24130 MAC ISLAND VISITOR CENTER - ADDENDUM 2.pdf

PDF 280 KB Posted

Attached to
751/24130. ABG; Mackinac Island Visitor Center
Solicitation number
RFQ-171-250000000243-4
Issued by
Macomb County, Mcbride Village, Michigan

About this file

This document is Addendum No. 2 for the DTMB Mackinac Island Visitor Center Renovations project, issued by MCSA Group on March 5, 2025, for the Department of Technology, Management, and Budget (DTMB) of Michigan. The project involves renovations at 7200 Lake Shore Drive, Mackinac Island, with a construction start date of October 27, 2025, substantial completion by April 10, 2026, and final completion on May 8, 2026. The bid due date is March 19, 2025, at 2:00 pm, with a mandatory pre-bid meeting held on March 4, 2025, via Teams. The addendum updates the project schedule, provides specific Michigan State Historic Park requirements, and includes answers to contractor questions regarding logistics, site access, and fire suppression system management.

The addendum outlines critical site-specific requirements, including waived docking and city fees, seasonal vehicle traffic restrictions, archeological coordination for digging, and staging limitations. Contractors must submit a two-week look-ahead schedule, provide their own porta-johns, and have all materials stored on-site by December 1st. The project requires secure storage units and builders risk insurance. Staging is limited to specific areas, and contractors must restore any damage to turf, walks, or roads. The fire suppression system must remain in service as much as possible, with minimal downtime during renovations. No housing will be provided for the contractor or subcontractors, and all vehicle traffic must be coordinated with park staff in advance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 2

March 5, 2025

DTMB Mackinac Island Visitor Center Renovations 7200 Lake Shore Drive, Mackinac Island MI 49757

751/24130.ABG

TO: ALL BIDDERS OF RECORD.

This Addendum forms a part of the contract documents and modifies the original Project Manual as noted below. This addendum consists of four pages.

1. Construction start has been changed to October 27, 2025 with substantial completion April 10, 2026 and final completion May 8, 2026.

2. The Schedule identified in Section 00120 – Supplementary Instructions and updated in Addendum 1 is revised as follows:

Issue for bids: 2-12-2025 Mandatory Team’s prebid meeting date: Tuesday, March 4th at 2pm Substitution requests: 3/12/2025 Last day for questions: 3/12/2025 Last addendum: 3/14/2025 Bid due date: Wednesday, March 19, 2025 at 2:00pm

Post bid interview: 3-24-25 Submit to Ad board: 3-31-25 Ad. Board: 4-22-25 Award: 5-7-25

Preconstruction meeting: 6-1-25 Submittal processing: begins no later than 6-30-25 and complete by 8-29-25.

Construction start: 10-27-25 Substantial completion: 4-10-26 Final completion: 5-8-26

3. See the attached attendance list from the Team’s prebid meeting.

4. Refer to Deductive Alternate 2. This alternate includes the demolition and removal from the island of the build-out items detailed on sheet A0.2.

5. See the attached ‘SPECIFIC MICHIGAN STATE HISTORIC PARK REQUIREMENTS’ which replaces that in Appendix I Special Working Conditions. Changes are bolded.

Page -2-

See the following questions with answers.

1. Q: Just to clarify, the FP contractor shall be responsible for all associated cost from the mainland to the Island for all materials, equipment, tools, manpower, and lodging, correct? Most likely we would need to get in and demo our piping in the restroom areas and come back when all framing is completed (probably after the first of the year).

A: This bid package is for General Construction. Sub-contractors, including FP contractor, to provide their quotes directly to the General Contractors bidding. Scheduling of work will be the responsibility of the General Contractor.

2. Q: Will the fire suppression system need to remain in service during construction? I’m assuming that we can plug off the required openings primarily in the restroom area and place the system back in service just leaving the renovated areas out of service.

A: The system to remain in service as much as possible. It is understood there will be downtimes such as during the replacement of the fire riser. Downtimes should be minimized. Multiple trips etc should be planned to minimize system downtime.

END OF ADDENDUM

Page -3-

SPECIFIC MICHIGAN STATE HISTORIC PARK REQUIREMENTS

1. The General Contractor is required to submit a two-week look ahead schedule prior to the bi-monthly

(i.e. twice a month) progress meetings. The schedule is to be updated regularly and submitted to the team electronically either through Procore or email in advance of the meeting. The two-week look cannot be hand written and must be computer generated using scheduling software, Excel, Word or similar programs.

2. Site Access and logistics:

a. The State will waive docking fees at British Landing.

b. All vehicle traffic on park roads to be coordinated with the park in advance to determine route and availability by park staff to provide an escort.

c. Seasonal time restrictions from British Landing on park roads to the project site are:

i. September 1st through October 31st - between the hours of 5am – 10am.

ii. November 1st through April 30th – there will be no time restrictions.

iii. May 1st through May 23rd - between the hours of 5am – 10am. The routes will vary depending upon scheduled road paving projects.

iv. June 1st through August 31st – all vehicle traffic to be completed by 8am

d. Materials moved through the City must be on drays. The City fees will be waived for this project.

Any vehicle traffic through the town will require a city permit. Note, the project site is located on a city road.

3. The General Contractor must coordinate with the Mackinac State Historic Park’s archeologist for all digging.

4. The General Contractor to provide their own porta-johns.

5. The State will not provide any housing for the General Contractor or their subcontractors.

6. The Contractor is required to have all materials stored on site prior to December 1st. The Contractor to include within their bid secure storage units as needed. Materials stored on site require completion of form DTMB-0487 and valid builders risk insurance for payment.

7. Staging – the contractor cannot block Lake Shore Drive. The green space east of the building or the State land by the existing Field Office can be used for staging or storage. The contractor is required restore any damage to turf, walks, roads etc.

Page -4-

PROJECT NAME: DTMB Mackinac Island Visitor Center Renovations

MANDATORY PREBID MEETING DATE: Tuesday, March 4, 2025 2-3pm via Teams BID DUE DATE: Wednesday, March 19, 2025 at 2:00pm

Address: 7200 Lake Shore Drive, Mackinac Island MI 49757

3-4-2025 Mandatory Pre-Bid Meeting Attendance via Teams

Alan Goschka DTMB Brian Guigue DTMB Kathleen Waters MCSA Group Ted Nelson Coastal Construction Dave Baker John E Green Company Ed Hechlik Nicolet Shores Plumbing Robin Hyman Matrix Brady Sak & Tom Depas Mihm Enterprises Myron Johnson MI St Park Steve Brisson MI St Park Commission Jerrod Glover Total Fire Biz Bob Spence Coastal Construction

END OF ADDENDUM

END OF ADDENDUM
SPECIFIC MICHIGAN STATE HISTORIC PARK REQUIREMENTS
END OF ADDENDUM