The acquisition involves primarily production to established government designs for integrated C5ISR systems, networks, and support equipment, with approved alternate part numbers permitted for supply chain or end-of-life issues. This is a new requirement, not a direct follow-on to the previous contract N6523618D8014 with Science Applications International Corporation (SAIC). Key differences include production requirements at numerous OCONUS locations and in classified environments across multiple locations, neither of which were part of the previous contract. The work requires a 300,000 square foot top-secret facility within a 50-mile radius of NIWC Atlantic in Charleston, SC; however, multiple facilities are acceptable. Production efforts will be executed under an HTR-FRP (Highest Technical Rating – Fixed Price Proposal) approach with no tradeoff between non-cost factors and price. The acquisition requires CMMC Level 2 self-assessment prior to contract award, with requirements flowing down to subcontractors. Evaluation factors include Corporate Experience (Factor A) as a gate criterion requiring demonstrated C5ISR production experience; Technical Approach (Factor B) with a 90-page limit; Small Business Participation (Factor C); and Price. The RFP response period will be 30 days. Subcontracting plans are required for large business offerors, with applicable socioeconomic categories to be identified in the final RFP. The NAICS code is 335999. No subcontractor geographical restrictions apply. Equipment Qualification Testing (EQT) may be conducted on-site at NIWC Atlantic facilities or outsourced to external test facilities. Proposed COTS alternatives to Technical Data Package (TDP)-specified equipment are not acceptable; offerors must propose in accordance with provided sample TDPs and Bills of Materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-SOLICITATION Q&A – N6523626RE073

C5ISR Acquisition, Engineering, and Integration (CAEI) Production

Q1. Is the anticipated work primarily production to established government designs, or will it also allow proposed improvements to compute hardware, cooling, and system configurations?

A1. Primarily production to established government designs. Some designs may require approved alternate part numbers due to supply chain issues, lead time or end of life.

Q2. Are space, power, cooling, or processing capacity constraints among the challenges this acquisition is intended to address, particularly for land-based and field-based systems?

A2. Most of these challenges won’t be part of this acquisition.

Q3. Could a specialist subcontractor perform a defined, unclassified compute or infrastructure work package, and what facility or security requirements would govern that role?

A3. Facility and security requirements would flow down to subcontractors from the prime contractor.

Q4. We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?

A4. This is a new requirement and is not a direct follow-on to any particular contract or task order. Currently, the production and delivery of integrated C5ISR systems, networks, and support equipment is executed under existing single award contract N6523618D8014 with Science Applications International Corporation (SAIC). The work contemplated under the proposed contract has changed significantly from the previous requirements. Amongst other diƯerences, production eƯorts under this contemplated contract are anticipated to be required at numerous OCONUS locations, which was not a part of the previous contract. Additionally, production eƯorts are anticipated to be required in classified environments across multiple locations, which is also not the case under the previous contract.

Q5. The work seems similar in scope to an SAIC NIWC contract. Can the Government please confirm whether SAIC is the incumbent or if there are other incumbents?

A5. See answer to Q4.

Q6. The facility requirements (300,000 sq ft (top secret) within a 50-mile radius of NIWC Atlantic Charleston) are restrictive with very limited vendors with the facilities to support the requirement. To align with the Navy’s objective to expand the maritime industrial base, would the Government consider making the requirement within 50 miles of major Naval facilities (San Diego, Norfolk)?

A6. No. Production requirements are the responsibility of the CAEI IPT, which is located at NIWC Atlantic in Charleston, SC area.

Q7. The Draft SOW identifies Controlled Unclassified Information (CUI) as applicable to the contract and establishes requirements for safeguarding and processing such information.

However, the draft solicitation does not expressly identify a Cybersecurity Maturity Model Certification (CMMC) level or the required compliance timeline. Please clarify whether CMMC Level 2 will be required for the basic contract or individual delivery/task orders, whether a CMMC assessment or status will be required at proposal submission, contract award, or prior to applicable performance, and whether these requirements will extend to subcontractors handling CUI.

A7. Yes. It is anticipated a CMMC Level 2 self-assessment will be required prior to contract award. The final RFP will include the applicable PWS paragraphs and clauses/provisions. The CMMC required flows down to subcontractors.

Q8. The corporate experience gate criteria appear to emphasize the prime contractor’s ability to manage large-scale contracts while also requiring demonstrated C5ISR production experience.

Would the Government consider allowing oƯerors to demonstrate these capabilities through a combination of comparable-value, non-C5ISR Government contracts that establish large-scale contract management experience and smaller-value C5ISR contracts that demonstrate relevant technical expertise in production, integration, and delivery?

This approach would allow the Government to evaluate both management capability and technical experience while potentially expanding competition among qualified oƯerors.

A8. No, the Government does not intend to expand the experience requirement to non- C5ISR contracts.

Q9. Please confirm whether the completed CAEI Project Management Plan template (Attachment 6), facility narrative, supplemental plan/process information, operations management plan, Integrated Master Schedule, and Work Breakdown Structure must all be contained within the single 90-page “TechApp” PDF submission. Please also identify which of these materials, if any, are excluded from the 90-page limit.

A9. In the posted DRAFT solicitation the overall page limit for Factor B is 90 pages. The resource plan (Attachment X) will not be included in the page count. Even so, the final page limitations and calculation of those page limitations are under consideration will be clear in the final RFP.

Q10. The Draft RFP requires oƯerors to address two sample tasks using a single Project Management Plan (PMP) template within the 90-page Factor B submission limit. Given the level of detail required by the PMP template and the separate Operations Management Plan (OMP) requirements, would the Government consider increasing the Factor B page limit, or alternatively excluding the completed PMP template from the 90-page limitation, to allow oƯerors suƯicient space to provide complete and meaningful responses to both sample tasks and the OMP requirements?

A10. See answer to Q9. While final page limitations are under consideration, it is NOT expected the page limitation for Factor B will exceed 90 pages in the final RFP.

Q11. Source Selection Methodology. Section M(a) provides for award to the technically superior proposal and includes a lowest-price tiebreaker, while Section M(c) states there will be no tradeoƯ between non-cost factors and price. Please confirm whether this is an HTR-FRP acquisition under FAR 15.103-3 (as implemented in the RFO) or a tradeoƯ acquisition and reconcile the lowest-price tiebreaker in M(a) with the no-tradeoƯ statement in M(c).

A11. Yes, this is an HTR-FRP approach as defined in FAR 15.103-3. There will be no tradeoƯ between the non-cost factors and price. The scenario of a lowest-price tie breaker is only in the event (albeit unlikely) that there are two oƯers both deemed to be the highest technically rated.

Q12. Draft RFP Section L - Factor A: COPROATE EXPERIENCE (GATE CRITERIA) Can the Government provide an explanation and the purpose for including this Gate?

A12. The Government considers current and relevant corporate experience to be critical for the successful execution of the required tasking. The successful oƯeror must be able to demonstrate experience with current and relevant contracts as defined by Section L of the solicitation.

Q13. Will the presolicitation conference slides be shared?

A13. Yes. The slides will be posted to PIEE Solicitation Module

Q14. Is EQT conducted on-site, outsourced or both? Can you expand?

A14. Both. We have the ability to leverage NIWC Atlantic facilities as well as external test facilities for EQT.

Q15. Does the 300,000 square feet of production floor space need to be in one facility, or can it be across several facilities?

A15. Multiple facilities are acceptable. The final RFP and PWS may be updated to further clarify any additional requirements in order to ensure an adequate approach.

Q16. Is there a subcontracting (SB, HubZone, etc.) requirement under the contract?

A16. A subcontracting plan is intended to be required for large business oƯerors and will be specified in Section L of the solicitation. These plans will be reviewed for acceptability and must be approved prior to contract award. Each oƯeror (both large and small) shall also address the Small Business Participation requirements (Factor C). Both of these will have applicable socioeconomic categories identified in the final

RFP.

Q17. Can you tell us who the incumbent contractor is currently.

A17. See answer to Q4.

Q18. Under subfactor B1's innovation section, can oƯerors propose COTS alternatives to TDP-specified equipment if they're lower cost or easier to sustain?

A18. Generally, no. If an item is specified in a TDP, proposed COTS alternatives are not acceptable. For the purposes of this RFP, it is expected offerors will be required to propose in accordance with the provided sample TDP and Bill of Materials. Under Subfactor B1 we’d be looking for innovation related to how an offeror would execute the required tasking.

Q19. Will the posted attendee list include business size and capability areas?

A19. Attendee list will be posted to PIEE Sol Module; however, business size and capability areas will not be included.

Q20. Are there subcontractor geographical requirements/limitations?

A20. No subcontractor Geographical requirements/limitations.

Q21. What is the NAICS code?

A21. 335999

Q22. How long do you intend to allow bidders to respond to the solicitation?

A22. The Government intends for the RFP response time to be 30 days.

Q23. Draft Section L, Factor A states: “CAUTION: Although a total contract amount may meet the relevancy requirement of $75 million stated above for line 6, if the invoiced amount does not meet or exceed $75 million, no credit will be given for that contract.”

This restriction makes no delineation between labor and material invoices – in execution this could be a combination of $70M of material procurements and $5M of labor invoiced.

Will the Government revise their relevancy threshold to accommodate a similar level of eƯort performed versus invoiced value? Based on the Draft PWS, a similarly scoped contract reference that requires 125 Full-time Equivalents (FTE) versus an arbitrary invoiced dollar value is a more realistic measure of relevance. Will NIWC Atlantic revise Section L’s relevancy measure to more closely align with the work solicited?

A23. The Government doesn’t intend to revise the relevancy thresholds or measures at this time. Note in the draft solicitation that was posted, in order to meet the relevancy definition, the minimum invoiced amount must be “for eƯorts that required the production and delivery of integrated C5ISR systems, networks, and support equipment for programs and platforms similar to those stated in the RFP”.

Q24. Draft Section L, Factor A states: “Contract reference information for any company, division, subsidiary, etc., that is not the prime contractor will not be considered. The prime contractor is considered to be the organization that signs and submits the proposal. The Government must be ensured that the prime contractor will be the organization performing the work. CAUTION: It is important to this evaluation that the contract reference(s) submitted represent the technical capability/experience of the same companies that are proposed to perform this eƯort. Therefore, the Government will be comparing the company name(s) and CAGE code(s) cited on the submitted contract reference(s) against the company name(s) and CAGE code(s) cited within the proposal. In cases where there is any variance between the actual company name(s) or CAGE code(s) cited on the submitted contract reference(s) and the company name(s) or CAGE code(s) identified within the proposal, the prime contractor shall provide rationale that clearly identifies the correlation and/or association of the company(s) and explain how the resources associated with the cited contract reference(s) are proposed for this eƯort.”

EƯective November 15, 2024, DOD updated DFARS Sub Topic 215.305 Proposal Evaluation, Section (a)(2) Past Performance Evaluation to include the following guidance regarding aƯiliate past performance:“(C) When evaluating the past performance of an oƯeror that is a small business concern in response to a competitive solicitation, contracting oƯicers shall consider relevant past performance information provided for aƯiliates of the oƯeror.”

Question: Will NIWC Atlantic revise Section L to permit Factor A evaluation of aƯiliate contracts for small business concerns in accordance with DFARS 215.305(a)(2)(C)?

A24: The Government is not evaluating Past Performance under Factor A, but rather an oƯeror’s current and relevant Corporate Experience. While the Government is considering changes to all aspects of the draft RFP, it is not anticipated the requested change will be made to Factor A.