25-63 ARR551 ITB ARR 551 Coach Paint, Repairs, HVAC Supports & Interior Refurb.pdf

PDF 2 MB Posted

Attached to
ITB 25-63 ARR551 ITB ARR 551 Coach Paint, Repairs, HVAC Supports & Interior Refurb
Solicitation number
25-63 ARR551 ITB ARR 551 Coach Paint, Repairs, HVA
Issued by
Aleutians East Borough, Alaska

About this file

This is an Invitation to Bid (ITB) issued by the Alaska Railroad Corporation (ARRC) for ARR 551 Coach Exterior Paint & Repairs, HVAC Supports and Interior Refurbishment. The project involves comprehensive maintenance and renovation of a passenger coach, with work to be performed in Anchorage, Alaska. The contractor will have access to the coach from October 15, 2025, and must complete all work by March 13, 2026. A mandatory pre-bid conference and site visit is scheduled for September 23, 2025, at 10:00 AM, requiring interested bidders to pre-register and wear appropriate personal protective equipment. The project scope includes disassembly, media blasting, metal repairs, vestibule stair and door replacement, HVAC support demolition and replacement, bodywork, roof and window sealing, painting, and interior galley and lavatory refurbishment.

The bid is structured with six base bid items, each to be priced as a lump sum, with a total bid evaluation based on these items. While there is no specific Disadvantaged Business Enterprise (DBE) contract goal, ARRC strongly encourages the use of small businesses and DBE subcontractors. The project is federally funded, potentially through the Federal Transit Administration (FTA), which introduces various compliance requirements including Buy America provisions, prevailing wage standards, and specific certification processes. Bidders must submit comprehensive documentation, including financial statements, company qualifications, and various federal certifications. The contract includes liquidated damages of $7,500 per calendar day for failure to meet substantial completion dates, with a maximum of 20% of the total contract price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARR 551 Coach Exterior Paint & Repairs, HVAC Supports and Interior Refurb

INVITATION TO BID

25-63-213811

SEPTEMBER 11, 2025

ALASKA RAILROAD CORPORATION

327 W. Ship Creek Ave.

Anchorage, AK 99501 ThompsonC@akrr.com

Phone 907-265-2068 Cell 907-854-3141

September 11, 2025

Invitation to Bid

25-63-213811

ARR 551 Coach Exterior Paint & Repairs, HVAC Supports and Interior Refurb

Cover Sheet

Response Required: This page must be completed and returned ensuring receipt of future addenda or additional information. Please email this form to ThompsonC@akrr.com all addenda will be forwarded to the contact’s name and number listed below.

Firms that have not returned this cover sheet will not be informed of addenda and will only be alerted to addenda by checking with the ARRC procurement officer or by checking ARRC’s internet site: www.akrr.com, select Suppliers and then Solicitations. Bidders must acknowledge the receipt of all issued addenda in their proposal/bid submittal.

Company Name ____________________________________________________

Mailing Address ____________________________________________________

City, State, Zip ____________________________________________________

Contact Name ____________________________________________________

Phone Number _______________________ Fax ________________________

Email Address ____________________________________________________

The Alaska Railroad Corporation web site www.alaskarailroad.com

327 W. Ship Creek Ave.

Anchorage, AK 99501 ThompsonC@akrr.com

Phone 907-265-2068 Cell 907-854-3141

THIS IS NOT AN ORDER INVITATION NUMBER: 25-63-213811

DATE OF INVITATION: Sept. 11, 2025

ARR 551 Coach Exterior Paint & Repairs, HVAC Supports and Interior Refurb

SEALED BIDS WILL BE RECEIVED AT: Alaska Railroad Corporation Attn. C. Lee Thompson 327 W. Ship Creek Avenue, Anchorage, Alaska 99501

Offers will be received until 3:00 pm local time on October 2th, 2025.

At which time bids will be publicly opened.

IMPORTANT

Pre-Bid Conference and /Site Visit: A pre-bid conference and site visit will be held on September 23, 2025 at 10:00 AM local time. Interested bidders will meet at the ARRC General Operations Building, 327 West Ship Creek Ave., Anchorage, AK 99501. Please dress appropriately for weather. PPE including safety vest; hardhats, and steel toe boots will be required. Request that interested parties pre-register by contact Lee Thompson at 907.854.3141 or ThompsonC@akrr.com

The Alaska Railroad Corporation (“ARRC”) is soliciting bids from interested parties to repaint and repair passenger coaches as specified herein. Interested parties are invited to submit a bid to supply said items to ARRC. Bids must be submitted on the bid form contained herein and must be mailed or delivered to the above address. Bids received via facsimile transmission will be considered non-responsive. The bid shall be in a sealed envelope with the bid number 25-63- 213811 clearly printed on the face of the envelope. Bids must be complete and in U.S. dollars.

See instructions and conditions enclosed herein.

ARRC reserves the right to reject any and all bids, or any part thereof, negotiate changes in bids, accept any bids or any part thereof, waive minor informalities or defects in any bids, and not to award the proposed contract if it is in the best interest of the ARRC.

ARRC shall not be held responsible for bidder’s lack of understanding of what is required by this bid. Should a bidder not understand any aspect of this bid, or require further explanation, or clarification regarding the intent or requirements of this bid, it shall be the responsibility of the bidder to seek guidance from the ARRC.

ARRC may award a contract resulting from this solicitation to the responsive offer whose offer conforming to this solicitation will be the most advantageous to the ARRC. ARRC may reject any or all offers if such action is in the best interest of ARRC, and waives informalities and minor irregularities in offers received. Any resulting contract from this solicitation shall incorporate the Standard Instructions, and General Terms and Conditions incorporated in this solicitation.

This solicitation is not to be construed as a commitment of any kind nor does it commit the ARRC to pay for any costs incurred in the submission of an offer or for any other incurred cost prior to the execution of a formal contract

BIDDER/VENDOR TERMS AND CONDITIONS: PROSPECTIVE BIDDERS ARE CAUTIONED

TO PAY PARTICULAR ATTENTION TO THIS CLAUSE. Bidder/contractor imposed terms and conditions which conflict with this Invitation to Bid terms and conditions are considered counter offers and, as such, will cause the Alaska Railroad Corporation to consider the bid non-responsive.

If a bidder attaches additional terms and conditions as part of the bid, such attachments must be accompanied by a disclaimer stating that in the event of conflict between the terms and conditions of this Invitation to Bid and the terms and conditions of the bidder/contractor, the terms and conditions of the Invitation to Bid will prevail.

ARRC Disadvantaged Business Enterprise (DBE) Program: ARRC is an equal opportunity corporation that encourages the participation of DBEs as prime contractors and subcontractors on its contracts funded in whole or in part by the Federal Transit Administration (FTA) or the Federal Highway Administration (FHWA). ARRC has a race neutral DBE Program and does not set DBE goals on individual solicitations. Nonetheless, the ARRC aspires to achieve an overall DBE participation of 4.0% in federal fiscal years 2025-2027 on contracts funded by agencies within the U.S. Department of Transportation. If this contract is funded in whole or in part by funds from the FTA, FEMA or the FHWA, it is imperative that you consult the Federal Terms and Conditions portion of this solicitation.

The Alaska Railroad is a member of Green Star (http://www.greenstarinc.org/). ARRC earned an initial Green Star Award in 1994 and a Green Star Air Quality Award in 2007. The Alaska Railroad considers Green Star membership to be a positive business attribute, and regards a Green Star award as a tangible sign of an organization’s commitment to environmental stewardship and continual improvement within its operations.

Preference and/or Alaskan Veteran Preference, the bid must also include a statement certifying that the bidder is eligible to receive said preferences. The application of preferences is for bid evaluation purposes only.

Please direct all responses and/or questions concerning this invitation to bid to Lee Thompson, Alaska Railroad Corporation, Supply Management, 327 W. Ship Creek Avenue, Anchorage, AK 99501, telephone number 907.854.3141, email address ThompsonC@akrr.com. Questions must be submitted in written form prior to May 30th, 2025. Questions submitted after that date will not be accepted.

Sincerely, C. Lee Thompson Contract Administrator Alaska Railroad Corporation

INDEX

APPENDIX A SCOPE OF WORK/MINIMUM QUALIFICATIONS

APPENDIX B SPECIFICATIONS

APPENDIX C COST SCHEDULE

APPENDIX D BIDDERS QUESTIONNAIRE

APPENDIX E SUPPLY BID FORM

APPENDIX F GENERAL TERMS AND CONDITIONS

APPENDIX G REQUIRED CONTRACT PROVISIONS FOR FEDERAL-

AID CONTRACTS (Revised August 19, 2013

ATTACHMENT A ARR 551-554 Exterior Repairs and Paint ATTACHMENT B ARR 551-554 Vestibule Parts ATTACHMENT C ARR 551-554 Undercar HVAC Subframe ATTACHMENT D ARR 551-554 Galley & Lav. Refurbishment

SUBMITTALS: Bids will not be considered if the following documents are not completely filled out and submitted at the time of bidding:

1. Supply Bid Form

2. Cost Schedule

3. Welding Qualifications

4. Bidder’s Questionnaire

5. Federal Requirements: Appendix H:

22. FTA BUY AMERICA REQUIREMENTS-49 USC §5323(j); 49 CFR Part 661

25. CERTIFICATION REGARDING USE OF CONTRACT FUNDS FOR

LOBBYING-31 USC 1352, 49 CFR Part 19, 20

APPENDIX A:

SCOPE OF WORK / MINIMUM QUALIFICATIONS

ARR 551 Coach Exterior Paint & Repairs, HVAC Supports and Interior Refurb

Schedule:

Contractor will have access to ARR 551 in Anchorage, AK October 15, 2025. ARR 551 must be returned to the ARRC Anchorage Car Shop no later than March 13th, 2026 for planned maintenance.

Tools and Materials

All tools and materials necessary to accomplish the repairs and painting described below are the responsibility of the contractor.

Overview of Scope

Coach ARR 551 is constructed with steel sheeting over steel substructure and requires sandblasting exterior sheeting to bare metal, repair of corrosion at the coach end/side sheet corners, emergency exit window frames and vestibules and replacement of the vestibule stairs, side entrance Dutch and trap doors, followed by body work and repainting to keep in good working order. Interior galley and lavatory need to be disassembled and removed to allow replacement of the subfloor in this portion of the car, followed by rebuilding of the lavatory walls, replacement of cabinets and installation of new ARRC provided galley stainless cabinetry and equipment.

Coach will be provided to the Contractor with the interior and underfloor equipment intact and care must be taken to ensure that no interior and underfloor equipment is damaged or adversely affected throughout the duration of the work. All costs associated with the repair or replacement of any portion of the interior or underfloor equipment, as either a direct or indirect result of the work performed under this Contract, will be the Contractor’s responsibility.

In preparation for paint, the Contactor shall remove all grab irons, exterior lighting (e.g. end lighting), louvers, trim, and any other appurtenances that are not intended to be painted. Dome windows are to remain installed and all exterior sealant is to be removed and replaced following inspection of the window frames. All items removed from the exterior of the coach are to be labeled, stored and protected from damage until re-installation or return to ARRC. No parts are to be discarded until the coach is accepted as complete by ARRC’s representative. Special care is to be taken when working near the windows to prevent damage. All removed painted parts are to be stripped and repainted per the specifications in Appendix B prior to reinstallation.

After assessment of the car structure, a general repair plan shall be prepared by the Contractor and agreed to by the Owners representative that addresses each failed or damaged item or member.

Minimum Qualifications

Contractor shall have its own rail accessible shop in which to perform all of the work required in this solicitation. Contractor’s paint and repair facility shall meet all Local, State and Federal requirements for performing this work. Image is important to Alaska Railroad and as such the Contractor shall have a minimum of five (5) years’ experience in painting and repair of heavy equipment. Experience painting railcars or locomotives are preferred. These minimum qualifications may not be satisfied by use of a sub-contractor.

Alaska Railroad employees must be allowed access to make repairs to car included in this contract while located at contractor’s shop on an as-needed basis.

Contractor shall perform pre-demolition walk through with owner's representative to field verify, confirm and mark all materials, systems and equipment to be removed prior to beginning demolition work. Any items designated for salvage shall be delivered to the ARRC.

Contractor to verify all dimensions prior to beginning the work or ordering materials. If the contractor determines the existing conditions vary from the contract documents, contractor is to promptly notify the owner’s representative.

Use only quality materials, e.g. primers, leveling compounds, adhesives, fasteners, cove base, plywood, HPL, etc. in the rebuild of passenger car galley and lavatory.

Cabinets and countertops to be shop fabricated by manufacturer with a minimum of 5 years experience. This may be satisfied by use of a sub-contractor.

Perform professional level, high quality fabrication, installation and refurbishment work.

Contractor will be required to provide labor and materials including fasteners, stainless steel wall lining and floor pans, HPL laminated plywood, stainless steel and aluminum trim and fabricated steel supports necessary to complete the work described in the plan set attached and specifications below, unless otherwise noted as “ARRC provided” in plans or in the schedule below.

Installed finish surfaces shall have matching heights at edges and joints shall be covered with appropriate trim. All gaps to be trimmed.

All finish flooring shall be in-plane with tight seams.

Requirements for Car-body Welding (Steel only)

Welding methods are restricted to shielded metal arc welding (SMAW), gas metal arc welding (GMAW), or flux core arc welding (FCAW). FCAW with dual shield is the preferred method.

Approved weld types include, but are not limited to: groove welds, fillet welds, plug welds, slot welds, and butt welds. The method of depositing metal shall be chosen to minimize warpage.

All welders performing work in accordance with listed welding procedures and types shall be qualified and copies of certifications must be provided to ARRC prior to beginning work.

Technique and Workmanship

Equipment: Welding and cutting equipment shall be so designed and manufactured and shall be in such condition as to enable qualified welders to obtain sound welds.

Welding Conditions: Welding shall be restricted to enclosed areas with temperatures not less than 50O Fahrenheit.

Discontinuity Repairs: The amount of metal removed shall be the minimum necessary to remove the discontinuity.

Weld Profiles: Face of fillet welds may be slightly convex, flat or slightly concave.

Repairs after welding

Joint preparation methods: Removal of weld material or portion of the base metal shall only be performed by machining, grinding, chipping, oxygen gouging, air arc, or plasma arc gouging.

Unacceptable portion of the weld shall be removed without substantial removal of the base metal.

Extent of Repair: The contractor has the option of either repairing an unacceptable weld or removing and replacing the entire weld.

Distortion Control (Steel): Where required, steel members distorted by welding shall be straightened by mechanical means or by carefully supervised application of a limited amount of localized heating.

Arc Strikes: Arc strikes outside the area of permanent welds should be avoided on any base metal. Cracks or blemishes caused by arc strikes shall be ground to a smooth contour and inspected to ensure soundness.

Cleaning of Single Pass and Multi Pass Welds: Before welding over previously deposited metal, all slag shall be removed and the weld and adjacent base metal shall be clean. This requirement shall apply not only to successive layers but also to successive beads and to the crater area when welding is resumed after any interruption.

Weld Appearance: Weld splatter adhesions shall be removed by sanding or grinding, as required.

Weld Termination: Welds shall be terminated at the end of a joint in a manner that will ensure sound welds.

Quality Control

The Contractor shall be responsible for controlling the quality of the work and all of the required materials that are not furnished by the Owner. The work noted herein requires documentation of conformance with material and installation specifications. Material documentation shall be furnished to the Owner prior to placement or use of the Contractor provided materials. Installation quality documentation shall be furnished to the Owner prior to any request for payment. Contractor is to supply quality control procedures for approval fifteen

(15) days prior to commencing work that is in compliance with the ARRC’s installation requirements noted herein and on the Plans.

Scope of Work – Base Bid Items Perform the following work on ARR 551 Coach:

Item No. 1: Disassembly and Media Blast

Disassembly

1. Remove all grab irons, blue flag brackets, vent covers and speakers from car body as shown in Attachment A drawings.

Media Blast

1. Protect all surfaces not scheduled for removal of finishes (trucks, wheels, undercar equipment, vents, windows, etc.) per Appendix B, section 3.2.6.

2. Media blast all painted surfaces and remove all plastic body filler down to bare metal per Appendix B, section 3.2.5.

Payment will be made under:

Item No. 2: Metal Repairs and Improvements

Vestibule Stair Replacement (both sides of coach)

1. Remove existing vestibule side exit stair treads.

2. Cut and remove existing stair box at body transition line (12” below vestibule floor elevation).

3. Weld 1”x0.5”x36” tap plates to outside of remaining stair box (4 places).

4. Fabricate new stair boxes per Attachment B.

5. Match drill and tap ¼”-20 through new stair boxes and tap plates.

6. Shim as needed to provide snug fit between existing stair box structure and new stair box and install into vestibule using ¼”-20 18-8 Stainless steel button head Torx screws.

Fasteners to be installed with Loctite Threadlocker Red 271 and torqued to 57 in-lb.

PAY ITEM

Item No.

Item Description Unit Quantity

1 Disassembly and media blast LS 1

7. Install Allgrip metal nosing as transition from vestibule floor to stairs.

Vestibule Dutch Door and Trap Door Replacement (both sides of coach)

1. Remove existing trap doors, upper and lower Dutch doors. Return all window glass and hardware to ARRC.

2. Fabricate vestibule doors and hinges per Attachment B.

3. Finish, paint and assemble new trap doors, upper and lower Dutch doors per Appendix B specifications.

4. Assemble and install trap doors, upper and lower Dutch doors per Attachment B.

Vestibule Improvements

1. Remove existing flooring, repair or replace underlying decayed metal.

2. Replace vestibule flooring with 3/16” 304SS diamond tread plate welded to existing structure.

3. Add 12ga stainless steel kick plate along base of forward vestibule wall per Attachment A page 2.

4. Remove existing end crossover plates.

5. Fabricate and install new crossover plates to match existing from 3/16” 304SS diamond tread plate.

End/Side Sheet Joint Reinforcement

1. Following sand blasting and sheeting repairs weld ASTM A588 2”x2”x1/8” angle from bottom of side sill to lower edge of end sheet roof radius at all four corners. Stitch weld to prevent warping the side sheets then weld gaps in stitch weld to provide continuous weld top and bottom. Break sharp edge of angle corner.

Bottom Side Skirts Repair

1. Remove hinged lower side skirt equipment doors.

2. Trim bottom edge of doors in straight line as directed by ARRC to match other low dome coaches. Break all sharp edges.

3. Sand blast inner and outer surfaces, repair all areas effected by corrosion, replace all decayed metal supports and paint with primer.

4. Paint doors per Appendix B specifications and Attachment A.

5. Reassemble doors and install new ARRC provided latches, striker pins and handles.

Underfloor Trash Locker Removal

1. Demolish and discard underfloor trash locker and door.

2. Fill through-floor cavity with fiberglass insulation batting.

3. Patch spark guard using 16ga steel galvanized sheet and 1/8” blind rivets.

Window Frame Repair

1. Remove all flat emergency exit side and upper windows.

2. Sand blast or grind all emergency exit window frames and adjacent sheeting to bare metal.

Inspect for decay.

3. Replace sheeting and repair underlying structure where decay is found.

4. Reinstall windows using existing or new ARRC provided rubber seals (as available).

Emergency Exit Horizontal Top Window Removal

1. Remove and return upper flat window glazing and seals above emergency exits to ARRC.

2. Provide and install plywood plug to fill window cavity.

3. Provide, install and seal sheet metal cover over removed window cavity. Sheetmetal to extend at least 1” beyond existing window cavity and be permanently sealed to carbody roof.

4. Seal around perimeter of patch.

Item No. 3: Underfloor HVAC Support Demo and Rebuild

Demolish and Discard Existing Underfloor HVAC Supports and Grey Water Tank

1. Demolish existing undercar steel HVAC support rails, through-floor penetrations and spark guards, four (4) places.

2. Demolish and discard existing greywater tank.

a. Coordinate re-routing of greywater plumbing and routing of new HVAC electrical conduit and conductors with ARRC Carmen and Jmechs.

3. Remove corrosion and scale from underlying car structure in areas of work. Coat with rust inhibiting primer and one coat of black finish paint.

Underfloor HVAC Subframe, Flashing & Spark Guard Installation

1. Install four (4) ARRC provided undercar HVAC subframe assemblies per Attachment C drawings.

2. Relocate and flash through-floor penetrations using 20ga galvanized sheet metal.

3. Install one (1) 11”x2”x18ga (9.75”R) galvanized air diverter per HVAC unit to replace original.

4. Install new underfloor fiberglass insulation batting matching original thickness where missing or removed.

5. Install new 16 ga galvanized spark guards where missing or damaged by this work.

PAY ITEM

Item No.

2 Metal Repairs and Improvements

LS 1

Item No. 4: Bodywork, Roof Sealing, Dome window Sealing and Prep for Paint

Bodywork

1. Prime all surfaces.

2. Apply minimum amount of new body filler to provide a smooth exterior surface and prepare for painting in accordance with Appendix B section 3.3.

Roof Panel Sealing

1. Seal all seams of mechanically fastened roof panels or welded seams with visible pitting or porosity with Sikaflex before painting.

Dome Window Sealing

1. Dome windows are not to be removed from Car Body. USE CAUTION WHEN WORKING

NEAR WINDOWS TO AVOID CAUSING ANY DAMAGE TO CURVED WINDOW GLASS.

2. Scrape or manually remove all exterior window sealant.

3. Manually sand or grind exposed metal window frame structure and adjacent sheeting to bare metal. Inspect for decay with ARRC representative.

4. Replace sheeting and repair underlying structure where decay is found.

5. Coat bare metal with primer.

6. Install new black Dowsil 795 Silicone Building Sealant continuously around window periphery in a tidy manner.

Prep for Painting

1. Clean and prepare all bodywork and primed surfaces scheduled for paint per Appendix B and the finish coating manufacturers specifications.

Item No.

3 Underfloor HVAC Support Demo & Rebuild

Item No.

4 Bodywork, Roof Sealing & Prep for Paint

Item No. 5: Paint Application, Finishing and Coach Reassembly

Paint Application

1. After all repairs and improvements are made, paint car per Appendix B, ‘Specifications for the repainting of passenger cars and locomotive exteriors’ and Attachment A page 3, ‘ARR 551-554 Paint and Stencil Arrangement’.

Reassembly

1. Install new ARRC provided vestibule door windows and rubber seals.

2. Reinstall all removed equipment back to original location of coach (unless specifically indicated to discard) using new hardware matching original.

Item No. 6: Interior Galley & Lavatory Refurbishment

Perform the following work on passenger car: ARR 551 per Attachment D drawings:

1. Disassemble and retain for reinstallation:

a. PA system

b. Lavatory faucets.

c. Lavatory doors, hardware and trim

2. Disassemble and return to ARRC:

a. Hallway stand-up freezer.

b. Microwave oven

c. Lang Meltmaster

d. Hatco heat strip

e. Galley faucets

f. Floor mounted galley equipment:

i. Refrigerated display case

ii. Remote compressor freezer

g. Galley under-sink instant hot water heater.

h. Galley under-counter exhaust fan.

3. Demolish and discard:

a. Lavatory cabinets and counter tops

b. Lavatory and hallway partitions

c. Floor mounted galley stainless cabinets and countertops.

d. Microwave shelf.

PAY ITEM

Item No.

Item Description Unit Quantity

5 Paint Application, Finishing & Coach Reassembly

e. Left-most column of wall shelving.

f. Galley exhaust hood.

g. Galley, hallway and lavatory area flooring and subfloor

h. Underfloor spark guards where corroded or decayed.

i. Remove corrosion and scale from underlying car structure. Coat with rust inhibiting primer.

4. Provide and Install:

a. New 16 ga galvanized spark guards where decayed or damaged by this work.

b. New underfloor fiberglass insulation batting matching original thickness under area of subfloor replacement.

c. Composite subfloor panels (ARRC provided)

i. Coat any area of floor joist bare metal from demolition with rust inhibiting coating prior to subfloor installation.

ii. New composite subfloor panels to be bonded to floor substructure per manufacturer’s instructions. Installation process includes solvent cleaning of floor beam members, measuring and applying leveling shims, trimming and dry-fit of composite panels, permanent bonding of panels to substructure using time sensitive adhesive (ARRC provided), application of weights during adhesive cure process, cleaning and bonding of panel joints.

iii. Additional floor support structure may be required to meet subfloor panel manufacturer’s maximum panel span. All edges of composite panels to be supported by minimum ½” overlap to sub-structure supports.

d. Composite lavatory cove base (ARRC provided)

e. New 3/4” APA A-B sanded plywood galley & lavatory partition walls to replace damaged walls (as required):

i. WF-1: Formica ‘Antique white’, matte finish, or approved equal in hallways and lavatories.

f. Extruded aluminum trim covering WF-1 and formed stainless steel trim covering

WF-2 as required.

g. New lavatory and hallway cabinets

i. Cabinet boxes to be factory built ¾” cabinet with ¾” shelves, overlap doors, soft-close hinges and non-locking latch and handle

ii. All exposed exterior surfaces to be laminated with WF-1 Formica ‘Antique White’, matte finish or approved equal, all other surfaces to be laminated with white HPL.

iii. Lavatory cabinets to match design of original. Hallway to be floor to ceiling cabinet to replace stand-up freezer.

h. New lavatory countertops

i. Countertops and backsplashes to be Dupont Corian solid surface in color

‘Aurora’, matching dimensions and thickness of original.

i. New 16ga 304 SS #4 finish galley lining to cover areas originally covered by casework. Lining to be installed in-plane with existing lining.

j. Galley Floor pans

i. Floor pans to be 14ga 304SS, ¾” height with 2”OD x 16” through-floor drains, welded construction, fabricated and installed after cabinetry.

5. Install (Existing or new ARRC provided):

a. Galley stainless steel cabinetry, counter tops & shelves.

b. Galley equipment, faucets and floor mats.

c. New ARRC provided lavatory exhaust fans.

i. Existing ceiling fan opening to be enlarged to 7” diameter hole centered to existing exhaust duct.

d. All utilities disturbed by this work.

i. All drain plumbing to be rigid copper piping with soldered connections.

ii. All water supply pluming to be PEX with crimp fittings (no push-to-fit connections)

e. Lavatory floor drains.

i. 14ga mounting plate with 1.5” OD x 0.049” wall x 16” 304SS drain.

Specifications of Contractor provided materials:

MATERIAL DESCRIPTION

HVAC SUPPORTS 4”x4”x 3/8” ASTM A36 ANGLE

HVAC DUCTING 20GA GALVANIZED STEEL SHEET, FABRICATED

UNDERFLOOR SPARK

GUARD 16GA GALVANIZED STEEL SHEET, FABRICATED

PRIMER, BODY FILLER,

PAINT & CLEARCOAT PER APPENDIX B SPECIFICATIONS

UNDERFLOOR

INSULATION

FIBERGLASS BATT, THICKNESS MATCHING

ORIGINAL

GREYWATER DRAIN

PLUMBING

1-1/2” RIGID COPPER PIPE AND FITTINGS,

SOLDERED CONNECTIONS

FRESH WATER SUPPLY

PLUMBING

½” PEX-A, ASTM F1807 METAL FITTINGS WITH

COPPER CRIMP RING OR STAINLESS STEEL

CLAMP. PUSH TYPE FITTINGS ARE NOT

ACCEPTABLE.

CABINET BOXES

¾” CABINET GRADE PLYWOOD, EXTERIOR

SURFACES WF-1 HPL, INTERIOR SURFACES

WHITE HPL, SHOP MANUFACTURED WITH

FLUSH DOORS AND SOFT CLOSE HINGES

LAVATORY COUNTER

AND BACKSPLASH

½” DUPONT CORIAN SOLID SURFACE IN COLOR

‘AURORA’

PLYWOOD WALLS

¾” APA A-B, SANDED, GROUP 1, EXPOSURE 1

HARDWOOD

PAY ITEM

Item No.

6 Galley & Lavatory Refurbishment LS 1

HIGH PRESSURE

LAMINATE, WF-1 FORMICA ‘ANTIQUE WHITE’, MATTE FINISH

GALLEY LINING 16GA 304 SS #4 FINISH

GALLEY FLOOR PANS

14GA 304SS, ¾” HEIGHT WITH 2”OD X 16”

THROUGH-FLOOR DRAINS, WELDED

CONSTRUCTION

Table 1: Contractor Provided Materials

Specifications of ARRC provided materials:

MATERIAL DESCRIPTION

UNDERCAR EQUIPMENT

DOOR LATCHES

HEAVY DUTY ROTARY PUSH-TO-CLOSE TWO

STAGE LATCH, STRIKER BOLT, FLUSH MOUNT

PADDLE LATCH AND LEVELING BUMPERS

COMPOSITE SUBFLOOR

PANELS & COVE BASE

¾” FIBERGLASS / FOAM, WATERPROOF PANELS

WITH INTEGRATED FINISHED FLOOR

COMPOSITE SUBFLOOR

PANEL INSTALLATION KIT

SHIMS, SPACERS, BACKER ROD & ADHESIVE FOR

BONDING SUBFLOOR TO SUBSTRUCTURE

INDUSTRIAL RUBBER

FLOORING

NORAMENT 962 GRANO, 1mx1mx3.5mm, COLOR 5306 CAMPHOR & HIGH-GRIP YELLOW

INDUSTRIAL RUBBER

FLOORING ADHESIVE NORA PU 310

LLEPM TRACK EXTRUDED ALUMINUM, DRILLED AND CSK 8”OC

LLEPM GLOW STRIP SELF ADHESIVE EXIT PATH MARKING STRIP

STAINLESS STEEL FLOOR

PANS

14GA 304 2B STAINLESS STEEL, WELDED

CONSTRUCTION

GALLEY FLOOR MATS

¾” GREASE RESISTANT DRAINING RUBBER

COMMERCIAL KITCHEN MAT

Table 2: ARRC Provided Materials

Required Submittals

1. Dome window sealant technical data sheet and receipt of material purchase.

2. Lavatory and hallway cabinet and counter top shop drawings.

3. WF-1 HPL technical data sheet.

Payment Schedule Application for progress payments may be submitted for up to 50% of each item as they are accomplished. Total progress payments may not exceed 75% of the total contract until final acceptance of coach has been approved by owner’s representative.

Contract Schedule Cars are available for work as shown in the table below:

CAR NUMBER AVAILABLE

STARTING

SUBSTANTIAL

COMPLETION

FINAL COMPLETION

ARR 551 October 15, 2025 February 27, 2026 March 13, 2026

Exterior Paint & Repairs Milestone inspections The Milestone Inspections listed below must be accomplished with Owner’s representative present and signed off by ARRC representatives prior to starting the subsequent work. Work performed under future Milestones prior to approval of previous Milestone may require rework to allow proper inspection:

1. Initial walkthrough

a. Inspect window glazing condition, interior condition, scope of work & expectations.

2. After sandblast

a. Identify corrosion and metal repairs.

3. After repairs and roof sealing

a. Metal repairs and roof sealing must be approved in bare-metal state prior to application of body filler or primer.

4. After bodywork and primer, before final paint.

5. After paint

a. Prior to Final Assembly to address any paint rework.

6. Final assembly / prior to delivery

Milestone inspections should be planned by the contractor approximately one week in advance of inspection date and include all ARRC stakeholder personnel.

Substantial Completion: Substantial Completion shall be on or before the dates listed above, unless accepted and agreed upon otherwise by the Owner. This completion scope includes all work items contained within the Contract Documents up through Paint Application and Interior Refurbish, properly completed, approved by the Owner and fully serviceable for the intended use.

Final Completion:

Final Completion of all work and return of ARR 551 shall be on or before March 13, 2026.

Liquidated Damages: Should the Delivery Date be missed and if the Owner and the Contractor cannot agree on amenable terms of an extension then liquidated damages may be deducted.

Liquidated damages will be assessed in the sum of $7,500 therein for each calendar day of delay beyond the date of Substantial Completion. Liquidated damages shall not, in any event, exceed twenty percent (20%) of the Contract Price.

End of Section

APPENDIX B

SPECIFICATIONS

SPECIFICATION FOR THE REPAINTING OF

PASSENGER CAR AND LOCOMOTIVE EXTERIORS

Revision No. 4, June 2016

SECTION PAGE

GENERAL 1

Scope 1 Reference Documents 1

MATERIALS 3

Abrasives 3 Coatings and Thinners 4 Colors 5 Caulks, Sealants and Body Fillers 6

EXECUTION 6

Workmanship 6 Surface Preparation 6 Seams, Uneven Surfaces 8 Application 8 Color Scheme 10

QUALITY CONTROL – CONTRATOR 11

UNACCEPTABLE DEFECTS 12

COMPLETION 12

WARRANTEE 12

TABLES 14

Table 1 – Coatings and thinners for the Exterior Surfaces 14 of Rail Cars.

Table 2 – Caulks, Sealants and Body Fillers for the 15 Exterior Surfaces of Rail Cars Table 3 – Surface Preparation and Maintenance Painting 16 Guidance for the Exterior Surfaces of Rail Cars.

Table 4 – Surface Preparation and Maintenance Painting 17 Guidance for the Exterior HVAC Wells and Roofs

1.0 GENERAL

1.1 Scope: This specification covers the surface preparation and coating application requirements for performing maintenance painting on the exterior of railroad passenger cars and locomotives for Alaska Railroad Corporation (ARRC). In this context, exterior refers to the sides, roof, ends, vestibule interior(s) and underframe equipment. Substrates include existing intact and adherent coating, high strength low alloy carbon steel, aluminum and durable epoxy body filler. Maintenance painting may include any of the following strategies: spot repairs, spot repairs and over coating, zone repairs and full removal and replacement.

Surface preparation shall include methods for spot repairs, spot repairs and over coating, zone repairs and full removal and replacement of existing coating systems.

Power Washing, LPWC SSPC-SP WJ-4/NACE WJ-4

Solvent Cleaning SSPC-SP 1

Hand and Power Tool Cleaning SSPC-SP 2, SSPC-SP 3, SSPC-SP 15, SSPC, SP 11

Abrasive Blast Cleaning SSPC- SP 7/NACE No. 4, SSPC-SP 6/NACE No. 3, SSPC-SP 16

Aluminum Preparation ASTM D1730

Coating application methods include brush, roller, dauber, conventional spray, HVLP (high volume low pressure) spray, airless spray and plural component airless spray for polyurea application.

1.2 Reference Documents: The following is a listing of the publications referenced in this section of the Technical Specifications. Unless otherwise noted, the latest revision of the standards in effect at the time of bid shall apply. The absence of a reference otherwise identified does not negate the requirements or information therein.

American Society for Testing Materials

ASTM D1730 09 Standard Practices for Preparation of Aluminum and Aluminum-Alloy Surfaces for Painting

ASTM D 3359 Standard Test Methods for Measuring Adhesion by Tape Test

ASTM D 4138 Standard Test Methods for Measurement of Dry Paint Thickness of Protective Coating Systems by Destructive Means

ASTM D 4285 Standard Test Method for Indicating Oil or Water in Compressed Air

ASTM D 4414 Standard Practice for Measurement of Wet Film Thickness by Notch Gages

ASTM D 4417 Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel. Method C

ASTM D 4541 Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers

ASTM D4752 Standard Test Method for Measuring MEK Resistance of Ethyl Silicate (Inorganic) Zinc-Rich Primers by Solvent Rub”

ASTM D 6386 Standard Practice for Preparation of Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting

ASTM D 7091 Standard Practice for Nondestructive Measurement of Dry Film Thickness of Nonmagnetic Coatings Applied to Ferrous Metals and Nonmagnetic, Nonconductive Coatings Applied to Non-Ferrous Metals

SSPC: The Society for Protective Coatings (SSPC)

SSPC-SP 1 Solvent Cleaning

SSPC-SP 2 Hand Tool Cleaning

SSPC-SP 3 Power Tool Cleaning

SSPC-SP 15 Commercial Grade Power Tool Cleaning

SSPC- SP 7/ NACE No. 4 Brush-Off Blast Cleaning

SSPC-SP 6/ NACE No. 3 Commercial Blast Cleaning

SSPC-SP WJ-4/NACE WJ-4 Waterjet Cleaning of Metals WJ-4 – Light Cleaning

SSPC-SP 16 Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non- Ferrous Metals

SSPC-VIS 1 Visual Standard for Abrasive Blast Cleaned Steel

SSPC-VIS 3 Visual Standard for Hand and Power Tool Cleaned Steel

Equipment and Coating Manufacturer Published Instructions Code of Federal Regulations (CFR)

29 CFR 1910, Occupational Safety and Health Regulations for General Industry

29 CFR 1926, Occupational Safety and Health Regulations for the Construction Industry

40 FR 261-268, Resource Conservation and Recovery Act (RCRA)

2.0 MATERIALS: All supplied materials shall be finest quality, suitable for the intended purpose and supplied in original unopened containers. Provide Manufacturer’s Warranties for coating performance including blisters and adhesion to properly prepared surfaces. All finish coating products shall also be supplied with the Manufacturer’s Warranty for gloss and color retention. Provide manufacture technical data sheets and material safety data sheets for all materials supplied and incorporated into the work.

2.1 Abrasives: Supply abrasives meeting the requirements of SSPC-AB 1 (Mineral and Slag Abrasives) and/or SSPC-AB 4 (Recyclable Encapsulated Abrasive Media). In no case shall steel or iron abrasives be used on stainless steel, aluminum or galvanized surfaces.

2.1.1 Mineral abrasives shall be Type 11, Grade 12 Class A3 mineral abrasives per SSPC-AB 1 that will remove existing coating, rust, and scale from substrates to be prepared by abrasive blast cleaning. Abrasives shall be free of oil and meet the water soluble contaminant requirements of Section

4.1.4. When recyclable abrasives are used verify the cleaned recycled abrasive meets the requirements of 4.4 Quality Control Tests for Recycled Work Mix.

2.1.2 Encapsulated abrasive (e.g. Spongjet) shall contain mineral abrasives meeting the requirements of 2.1.1. and produce an anchor profile of 0.5 to

1.5 mils. Recycled and cleaned encapsulated abrasive media shall conform to the requirements of SSPC-AB 4 Sections 6.2.1.2 Test for Classifier Efficiency, 6.2.2 Water-Soluble Contaminants and 6.2.3 Oil Content.

2.2 Coatings and Thinners: Provide paints, coatings, thinners in original unopened containers. Products or product components that have exceeded their shelf life before the date of application shall not be used. Use only thinners recommended by the coating manufacturer. The coating products listed herein are representative of the type and quality required for application. All coatings shall be provided by the same manufacturer4. Table 1 provides alternate systems by PPG Industries and Sherwin-Williams.

2.2.1 Substitutions - Materials specified are those which have been evaluated for the specific service. Products are listed to establish a standard of

1 Natural mineral Abrasives 2 Abrasives that produce surface profiles of 1.5 to 2.5 mils (38 to 64 micrometers [μm]) when tested in accordance with Section 4.1.8.

3 Containing no more than 1.0% free silica 4 Should use of materials from different manufacturers be requested include a letter from at least one of the manufacturers that states it will warranty against all compatibility related failures.

quality. ARRC approved equal(s) for each product may be substituted.

Submit requests for material substitution no later than two weeks5 prior to date of surface preparation. No substitution of materials is allowed without ARRC written approval. All coatings shall be provided by the same manufacturer4. Products of manufacturers other than those specified or approved by ARRC will be accepted when proven to the satisfaction of the County they are equal in composition, durability, usefulness and convenience for the purpose intended. Substitutions will be considered provided the following minimum conditions are met:

The proposed coating or paint system shall have a dry film thickness (DFT) equal to or greater than that of the specified system.

The proposed coating or paint system shall employ an equal or greater number of separate coats.

The proposed coating or paint system shall employ coatings or paints of the same generic type.

All requests for substitution shall carry full descriptive literature and directions for application, along with complete information on generic type, non-volatile content by volume and a list of 10 similar projects, all at least three years old, where the coatings or paints have been applied to a similar exposure.

If the above mentioned data appears to be in order, ARRC may require that the Contractor provide certified laboratory data sheets showing the results of complete spectrographic and durability tests accomplished on the proposed substitute. An independent testing laboratory satisfactory to ARRC shall accomplish tests and all costs incurred in the testing program shall be borne by the Contractor. In any case, ARRC shall be sole and final judge of the acceptability of any proposed substitution. Requests for substitution must be approved in writing.

2.2.2 Primer: Primer coats may include wash primers for aluminum, galvanized and stainless substrates, epoxy primer for steel surfaces or penetrating sealers to serve as tie- coats for application over existing coatings.

Dupont WP™ Chrome-Free Wash/Etching Pre-Treatment Primer

Corlar® 2.1-St™ Satin High Solids Epoxy Mastic

Imron® Industrial Strength Low VOC Polyurethane Primer

DuPont™ Epoxy DTM Primer/Sealer 2510S/2540S/2570S/2580CR under filler

5 material availability may require a different lead time

2.2.3 Intermediate Coat: Intermediate coats may include epoxy, polyurethane or moisture cure polyurethane to provide barrier protection and film build.

Corlar® 2.1-St™ Satin High Solids Epoxy Mastic

2.2.4 Finish Coat: The finish coat shall be a two component polyurethane product with excellent color retention weather resistance. Fluoropolymer coatings based on urethane chemistry may be submitted for review. Provide finish coating products in the colors required for the work. See Section 2.3 and Section 4.0 of this specification.

Imron® 3.5 HG™ +Polyurethane High Gloss Topcoat

Clear Coat- The clear coat shall be two-component polyurethane compatible with the finish coat

Imron® 3.5 HG-C™ High Gloss Clear Polyurethane

2.3 Colors: Provide finish coats to match the following color designations even if the coating supplier is not the manufacturer identified.

Aluminum: Seymour of Sycamore, Inc. #620-1411 Sherwin Williams B59S11

Other Colors:

Exterior Dupont Imron 5000 (numbers for Imron 3.5HG):

Yellow: 54701 Blue: 63203 Black: 24926 Silver: see Aluminum Clear Coat: Imron 3.5HG-C clear

Interior Dulux Color Numbers:

Beige: LFQ4G34P (locomotive cabs and short hoods) Grey: LF25W34P (locomotive engine rooms)

2.4 Caulks, Sealants and Body Fillers: Provide paintable caulks and sealants recommended by the coating manufacturer. Use high solids epoxy body putty suitable for repair of dents, buckles and depressions in the car bodies. Table 2 provides alternate products for use with PPG Industries systems.

Suitable products include:

DuPont™ Premier Filler™ LE 3401S™/LE 3404S™/ LE 3407S™ Urethane Primer Filler

DuPont Premium Lightweight Body Filler 313

3M™ Quick Grip Filler /3M™ Short Strand Fiberglass Reinforced Filler

3.0 EXECUTION

3.1 Workmanship: The performance of all work will be in accordance with industry standards, best practices and applicable state local and federal safety and environmental rules and regulations. Public image is very important to ARRC and the major purpose in undertaking this work is to promote that image including appearance and stewardship.

3.2 Surface Preparation

NOTE: The contractor is hereby advised that many passenger cars still in service were built long before lead-based paints went out of favor and it is most likely that such paint will be found on them.

3.2.1 Surfaces shall be prepared in accordance with paint manufacturer’s requirements and recommendations to the extent that they exceed this specification. The contractor shall bring to the attention of ARRC’s project manager for resolution any conflict between these specifications and the manufacturer’s published data. Tables 3 and 4 provides summary directions for surface preparation based on the substrate and maintenance painting requirements. Do not conduct final surface preparation unless the substrate temperature is a minimum of 5oF above the dew point. Provide clean dry compressed air for all operations where air may be used for surface preparation, surface blow-down, and coating application.

3.2.2 Cleaning- Prior to beginning surface preparation power wash and solvent clean (SSPC-SP 1) all surfaces to be prepared and coated. Use cleaning aids acceptable to the Engineer as necessary to remove soot, soils, sap, and surface dirt. Do not conduct surface preparation unless the substrate temperature is a minimum of 5oF above the dew point.

3.2.3 Spot Repairs- All areas of rust, corrosion, defective paint, cracked, lifting, deformed or otherwise defective caulks, sealers and fillers and oxidation shall be removed Exposed bare metal shall be solvent cleaned and prepared by abrasive blast cleaning (SSPC-SP 6) or may be prepared using power tool cleaning (SSPC-SP 11 or SSPC-SP 15). Produce an anchor profile of 1.5 to 2.0 mils as measured in accordance with ASTM D4417 Method C. Any defects on passenger cars requiring more than 1/8" of filler shall be brought to the attention of ARRC and work held pending a decision as to best method for repair.

Prepare existing adherent existing coating that will remain around the spot repair by sanding using hand or power tools (SSPC-SP 2 or SSPC-SP 3).

Feather the edges of the coating around all spot repairs a minimum of 2 inches onto the existing coating and provide a smooth transition for the coating to be applied. Note that removed caulks, sealants and fillers will be replaced in kind. 3.2.3.

3.2.4 Spot Repairs and Overcoating- Perform spot repairs as required in Section

3.2.2. Adherent paint that will remain and be overcoated shall be etched or sanded in accordance with SSPC-SP 3 or SSPC-SP 7 for Steel and SSPC- SP 3 or SSPC-SP 16 for Aluminum and/or Stainless Steel.

3.2.5 Removal and Replacement- Complete or zone removal6 of the existing coatings shall be performed by abrasive blast cleaning in accordance with SSPC-SP 6. Provide an anchor profile of 1.5 to 2.0 mils as measured in accordance with ASTM D4417 Method C. Conduct the cleaning with care when moving from steel to aluminum or stainless steel surfaces to avoid excess damage and unacceptable anchor profiles.

3.2.6 Use of Abrasives- Whenever abrasive blasting is performed; protect all surfaces not to be painted from damage and contamination by abrasives.

This shall include air intakes, vents, bright metal, glass, gaskets, machined surfaces and mechanical and electrical equipment. All dust, abrasives and other interference materials shall be removed before priming.

3.2.7 Cleanliness-Verify the degree of cleanliness meets the applicable surface preparation criteria. Use SSPC-Vis 1 as an aid in evaluating surfaces prepared by abrasive blast cleaning. Use SSPC-Vis 3 as an aid in evaluating surfaces prepared by hand and power tool cleaning.

3.3 Seams and Uneven Surfaces

All seams and uneven surfaces, dents (depressions) in surface shall be roughened, feathered out primed and filled with compatible body filler suitable for temperature extremes of -60 to +100 F. Some patch work may need to be continuous from seam to seam, to prevent an undesirable finish variation. Old lettering (unless it is to be reapplied) shall be sanded out or filled so as to be illegible after application of the primer coat.

3.3.1 In preparation for painting, girder sheets shall be repaired and any loose side sheeting re-secured using fastening techniques standard to the car’s original construction.

3.3.2 Holes, large dents, tears and corroded areas shall be patched (by welding with applicable type of stainless steel, aluminum or steel rod). Small dents (up to 1/8" deep) shall be filled using an epoxy or polyurethane body filler.

Patch all damaged areas. Priming of mild carbon steel and non-ferrous metals shall be done before occurrence of any corrosion (detectable by eye or touch). Total film thickness of primer shall be 5 to 6 mils (wet) applied in one coat.

6 Zone removal refers to large surface areas that require removal and replacement but not to the extent that the entire car requires maintenance painting. For example, the work may be limited to trucks or roofs.

3.4 Application

3.4.1 All materials shall be applied and allowed to cure in strict accordance with manufacturer’s requirements and recommendations. All applications and curing shall be done in a warm, dry and dust free atmosphere.

Ambient Conditions - Apply coatings under the following conditions unless the requirements of the coating manufacturer are more restrictive. .

Surface and Air Temperatures - Between 50ºF and 110ºF.

Relative Humidity - Less than 85%.

Dew Point - Surface temperature at least 5ºF above the dew point temperature of the surrounding air.

Frost/Rain - Do not apply coatings to surfaces containing frost or during rain, fog, or similar conditions.

Remove and replace any paint that is exposed to unacceptable conditions (e.g. rain or dew) prior to adequate curing.

It is the responsibility of the contractor to assure that the old finish is compatible with the new materials for spot repairs and overcoating. Any rework necessary due to reaction between the two materials shall be performed at no charge to ARRC.

3.4.2 Pre-treat prepared bare aluminum surfaces with Dupont WP™ Chrome-

Free Wash/Etching Pre-Treatment Primer Primer Urethane DFT 3-5 Primer Epoxy Mastic DFT 5-8

3.4.3 Primer shall be applied immediately after completion of surface preparation. In the case of bare metal, it shall be completed before the formation of any oxides.

3.4.4 Total film thickness of primer shall be 5 to 6 mils.

3.4.5 Finish coat and lettering

3.4.6 Finish coats shall be applied well within the time limits after immediately prior coat as specified by the paint manufacturer.

3.4.7 Application shall consist of two coats totaling 1.5 to 2 mils DFT.

3.4.8 Lettering shall be applied as shown on the detailed diagram.

3.4.9 Required lettering and logos will be painted on and cleared over.

3.4.10 Edges of all logos and any other decals or Scotch-Lite shall be sealed with a coat of clear lacquer prior to final (clear) coat.

3.4.11 Final Coat: After all painting and lettering is complete the entire car body shall be given one coat of Dupont Imron 3.5 HG-C™ clear-coat within the recoat window of the pigmented finish coats. The finished product shall present a high gloss “wet” appearance.

4.0 Color Scheme

Paint scheme shall be as described on the specific painting diagram for the particular piece of equipment involved. The basic color scheme is described here for information only:

4.1 Aluminum, HSLA steel and flat panel Budd built (“smooth side”) passenger cars:

Car body:

Blue with two yellow strips (on…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .