SOW 3-6-23.pdf
PDF 197 KB Posted
- Attached to
- Water Main Extension and Water Service Line Federal contract opportunity
- Solicitation number
- 246-23-Q-0051
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Sheet REV 3-6-23.pdf | ||
| Questions and Answers.docx | DOCX document | |
| Bid Sheet REV 3-6-23.pdf | ||
| SF18 RFQ.pdf | ||
| SF18 RFQ.pdf | ||
| Bid Sheet.xlsx | XLSX spreadsheet | |
| Drawing.pdf | ||
| Spec. Reference ODEQ Chapter 626.19.pdf | ||
| Specs 091222.pdf | ||
| 4208 Bush SOW REV 2 jge.pdf | ||
| ok31.txt | TXT text file |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PAWNEE OFFICE OF ENVIRONMENTAL HEALTH & ENGINEERING
PAYNE COUNTY RURAL WATER DISTRICT #4
WATER MAIN EXTENSION
SERVICE REQUEST #4208
IHS PROJECT OK 18-V09
SCOPE OF WORK
Location: 2515 S Greenwood Rd, Yale, OK 74085, Contractor shall furnish and install approximately 938 linear feet 2” water main extension of the Payne County Rural Water District
#4 (District) water system. This project is to install 938 linear feet of 2” water main, 515 linear feet of 1” water service line, new meter vault and meter, and all appurtenances.
The contractor shall perform all work described in the contract documents for the unit prices or lump sums stated in the completed bid schedule to be submitted for this project. Any item required for completion of the project that is not listed in the Bid Schedule shall be included by the Bidder in any of the bid items currently listed on the Bid Schedule. Tasks to be completed by the selected contractor include:
Install 938 LF of 2” SDR 11 HDPE along S Greenwood Rd Install 515 LF of 1” SDR 11 HDPE from S Greenwood Rd to Home Install 1453 LF of tracer wire Connect the new water main to the existing system in one (1) location Install two (2) 2-inch gate valves and boxes Open Cut 182 LF of gravel driveway and restore to previous condition Install 3” HDPE casing at road and driveway crossing locations where 2” HDPE is installed Bore under County Road 6 feet below the lowest point of the County ROW.
Install 2” HDPE casing at driveway crossing locations where 1” HDPE is installed Install end of line tee and flush hydrant Install one (1) 2” meter vault Connect new water service line to home
All work shall be done in accordance with Oklahoma Department of Environmental Quality
(ODEQ) rules and regulations found in, but not limited to, OAC 252:626 - Public Water Supply
Construction Standards. All work must also conform to the contract plans & specifications.
CONTACTS
Utility Owner:
Payne County RWD #4
108 N. Main
Yale, OK 74085
P: 918-387-2035
Engineering:
Indian Health Service
1201 Heritage Cir
Pawnee, OK 74058
Patty S. Thompson
P: 918-762-6588
Email: patty.thompson@ihs.gov
Caylen Willingham
P: 918-762-6582
Email: caylen.willingham@ihs.gov