240209_JMU Steam Line MH30-31_Project Manual_CD.pdf
PDF 1 MB Posted
- Solicitation number
- 60200
- Issued by
- Harrisonburg City, Virginia
About this file
This document is an Invitation for Bid (IFB) from James Madison University for the MH-30 to MH-31 Piping Replacement project, designated as IFB 23-449314-001. The project involves demolishing and replacing approximately 647 linear feet of 10-inch high-pressure steam and 4-inch condensate return direct-buried piping, modifying piping and valves in steam vaults, and performing site demolition and restoration work as detailed in the contract documents. The bid submission deadline and the anticipated award date are not provided.
The pricing terms, funding requirements, and other salient commercial details are not included in this document. The project will be constructed under a single prime contract, and the Owner is James Madison University, located in Harrisonburg, Virginia.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NOTICE OF IFB 23-449314-001.pdf | ||
| 240209_JMU Steam Line MH30-31_Construction Drawings.pdf | ||
| Intent to Award to Riddleberger Brothers, Inc. | — | |
| parkingmap.pdf | ||
| Bid Form.doc | DOC document | |
| Award to Riddleberger Bros. | — | |
| dgs-30-272_pre-bid_question_form.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
127 Nationwide Drive, Lynchburg, VA 24502 100% EMPLOYEE-OWNED | WILEYWILSON.COM
Project Manual
FOR
JAMES MADISON UNIVERSITY
Steam and Condensate Replacement MH-30 to MH-31B
Project No. 23-449314-001
Comm. No.: 222188
Working Drawings
February 9, 202402-09-24
Construction Documents
02/09/2024
WILEY|WILSON JAMES MADISON UNIVERSITY
STEAM AND CONDENSATE REPLACEMENT MH-30 TO MH-31B
PROJECT No. 23-449314-001 COMM. No. 230214
TABLE OF CONTENTS TOC - i
Table of Contents
Division Section Title Pages
DIVISION 01 - GENERAL REQUIREMENTS
011000 ....... SUMMARY
013100 ....... PROJECT MANAGEMENT AND COORDINATION
013200 ....... CONSTRUCTION PROGRESS DOCUMENTATION
013300 ....... SUBMITTAL PROCEDURES
015639 ....... TEMPORARY TREE AND PLANT PROTECTION
017300 ....... EXECUTION
017700 ....... CLOSEOUT PROCEDURES
017839 ....... PROJECT RECORD DOCUMENTS
DIVISION 02 - EXISTING CONDITIONS
024119 ....... SELECTIVE DEMOLITION
DIVISION 03 - CONCRETE
031000 ....... CONCRETE FORMING AND ACCESSORIES
032000 ....... CONCRETE REINFORCING
033000 ....... CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
055000 ....... METAL FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
071353 ....... ELASTOMERIC SHEET WATERPROOFING
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
230516 ....... EXPANSION FITTINGS FOR PIPING
230517
230523 ....... GENERAL-DUTY VALVES (MANUAL)
230719 ....... PIPING INSULATION
232213 ....... STEAM AND CONDENSATE PIPING
DIVISION 31 - EARTHWORK
311000 ....... SITE CLEARING
312000 ....... EARTH MOVING
DIVISION 32 - EXTERIOR IMPROVEMENTS
321313 ....... CONCRETE PAVING
DIVISION 33 - UTILITIES
336313 ....... PRE-INSULATED STEAM AND CONDENSATE DISTRIBUTION PIPING
END OF TABLE OF CONTENTS
ITTINGS FOR PIPING
SLEEVE SEALS FOR PIPING
E PIPING
PROJECT No. 23-449314-001 COMM. No. 230214
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Access to site.
4. Coordination with occupants.
5. Work restrictions.
6. Specification and Drawing conventions.
1.3 PROJECT INFORMATION
A. Project Identification: James Madison University Steam and Condensate Replacement MH-30 to MH-31B. Project Number 23-449314-001.
1. Project Location: James Madison University, Parking Lot F area adjacent to Godwin Hall, Harrisonburg, Virginia 22807.
B. Owner: James Madison University.
1. Owner's Representative: Dennis Hart, Power Plant Manager
C. Engineer: Wiley|Wilson.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Demolish and replace portions of steam and condensate lines, modify piping and valves in steam vaults, site demolition and restoration, and other Work as indicated in the Contract Documents.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
PROJECT No. 23-449314-001 COMM. No. 230214
SUMMARY 011000 - 2
1.5 ACCESS TO SITE
A. General: Contractor shall have access to the site throughout the construction period and may use the area for staging as directed by the Project Manager.
1.6 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing building during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, and other adjacent occupied or used facilities. Do not close or obstruct walkways or other occupied or used facilities without written permission from Owner.
2. Notify Owner not less than 7 days in advance of activities that will affect Owner's operations.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Limit work to normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated or allowed by Owner.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner unless permitted under the following conditions:
1. Notify Owner not less than seven days in advance of proposed utility interruptions.
C. Restricted Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
1.8 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
PROJECT No. 23-449314-001 COMM. No. 230214
SUMMARY 011000 - 3
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
PROJECT NO. 23449314-001
COMM. NO. 230214
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. RFIs.
3. Digital project management procedures.
4. Project meetings.
B. Each contractor shall participate in coordination requirements.
C. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.
2. Section 017300 "Execution" for procedures for coordinating general installation.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request for Information. Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
PROJECT NO. 23449314-001
COMM. NO. 230214
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
6. Startup and adjustment of systems.
1.6 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Engineer will return without response those RFIs submitted to Engineer by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
PROJECT NO. 23449314-001
COMM. NO. 230214
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
4. Name of Contractor.
5. Name of Engineer.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. RFI Forms: Software-generated form with substantially the same content as indicated above.
1. Attachments shall be electronic files in PDF format.
D. Engineer’s Action: Engineer will review each RFI, determine action required, and respond.
Allow seven working days for Engineer’s response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Engineer’s actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Engineer's action may include a request for additional information, in which case Engineer's time for response will date from time of receipt by Engineer of additional information.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log bi-weekly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Engineer.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Engineer's response was received.
8. Identification of related Minor Change in the Work, Construction Change Directive, and
Proposal Request, as appropriate.
PROJECT NO. 23449314-001
COMM. NO. 230214
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.
F. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Engineer within seven days if Contractor disagrees with response.
1.7 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Use of Engineer's Digital Data Files: Digital data files of Engineer's CAD drawings will be provided by Engineer for Contractor's use during construction if requested.
1. Engineer makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.
2. Contractor shall execute a data licensing agreement in a form acceptable to the Engineer.
a. Subcontractors and other parties granted access by Contractor to Engineer's digital data files shall execute a data licensing agreement in the same form used by the Contractor.
1.8 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner of scheduled meeting dates and times a minimum of 10 working days prior to meeting.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Engineer within three days of the meeting.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner, but no later than 15 days after execution of the Agreement.
1. Attendees: Authorized representatives of Owner; Contractor and its superintendent;
major subcontractors; suppliers; and other concerned parties shall attend the conference.
Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
PROJECT NO. 23449314-001
COMM. NO. 230214
PROJECT MANAGEMENT AND COORDINATION 013100 - 5
e. Designation of key personnel and their duties.
f. Lines of communications.
g. Procedures for processing field decisions and Change Orders.
h. Procedures for RFIs.
i. Procedures for testing and inspecting.
j. Procedures for processing Applications for Payment.
k. Distribution of the Contract Documents.
l. Submittal procedures.
m. Use of the premises and existing buildings.
n. Work restrictions.
o. Working hours.
p. Owner's occupancy requirements.
q. Procedures for disruptions and shutdowns.
r. Parking availability.
s. Office, work, and storage areas.
t. Equipment deliveries and priorities.
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Progress Meetings: Conduct progress meetings at biweekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Site use.
7) Quality and work standards.
8) Status of correction of deficient items.
9) Field observations.
10) Status of RFIs.
11) Status of Proposal Requests.
PROJECT NO. 23449314-001
COMM. NO. 230214
PROJECT MANAGEMENT AND COORDINATION 013100 - 6
12) Pending changes.
13) Status of Change Orders.
14) Pending claims and disputes.
15) Documentation of information for payment requests.
3. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
PROJECT No. 23-449314-001 COMM. No. 230214
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Construction schedule updating reports.
3. Site condition reports.
4. Unusual event reports.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
C. Event: The starting or ending point of an activity.
D. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
PROJECT No. 23-449314-001 COMM. No. 230214
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2
E. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.
1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. PDF file.
B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
C. Construction Schedule Updating Reports: Submit with Applications for Payment.
D. Unusual Event Reports: Submit at time of unusual event.
1.5 COORDINATION
A. Coordinate Contractor's Construction Schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.6 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.
B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Work Restrictions: Show the effect of the following items on the schedule:
a. Uninterruptible services.
b. Use-of-premises restrictions.
3. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:
PROJECT No. 23-449314-001 COMM. No. 230214
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 3
a. Submittals.
b. Purchases.
c. Fabrication.
d. Deliveries.
e. Installation.
f. Tests and inspections.
D. Contractor's Construction Schedule Updating: At bi-weekly intervals, update schedule to reflect actual construction progress and activities. Issue schedule two days before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate final completion percentage for each activity.
E. Distribution: Distribute copies of approved schedule to Engineer, Owner, separate contractors, and other parties identified by Contractor with a need-to-know schedule responsibility.
1.7 REPORTS
A. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
B. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.
1. Submit unusual event reports directly to Owner within two days of an occurrence.
Distribute copies of report to parties affected by the occurrence.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013200
PROJECT No. 23-449314-001 COMM. No. 230214
SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for submittals.
B. Related Requirements:
1. Section 013100 "Project Management and Coordination" for submitting subcontract list.
2. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.
3. Section 017700 "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.
4. Section 017839 "Project Record Documents" for submitting record Drawings, record
Specifications, and record Product Data.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information that require Engineer's responsive action.
Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements.
Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.4 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Engineer.
4. Name of Contractor.
PROJECT No. 23-449314-001 COMM. No. 230214
SUBMITTAL PROCEDURES 013300 - 2
5. Name of firm or entity that prepared submittal.
6. Names of subcontractor, manufacturer, and supplier.
7. Unique submittal number, including revision identifier.
8. Category and type of submittal.
9. Submittal purpose and description.
10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
11. Drawing number and detail references, as appropriate.
12. Indication of full or partial submittal.
13. Location(s) where product is to be installed, as appropriate.
14. Other necessary identification.
15. Remarks.
16. Signature of transmitter.
B. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Engineer on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
C. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
1.5 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Email: Prepare submittals as PDF package and transmit to Engineer by sending via email.
Include PDF transmittal form.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are required.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
PROJECT No. 23-449314-001 COMM. No. 230214
SUBMITTAL PROCEDURES 013300 - 3
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.
Time for review shall commence on Engineer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Submittal Review: Allow 15 days for review of each submittal.
D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Engineer's action stamp.
E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.
1.6 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
Generic product literature is not acceptable without specific details (such as part number, materials of construction, size, type, etc.) clearly identified.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Statement of compliance with specified referenced standards.
d. Testing by recognized testing agency.
e. Application of testing agency labels and seals.
f. Notation of coordination requirements.
g. Availability and delivery time information.
B. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.
PROJECT No. 23-449314-001 COMM. No. 230214
SUBMITTAL PROCEDURES 013300 - 4
C. Certificates:
1. Certificates and Certifications Submittals: When required in an individual specification section submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
1.7 CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.
Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
1. Engineer will not review submittals received from Contractor that do not have Contractor's review and approval.
1.8 ENGINEER'S REVIEW
A. Action Submittals: Engineer will review each submittal, indicate corrections or revisions required, and return it.
1. PDF Submittals: Engineer will indicate, via markup on each submittal, the appropriate action.
B. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements.
C. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
D. Engineer will return without review submittals received from sources other than Contractor.
E. Submittals not required by the Contract Documents will be returned by Engineer without action.
PROJECT No. 23-449314-001 COMM. No. 230214
SUBMITTAL PROCEDURES 013300 - 5
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013300
PROJECT No. 23-449314-001 COMM. No. 230214
TEMPORARY TREE AND PLANT PROTECTION 015639 - 1
SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes general protection of existing trees and plants that are affected by execution of the Work, whether temporary or permanent construction.
B. Related Sections:
1. Section 311000 "Site Clearing" for removing existing shrubs.
1.3 DEFINITIONS
A. Caliper: Diameter of a trunk measured by a diameter tape at 6 inches above the ground for trees up to, and including, 4-inch size; and 12 inches above the ground for trees larger than 4-inch size.
B. Plant-Protection Zone: Area surrounding individual trees, groups of trees, shrubs, or other vegetation to be protected during construction, and indicated on Drawings.
C. Tree-Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction and indicated on Drawings.
D. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.4 INFORMATIONAL SUBMITTALS
A. Existing Conditions: Documentation of existing trees and plantings indicated to remain, which establishes preconstruction conditions that might be misconstrued as damage caused by construction activities.
1. Use sufficiently detailed photographs or videotape.
2. Include plans and notations to indicate specific wounds and damage conditions of each tree or other plants designated to remain.
PROJECT No. 23-449314-001 COMM. No. 230214
TEMPORARY TREE AND PLANT PROTECTION 015639 - 2
1.5 PROJECT CONDITIONS
A. The following practices are prohibited within protection zones:
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Foot traffic.
4. Impoundment of water.
5. Excavation or other digging unless otherwise indicated.
6. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.
B. Do not direct vehicle or equipment exhaust toward protection zones.
C. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Protection-Zone Fencing: Fencing fixed in position and meeting the following requirements. Previously used materials may be used when approved by Owner.
1. Chain-Link Protection-Zone Fencing: Galvanized steel fencing fabricated from minimum 2-inch opening, 0.148-inch- diameter wire chain-link fabric; with pipe posts, minimum 2-3/8-inch- OD line posts, and 2-7/8-inch- OD corner and pull posts; with 1- 5/8-inch- OD top rails; with 0.177-inch- diameter top tension wire and 0.177-inch-diameter bottom tension wire; with tie wires, hog ring ties, and other accessories for a complete fence system.
a. Height: 4 feet.
b. Coating: Galvanized.
2. Gates: Single swing access gates matching material and appearance of fencing, to allow for maintenance activities within protection zones; leaf width 36 inches.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Erosion and Sedimentation Control: Examine the site to verify that temporary erosion- and sedimentation-control measures are in place. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.
B. For the record, prepare written report listing conditions detrimental to tree and plant protection.
PROJECT No. 23-449314-001 COMM. No. 230214
TEMPORARY TREE AND PLANT PROTECTION 015639 - 3
3.2 PREPARATION
A. Locate and clearly identify trees, shrubs, and other vegetation to remain. Flag each tree trunk at 54 inches above the ground.
B. Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials. Protect root systems from ponding, eroding, or excessive wetting caused by dewatering operations.
3.3 TREE- AND PLANT-PROTECTION ZONES
A. Protection-Zone Fencing: Install protection-zone fencing along edges of protection zones before materials or equipment are brought on the site and construction operations begin in a manner that will prevent people and animals from easily entering protected area except by entrance gates. Fencing shall extend a distance from the trunk of 1.25 feet per inch of trunk diameter or 6 feet, whichever is greater. Construct fencing so as not to obstruct safe passage or visibility at vehicle intersections where fencing is located adjacent to pedestrian walkways or in close proximity to street intersections, drives, or other vehicular circulation.
1. Chain-Link Fencing: Install to comply with ASTM F 567 and with manufacturer's written instructions.
2. Posts: Set or drive posts into ground one-third the total height of the fence without concrete footings. Where a post is located on existing paving or concrete to remain, provide appropriate means of post support acceptable to Engineer.
3. Access Gates: Install where needed; adjust to operate smoothly, easily, and quietly, free of binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that latches and locks engage accurately and securely without forcing or binding.
B. Maintain protection zones free of weeds and trash.
C. Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are damaged by construction operations, in a manner approved by Owner.
D. Maintain protection-zone fencing and signage in good condition as acceptable to Engineer and remove when construction operations are complete, and equipment has been removed from the site.
1. Do not remove protection-zone fencing, even temporarily, to allow deliveries or equipment access through the protection zone.
3.4 EXCAVATION
A. General: Excavate at edge of protection zones and for trenches indicated within protection zones according to requirements in Section 312000 "Earth Moving."
PROJECT No. 23-449314-001 COMM. No. 230214
TEMPORARY TREE AND PLANT PROTECTION 015639 - 4
B. Trenching near Trees: Where utility trenches are required within protection zones, hand excavate under or around tree roots or tunnel under the roots by drilling, auger boring, or pipe jacking. Do not cut main lateral tree roots or taproots; cut only smaller roots that interfere with installation of utilities. Cut roots as required for root pruning. Roots encountered outside of the tree protection area require notifying the JMU PM.
C. Redirect roots in backfill areas where possible. If encountering large, main lateral roots, expose roots beyond excavation limits as required to bend and redirect them without breaking. If encountered immediately adjacent to location of new construction and redirection is not practical, cut roots approximately 3 inches back from new construction and as required for root pruning.
D. Do not allow exposed roots to dry out before placing permanent backfill. Provide temporary earth cover or pack with peat moss and wrap with burlap. Water and maintain in a moist condition. Temporarily support and protect roots from damage until they are permanently relocated and covered with soil.
3.5 ROOT PRUNING
A. Prune roots that are affected by temporary and permanent construction. Prune roots as shown on Drawings and as follows:
1. Cut roots manually by digging a trench and cutting exposed roots with sharp pruning instruments; do not break, tear, chop, or slant the cuts. Do not use a backhoe or other equipment that rips, tears, or pulls roots.
2. Cut Ends: Coat cut ends of roots more than 1-1/2 inches in diameter with an emulsified asphalt or other coating formulated for use on damaged plant tissues and that is acceptable to tree service firm.
3. Temporarily support and protect roots from damage until they are permanently redirected and covered with soil.
4. Cover exposed roots with burlap and water regularly.
5. Backfill as soon as possible according to requirements in Section 312000 "Earth
Moving."
B. Root Pruning at Edge of Protection Zone: Prune roots flush with the edge of the protection zone, by cleanly cutting all roots to the depth of the required excavation.
C. Root Pruning within Protection Zone: Clear and excavate by hand to the depth of the required excavation to minimize damage to root systems. Use narrow tine spading forks, comb soil to expose roots, and cleanly cut roots as close to excavation as possible.
3.6 CROWN PRUNING
A. Prune branches that are affected by temporary and permanent construction. Prune branches as follows:
PROJECT No. 23-449314-001 COMM. No. 230214
TEMPORARY TREE AND PLANT PROTECTION 015639 - 5
1. Prune trees to remain to compensate for root loss caused by damaging or cutting root system. Provide subsequent maintenance during Contract period as recommended by tree service firm.
2. Pruning Standards: Prune trees according to ANSI A300 (Part 1)
3. Cut branches with sharp pruning instruments; do not break or chop.
4. Do not apply pruning paint to wounds.
B. Chip removed branches and dispose of off-site.
3.7 FIELD QUALITY CONTROL
A. Inspections: Engage a qualified tree service firm to direct plant-protection measures in the vicinity of trees, shrubs, and other vegetation indicated to remain and to prepare inspection reports.
3.8 REPAIR AND REPLACEMENT
A. General: Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are damaged by construction operations, in a manner approved by Owner.
1. Submit details of proposed root cutting and tree and shrub repairs.
2. Have tree service firm perform the root cutting, branch pruning, and damage repair of trees and shrubs.
3. Treat damaged trunks, limbs, and roots according to tree service firm's written instructions.
4. Perform repairs within 24 hours.
5. Replace vegetation that cannot be repaired and restored to full-growth status, as determined by Owner.
B. Trees: Remove and replace trees damaged during construction operations that Owner determines are incapable of restoring to normal growth pattern.
1. Provide new tree(s) of 2-inch caliper size for each tree being replaced.
a. Species: Same tree species as damaged, as shown on plans.
C. Soil Aeration: Where directed by Owner, aerate surface soil compacted during construction.
Aerate 10 feet beyond drip line and no closer than 36 inches to tree trunk. Drill 2-inch-diameter holes a minimum of 12 inches deep at 24 inches o.c. Backfill holes with an equal mix of augered soil and sand.
3.9 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Disposal: Remove excess excavated material, displaced trees, trash and debris, and legally dispose of them off Owner's property.
PROJECT No. 23-449314-001 COMM. No. 230214
TEMPORARY TREE AND PLANT PROTECTION 015639 - 6
END OF SECTION 015639
PROJECT No. 23-449314-001 COMM. No. 230214
EXECUTION 017300 - 1
SECTION 017300 - EXECUTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:
1. Installation of the Work.
2. Cutting and patching.
3. Progress cleaning.
4. Protection of installed construction.
1.3 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work.
B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.
1.4 QUALITY ASSURANCE
A. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.
1. Structural Elements: Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.
2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operational elements include the following:
a. Mechanical systems piping.
b. Steam vaults.
PROJECT No. 23-449314-001 COMM. No. 230214
EXECUTION 017300 - 2
PART 2 - PRODUCTS
2.1 MATERIALS
A. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.
1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Owner for the visual and functional performance of in-place materials.
PART 3 - EXECUTION
3.1 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication.
B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.
C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Engineer according to requirements in Section 013100 "Project Management and Coordination."
3.2 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Install products at the time and under conditions that will ensure the best possible results.
Maintain conditions required for product performance until Substantial Completion.
D. Repair or remove and replace damaged, defective, or nonconforming Work.
1. Comply with Section 017700 "Closeout Procedures" for repairing or removing and replacing defective Work.
PROJECT No. 23-449314-001 COMM. No. 230214
EXECUTION 017300 - 3
3.3 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching.
Proceed with cutting and patching at the earliest feasible time, and complete without delay.
B. Protection: Protect in-place construction during cutting and patching to prevent damage.
C. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, using methods least likely to damage elements retained or adjoining construction.
D. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work.
E. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.
3.4 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully.
1. Do not hold waste materials more than seven days.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
D. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways.
3.5 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work.
END OF SECTION 017300
PROJECT No. 23-449314-001 COMM. No. 230214
CLOSEOUT PROCEDURES 017700 - 1
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair of the Work.
B. Related Requirements:
1. Section 017839 "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.
1.3 ACTION SUBMITTALS
A. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
B. Certified List of Incomplete Items: Final submittal at final completion.
1.4 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's punch list), indicating the value of each item on the list and reasons why the Work is incomplete.
B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
1. Submit closeout submittals specified in other Division 01 Sections, including project record documents, operation and maintenance manuals, and similar final record information.
PROJECT No. 23-449314-001 COMM. No. 230214
CLOSEOUT PROCEDURES 017700 - 2
2. Submit closeout submittals specified in individual Sections, including specific warranties, final certifications, and similar documents.
C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
1. Complete startup and testing of systems and equipment.
2. Complete final cleaning requirements.
D. Inspection: Submit a written request for inspection to determine…