About this file

This document is an Individual Environmental Resource Permit (No. 11-106873-P) issued by the South Florida Water Management District (SFWMD) to Collier County Board of County Commissioners on May 20, 2022, for the Stan Gober Memorial Bridge Rehabilitation Project. The permit authorizes construction and operation of a stormwater management system serving 6.00 acres of transportation development, specifically involving repairs to an existing bridge. The proposed work includes placement of bedding stone and clean rubble riprap in scour holes around five existing bridge piers, concrete spall repair, beam repair, and deck repairs. The project is located in Collier County within the Rookery Bay Aquatic Preserve and has an existing Sovereign Submerged Lands easement.

The permit includes several critical environmental conditions, notably requiring compliance with manatee and marine species protection protocols, implementation of turbidity control measures, and adherence to best management practices during construction. The project previously had an environmental permit (No. 11-03089-P) from 2009 that authorized similar bridge and scour remediation activities. The permit is valid until May 20, 2027, and places perpetual operation and maintenance responsibilities on Collier County. Environmental considerations include protecting wetland-dependent species, maintaining water quality standards, and ensuring no adverse impacts to sovereign submerged lands or aquatic habitats.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

South Florida Water Management District Individual Environmental Resource Permit No. 11-106873-P

Date Issued: May 20, 2022

Permittee: Collier County Board Of County Commissioners Transportation Engineering 2885 South Horseshoe Drive Naples, FL 34104

Project:

Stan Gober Memorial Bridge Rehabilitation

Application No. 220324-33667

Location: Collier County, See Exhibit 1

Your application for an Individual Environmental Resource Permit is approved. This action is taken based on Chapter 373, Part IV, of Florida Statutes (F.S.) and the rules in Chapter 62-330, Florida Administrative Code (F.A.C.). Unless otherwise stated, this permit constitutes certification of compliance with state water quality standards under section 401 of the Clean Water Act, 33 U.S.C. 1341, and a finding of consistency with the Florida Coastal Management Program. Please read this entire agency action thoroughly and understand its contents.

This permit is subject to:

Not receiving a filed request for a Chapter 120, F.S., administrative hearing.

The attached General Conditions for Environmental Resource Permits.

The attached General Conditions for Authorizations.

The attached Special Conditions.

All referenced Exhibits.

All documents are available online through the District's ePermitting site at www.sfwmd.gov/ePermitting.

If you object to these conditions, please refer to the attached "Notice of Rights" which addresses the procedures to be followed if you desire a public hearing or other review of the proposed agency action.

Please contact this office if you have any questions concerning this matter. If we do not hear from you in accordance with the "Notice of Rights", we will assume that you concur with the District's action.

The District does not publish notices of action. If you wish to limit the time within which a person may request an administrative hearing regarding this action, you are encouraged to publish, at your own expense, a notice of agency action in the legal advertisement section of a newspaper of general circulation in the county or counties where the activity will occur. Legal requirements and instructions for publishing a notice of agency action, as well as a noticing format that can be used, are available upon request. If you publish a notice of agency action, please send a copy of the affidavit of publication provided by the newspaper to the District's West Palm Beach office for retention in this file.

If you have any questions regarding your permit or need any other information, please call us at 1-800-432-2045 or email epermits@sfwmd.gov.

Lisa Prather Section Administrator

Permit No: 11-106873-P, Page 1 of 19 http://www.sfwmd.gov/ePermitting mailto:epermits@sfwmd.gov

South Florida Water Management District Individual Environmental Resource Permit No. 11-106873-P

Date Issued: May 20, 2022 Expiration Date: May 20, 2027

Project Name: Stan Gober Memorial Bridge Rehabilitation

Permittee: Collier County Board Of County Commissioners

Operating Entity: Collier County Board Of County Commissioners

Location:

Collier County

Permit Acres:

6.00 acres

Project Land Use:

Transportation

Special Drainage District:

N/A

Water Body Classification:

CLASS II

FDEP Water Body ID:

Conservation Easement to District:

No

Sovereign Submerged Lands: Yes Type: Letter of Consent Project Summary This Environmental Resource Permit authorizes Construction and Operation of a stormwater management (SWM) system serving 6.00 acres of transportation development known as Stan Gober Memorial Bridge Rehabilitiation.

The proposed project consists of repairs to an existing bridge; including placement of bedding stone and clean rubble riprap in scour holes around five existing piers, concrete spall repair, beam repair, and deck repairs.

Issuance of this permit constitutes certification of compliance with state water quality standards in accordance with Rule 62-330.062, F.A.C.

Site Description The site contains an existing roadway bridge. Please refer to Exhibit No. 1.0 for a location map.

For information on wetland and surface water impacts, please see the Wetlands and Other Surface Water section of this permit.

Background Environmental Resource Permit number 11-03089-P, Application No. 090220-23, issued on December 16, 2009 authorized bridge and scour remediation activities for this bridge. The construction included placement of 0.11 acres of marine mattresses around existing bridge pilings

Permit No: 11-106873-P, Page 2 of 19 where scour had occurred, and placement of 0.05 acres of rip-rap around the eastern bridge abutment (STA 287+26.00).

Ownership, Operation and Maintenance Perpetual operation and maintenance of the SWM system will be the responsibility of the Collier County Board Of County Commissioners. Upon conveyance or division of ownership or control of the property or the system, the permittee must notify the Agency in writing within 30 days, and the new owner must request transfer of the permit.

Engineering Evaluation:

Land Use Refer to Land Use Data Table.

Water Quality Best Management Practices will be used during construction. The applicant will use floating and staked turbidity barriers. Staked turbidity barriers will be placed around mangrove areas. The floating turbidity barriers will be used for the placement of the rubble rip-rap and the barriers will be weighted down to prevent lifting off the bottom. Monitoring for turbidity around the work areas will be taken twice a day. The barriers will advance as the riprap is installed to prevent obstruction to navigation and to not impound any water dependent species such as the West Indian Manatee.

Turbidity levels shall be at zero Nephelometric Turbidity Units (NTU's). Should NTU's go above zero due to failure of the turbidity barriers, construction shall immediately cease for at least 24 hours or until turbidity has settled. Please refer to Exhibit 2.0, Sheet B1-3 for tubidity monitoring plan.

The project includes implementation of a Turbidity and Erosion Control Plan, (Exhibit No. 2.0), as additional reasonable assurance of compliance with water quality criteria during construction and operation.

Water Quantity Discharge Discharge from the bridge structure will remain as currently constructed, no additional discharge will occur with this application.

Certification, Operation, and Maintenance Pursuant to Chapter 62-330.310, F.A.C., Individual Permits will not be converted from the construction phase to the operation phase until construction completion certification of the project is submitted to and accepted by the District. This includes compliance with all permit conditions, except for any long term maintenance and monitoring requirements. It is suggested that the permittee retain the services of an appropriate professional registered in the State of Florida for periodic observation of construction of the project.

For projects permitted with an operating entity that is different from the permittee, it should be noted that until the construction completion certification is accepted by the District and the permit is transferred to an acceptable operating entity pursuant to Sections 12.1-12.3 of the Applicant's Handbook Volume I and Section 62-330.310, F.A.C., the permittee is liable for operation and maintenance in compliance with the terms and conditions of this permit.

In accordance with Section 373.416(2), F.S., unless revoked or abandoned, all SWM systems and works permitted under Part IV of Chapter 373, F.S., must be operated and maintained in perpetuity.

The efficiency of SWM systems, dams, impoundments, and most other project components will decrease over time without periodic maintenance. The operation and maintenance entity must perform periodic inspections to identify if there are any deficiencies in structural integrity, Permit No: 11-106873-P, Page 3 of 19 degradation due to insufficient maintenance, or improper operation of projects that may endanger public health, safety, or welfare, or the water resources. If deficiencies are found, the operation and maintenance entity is responsible for correcting the deficiencies in a timely manner to prevent compromises to flood protection and water quality. See Section 12.4 of the Applicant's Handbook Volume I for Minimum Operation and Maintenance Standards.

Permit No: 11-106873-P, Page 4 of 19

Engineering Evaluation Tables:

Land Use

Basin Land Type

Area (ac) % of Total

Basin

Site Roadway 6.00 100.00

Total: 6.00 100%

Permit No: 11-106873-P, Page 5 of 19

Environmental Evaluation:

Wetlands and Other Surface Waters The project site contains other surface waters (OSW) totaling 0.52 acres of Goodland Bay. The project will result in 0.52 acres of OSW impacts. The project is proposing re-stabilization of five existing bridge piers (12 through 16), within the existing footprint of the bridge. See Sheet No.

B1-1 of Exhibit 2.0 for the location of the proposed work. These areas were previously authorized for impact under Permit No. 11-03089-P (Application No. 090220-23).

Turbidity control measures shall be implemented per Special Condition No. 8.

Fish, Wildlife, and Listed Species The project site is located within the Rookery Bay Aquatic Preserve and does contain preferred habitat for wetland-dependent endangered or threatened wildlife species or species of special concern. Potential listed species of concern within this portion of the Aquatic Preserve area include the manatee, sea turtles, sharks, commercial shell fish, pink shrimp, blue crab and stone crab. A submerged aquatic vegetation survey was conducted in September of 2021. No submerged aquatic vegetation was found in or around the proposed project area.

The applicant will comply with the 2011 Standard Manatee Construction Conditions for in water construction and the Sea Turtle and Smalltooth Sawfish Construction Conditions of March 2009.

This permit does not relieve the applicant from complying with all applicable rules and any other agencies' requirements if, in the future, endangered or threatened species or species of special concern are discovered on the site.

Sovereignty Submerged Lands The proposed work is located within, and is not anticipated to adversely affect, sovereign submerged lands. There is an existing Sovereign Submerged Lands easement no.

25301(2455-11) for the bridge. The proposed in-water work is within the same footprint as previously authorized for the bridge under Permit No. 11-03089-P. The proposed remediation activities qualify for a Letter of Consent under Chapter 18-21. F.A.C.

Permit No: 11-106873-P, Page 6 of 19

Related Concerns:

Water Use Permit Status The applicant has indicated that there will be no irrigation.

The applicant has indicated that dewatering is not required for construction of this project.

This permit does not release the permittee from obtaining all necessary Water Use authorization(s) prior to the commencement of activities which will require such authorization, including construction dewatering and irrigation.

Historical/ Archeological Resources No information has been received that indicates the presence of archaeological or historical resources on the project site or indicating that the project will have any effect upon significant historic properties listed, or eligible for listing in the National Register of Historic Places.

This permit does not release the permittee from complying with any other agencies requirements in the event that historical and/or archaeological resources are found on the site.

Permit No: 11-106873-P, Page 7 of 19

General Conditions for Individual Environmental Resource Permits, 62-330.350, F.A.C.

1. All activities shall be implemented following the plans, specifications and performance criteria approved by this permit. Any deviations must be authorized in a permit modification in accordance with rule 62-330.315, F.A.C. Any deviations that are not so authorized may subject the permittee to enforcement action and revocation of the permit under Chapter 373, F.S.

2. A complete copy of this permit shall be kept at the work site of the permitted activity during the construction phase, and shall be available for review at the work site upon request by the Agency staff. The permittee shall require the contractor to review the complete permit prior to beginning construction.

3. Activities shall be conducted in a manner that does not cause or contribute to violations of state water quality standards. Performance-based erosion and sediment control best management practices shall be installed immediately prior to, and be maintained during and after construction as needed, to prevent adverse impacts to the water resources and adjacent lands. Such practices shall be in accordance with the State of Florida Erosion and Sediment Control Designer and Reviewer Manual (Florida Department of Environmental Protection and Florida Department of Transportation, June 2007), and the Florida Stormwater Erosion and Sedimentation Control Inspector’s Manual (Florida Department of Environmental Protection, Nonpoint Source Management Section, Tallahassee, Florida, July 2008), which are both incorporated by reference in subparagraph 62-330.050(9)(b)5., F.A.C., unless a project-specific erosion and sediment control plan is approved or other water quality control measures are required as part of the permit.

4. At least 48 hours prior to beginning the authorized activities, the permittee shall submit to the Agency a fully executed Form 62-330.350(1), “Construction Commencement Notice,” (October 1, 2013), (http://www.flrules.org/Gateway/reference.asp?No=Ref-02505), incorporated by reference herein, indicating the expected start and completion dates. A copy of this form may be obtained from the Agency, as described in subsection 62-330.010(5), F.A.C., and shall be submitted electronically or by mail to the Agency. However, for activities involving more than one acre of construction that also require a NPDES stormwater construction general permit, submittal of the Notice of Intent to Use Generic Permit for Stormwater Discharge from Large and Small Construction Activities, DEP Form 62-621.300(4)(b), shall also serve as notice of commencement of construction under this chapter and, in such a case, submittal of Form 62-330.350(1) is not required.

5. Unless the permit is transferred under rule 62-330.340, F.A.C., or transferred to an operating entity under rule 62-330.310, F.A.C., the permittee is liable to comply with the plans, terms, and conditions of the permit for the life of the project or activity.

6. Within 30 days after completing construction of the entire project, or any independent portion of the project, the permittee shall provide the following to the Agency, as applicable:

a. For an individual, private single-family residential dwelling unit, duplex, triplex, or quadruplex- "Construction Completion and Inspection Certification for Activities Associated With a Private Single-Family Dwelling Unit"[Form 62-330.310(3)]; or

b. For all other activities- "As-Built Certification and Request for Conversion to Operational Phase" [Form 62-330.310(1)].

c. If available, an Agency website that fulfills this certification requirement may be used in lieu of the form.

7. If the final operation and maintenance entity is a third party:

a. Prior to sales of any lot or unit served by the activity and within one year of permit issuance, or within 30 days of as-built certification, whichever comes first, the permittee shall submit, as

Permit No: 11-106873-P, Page 8 of 19 applicable, a copy of the operation and maintenance documents (see sections 12.3 thru 12.3.4 of Volume I) as filed with the Florida Department of State, Division of Corporations, and a copy of any easement, plat, or deed restriction needed to operate or maintain the project, as recorded with the Clerk of the Court in the County in which the activity is located.

b. Within 30 days of submittal of the as-built certification, the permittee shall submit “Request for Transfer of Environmental Resource Permit to the Perpetual Operation and Maintenance Entity” [Form 62-330.310(2)] to transfer the permit to the operation and maintenance entity, along with the documentation requested in the form. If available, an Agency website that fulfills this transfer requirement may be used in lieu of the form.

8. The permittee shall notify the Agency in writing of changes required by any other regulatory agency that require changes to the permitted activity, and any required modification of this permit must be obtained prior to implementing the changes.

9. This permit does not:

a. Convey to the permittee any property rights or privileges, or any other rights or privileges other than those specified herein or in Chapter 62-330, F.A.C.;

b. Convey to the permittee or create in the permittee any interest in real property;

c. Relieve the permittee from the need to obtain and comply with any other required federal, state, and local authorization, law, rule, or ordinance; or

d. Authorize any entrance upon or work on property that is not owned, held in easement, or controlled by the permittee.

10. Prior to conducting any activities on state-owned submerged lands or other lands of the state, title to which is vested in the Board of Trustees of the Internal Improvement Trust Fund, the permittee must receive all necessary approvals and authorizations under Chapters 253 and 258, F.S. Written authorization that requires formal execution by the Board of Trustees of the Internal Improvement Trust Fund shall not be considered received until it has been fully executed.

11. The permittee shall hold and save the Agency harmless from any and all damages, claims, or liabilities that may arise by reason of the construction, alteration, operation, maintenance, removal, abandonment or use of any project authorized by the permit.

12. The permittee shall notify the Agency in writing:

a. Immediately if any previously submitted information is discovered to be inaccurate; and

b. Within 30 days of any conveyance or division of ownership or control of the property or the system, other than conveyance via a long-term lease, and the new owner shall request transfer of the permit in accordance with Rule 62-330.340, F.A.C. This does not apply to the sale of lots or units in residential or commercial subdivisions or condominiums where the stormwater management system has been completed and converted to the operation phase.

13. Upon reasonable notice to the permittee, Agency staff with proper identification shall have permission to enter, inspect, sample and test the project or activities to ensure conformity with the plans and specifications authorized in the permit.

14. If prehistoric or historic artifacts, such as pottery or ceramics, projectile points, stone tools, dugout canoes, metal implements, historic building materials, or any other physical remains that could be associated with Native American, early European, or American settlement are encountered at any time within the project site area, the permitted project shall cease all activities involving subsurface disturbance in the vicinity of the discovery. The permittee or other designee shall contact the Florida Department of State, Division of Historical Resources, Compliance Review Section (DHR), at (850)245-6333, as well as the appropriate permitting agency office. Project activities shall not resume without verbal or written authorization from

Permit No: 11-106873-P, Page 9 of 19 the Division of Historical Resources. If unmarked human remains are encountered, all work shall stop immediately and the proper authorities notified in accordance with section 872.05, F.S. For project activities subject to prior consultation with the DHR and as an alternative to the above requirements, the permittee may follow procedures for unanticipated discoveries as set forth within a cultural resources assessment survey determined complete and sufficient by DHR and included as a specific permit condition herein.

15. Any delineation of the extent of a wetland or other surface water submitted as part of the permit application, including plans or other supporting documentation, shall not be considered binding unless a specific condition of this permit or a formal determination under Rule 62-330.201, F.A.C., provides otherwise.

16. The permittee shall provide routine maintenance of all components of the stormwater management system to remove trapped sediments and debris. Removed materials shall be disposed of in a landfill or other uplands in a manner that does not require a permit under Chapter 62-330, F.A.C., or cause violations of state water quality standards.

17. This permit is issued based on the applicant's submitted information that reasonably demonstrates that adverse water resource-related impacts will not be caused by the completed permit activity. If any adverse impacts result, the Agency will require the permittee to eliminate the cause, obtain any necessary permit modification, and take any necessary corrective actions to resolve the adverse impacts.

18. A Recorded Notice of Environmental Resource Permit may be recorded in the county public records in accordance with Rule 62-330.090(7), F.A.C. Such notice is not an encumbrance upon the property.

Permit No: 11-106873-P, Page 10 of 19

General Conditions for Authorizations for Use of Sovereign Submerged Lands, Rule 18-21.004(7), F.A.C.

All authorizations granted by rule or in writing under Rule 18-21.005, F.A.C., except those for aquaculture activities and geophysical testing, shall be subject to the general conditions as set forth in paragraphs (a) through (i) below. The general conditions shall be part of all authorizations under this chapter, shall be binding upon the grantee, and shall be enforceable under Chapter 253 or Chapter 258, Part II, F.S.

(a) Authorizations are valid only for the specified activity or use. Any unauthorized deviation from the specified activity or use and the conditions for undertaking that activity or use shall constitute a violation. Violation of the authorization shall result in suspension or revocation of the grantee's use of the sovereignty submerged land unless cured to the satisfaction of the Board.

(b) Authorizations convey no title to sovereignty submerged land or water column, nor do they constitute recognition or acknowledgment of any other person's title to such land or water.

(c) Authorizations may be modified, suspended or revoked in accordance with their terms or the remedies provided in Sections 253.04 and 258.46, F.S., or Chapter 18-14, F.A.C.

(d) Structures or activities shall be constructed and used to avoid or minimize adverse impacts to sovereignty submerged lands and resources.

(e) Construction, use, or operation of the structure or activity shall not adversely affect any species which is endangered, threatened or of special concern, as listed in Rules 68A-27.003, 68A-27.004, and 68A-27.005, F.A.C.

(f) Structures or activities shall not unreasonably interfere with riparian rights. When a court of competent jurisdiction determines that riparian rights have been unlawfully affected, the structure or activity shall be modified in accordance with the court's decision.

(g) Structures or activities shall not create a navigational hazard.

(h) Structures shall be maintained in a functional condition and shall be repaired or removed if they become dilapidated to such an extent that they are no longer functional. This shall not be construed to prohibit the repair or replacement subject to the provisions of Rule 18-21.005, F.A.C., within one year, of a structure damaged in a discrete event such as a storm, flood, accident, or fire.

(i) Structures or activities shall be constructed, operated, and maintained solely for water dependent purposes, or for non-water dependent activities authorized under paragraph 18-21.004(1)(g), F.A.C., or any other applicable law.

Permit No: 11-106873-P, Page 11 of 19

Special Conditions for Individual Environmental Resource Permits, 62-330.350, F.A.C.

1. The construction authorization for this permit shall expire on the date shown on page 2.

2.Operation and maintenance of the stormwater management system shall be the responsibility of the Collier County Board Of County Commissioners. The permittee shall notify the Agency in writing within 30 days of any conveyance or division of ownership or control of the property of the system, and the new owner must request transfer of the permit in accordance with Rule 62-330.340, F.A.C.

3.A stable, permanent and accessible elevation reference shall be established on or within one hundred (100) feet of all permitted discharge structures no later than the submission of the certification report. The location of the elevation reference must be noted on or with the certification report.

4.Prior to any future construction, the permittee shall apply for and receive an Individual ERP. As part of the permit application, the applicant for that phase shall provide documentation verifying that the proposed construction is consistent with the design of the master stormwater management system, including the land use and site grading assumptions.

5.Prior to initiating construction activities associated with this Environmental Resource Permit

(ERP), the permittee is required to hold a pre-construction meeting with field representatives, consultants, contractors, District Environmental Resource Bureau (ERB) staff, and any other local government entities as necessary. The purpose of the pre-construction meeting is to discuss construction methods, sequencing, best management practices, identify work areas, staking and roping of preserves where applicable, and to facilitate coordination and assistance amongst relevant parties. To schedule a pre-construction meeting, please contact ERB staff from the Fort Myers Service Center at (239) 338-2929 or via e-mail at: precon@sfwmd.gov. When sending a request for a pre-construction meeting, please include the application number, permit number, and contact name and phone number.

6.This permit does not authorize the permittee to cause any adverse impact to or “take” of state listed species and other regulated species of fish and wildlife. Compliance with state laws regulating the take of fish and wildlife is the responsibility of the owner or applicant associated with this project. Please refer to Chapter 68A-27 of the Florida Administrative Code for definitions of “take” and a list of fish and wildlife species. If listed species are observed onsite, FWC staff are available to provide decision support information or assist in obtaining the appropriate FWC permits. Most marine endangered and threatened species are statutorily protected and a “take” permit cannot be issued. Requests for further information or review can be sent to:

FWCConservationPlanningServices@MyFWC.com.

7.The permittee shall comply with the following when performing work within waters accessible to federally- or state-listed aquatic species, such as manatees, marine turtles, smalltooth sawfish, and Gulf sturgeon: a. All vessels associated with the project shall operate at "Idle Speed/No Wake" at all times while in the work area and where the draft of the vessels provides less than a four-foot clearance from the bottom. All vessels will follow routes of deep water whenever possible. b. All deployed siltation or turbidity barriers shall be properly secured, monitored, and maintained to prevent entanglement or entrapment of listed species. c. All in-water activities, Permit No: 11-106873-P, Page 12 of 19 including vessel operation, must be shutdown if a listed species comes within 50 feet of the work area. Activities shall not resume until the animal(s) has moved beyond a 50-foot radius of the in-water work, or until 30 minutes elapses since the last sighting within 50 feet. Animals must not be herded away or harassed into leaving. All on-site project personnel are responsible for observing water-related activities for the presence of listed species. d. Any listed species that is killed or injured by work associated with activities performed shall be reported immediately to the Florida Fish and Wildlife Conservation Commission (FWC) Hotline at 1-888-404-3922 and ImperiledSpecies@myFWC.com. e. Whenever there is a spill or frac-out of drilling fluid into waters accessible to the above species during a directional drilling operation, the FWC shall be notified at imperiledspecies@myfwc.com with details of the event within 24 hours following detection of the spill or frac-out.

8.Turbidity control measures shall be implemented in accordance with Sheet No. B1-2 of Exhibit No. 2.0. Prior to the commencement of construction in the Rookery Bay Aquatic Preserve, floating turbidity curtains with weighted skirts that extend to the bottom of the water body shall be properly installed to isolate adjacent waters from the work area. The floating turbidity curtains shall be maintained and shall remain in place until all construction is complete and turbidity levels in the project area are within 0 NTUs of background levels. The permittee shall be responsible for ensuring that turbidity control devices are inspected daily and maintained in good working order so that there are no violations of state water quality standards outside of the turbidity screens.

9.STANDARD MANATEE CONDITIONS FOR IN-WATER WORK (2011) The permittee shall comply with the following conditions intended to protect manatees from direct project effects: a.

All personnel associated with the project shall be instructed about the presence of manatees and manatee speed zones, and the need to avoid collisions with and injury to manatees. The permittee shall advise all construction personnel that there are civil and criminal penalties for harming, harassing, or killing manatees which are protected under the Marine Mammal Protection Act, the Endangered Species Act, and the Florida Manatee Sanctuary Act. b. All vessels associated with the construction project shall operate at "Idle Speed/No Wake� at all times while in the immediate area and while in water where the draft of the vessel provides less than a four-foot clearance from the bottom. All vessels will follow routes of deep water whenever possible. c. Siltation or turbidity barriers shall be made of material in which manatees cannot become entangled, shall be properly secured, and shall be regularly monitored to avoid manatee entanglement or entrapment. Barriers must not impede manatee movement. d. All on-site project personnel are responsible for observing water-related activities for the presence of manatee(s).

All in-water operations, including vessels, must be shutdown if a manatee(s) comes within 50 feet of the operation. Activities will not resume until the manatee(s) has moved beyond the 50-foot radius of the project operation, or until 30 minutes elapses if the manatee(s) has not reappeared within 50 feet of the operation. Animals must not be herded away or harassed into leaving. e. Any collision with or injury to a manatee shall be reported immediately to the Florida Fish and Wildlife Conservation Commission (FWC) Hotline at 1-888-404-3922. Collision and/or injury should also be reported to the U.S. Fish and Wildlife Service in Jacksonville (1-904-731-3336) for north Florida or Vero Beach (1-772-562-3909) for south Florida, and to FWC at ImperiledSpecies@myFWC.com f. Temporary signs concerning manatees shall be posted prior to and during all in-water project activities. All signs are to be removed by the permittee upon completion of the project. Temporary signs that have already been approved for this use by the FWC must be used. One sign which reads Caution: Boaters must be posted. A second sign measuring at least 8 ½� by 11" explaining the requirements for “Idle Speed/No Wake� and the shut down of in-water operations must be posted in a location prominently visible to all personnel engaged in water-related activities. These signs can be viewed at MyFWC.com/manatee. Questions concerning these signs can be sent to the email address listed above.

Permit No: 11-106873-P, Page 13 of 19

Permit No: 11-106873-P, Page 14 of 19

Project Work Schedule for Permit No. 11-106873-P

The following activities are requirements of this Permit and shall be completed in accordance with the Project Work Schedule below. Please refer to General Conditions, Special Conditions and/or Specific Conditions for more information. Any deviation from these time frames will require prior approval from the District’s Environmental Resources Bureau and may require a minor modification to this permit. Such requests must be made in writing and shall include: (1) reason for the change, (2) proposed start/finish and/or completion dates, and (3) progress report on the status of the project.

Condition No. Date Added Description (Application Number) Due Date Date Satisfied

GC 4 05/20/2022 Construction Commencement Notice Prior to Construction

GC 6 05/20/2022 Submit Certification 30 Days After Construction Completion

SC 5 05/20/2022 Pre-Construction Meeting Prior to Construction

GC = General Condition

SC = Special Condition

Permit No: 11-106873-P, Page 15 of 19

Distribution List

Ryan Horstman, ESA

Ananda Bergeron, Cardno

Audubon of Florida

Florida Department of Environmental Protection

US Army Corps of Engineers - Permit Section

Permit No: 11-106873-P, Page 16 of 19

Exhibits

The following exhibits to this permit are incorporated by reference. The exhibits can be viewed by clicking on the links below or by visiting the District's ePermitting website at http://my.sfwmd.gov/ePermitting and searching under this application number 220324-33667 .

Exhibit No. 1.0 Location Map

Exhibit No. 2.0 Construction Plans

Permit No: 11-106873-P, Page 17 of 19 http://my.sfwmd.gov/ePermitting https://api.sfwmd.gov/v1/service/cms/documents/0900eeea9342ebdf/content https://api.sfwmd.gov/v1/service/cms/documents/0900eeea934d296c/content

NOTICE OF RIGHTS

As required by Chapter 120, Florida Statutes, the following provides notice of the opportunities which may be available for administrative hearing pursuant to Sections 120.569 and 120.57, Florida Statutes, or judicial review pursuant to Section 120.68, Florida Statutes, when the substantial interests of a party are determined by an agency. Please note that this Notice of Rights is not intended to provide legal advice. Some of the legal proceedings detailed below may not be applicable or appropriate for your situation. You may wish to consult an attorney regarding your legal rights.

RIGHT TO REQUEST ADMINISTRATIVE HEARING

A person whose substantial interests are or may be affected by the South Florida Water Management District’s (District) action has the right to request an administrative hearing on that action pursuant to Sections 120.569 and 120.57, Florida Statutes. Persons seeking a hearing on a District decision which affects or may affect their substantial interests shall file a petition for hearing in accordance with the filing instructions set forth herein within 21 days of receipt of written notice of the decision unless one of the following shorter time periods apply:

(1) within 14 days of the notice of consolidated intent to grant or deny concurrently reviewed applications for environmental resource permits and use of sovereign submerged lands pursuant to Section 373.427, Florida Statutes; or (2) within 14 days of service of an Administrative Order pursuant to Section 373.119(1), Florida Statutes. "Receipt of written notice of agency decision" means receipt of written notice through mail, electronic mail, posting, or publication that the District has taken or intends to take final agency action. Any person who receives written notice of a District decision and fails to file a written request for hearing within the timeframe described above waives the right to request a hearing on that decision.

If the District takes final agency action that materially differs from the noticed intended agency decision, persons who may be substantially affected shall, unless otherwise provided by law, have an additional point of entry pursuant to Rule 28-106.111, Florida Administrative Code.

Any person to whom an emergency order is directed pursuant to Section 373.119(2), Florida Statutes, shall comply therewith immediately, but on petition to the board shall be afforded a hearing as soon as possible.

A person may file a request for an extension of time for filing a petition. The District may grant the request for good cause. Requests for extension of time must be filed with the District prior to the deadline for filing a petition for hearing. Such requests for extension shall contain a certificate that the moving party has consulted with all other parties concerning the extension and whether the District and any other parties agree to or oppose the extension. A timely request for an extension of time shall toll the running of the time period for filing a petition until the request is acted upon.

FILING INSTRUCTIONS

A petition for administrative hearing must be filed with the Office of the District Clerk. Filings with the Office of the District Clerk may be made by mail, hand-delivery, or e-mail. Filings by facsimile will not be accepted. A petition for administrative hearing or other document is deemed filed upon receipt during normal business hours by the Office of the District Clerk at the District’s headquarters in West Palm Beach, Florida. The District’s normal business hours are 8:00 a.m. – 5:00 p.m., excluding weekends and District holidays. Any document received by the Office of the District Clerk after 5:00 p.m. shall be deemed filed as of 8:00 a.m. on the next regular business day.

Rev. 1/16/20 1 Permit No: 11-106873-P, Page 18 of

Additional filing instructions are as follows:

Filings by mail must be addressed to the Office of the District Clerk, 3301 Gun Club Road, West Palm Beach, Florida 33406.

Filings by hand-delivery must be delivered to the Office of the District Clerk. Delivery of a petition to the District's security desk does not constitute filing. It will be necessary to request that the District's security officer contact the Office of the District Clerk. An employee of the District's Clerk's office will receive and process the petition.

Filings by e-mail must be transmitted to the Office of the District Clerk at clerk@sfwmd.gov.

The filing date for a document transmitted by electronic mail shall be the date the Office of the District Clerk receives the complete document.

INITIATION OF ADMINISTRATIVE HEARING

Pursuant to Sections 120.54(5)(b)4. and 120.569(2)(c), Florida Statutes, and Rules 28-106.201 and 28-106.301, Florida Administrative Code, initiation of an administrative hearing shall be made by written petition to the District in legible form and on 8 1/2 by 11 inch white paper. All petitions shall contain:

Identification of the action being contested, including the permit number, application1.

number, District file number or any other District identification number, if known.

The name, address, any email address, any facsimile number, and telephone number of2.

the petitioner, petitioner’s attorney or qualified representative, if any.

An explanation of how the petitioner’s substantial interests will be affected by the agency3.

determination.

A statement of when and how the petitioner received notice of the District’s decision.4.

A statement of all disputed issues of material fact. If there are none, the petition must so5.

indicate.

A concise statement of the ultimate facts alleged, including the specific facts the petitioner6.

contends warrant reversal or modification of the District’s proposed action.

A statement of the specific rules or statutes the petitioner contends require reversal or7.

modification of the District’s proposed action.

If disputed issues of material fact exist, the statement must also include an explanation of8.

how the alleged facts relate to the specific rules or statutes.

A statement of the relief sought by the petitioner, stating precisely the action the petitioner9.

wishes the District to take with respect to the District’s proposed action.

MEDIATION

The procedures for pursuing mediation are set forth in Section 120.573, Florida Statutes, and Rules 28-106.111 and 28-106.401–.405, Florida Administrative Code. The District is not proposing mediation for this agency action under Section 120.573, Florida Statutes, at this time.

RIGHT TO SEEK JUDICIAL REVIEW

Pursuant to Section 120.68, Florida Statutes, and in accordance with Florida Rule of Appellate Procedure 9.110, a party who is adversely affected by final District action may seek judicial review of the District's final decision by filing a notice of appeal with the Office of the District Clerk in accordance with the filing instructions set forth herein within 30 days of rendition of the order to be reviewed, and by filing a copy of the notice with the appropriate district court of appeals via the Florida Courts E-Filing Portal.