SOW 3-6-23.pdf

PDF 197 KB Posted

Attached to
Water Main Extension and Water Service Line Federal contract opportunity
Solicitation number
246-23-Q-0051
Issued by
Department of Health and Human Services Indian Health Service

View the file

Other files for this federal contract opportunity

Other files attached to Water Main Extension and Water Service Line, newest first.
File Type Posted
Bid Sheet REV 3-6-23.pdf PDF
Questions and Answers.docx DOCX document
Bid Sheet REV 3-6-23.pdf PDF
SF18 RFQ.pdf PDF
SF18 RFQ.pdf PDF
Bid Sheet.xlsx XLSX spreadsheet
Drawing.pdf PDF
Spec. Reference ODEQ Chapter 626.19.pdf PDF
Specs 091222.pdf PDF
4208 Bush SOW REV 2 jge.pdf PDF
ok31.txt TXT text file
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PAWNEE OFFICE OF ENVIRONMENTAL HEALTH & ENGINEERING

PAYNE COUNTY RURAL WATER DISTRICT #4

WATER MAIN EXTENSION

SERVICE REQUEST #4208

IHS PROJECT OK 18-V09

SCOPE OF WORK

Location: 2515 S Greenwood Rd, Yale, OK 74085, Contractor shall furnish and install approximately 938 linear feet 2” water main extension of the Payne County Rural Water District

#4 (District) water system. This project is to install 938 linear feet of 2” water main, 515 linear feet of 1” water service line, new meter vault and meter, and all appurtenances.

The contractor shall perform all work described in the contract documents for the unit prices or lump sums stated in the completed bid schedule to be submitted for this project. Any item required for completion of the project that is not listed in the Bid Schedule shall be included by the Bidder in any of the bid items currently listed on the Bid Schedule. Tasks to be completed by the selected contractor include:

Install 938 LF of 2” SDR 11 HDPE along S Greenwood Rd Install 515 LF of 1” SDR 11 HDPE from S Greenwood Rd to Home Install 1453 LF of tracer wire Connect the new water main to the existing system in one (1) location Install two (2) 2-inch gate valves and boxes Open Cut 182 LF of gravel driveway and restore to previous condition Install 3” HDPE casing at road and driveway crossing locations where 2” HDPE is installed Bore under County Road 6 feet below the lowest point of the County ROW.

Install 2” HDPE casing at driveway crossing locations where 1” HDPE is installed Install end of line tee and flush hydrant Install one (1) 2” meter vault Connect new water service line to home

All work shall be done in accordance with Oklahoma Department of Environmental Quality

(ODEQ) rules and regulations found in, but not limited to, OAC 252:626 - Public Water Supply

Construction Standards. All work must also conform to the contract plans & specifications.

CONTACTS

Utility Owner:

Payne County RWD #4

108 N. Main

Yale, OK 74085

P: 918-387-2035

Engineering:

Indian Health Service

1201 Heritage Cir

Pawnee, OK 74058

Patty S. Thompson

P: 918-762-6588

Email: patty.thompson@ihs.gov

Caylen Willingham

P: 918-762-6582

Email: caylen.willingham@ihs.gov

File details come from the government source that posted it. Updated .