25-8614_Bid_Schedule.xlsx
XLSX spreadsheet 17 KB Posted
- Attached to
- Everglades Airpark Hangar Repairs - GRANT FUNDED
- Solicitation number
- 25-8614
- Issued by
- Collier County, Florida
About this file
This is a bid schedule document for Collier County, Florida's solicitation 25-8614 for construction services to repair and restore aircraft hangar facilities at Everglades Airpark following Hurricane Ian damage. The project encompasses comprehensive repair work including demolition, repair or replacement of eight bifold hangar doors (43' wide x 16' high) with associated personnel access doors, remounting of 16 hangar door motors on elevated steel frame mounts, replacement of damaged roll-up and access doors, repair and replacement of exterior metal cladding systems (approximately 6,700 square feet of corrugated metal panels), replacement of approximately 2,000 square feet of fire-rated gypsum board, painting of approximately 12,700 square feet of surfaces, sealing of approximately 10,700 square feet of concrete floor slabs, cleaning and refinishing of 34 structural columns, repair of fencing and security systems, and complete replacement of the building electrical system. A non-mandatory pre-bid meeting is scheduled for February 25, 2026 at 10:00 a.m. at the Everglades Airpark, 650 E C Airpark Road, Everglades City, Florida 34114. Sealed bids must be submitted electronically through the County's OpenGov procurement portal no later than March 30, 2026 at 3:00 p.m. local time. The successful bidder must achieve substantial completion within 150 calendar days from the Notice to Proceed, with daily liquidated damages of $1,380 per day for delays, and final completion within 30 calendar days after punch list delivery.
The Engineer's Opinion of Probable Cost for the base bid is $1,193,500, with a bid alternate option to provide all new bifold hangar doors with warranty for an additional $100,000, bringing the anticipated total project budget to $1,293,500. Contractors must provide a mandatory unit price of $125 per square foot for repair of any damaged metal studs and accessories based on a possible repair area of 3,030 square feet. An Owner's Allowance of $378,750 is allocated for unforeseen conditions and will be expended only through written Change Order. This grant-funded project is subject to FEMA Public Assistance funding requirements, including compliance with 2 CFR Part 200, 44 CFR Part 206, and federal labor standards including prevailing wage requirements for contracts exceeding $100,000. Bidders must provide a bid bond equal to 5 percent of the maximum possible award, and the successful bidder must execute the contract within 10 calendar days of award and provide performance and payment bonds equal to 100 percent of the contract amount, with required insurance including Workers' Compensation at statutory limits, Commercial General Liability ($1,000,000 single limit per occurrence, $2,000,000 aggregate), Employer's Liability ($1,000,000 single limit), and Automobile Liability ($1,000,000 each occurrence). Work hours are limited to 7:00 a.m. to 7:00 p.m., Monday through Friday, unless otherwise specified, and all work must comply with the Florida Building Code (2023 Edition), Florida Fire Prevention Code, NFPA 101 Life Safety Code, NFPA 409 Standards on Aircraft Hangars (2016 Edition), and FEMA TB-2 flood-resistant material specifications for components at or below the Base Flood Elevation of 15 feet.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Solicitation No. | 25-8614 |
| Solicitation Title | Everglades Airpark Hangar Repairs – Grant funded |
| BID SCHEDULE |
| BASE BID | ||||||
| SUMMARY DESCRIPTION | Quantity | Unit | Bid Amount | |||
| Miscellaneous Demolition | 1 | LS | ||||
| A.1 | Exterior Building Envelope & Doors | |||||
| A.1.a* | Repair/Replace ALL Damaged Bi-fold Hangar Door Components (except motors/elec.) | 1 | LS | |||
| A.1.b* | Remount 16 hangar door motors on new steel frame mounts higher above the floor | 1 | LS | |||
| A.1.c | Repair/Replace Damaged Building Cladding Systems | 1 | LS | |||
| A.1.d | Replace (2) Damaged Hollow Metal Access Doors | 1 | LS | |||
| A.1.e | Replace 2 Damaged Roll-up Doors (approx. 8'W x 12'H) at Storage Units | 1 | LS | |||
| A.2 | Interior Work | |||||
| A.2.a | Repair/Replace Damaged Fire-Rated Partitions Between Storage Units & Hangar Bay (Replace Gyp. Bd. and Firestopping up to 8'-0" A.F.F. (approx. 2,000 SF); Prep, Prime & Paint Walls (approx. 5,200 SF)) | 1 | LS | |||
| A.2.b | Prep, Prime and Paint Existing High Gyp. Bd. Between Hangar Bays (approx. 7,500 SF) | 1 | LS | |||
| A.2.c | Allowance for Existing Metal Stud/-Channel/-Fastener Replacement (if corroded, etc.) | 1 | LS | |||
| A.2.d | Install Corrugated Metal Panels at Partitions Between Hangar Bays (Approx. 6,700 SF) | 1 | LS | |||
| A.2.e | Prep & Paint Structural Columns & Base Plates (34 each) | 1 | LS | |||
| A.2.f | Floor Slab Cleaning, Stripping & Sealing (approx. 10,700 SF) | 1 | LS | |||
| B through F | Electrical and Site Work | |||||
| B* | Hangar Door Motor Replacement & Associated Electrical Work (16 each of: Motors, Disconnects, Push Button Stations, Sprockets, Chain, etc. | |||||
| Labor, Install & Inspection) | 1 | LS | ||||
| C | Hangar Building Electrical System - Remove/Replace all damaged components | 1 | LS | |||
| D | Repair/Replace Damaged Fence/Gates/Entry (Include Repair/Replace for Damaged Security System and Electric Gate) | 1 | LS | |||
| E | Miscellaneous Metal Debris Collection & Disposal | 1 | LS | |||
| F | Exterior Cleaning | 1 | LS | |||
| Total Base Bid | $0.00 |
Bid Alternate Provide ALL NEW Bi-fold Hangar Doors and associated components (Warrantied) 1 LS
| TOTAL BASE BID LESS * LINE ITEMS | 1 | LS | $0.00 | |
| BASE BID LESS * LINE ITEMS + BID ALTERNATE | 1 | LS | $0.00 | |
| (*) | The Base Bid shall include all line items except A.1.a, A.1.b, and B, which are existing door repair items marked with an asterisk (). If Bid Alternate No. 1 (New Doors) is awarded, the cost of A.1.a, A.1.b, and B shall be deducted from the Base Bid total |
Unit Price Additional mandatory unit price to be provided:
Repair of Any Damaged Metal Studs & Accessories Based on 3,030 SF possible metal stud repair area (505 LF x 6' ht. assumed)/per SF
* Staff has allocated $378,750 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.
File details come from the government source that posted it. Updated .