24Q0033_ATTCH8draftQASP_062124.docx
DOCX document 47 KB Posted
- Solicitation number
- HE125424Q0033
- Issued by
-
Department of Defense Education Activity
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for a federal contract opportunity related to K-8 Social-Emotional Learning (SEL) Instructional Resources and Screener.
The QASP outlines the performance standards, acceptable quality levels, inspection methods, and documentation requirements for evaluating the Contractor's performance on this contract. Key objectives include providing MTSS-aligned, vendor-hosted, web-based supplemental SEL resources and screening instruments that are customizable, intuitive, and engaging for K-8 students. The Government personnel responsible for overseeing and coordinating surveillance are identified, as well as the Contractor's program manager. The QASP details the performance standards, acceptable quality levels, and methods for monitoring and documenting Contractor performance, including direct observation, periodic inspection, and validated user/customer complaints. It specifies the rating scale, performance assessment meeting frequency, and contents of the Contracting Officer's Representative's quality surveillance file.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24Q0033_QA_072224.pdf | ||
| 24Q0033_SOL_Amend_072324.pdf | ||
| 24Q0033_SOL_Amend_072324.pdf | ||
| 24Q0033_ATTCH1PricingWrksht_072224.xlsx | XLSX spreadsheet | |
| SEL-PWS-22July24.pdf | ||
| 24Q0033_QA_072224.pdf | ||
| 24Q0033_ATTCH7PPQuestionnaire_062124.docx | DOCX document | |
| 24Q0033_ATTCH2TOS_062124.docx | DOCX document | |
| 24Q0033_ATTCH4CloudQ062124.pdf | ||
| 24Q0033_SOL_070124.pdf | ||
| 24Q0033_ATTCH1PricingWrksht_062124.xlsx | XLSX spreadsheet | |
| 24Q0033_PWS_062124.pdf | ||
| 24Q0033_ATTCH62930a_062124.pdf | ||
| 24Q0033_ATTCH5PrivChklist_040224.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan
K-8 Social-Emotional Learning (SEL) Instructional Resources and Screener
1. Purpose This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract by explaining (1) what is monitored, (2) how monitoring occurs, (3) who monitors, and (4) how monitoring efforts and results are documented.
2. Background DoDEA has never awarded a systemic contract for this requirement.
3. Objectives DoDEA requires an MTSS-aligned, vendor-hosted, web-based supplemental resource and presentation materials that support SEL for K-8 students in Tiers 1-3. The interactive supplemental resources and screener shall be customizable and intuitive and include lesson plans and activities that are engaging and age- and developmentally appropriate for all users including students with differing abilities, students with disabilities (to include students with significant disabilities), and multi-lingual learners. They shall be supported by virtual professional learning, open-source resource materials, open-source readings for deeper learning, and digital presentation materials for district support teams, parents/sponsors, and the community.
This QASP does not detail how the Contractor accomplishes the work but is based on the premise that the Contractor is responsible for management and quality control actions to meet the terms of the contract. The Government is responsibility to be objective, fair, and consistent in evaluating performance. The QASP takes into account that unforeseen and uncontrollable situations may occur. It is a living document, which the Government may review and revise on a regular basis to ensure it remains valid, useful, and enforceable. The Government will coordinate any changes with the Contractor. DoDEA will provide copies of the original QASP and revisions to the Contractor and Government officials implementing the surveillance activities.
4. Government Personnel Responsible to Oversee and Coordinate Surveillance Contracting Officer (KO) - Ensures performance of all necessary actions for effective contracting, compliance with the contract terms, and safeguarding the interests of the Government in the contractual relationship. Ensures the Contractor receives impartial, fair, and equitable treatment under this contract. Is responsible for the final determination of Contractor performance.
Assigned KO: Alim Koroma DoDEA HQ - 571-372-1473 - alim.koroma@dodea.edu
Contracting Officer’s Representative (COR) - Is responsible for technical administration of the contract, ensures proper Government surveillance of Contractor performance. Keeps a quality assurance file. Provides all corresponding documentation to the KO when the contract expires. Is not empowered to make any contractual commitments or authorize any contractual changes on the Government’s behalf. The Contractor shall refer any changes that may affect contract price, terms, or conditions to the KO for action.
Assigned COR: Michael Thompson, Student Services Branch Program Manager DoDEA-HQ – 571-372-0577 – michael.thompson@dodea.edu
5. Contractor Representatives The following Contractor employee serves as the Contractor’s Program Manager/Task Manager for this contract:
Program Manager: TBD Organization: xxx-xxx-xxxx – email address
6. Performance Standards Performance standards define desired services. The Government performs surveillance to determine if the Contractor exceeds, meets or does not meet contract standards. The Performance Requirements Summary Matrix below includes the performance standards. The Government will determine Contractor performance by comparing them to the Acceptable Quality Level (AQL).
| Performance Objective |
| Performance Standard |
| Acceptable Quality Level (AQL) |
| Inspection Method |
| Task 1, SEL Instructional Resources, PWS 2.1 |
| 100% compliance with PWS |
| Resources are available except during scheduled downtimes |
| COR inspection and stakeholder feedback |
| Task 2, SEL Screener, PWS 2.2 |
| 100% compliance with PWS |
| Screening instruments are available except during scheduled downtimes |
| COR inspection and stakeholder feedback |
| Task 3, SEL Dashboard, PWS 2.3 |
| 100% compliance with PWS |
| Dashboard is available except during scheduled downtimes |
| COR inspection and stakeholder feedback |
| Task 4, Virtual Professional Learning, PWS 2.4 |
| 100% compliance with PWS |
| No more than one session shall need to be rescheduled each semester due to Contractor “issues” |
| COR inspection and stakeholder feedback |
| Public Relations Support, PWS 2.5 |
| 100% compliance with PWS |
| PR materials & communications support provided as scheduled post-award |
| COR inspection and stakeholder feedback |
| Delivery of Digital Resources, PWS 2.6.3 |
| 100% compliance with PWS |
| Access codes shall be provided no more than one business day late. |
| COR inspection and stakeholder feedback |
Technical Support
PWS 2.6.4
| 100% compliance with PWS |
| Acknowledge receipt of request within two hours. Resolve 90% of requests in one business day. Resolve remaining 10% in five business days. |
| COR inspection and stakeholder feedback |
Privacy Training
PWS 3.7.3
| 100% compliance with PWS |
| No more than one request per year submitted late. |
| COR inspection |
Privacy Verification
PWS 3.7.4
| 100% compliance with PWS |
| Submitted 120 calendar days prior to the end of each contract year |
| COR inspection |
7. Incentives Exercise option and positive performance evaluation
8. Methods of QA Surveillance Various methods exist to monitor performance. The COR will use the surveillance methods listed below. Regardless of the surveillance method, the COR will always contact the Contractor's task manager or on-site representative when a defect is identified and inform him/her of the specifics. The COR is responsible to monitor Contractor performance in meeting a specific performance standard/AQL usually by one of the following methods:
· Direct Observation: Performed periodically or through 100% surveillance as needed.
· Periodic Inspection: Done as required.
· Validated User/Customer Complaints: Based on complaints from stakeholders.
· 100% Inspection
Surveillance results may be used as the basis for actions (including payment deductions) against the Contractor. In such cases, the contract’s Inspection of Services clause becomes the basis for the KO’s actions.
9. Ratings Metrics and methods are designed to determine if performance exceeds, meets, or does not meet a given standard and acceptable quality level. Unless otherwise specified, the following rating scale will be used:
· Exceptional: Performance significantly exceeds requirements to the Government’s benefit.
· Satisfactory: Performance meets contractual requirements.
· Unsatisfactory: Performance does not meet contractual requirements.
10. Documenting Performance
· Acceptable Performance: DoDEA will document acceptable performance. Any report may become a part of the supporting documentation history. A report template is attached.
· Unacceptable Performance: When unacceptable performance occurs, the COR will inform the Contractor. Notification will normally be in writing unless circumstances necessitate verbal communication. In any case, the COR will document the discussion and place it in the COR file. When the COR determines formal written communication is required, s/he will prepare a Contract Discrepancy Report (CDR) and present it to the Contractor's task manager or on-site representative. A CDR template is attached.
The Contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the Contractor is required to prepare a corrective action plan, i.e., the Contractor’s plan to correct the unacceptable performance and avoid a recurrence. The CDR will also state how long the Contractor has to present this corrective action plan to the COR. The Government will review the Contractor's corrective action plan to determine acceptability. A CDR may become a part of the supporting documentation for contract payment deductions or other actions deemed to be necessary by the KO.
11. Measurement
· Frequency of Measurement: During contract/order performance, the COR will take periodic measurements, as specified in the AQL column of the Performance Requirements Summary Matrix and analyze whether the negotiated frequency of measurement is appropriate for the work being performed.
· Frequency of Performance Assessment Meetings: The COR will meet with the Contractor at a minimum of once per year to assess performance and obtain a written assessment.
12. COR’s Quality Surveillance File The COR’s quality surveillance file shall contain the following documentation:
1) COR appointment letter, any changes to that letter, and any termination letters
2) COR training certificates
3) Contract and all contract modifications
4) Applicable quality assurance surveillance plan (QASP)
5) Names, titles, and contact information of key Government and Contractor personnel assigned to this contract
6) Surveillance schedules / checklists, if applicable
7) All correspondence (1) by authorized Contractor and Government personnel regarding performance of the contract and (2) customer feedback
8) Memoranda for record of minutes of any meeting, telephone conversations and discussions with the Contractor or others pertaining to the contract or contract performance
9) Documentation pertaining to acceptance of services, reports or data
10) Contractor’s quality control plan (QCP), if applicable
Digital Signature Michael Thompson, Student Services Branch Program Manager
Performance Report < This template will be used to formally document surveillance. >
1. Contract number:
2. Prepared by:
3. Date and time of observation:
4. Observation:
<Examples of items to include in a report are:
· Method of surveillance.
· How frequently you conducted surveillance.
· Surveillance results.
· Number of observations.
Prepared by:
Digital Signature Michael Thompson, Contracting Officer’s Representative
Contract Discrepancy Report (CDR) < This template will be used to formally document discrepancies. >
1. Contract Number:
2. To: (Contractor Task Manager or on-site representative)
3. From: TBD
4. Date and time observed discrepancy:
5. Discrepancy or problem:
<Describe in detail. Identify any attachments.>
6. Corrective action plan:
A written corrective action plan < is / is not > required.
< If a written corrective action plan is required include the following. > The written Corrective Action Plan will be provided to the undersigned not later than < # days after receipt of this CDR. >
Prepared by:
Michael Thompson, Contracting Officer’s Representative
Received by:
Contractor Task Manager or On-Site Representative
The COR may initiate a CDR at any time, including when (1) the number of monthly recorded defects for a performance standard exceeds the allowable number of defects, (2) unacceptable performance is determined critical in nature and requires formal corrective action, and (3) an unfavorable trend in Contractor performance is detected.
21 Sep 24 5