are to be adequately protected.

Specifics include but are not limited to:

• Damaged, blocked, or missing sections of sidewalks, bike paths or other pedestrian access zones shall be protected with orange barricade fencing, barricades with yellow or red tape (depending on the hazard) or an equivalent means of protection. Sidewalks must also be posted as being closed on both sides with a white sign with black letters.

• Excavations must be protected in a similar manner as listed above if they must be left open overnight, during weekend hours, etc.

• All other hazards shall be evaluated by the contractor to ensure there are no dangerous conditions remaining that could be inadvertently encountered by collier county employees and/or the public while the construction site is not active (i.e., when no construction work is taking place).

6. Contractor must agree that all work must meet or exceed the standards set forth in the

Collier County Vertical Construction Standards and Collier County IT Construction Standards

(if applicable) unless specifically exempted in writing by Facilities Management Division

Director and Risk Management Director.