25-0425 1101 FORKLIFT RAMP - SUBMITTAL REGISTER.pdf
PDF 62 KB Posted
- Attached to
- 1101 Forklift Ramp
- Solicitation number
- N4008525R9014
About this file
This is a Submittal Register for a Naval Facilities Engineering Command contract (Solicitation Number N4008525R9014) for a 1101 Forklift Ramp project. The document outlines multiple required preconstruction, test, product data, certificates, and closeout submittals that the contractor must provide during the project lifecycle. Key submittal categories include construction schedules, equipment delivery schedules, accident prevention plans, quality control plans, environmental protection plans, activity hazard analyses, crane-related documentation, traffic control plans, and various certifications such as backflow preventer certificates and third-party crane certifications. The register is structured to track each submittal's paragraph reference, description, contractor action dates, approval needed dates, and material needed dates, providing a comprehensive tracking mechanism for project documentation and compliance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NO.
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5
1.11
Regulatory Citations and Violations
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
(Enter Contract No. Here)
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
SUBMITTAL REGISTER
P A R A G R A P H
N O
S P E C
S E C T
(d)
Contractor Action
DESCRIPTION
ITEM SUBMITTED
(Enter Contractor Name Here)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
SD-01 PRECONSTRUCTION SUBMITTALS
Submittal Register
Complete Submittal Package
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
Approving AuthorityContractor Schedule Dates
SD-11 CLOSEOUT SUBMITTALS
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Crane Reports
SD-07 CERTIFICATES
Confined Space Entry Permit
1.14.6
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
DRAWINGS
G
G
G
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
Backflow Preventers Certificate (If Applicable)
SD-06 TEST REPORTS
SD-07 CERTIFICATES
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicab
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
Backflow Tester Certification (If Applicable)
Backflow Preventer Tests (If Applicable)
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
Qaulity Control Plan (QC Plan)
Certificate of Compliance
Concrete Mix Written Report; Batch Ticket
SD-11 CLOSEOUT SUBMITTALS
Third Party Certification of Barge-
Mounted Movile Cranes