This is a Utility Work Schedule document prepared by the Florida Department of Transportation (FDOT) in coordination with CenturyLink Communications, LLC, outlining the relocation and adjustment of telecommunications utilities for the 16th Street NE Bridge Project in Collier County, Florida. The utility work involves 48 separate activities encompassing the removal, protection, adjustment, boring, and splicing of various telecommunications facilities including buried trunk (BT) cables, buried drop wires (BDW), aerial drop wires (ADW), pedestals, hand holes, and related infrastructure along approximately 2.5 miles of roadway corridor (station 503+70 through 1174+00). All utility work is scheduled to occur during FDOT project construction, with each individual activity requiring one consecutive calendar day for completion. The project is based on FDOT plans dated August 1, 2023, and the utility work schedule was executed by Troy Inniss, Network Implementation Program Manager for CenturyLink, on September 19, 2023, with engineering approval from Jesse E. Gill, P.E.
CenturyLink requires five business days' advance notice prior to the start of construction and prior to any required utility work activities, with all work to be performed between 8:00 a.m. and 4:00 p.m., Monday through Friday, unless otherwise coordinated with 48 hours' notice. The utility contractor must obtain a utility permit and comply with the 2017 Utility Accommodation Manual requirements. CenturyLink has requested 60 days prior to construction to address engineering, permitting, funding, and material procurement activities. The utility work is dependent upon the roadway contractor's completion of staking, excavation, drainage work, hard surface removal, and grading activities as detailed for each work activity. CenturyLink retains the right to maintain access throughout the project duration to monitor and service its facilities.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rule 14-46.001 F.A.C
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.
FDOT PROJECT INFORMATION
Financial Project ID: 451283-1-58-01 Federal Project ID:
State Road Number: NA County: Collier
FDOT Plans Dated: 08/1/2023 District Document No.:
UTILITY AGENCY/OWNER (UAO)
Utility Company: CenturyLink Communications, LLC
UAO Project Rep: Troy Inniss Phone: 239-920-5821 E-mail: troy.inniss@lumen.com
UAO Field Rep: Troy Inniss Phone: 239-920-5821 E-mail: troy.inniss@lumen.com
UTILITY SIGNATURE
I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.
UAO Rep. Date 9 / 19 / 2023
Name Troy Inniss
Title Network Implementation Program Manager
ENGINEER OF RECORD SIGNATURE
I attest this utility work schedule is compatible with the FDOT plans referenced above.
EOR. Date / /
Name Jesse E. Gill P.E.
Title Engineer of Record
APPROVAL BY DISTRICT UTILITIES
This utility work schedule is complete and acceptable to FDOT.
FDOT Rep. Date / /
Name Wayne Shelton
Title District Utility Coordinator
SECTION A: SUMMARY OF UTILITY WORK
The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.
Days prior to FDOT project construction: 0 Days during FDOT project construction: 51 jgill Text Box 03 15 2024
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Financial Project ID: 451283-1-58-01
Utility Company: CenturyLink Communications, LLC
FDOT Plans Dated: 08/1/2023
SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS
Definitions:
Locate: Utilizing electromagnetic, and other energy fields for determining the existence and approximate horizontal location of underground facilities. Underground facilities will be marked by stakes, flags, paint or other suitable materials in varying combinations dependent upon surface conditions using American Public Works Association Utility Location Coordination Council Color Codes.
Protect: Shall include but is not limited to the use of strapping, sheeting, guarding with either mechanized or non-mechanized equipment.
Adjust: Shall include permittee’s use of an onsite representative during active construction operations. During excavation operations the
CenturyLink Local representative shall adjust the location of CenturyLink Local facilties either horizontally or vertically to address conflicts with proposed road facilities.
1) Contact Troy Inniss, Roadmoves field Rep. @ 239.920.5821, 5 business days prior to start of construction and 5 business days prior to required work by CenturyLink Local as listed in Section C.
2) This work schedule is based on calendar days as shown in Section C. CenturyLink Local working hours are 8 AM to 4 PM Monday thru
Friday. Any request for work activities outside that time frame will need to be coordinated at least 48 hours in advance of required work.
3) Locate, Protect & Adjust activities to be provided by CenturyLink Local master contractor who will work closely with the roadway contractor.
4) CenturyLink Local requests to have access throughout the duration of the project to monitor and maintain its facilities for the ability to provide service and will coordinate with the road contractor.
5) CenturyLink local will need 60 days prior to construction to address Engineering, permitting, funding and material procurement.
All existing cable and facilities shown on the plans are to remain and will not be adjusted unless otherwise detailed in Section C.
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 08/1/2023
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
BFO 12, (2) 900 BT &
104 BT
1003+50
/ 34’ LT
1005+85
/ 70’ LT
Remove BT Cables where accessible
Staking for drainage, R/W, excavation & removal of hard surfaces
1 0 1
2 100 BT
1005+75
/ 20’ LT
1005+75
/ 54’ LT
Hold, Protect & Adjust
BT during construction
Staking & excavation for side drain, ditch, & sidewalk
1 0 1
3 Hand Hole 1005+75
/ 68’ LT
NA
Adjust Hand Hole to final grade
Staking & grading for sidewalk & R/W 1 0 1
(2) 900 BT, 600 BT &
100 BT
1005+90
/ 27’ LT
1005+95
/ 70’ LT
Remove BT Cables where accessible
Staking for drainage, R/W, excavation & removal of hard surfaces
1 0 1
5 Pedestal 1006+20
/ 26’ RT
NA
Adjust Pedestal to final grade
Staking for drainage, R/W, excavation of ditch
1 0 1
6 pair buried drop wire
(BDW)
1008+30
/ 30’ RT
1009+80
/ 60’ LT
Bore BDW & splice for connectivity
Staking for drainage, R/W & sidewalk 1 0 1
6 pair buried drop wire
(BDW)
1008+30
/ 30’ RT
1008+80
/ 30’ RT
Bore BDW & splice for connectivity
Staking for drainage &
R/W 1 0 1
6 pair buried drop wire
(BDW)
1008+80
/ 30’ LT
1008+80
/ 30’ RT
Removal BDW where accessible
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
6 pair buried drop wire
(BDW)
1008+30
/ 60’ LT
1009+80
/ 60’ LT
Removal BDW where accessible
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 08/1/2023
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
10 Pedestal 1008+30
/ 30’ LT
NA Remove Pedestal
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
11 Pedestal 1008+30
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
12 Pedestal 1012+25
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
13 Pedestal 1013+62
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
14 Pedestal 1017+22
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
15 Pedestal 1019+10
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
16 Pedestal 1020+22
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
17 Pedestal 1022+00
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
6 pair buried drop wire
(BDW)
1025+95
/ 60’ LT
1026+81
/ 30’ RT
Removal BDW where accessible
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
6 pair buried drop wire
(BDW)
1025+95
/ 60’ LT
1026+82
/ 30’ RT
Bore BDW & splice for connectivity
Staking for drainage, R/W & sidewalk 1 0 1
20 Pedestal 1026+82
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch & side drain 1 0 1
21 Pedestal 1028+60
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
22 Pedestal 1031+90
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch & side drain
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 08/1/2023
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
6 pair buried drop wire
(BDW)
1034+58
/ 75’ LT
1035+20
/ 30’ RT
Removal BDW where accessible
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
6 pair buried drop wire
(BDW)
1034+58
/ 75’ LT
1035+20
/ 30’ RT
Bore BDW & splice for connectivity
Staking for drainage, R/W & sidewalk 1 0 1
25 Pedestal 1035+20
/ 32’ LT
NA Remove Pedestal
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
26 Pedestal 1035+20
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
27 Pedestal 1040+20
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
28 Pedestal 1042+00
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
29 Pedestal 1045+25
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
30 Pedestal 1047+40
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
31 Pedestal 1048+78
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
32 Pedestal 1052+18
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
33 Pedestal 1055+50
/ 30’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
34 Pedestal 1056+80
/ 35’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch & side drain 1 0 1
35 Pedestal 1058+30
/ 40’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 08/1/2023
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
6 pair aerial drop wire
(ADW)
1063+75
/ 51’ LT
1063+80
/ 40’ RT
Removal ADW
Placement &
Activation of new cables
1 0 1
37 25 BT
1063+80
/ 40’ RT
1066+80
/ 26’ RT
Removal BT cable where accessible
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
6 pair aerial drop wire
(ADW)
1064+25
/ 27’ LT
1065+30
/ 33’ RT
Removal ADW
Placement &
Activation of new cables
1 0 1
39 Pedestal 1065+30
/ 33’ RT
NA Remove Pedestal
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
6 pair buried drop wire
(BDW)
1063+75
/ 53’ LT
1066+82
/ 30’ RT
Bore BDW & splice for connectivity
Staking for drainage, R/W & sidewalk 1 0 1
41 25 BT
1134+90
/ 30’ LT
1134+90
/ 70’ LT
Hold, Protect & Adjust
BT during construction
Staking & excavation for side drain, ditch, & sidewalk
1 0 1
42 100 BT
1172+80
/ 26’ RT
1174+00
/ 26’ RT
Hold, Protect & Adjust
BT during construction
Staking & excavation for ditch 1 0 1
43 Pedestal 1173+95
/ 27’ RT
NA
Adjust Pedestal to final grade
Staking & grading of ditch 1 0 1
44 25 BT
503+70 /
65’ RT
514+30 /
67’ RT
Bore BT & splice for connectivity
Staking for drainage, R/W & sidewalk 1 0 3
45 25 BT
503+70 /
65’ RT
514+30 /
65’ RT
Removal cable where accessible
Placement &
Activation of new cables & removal of hard surfaces
1 0 2
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 08/1/2023
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
46 Pedestal 507+00 /
65’ RT
NA Remove Pedestal
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
47 Pedestal 510+40 /
65’ RT
NA Remove Pedestal
Placement &
Activation of new cables & removal of hard surfaces
1 0 1
48 100 BT
514+25 /
65’ RT
514+45 /
40’ RT
Hold, Protect & Adjust
BT 100 during construction
Staking of mast arm foundation & removal of hard surfaces
| 2024-03-15T14:08:06-0400 | |