24-8243_Bid_Schedule.xlsx
XLSX spreadsheet 93 KB Posted
- Attached to
- Naples Depot Museum Hurricane Ian Repairs
- Solicitation number
- 24-8243
- Issued by
- Collier County, Florida
About this file
The provided document is a Bid Schedule for the Naples Depot Museum Hurricane Ian Repairs (ITB No. 24-8243) issued by Collier County, Florida. The project involves comprehensive historical restoration and construction work at 1051 5th Ave S, Naples, FL, focusing on repairs necessitated by Hurricane Ian. The bid is scheduled for release on August 22, 2024, with sealed bids due by October 7, 2024, at 3:00 p.m. local time. A non-mandatory pre-bid meeting and site visit are planned for September 5, 2024, at 10:00 a.m. at the project location. The bid covers multiple construction divisions including general requirements, demolition, metals, woods, thermal protection, openings, finishes, specialties, fire suppression, plumbing, HVAC, electrical, and communications work.
The bid schedule includes a base bid and ten add/deduct alternates, with award criteria based on the lowest base bid plus selected alternates. Specific work items include replacing and repairing various museum cases, exhibit displays, and infrastructure components such as lobby desks, station master cases, baggage room cases, and video wall installations. Alternates cover additional scope items like baggage car repairs, platform reconstructions, HVAC upgrades, and exhibit-related modifications. Prospective bidders are required to register on the Collier County procurement portal to obtain complete bid documents, with no explicit mention of funding sources or contract term length.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule
| Naples Depot Museum Hurricane Ian Repairs |
| Construction ITB No. 24-8243 |
| BID SCHEDULE |
| PROJECT ADDRESS: 1051 5th Ave S, Naples, FL 34102 |
| AWARD CRITERIA: Lowest Base Bid Plus Selected Alternates |
| Plan Sheet No. | Scope Description | Unit | Qty | Total |
| Historical Restoration Work, Building and Exterior Site Repairs | ||||
| A0-0 through A4-2; M0-1through M2-1; E0-1 through E5-1; S-1 | Division 1 - General Requirements | LS | 1 | |
| Division 2 - Demolition/Existing Conditions | LS | 1 | ||
| Division 5 - Metals | LS | 1 | ||
| Division 6 - Woods, Plastics, and Composites | LS | 1 | ||
| Division 7 - Thermal and Moisture Protection | LS | 1 | ||
| Division 8 - Openings | LS | 1 | ||
| Division 9 - Finishes | LS | 1 | ||
| Division 10 - Specialties | LS | 1 | ||
| Division 21 - Fire Suppression | LS | 1 | ||
| Division 22 - Plumbing | LS | 1 | ||
| Division 23 - HVAC | LS | 1 | ||
| Division 26 - Electrical | LS | 1 | ||
| Division 27 - Communications | LS | 1 | ||
| Contents | ||||
| A4-3 | Replace Lobby Desk | LS | 1 | |
| A4-3 | Replace Station Master Case 1 | LS | 1 | |
| A4-3 | Replace Station Master Case 2 | LS | 1 | |
| A4-3 | Replace BPWR Case 3 | LS | 1 | |
| A4-3 | Replace BPWR Case 4 | LS | 1 | |
| A4-3 | Replace BPWR Case 5 | LS | 1 | |
| A4-3 | Replace REA Case 6 | LS | 1 | |
| A4-3 | Replace REA Case 7 | LS | 1 | |
| A4-3 | Replace REA Case 8 | LS | 1 | |
| A4-3 | Repair REA Case 9 | LS | 1 | |
| A4-3 | Replace Baggage Room Case 10 | LS | 1 | |
| A4-3 | Replace Baggage Room Case 11 | LS | 1 | |
| A4-3 | Replace Baggage Room Case 12 | LS | 1 | |
| A4-3 | Replace Baggage Room Case 13 | LS | 1 | |
| A4-3 | Replace Baggage Room Case 14 | LS | 1 | |
| Total Base Bid | $0.00 |
| Add (+) / Deduct (-) Alternates | ||||
| Plan Sheet No. | Scope Description | Unit | Qty | Total |
| A4-4 | ADD ALTERNATE 1: Baggage Car (Green) - Repair Handrail, Stairs and Platform | LS | 1 | |
| A4-4 | ADD ALTERNATE 2: Baggage Car (Green) - Replace Handrail, Stairs and Platform | LS | 1 | |
| A4-4 | ADD ALTERNATE 3: Baggage Car (Green) - Replace Air Conditioning Unit | LS | 1 | |
| A4-4 | ADD ALTERNATE 4: Silver Train Car HVAC Platforms | LS | 1 | |
| A4-4 | ADD/DEDUCT ALTERNATE 5: Replace Station Master Case 2 with Modified Design | LS | 1 | |
| A4-4 | ADD/DEDUCT ALTERNATE 6: REA Case 9 (Canoe Exhibit) on new Platform | LS | 1 | |
| A4-4 | ADD ALTERNATE 7: Station Master: Replace Video Wall with 8 TV's | LS | 1 | |
| A4-4 | ADD ALTERNATE 8: Replace Video Wall with Modified Design - in Lobby with 4 TV's | LS | 1 | |
| A4-4 | ADD/DEDUCT ALTERNATE 9: Baggage Room Case 12: Construct New Platform | LS | 1 | |
| A4-4 | ADD ALTERNATE 10: Replace REA Luggage Display with Platform | LS | 1 | |
| Total Add/Deduct Alternates | $0.00 |
Total Base Bid + All Add/Deduct Alternates $0.00