24 St. Lawrence Kitchen Upgrade Project Scope.docx

DOCX document 65 KB Posted

Attached to
24 St. Lawrence Kitchen Renovation Project
Solicitation number
2137450
Issued by
Genesee County, New York

About this file

This is a Project Scope document issued by the New York State Office for People with Developmental Disabilities (OPWDD) for kitchen renovation services at the Sunmount DDSO facility located at 2445 State Route 30, Tupper Lake, NY 12986. The project requires comprehensive renovation of an existing kitchen, including demolition of current fixtures and installation of new flooring, cabinetry, countertops, sinks, backsplash, lighting fixtures, and electrical outlets. Specific materials include Mohawk Hot & Heavy luxury vinyl plank flooring (approximately 218 square feet), new cabinetry and solid surface countertops (Pental/Quartz or equivalent) with colors and styles to be selected by OPWDD staff, and reinstallation of existing appliances in their original locations. Work must be completed within 30 days of award and performed between 7:00 AM and 3:30 PM, Monday through Friday. A mandatory site visit is scheduled for Wednesday, August 26, 2026 at 10:00 AM for exact jobsite measurements. Proposals must be submitted by 3:00 PM on Thursday, September 10, 2026, via email to Marissa.t.patenaude@opwdd.ny.gov, by mail to the Sunmount DDSO facility, or by fax to (518) 359-4230.

This procurement is limited exclusively to New York State Small Businesses, MWBE (Minority or Woman-Owned Business) firms certified pursuant to Articles 15-A and 17-B of the New York State Executive Law, or SDVOB (Service-Disabled Veteran-Owned Business) firms certified by the New York State Office of General Services. Bidders must provide copies of their firm's certification documents with their quotes. All proposals must include labor, materials, disposal fees, and site cleanup costs. The facility operates as a public works project requiring prevailing wage payments and certified payroll submissions upon completion. Contractor responsibilities include site security and daily cleanup, mandatory pre-safety meetings, coordination with OPWDD Operations and Maintenance staff, compliance with smoking prohibitions, liability for any property damage, and submission of a safety plan prior to work commencement. The point of contact is Max Gerstenberger, MS2, at 518-554-8115 or max.l.gerstenberger@opwdd.ny.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SCOPE

Facility:

Sunmount DDSO Facility Address:

2445 State Route 30, Tupper Lake, NY 12986

Point of Contact:

Max Gerstenberger, MS2 Contact Phone Number:

518-554-8115, max.l.gerstenberger@opwdd.ny.gov

Project Title:

Kitchen renovation Summary of Work:

Renovate existing kitchen to include new flooring, cabinetry, and countertops

DESCRIPTION:

24 St. Lawrence Kitchen Renovation. The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work and architectural drawings if supplied. Work is to be completed within 30 days of award, unless modified below This is a NYS Public Works project, and prevailing wages are to be paid, and Certified Payrolls must be submitted at time of completion. Refer to attached specification for the following scope of work. Site must be cleaned, and all materials secured at the end of each workday. Absolutely no scraps, especially fasteners, are to be left unsecured. Upon completion of the kitchen renovation, before removal of equipment, contractor is to schedule a quality control and quality assurance inspection with Plant Superintendent or his/her representative.

SCOPE OF WORK includes, but is not necessarily limited to the following:

A: Demolition Removal of existing appliances. Appliances are to be stored in the house for reuse.

Removal and proper disposal of existing countertops, cabinetry, backsplash tile, and flooring.

Removal of existing light fixtures for replacement.

Repair, as necessary, existing walls, ceiling, and subfloor to accommodate new installations.

B: New Construction

1. Provide and install new Mohawk Hot & Heavy luxury vinyl plank flooring. Floor approximately 218 sq/ft. Color to be chosen by OPWDD staff.

2. Provide and install new cabinetry. Cabinet style and manufacturer to be chosen by OPWDD staff from contractor submittals.

3. Provide and install new solid surface countertops (Pental/Quartz or equivalent). Colors/patterns to be chosen by OPWDD staff.

4. Provide and install new sinks at original locations. Installation to include new supply and drain lines.

5. Provide and install new backsplash on exterior wall. backsplash to be chosen by OPWDD staff.

6. Install new lighting fixtures (to include range hoods) and electrical outlets in existing locations.

7. Reinstall all previously removed appliances in original locations.

GENERAL REQUIREMENTS:

0. Proposal shall include all materials, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.

Work is to be done between the hours of 7:00am and 3.3ppm, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times.

24 St. Lawrence is located in Secure Area on Campus, Contractors must report to Building 14 for Pre-Safety Meeting on first day of Project. Escorts will be provided by OPWDD. All tools must always be controlled, and debris, tools and materials secured, stored and inventoried by SAFETY at the beginning and end of each workday.

Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent or his/her representative listed above immediately upon discovery.

Smoking is prohibited by contractors at all residential and program sites owned by OPWDD.

Prior to the commencement of the work, there shall be a meeting with OPWDD Operations and Maintenance staff and Safety Department to discuss specific safety requirements needed to be adhered to during the work period.

Safety Data Sheets as applicable will be provided to the Plant Superintendent or his/her representative prior to the start of work and a copy maintained at the property.

All applicable environmental testing associated with this work will be provided to the contractor prior to start of work, if necessary.

SITE VISIT:

A MANDATORY site visit has been scheduled for Wednesday August 26,2026 at 10:00 am, for exact measurements of jobsite. If you cannot attend on above date, please call and accommodations will be made, if possible, for an alternate date. Please call (518)-554-8115 to schedule a time at the project site. All questions or requests for information shall be submitted, in writing to max.l.gerstenberger@opwdd.ny.gov. Proposals must be submitted to the Facility by 3 PM on Thursday September 10,2026.

Proposals:

You may email proposals to: Marissa.t.patenaude@opwdd.ny.gov OR Via mail:

SUNMOUNT DDSO (ATTN: Marissa Patenaude/Proposals)

2445 STATE RTE 30,

TUPPER LAKE, NY 12986

OR

Via Fax: (518)359-4230 (ATTN: Marissa Patenaude)

A. Lawn Damage/Property Damage

· If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.

· Personal vehicles are not to be parked on the grass.

· Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.

B. Continuity of Work/Communication/Scheduling

· Once the job has begun, it is to be worked on continuously until completed.

· If there are any delays, even if due to inclement weather, a Work Control Representative MUST be contacted.

C. Work must be scheduled to start within 30 days of receiving the material.

D. General Safety

· The campus operates 7 days a week, 24 hours per day.

· The contractor must take all reasonable care to safeguard the residents and the staff.

· The contractor shall ensure all tools, materials and other items are picked up, removed, or stored and are safely secured at the end of each workday.

· Any ladders, scaffolding or lifts used in conjunction with this job are to be stored to the satisfaction of the safety Director at the end of the day.

· The work as indicated above shall be scheduled as not to interfered with other functions of the campus. All work performed as part of this job is to be coordinated with the Safety Director and Plant Superintendent or his/her representative listed above.

· The awarded vendor/contractor will provide a safety plan to the Plant Superintendent or his/her representative before work begins.