24-43 Addendum 03 05-19-2026.pdf
PDF 4 MB Posted
- Attached to
- Forest Hill Nature Center - New Building
- Solicitation number
- RFP GIR 260000001926 5
- Issued by
- Ingham County, Huntington Woods City, Michigan
About this file
This file contains Addendum #3, a Bid Proposal Form, and a Questions & Answers document for a construction contract issued by Roger L. Donaldson, AIA P.L.C. on behalf of the Gratiot-Isabella Residential Educational Service District (RESD) for the Forest Hills Nature Center new building project located at 11297 N. Rich Road, Alma, Michigan 48801. The project, designated as Project #24-43, involves construction of a new nature center with demolition of two existing structures and is divided into two phases: Phase 1 includes the new nature center and demolition of existing structures, while Phase 2 includes additional classrooms and hallway additions. Addendum #3 was issued on May 19, 2026, following Addendum #1 (May 13, 2026) and Addendum #2 (May 18, 2026), and includes modifications to door frame schedules, mechanical room fire dampers, electrical fixture specifications, smoke detector removals, fire alarm device replacements, and circuit designations for mechanical equipment. Bids are due on May 26, 2026, at 2:00 p.m. local time at the Gratiot-Isabella RESD office located at 1131 E. Center, Ithaca, Michigan 48847. The contractor must note receipt of all addenda on the proposal form, and failure to do so may result in bid disqualification. The project is anticipated to begin in August 2026 and is expected to take 12 to 18 months depending on product delivery schedules, with the contractor having 24-hour access to the site.
The bid proposal requires separate pricing for Phase 1, Phase 2, and a combined Phase 1 & Phase 2 option, with pricing presented in both words and figures. Three alternates are available: Alternate #1 for asphalt shingles roofing, Alternate #2 for a geothermal system in lieu of propane and cooling tower, and Alternate #3 for a new well installation. The contractor is responsible for site control and coordination of all trades, with all costs included in the bid. A $10,000 allowance is required for asbestos testing and abatement, and a $40,000 allowance for water filter and water softener equipment and installation. The contractor must obtain temporary power from Consumers Energy and cover all associated costs, provide all bonds (100% Performance & Payment and 5% Bid Bond), and carry builders risk insurance. Change order work performed by the contractor's own forces includes a 5% markup for overhead and profit, while subcontracted work includes a 5% markup on the subcontract sum. The project is not subject to prevailing wage requirements and is not a "Buy America" project. No liquidated damages apply to this contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Member International Code Council U.S. Green Building Council
American Institute of Architects Association of Licensed Architects National Fire Protection Association National Frame Builders Association
Construction Specifications Institute National Council of Architectural Registration Boards
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011 email voice
D E S I G N I N G A B E T T E R F U T U R E
ROGER L. DONALDSON, AIA P.L.C.ROGER L. DONALDSON, AIA P.L.C.ROGER L. DONALDSON, AIA P.L.C.ROGER L. DONALDSON, AIA P.L.C.
ARCHITECTARCHITECTARCHITECTARCHITECT
ADDENDUM #3
PURPOSE:
This addendum is issued for the purpose of modifying and/or clarifying the original plans and specifications and shall take precedence over them. This addendum forms a part of the Contract Documents.
All work included herein shall be in accordance with the original plans and specifications except as specifically noted herein. All incidental items required to provide the following modifications shall be included even though not specifically described.
This addendum is being submitted to the State of Michigan SIGMA website.
Receipt of this addendum shall be noted on the Proposal Form in the appropriate locations. Failure to note receipt of any addendum may disqualify the Bidder.
Note: Addendum items are consecutively numbers.
Addendum #1 issued May 13, 2026 Items 1-19
Addendum #2 issued May 18, 2026 Items 20-29
ITEMS INCLUDED WITH ADDENDA:
ADDENDUM #3 ................................................................................................... Issued 05/18/2026
SECTION 00 41 13 BID PROPOSAL FORM .............................................................. Reissued 05/19/2026
QUESTIONS & ANSWERS .............................................................................................. ISSUED 05/13/2026
DRAWING SHEET M-702 .................................................................................... REIssued 05/19/2026
DRAWING SHEET E-100 ..................................................................................... REIssued 05/19/2026
DRAWING SHEET E-500 ..................................................................................... REIssued 05/19/2026
DRAWING SHEET E-700 ..................................................................................... REIssued 05/19/2026
30. SHEET A4.2 ROOM FINISH SCHEDULE: Under Remarks, change reference to “Note #4” to “Note #3”.
31. SHEET A4.2 DOOR & FRAME SCHEUDLE: Change
a. Door 102 to Frame VIII.
b. Door 108A to Frame V.
c. Door 110 to Frame V.
d. Door 111A to Frame V.
e. Door 1112A to Frame V.
f. Door 201 to Frame VIII.
g. Door 202 to Frame VII.
h. Door 202A to Frame VII.
i. Door 203 to Frame VIII.
j. Door 204A to Frame V.
k. Door 207A to Frame V.
32. SHEET M-702 (SHEET RE-ISSUED):
a. Added a fire damper at 114-Mechanical room wall to Outside Air duct serving HP-4.
33. SHEET E-100 (SHEET RE-ISSUED):
a. Added equals fixture for fixture types “LH”, “LJ”, “LL”, “XA”, and “XB”.
b. Modified part number for fixture type “LJ” to provide a more budget friendly exterior fixture.
34. SHEET E-500 (SHEET RE-ISSUED):
a. Modified drawings to remove smoke detectors in Hall 124, Entry Hall 102, and Hall 202.
b. Modified drawings to add/remove various fire alarm devices.
c. Modified drawings to show circuit designation for mechanical equipment ERV-3.
d. Modified drawings to replace horn & strobe fire alarm devices for speaker & strobe fire alarm devices per code requirements.
35. SHEET E-700 (SHEET RE-ISSUED):
NEW NATURE CENTER
GRATIOT-ISABELLA RESD
FOREST HILLS NATURE CENTER
11297 N. RICH ROAD
ALMA, MICHIGAN 48801
ARCHITECTS PROJECT #24-43
Date: May 19, 2026
FOREST HILLS NATURE CENTER3 Project #24-43 d:\projects\clients\24\24-43\24-43 bidding\addendum 3\24-43 addendum 03.docx
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011 email voice
D E S I G N I N G A B E T T E R F U T U R E
ROGER L. DONALDSON, AIA P.L.C.ROGER L. DONALDSON, AIA P.L.C.ROGER L. DONALDSON, AIA P.L.C.ROGER L. DONALDSON, AIA P.L.C.
ARCHITECTARCHITECTARCHITECTARCHITECT
a. Modified drawings to show circuit designation for mechanical equipment GFU-1.
b. Modified drawings to show carbon monoxide detector in mechanical room.
END OF ADDENDUM #3
GRATIOT-ISABELLA RESD
NEW NATURE CENTER - FOREST HILLS NATURE CENTER
ROGER L DONALDSON, AIA P.L.C.
PROJECT #24-43 00 41 13 - 1
SECTION 00 41 13
BID PROPOSAL FORM
BIDDERS NAME: _________________________________________________________
LEGAL ADDRESS: _________________________________________________________
TELEPHONE NO.: _________________________________________________________
FACSIMILE NO.: _________________________________________________________
EMAIL ADDRESS: _________________________________________________________
CONTACT NAME: _________________________________________________________
CONTACT MOBILE PHONE _________________________________________________________
PROPOSAL FOR: ALL TRADES CONSTRUCTION WORK
PROJECT NAME: GRATIOT-ISABELLA RESD
NEW NATURE CENTER
ROGER L. DONALDSON, AIA P.L.C.
PROJECT #24-43 - FOREST HILLS NATURE CENTER
11297 N. RICH RD
ALMA, MICHIGAN 48801
PROPOSAL
In response to your invitation to bid, the undersigned submits the following offer to enter into a contract with you and extends this offer for 90 calendar days subsequent to the opening of bids. This offer has been prepared after our examination of the complete plans and specifications, together with their related documents, and our examination of the site and conditions surrounding the construction of the proposed work including the availability of materials, equipment and labor. Included in this offer are all costs necessary to complete the
ALL CONSTRUCTION WORK in accordance with the contract documents prepared by Roger L. Donaldson, AIA P.L.C. within the time set forth herein for the sum of:
Bids Due – May 26, 2026 - 2:00 pm pm local time
GRATIOT-ISABELLA RESD – 1131 E. CENTER, ITHACA, MI 48847
ADDENDUM SCHEDULE:
The above proposed bids and schedule includes the following addenda:
No. 1 dated No. 2 dated No. 3 dated
BID PROPOSALS:
Contractor shall submit a separate Proposal Number for all Trades for that Project Work is to be performed. Contractor is not required to submit a proposal for each project.
PROJECT #24-43 - NEW NATURE CENTER
FOREST HILLS NATURE CENTER - PHASE 1
Provide all work for New Nature Center and Demoltiono of 2 existing structures and related Work:
Dollars
(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)
The undersigned hereby agrees to complete the above buildings area work within calendar days.
PROJECT #24-43 - NEW NATURE CENTER
FOREST HILLS NATURE CENTER – PHASE 2
Provide all work for additional classrooms and hallway for New Nature Center and related Work:
Dollars
(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)
The undersigned hereby agrees to complete the above buildings area work within calendar days.
SECTION 00 41 13
BID PROPOSAL FORM
GRATIOT-ISABELLA RESD
NEW NATURE CENTER - FOREST HILLS NATURE CENTER
ROGER L DONALDSON, AIA P.L.C.
PROJECT #24-43 00 41 13- 2
PROJECT #24-43 - NEW NATURE CENTER
FOREST HILLS NATURE CENTER – COMBINED PHASE 1 & PHASE 2
Provide all work for New Nature Center and Demoltiono of 2 existing structures and related Work:
Dollars
(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)
The undersigned hereby agrees to complete the above buildings area work within calendar days.
Alternates
ALTERNATE #1 PROJECT #24-43 - NEW NATURE CENTER
ALTERNATE #1 – ASPHALT SHINGLES
Provide Asphalt Shingles, and related work as shown, (Add/Deduct ) $
Dollars
(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)
If awarded this Alternate the undersigned hereby agrees to complete the work within (additional / decreased) calendar days, ALTERNATE #2 PROJECT #24-43 - NEW NATURE CENTER
ALTERNATE #2 – GEOTHERMAL SYSTEM
Provide all work for providing a Design/Build Geothermal System instead of Propane & Cooling Tower
(Add/Deduct ) $
Dollars
(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)
If awarded this Alternate the undersigned hereby agrees to complete the work within (additional / decreased) calendar days, ALTERNATE #3 PROJECT #24-43 - NEW NATURE CENTER
ALTERNATE #3– NEW WELL
Provide alternate pricing for providing and installing a new well, pump, piping, pressure tank, and all associated accessories for the building.
(Add/Deduct ) $
Dollars
(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)
If awarded this Alternate the undersigned hereby agrees to complete the work within (additional / decreased) calendar days, FORFEITURE OF BID SECURITY
If within the 90 days this offer is valid, a letter is sent notifying the undersigned of the acceptance of this proposal, the undersigned agrees to deliver within the 10 succeeding days surety bonds in the form specified or will forfeit the enclosed certified or cashier's check or bid bond which accompanies this proposal.
FEE FOR CHANGES IN THE WORK
The undersigned hereby agrees to perform all additional changes in the work ordered by the Owner on the basis of reasonable expenditures, plus reasonable allowance of said cost for overhead and profit. Cost shall be limited to the following: Cost of materials, including sales tax and cost of delivery; cost of labor, including social security, old age and unemployment insurance and fringe benefits required by agreement or custom; workers' or workmen's compensation insurance; bond premiums; rental value of equipment and machinery; and the additional costs of supervision and field office personnel directly attributable to the change.
The undersigned hereby agrees to charge the following fees, based on a mark-up percentage of the actual cost for overhead and profit combined, as stated hereinafter:
- For all additional work performed by the contractor's own forces, a fee of 5% percent of the actual cost as defined above.
GRATIOT-ISABELLA RESD
NEW NATURE CENTER - FOREST HILLS NATURE CENTER
ROGER L DONALDSON, AIA P.L.C.
PROJECT #24-43 00 41 13- 3
- For all additional work subcontracted by the contractor, a fee of 5% percent of the subcontract sum for management, overhead and profit.
JOB CONTROL AND COORDINATION
If awarded the All Trades Construction Work Contract, the undersigned will assume control of the site and will coordinate the work of all the trades. All costs of controlling the site and coordinating the work of the subcontractors are included in this proposal.
SUBCONTRACTOR LISTING
The following is a list of the subcontractor(s) that will be performing work or manufacturer supplying material(s) on this project:
Excavation ___________________________________________
Building Structures ___________________________________________
Concrete ___________________________________________
Mechanical ___________________________________________
Plumbing ___________________________________________
Electrical ___________________________________________
Fire Alarm ___________________________________________
REGULATORY REQUIREMENTS
It is the Contractor's responsibility to confirm that all subcontractors are properly licensed and that all necessary permits are obtained before starting work.
The Owner reserves the right to reject any subcontractor not considered competent to prosecute the work. The Owner representative (s) may request the removal of any contracted person who is deemed unfit to perform the specified work in a competent and professional manner.
The site will be available for the contractor will have full access to the building, 24 hours a day..
The contractor will take every precaution to minimize the migration of dust and debris and to minimize noise where possible. The corridors will remain free of stored materials and debris during business hours. The Contractor will remove all debris created by this contract from the premises at the end of each workday.
If awarded this Contract, the undersigned agrees to commence work immediately upon receipt of Notice to Proceed.
In submitting this Proposal, it is understood that the right is reserved by the Owner to reject any and all Proposals.
The Owner reserves the right to accept or reject all alternates or to accept any one or more alternates without accepting those remaining.
TIME OF COMPLETION
1. Completion in general is defined as all work required and included in the Bid Documents, Specifications, Drawings, Federal and State Regulations, including clean-up, restoration, acceptable visual inspections, completion of change orders approved by the Owner, Architect and Contractor and do not add days to the construction calendar.
2. The Contractor agrees that by submitting a Bid, for base bid, to complete the project within the stipulated number of day to complete using regular and premium work hours as required to complete the project.
3. Contractor realizes he may need to work multiple shifts, weekends and holidays. Any premium wages are included in his Bid.
4. Days are noted as calendar days.
5. The Contractor has full access to the site during all hours.
SIGNATURE
The bidder declares the following legal status in submitting this proposal: (check one)
( ) A Corporation (INC or LLC) organized and existing under the laws of the state of Michigan, ( ) A Partnership, ( ) An Individual doing business as .
Respectfully submitted, By:
Title:
Date:
GRATIOT-ISABELLA RESD
NEW NATURE CENTER - FOREST HILLS NATURE CENTER
ROGER L DONALDSON, AIA P.L.C.
PROJECT #24-43 00 41 13- 4
Fed. Employer Identification No.:
State License No.:
END OF SECTION 00 41 13
GRATIOT-ISABELLA RESD
NEW NATURE CENTER - FOREST HILLS NATURE CENTER
ROGER L DONALDSON, AIA P.L.C.
PROJECT #24-43 00 41 13- 5
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011
RRRROGER OGER OGER OGER L.L.L.L. DDDDONALDSONONALDSONONALDSONONALDSON,,,, AIAAIAAIAAIA P.L.C.P.L.C.P.L.C.P.L.C.
AAAARCHITECTRCHITECTRCHITECTRCHITECT
Member International Code Council
American Institute of Architects Association of Licensed Architects
National Fire Protection Association National Frame Builders Association
Construction Specifications Institute National Council of Architectural Registration Boards
NEW NATURE CENTER
GRATIOT-ISABELLA RESD
FOREST HILL HATURE CENTER
11297 N. RICH ROAD
ALMA, MICHIGAN 48801
ARCHITECTS PROJECT #24-43
DATE: May 19, 2026
Questions & Answers
The following clarifications, modifications and/or revisions to the above project shall be considered a part of the original specifications:
1. What is the project Schedule Response: Plan on Starting by August. Project is likely a 12-18 month project depending on product delivery schedules.
2. Is this a “Buy America” project?
Response: No
3. Who will be responsible for contacting and payment for the power company to relocate the existing Power Pole(s)?
Response: Contractor or Electrical Contractor
4. Do you have a preference for a well drilling contractor, I assume this is by GC?
Response: Owner has used Trayers out of Vestaburg, but not mandatory to use them.
5. Are there any Liquidated Damages on the project?
Response: No
6. Builders Risk to be by Contractor or the owner?
Response: By Contractor
7. What are the requirements for temp power on the buildings Response: 240/120 volt, single phase, 100 amps to the granary building plus whatever power is required for new construction.
8. Has consumers energy been contacted for power removal/temp power?
Response: Not for temporary power
9. Is contractor to pay for temp power? If so, what are the past couple months of usage on buildings so they can be calculated into price?
Response: Yes
10. Is there an asbestos report or does contractor need to include report and allowance for abatement?
Response: Provide an $10,000 Allowance for the report and any abatements that is required.
11. To confirm only bonds on project are 100% Performance & Payment and 5% Bid Bond?
Response: Refer to Section 00 52 24 AIA A101- Exhibit A for insurance and bond requirements.
12. On the Forest Hills Nature Center the plans call for 84’7” trusses in 1 piece. Both of my truss suppliers I work with can’t/won’t make them or ship them. Wondering how you want me to approach that.
d:\projects\clients\24\24-43\24-43 bidding\addendum 1\24-43 question answer.docx
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011
RRRROGER OGER OGER OGER L.L.L.L. DDDDONALDSON ONALDSON ONALDSON ONALDSON AIAAIAAIAAIA PLCPLCPLCPLC
Response: We can accept 2-piece trusses, piggyback trusses may be used the top over 2x4 purlins as directed by the Truss Engineer.
13. The exterior walls call for 7/16 OSB with Rigid R5 insulation or zip. My zip options are R3.6 or R6.6. which would you prefer?
Response: Code minimum is R-5, so we need to use the R6.6.
14. I see in Specification Section 84200-Aluminum Glass Doors it appears Cross Aluminum is a sole supplier. Will any other Door Suppliers be considered as equal such as Specialite, Vale Doors, Kawneer, or Tubelite?
Response: Main Entrance Door to be Cross, Kawneer, Tubelite, SpecialLite or Vale
15. Regarding the FRP Doors called out in the door schedule, I am not seeing a FRP Door specification. Will Specialite or Vale Doors be viable suppliers for the FRP Doors.
Response: Yes, Special Lite is basis of design, Spec to be issued with Addendum #1.
16. At Doors 118A and 201, a hollow metal door frame is called for. Shouldn’t these door frames be Aluminum, typical to the rest of the FRP Door /aluminum frames in the door schedule?
Response: FRP Door in AL frame.
17. Confirm requirements / responsibility for third party testing, commissioning, etc. Or if any scope will be owner direct.
Response: Contractor is responsible
18. Confirm whether Owner or Contractor carries geotechnical/testing agency costs, including SME observations, proofrolling, compaction testing, and special inspections.
Response: Owner has paid for test to date; Contractor will include cost for during construction
19. Clarify base-bid assumptions for unsuitable soils, undercutting, existing fill removal, proofrolling, engineered fill, and unit prices/allowances.
Response: See Section 00 31 32 - Geotechnical Data
20. Confirm all allowances to include in base bid, including testing, inspections, controls, signage, utility work, or owner-directed items.
Response: Contractor is responsible
21. Confirm responsibility for temporary utilities, temporary heat, snow removal, site access, staging, fencing, and site security.
Response: Contractor is responsible
22. Identify existing utilities to remain, be relocated, abandoned in place, or removed; provide a utility responsibility matrix.
Response: Utility is shown on the Site Civil sheets developed by KEBS, sheets 1 through 9
23. Confirm demolition scope for existing Nature Center and adjoining/northern storage or ancillary building, including foundations, slabs, utilities, septic, salvage, disposal, and restoration.
Response: Contractor to remove all and restore surfaces with grass seeding. Existing Septic field may be abandoned in place.
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011
RRRROGER OGER OGER OGER L.L.L.L. DDDDONALDSON ONALDSON ONALDSON ONALDSON AIAAIAAIAAIA PLCPLCPLCPLC
24. Confirm whether hazardous material testing has been completed. Age and condition of existing buildings and infrastructure isn't clear from documents included.
Response: No testing has been completed. Provide an $10,000 Allowance for the report and any abatements that is required.
25. Clarify asphalt shingle alternate scope, including underlayment, ice/water shield, flashing, gutters, fascia/trim, snow guards, roof penetrations, warranty, and structural/loading changes.
Response: See Section 07 31 13 Asphalt Shingles.
26. Clarify propane provider scope and cost responsibility, including tank lease/purchase, pad/protection, trenching/backfill, regulator, piping limits, coordination, startup, and initial fuel fill.
Response: The propane provider shall provide and install the propane tank, regaulator, piping, and all associated accessories between the tank and regulator. Tank to be filled full.
27. Confirm well provider scope and cost responsibility, including pressure tank, piping/accessories between well and pressure tank, controls, power, startup, and where plumbing scope begins.
Response: The well drilling contractor is responsible for extending a new 2” water line from the existing well to the new building. The contractor is responsible for providing and installing the piping, pressure tank, and all associated accessories. Plumbing contractors scope starts after the pressure tank.
See Addedum #1, Note added to Sheet C-400
28. Confirm water filter and water softener basis of design and whether an addendum will be issued before bid; if not, provide required allowance.
Response: Provide $40,000 allowance for equipment and labor to install water filter and water softener.
29. Confirm Owner vs Contractor responsibility for access control software, credentials, programming, cloud/subscription fees, commissioning, and training.
Response: Contractor to furnish and install all equipment, wiring, and conduit and to coordinate integration into the RESD's existing multi-building system. New software for this building, commissioning and training are to be provided by the contractor. Coordinate programming with owner. All costs associated with this project are to be included in the bid.
30. Can you please specify the window materials, or is there a desired manufacturer Response: Anderson “A” Series, Spec to be issued with Addendum #1.
31. Can you please specify the desired fence around the electrical equipment.
Response: See KEBS Drawings, Sheet 9, “TYPICAL WOOD SCREEN FENCE ELEVATION”
32. Will there be a landscaping plan, or should we include an allowance?
Response: By Owner
33. Is there a spec for the exterior signage, or is this owner provided?
Response: By Owner
34. Is this a prevailing wage project?
Response: No
35. The wood door veneer sates cut red oak, but this cut is not available in red oak. Only plain sliced is available for this door is that acceptable?
Response: Yes, plain sliced is acceptable
36. Door 118A - Reads FRP to HM but is an AL callout on drawing, Please Confirm the correct door type.
Response: FRP Door in AL frame.
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011
RRRROGER OGER OGER OGER L.L.L.L. DDDDONALDSON ONALDSON ONALDSON ONALDSON AIAAIAAIAAIA PLCPLCPLCPLC
37. Door 201 - Reads FRP to HM but is an AL callout on drawing. Please Confirm the correct door type.
Response: FRP Door in AL frame.
38. Door113 shows 1 hour rating but that is actually 114. Please confirm which door is fire rated.
Response: Yes, Door 113 should be 1 hour rated.
39. What finish level of concrete polishing is required.
Response: Class B “salt & pepper”, Level 3 (gloss) finish, Spec to be issued with Addendum #1.
40. Will the ductwork (spiral) be painted?
Response: No, exposed
41. Will the T&G need to be stained and finished?
Response: Yes
42. Will the exposed trusses need and stain and finish?
Response: Yes
43. What will be the finish on the FRP doors?
Response: FRP Doors are prefinished
44. Door #118A and 201 – Frames and door slab styles do not match.
Response: FRP Doors in AL frames
45. We would like to know if there is a spec for 27 0000 or bid category or if the owner installs this.We need clarification on the key notes for Print E-500.
Response: Keyynotes #9, 10 addeed, Sheet E-500 Reisssued with Addendum #1.
46. I can’t find the thickness of the Tectum ceiling panels, can you please provide that information?
Response: Tectum Pinacle Panels are standard 1” Thick.
Issued with Addendum #3:
47. Are the Tectum panels natural and getting painted or are they factory white? Are the panels square edge or beveled?
Response: The Tectum Finale PB panels come standard with beveled edges and have 26 available colors to select from..
48. What is the Occupany Type and Number for the project.
Response: Occupancy Type: E-Educational, Combined Phase 1 and 2 Occupancy of 250.
49. Specs reference Fire suppression.
Response: No Fire Suppression is required.
50. A1.1 references section 6/A3.3. This detail does not exist on sheet A3.3.
Response: Section 6/A3.3 is shown on Sheet A3.2.
51. A1.1 references section 5/A3.1, but no detail exist Response: Section 5/A3.1 is shown on Sheet 3.2, Detail 5/A3.2
52. Addendum sheet A3.3 shows a blow-up on the outside wall, but not detail is referenced Response: Typical Exterior wall, Detail 1/A5.1
53. Is there a detail for the canopy columns
4787 Tartan Lane • Holt, Michigan 48842-1935
RogerAIA@comcast.net (517) 694-0011
RRRROGER OGER OGER OGER L.L.L.L. DDDDONALDSON ONALDSON ONALDSON ONALDSON AIAAIAAIAAIA PLCPLCPLCPLC
Response: Not show, basic 8” Concrete Masonry base with stone veneer finish and limestone cap. Steel Column to extend to top of Concrete Foundation Pier.
54. Frame elevation IX – Does not match the building elevations Response: Elevation does not show the perimeter frame that is shown on Elevation IX.
55. FrIs the clerestory opening shown on A2.1 West Elevation to be storefront?
Response: Windows to match the fixed windows below, Anderson Series “A” Stationary or equal.
EG-1 400
20"x10" ---
EG-1 400
20"x10" ---
RG-1 325
22"x10" ---
RG-1 325
22"x10" ---
RG-1 325
22"x10" ---
EG-1 400
20"x10" ---
STORAGE
CLOSET
STORAGE
CLOSET
CLOSET
STORAGE
HALL
EA
EA EA
14" Ø
10"x8"
10"x8"
(ATTIC)
10"x8"
OA
SA
OA
10"x10" (ATTIC)14"x12"
(ATTIC)
EAEA
10"x8" 20"x16"EA UP TO RLH-1
SD-1 50
6"Ø ---
HP-5HP-6
HP-7
8"x6"
SD-1 150
8"Ø TYP. 3
12"x12"
(ATTIC)
16"x12"
(ATTIC)
14"x10"
(ATTIC)
12"x8" OA DN 12"x8" OA DN
12"x8" OA DN 20" Ø 20" Ø
20"x16" OA
UP TO IAH-1
OA
SA
18"x12"
(ATTIC)
10"x10"
(ATTIC)
ERV-1
(2150 CFM)
SA
SA
SA
OA
14" Ø
14" Ø
EG-1 250
12"x10" ---
EG-1 100
6"x6" ---
14"x10"
(ATTIC)
14"x12"
16"x10" RA DN
16"x10" RA DN 16"x10" RA DN
8" Ø
8" Ø 10"x10"
(ATTIC)
6"x6" (ATTIC) 6"x6"
(ATTIC)
12"x8"
(ATTIC)
12"x8"
(ATTIC)
14"x12"
(ATTIC)
16" Ø
14"x12"
10"x10"
(ATTIC)
6"x6"
18"x18" SA DN 18"x18" SA DN
8"x8"
(ATTIC)
18"x18" SA DN
HVAC KEY NOTES
INSTALL INTAKE/RELIEF AIR HOOD AND ASSOCIATED CURB ON
ROOF AT LOCATION SHOWN. INTAKE AIR HOOD SHALL BE
INSTALLED AT LEAST 10' AWAY FROM BUILDING AND PLUMBING
EXHAUST/VENT TERMINATIONS.
INSTALL ENERGY RECOVERY VENTILATOR IN ATTIC AT LOCATION
SHOWN. ASSOCIATED OUTSIDE AIR AND EXHAUST DUCTWORK
SHALL BE INSULATED AND ROUTED THROUGH THE ATTIC FROM
THE ENERGY RECOVERY VENTILATOR TO THE ASSOCIATED
EXHAUST GRILL/HEAT PUMP. COORDINATE THE INSTALLATION
ATTIC ACCESS WITH GENERAL TRADES CONTRACTOR PRIOR TO
CONSTRUCTION. COORDINATE THE UNIT SIZE AND CLEARANCES
WITH THE GENERAL TRADES CONTRACTOR PRIOR TO THE
TRUSSES BEING ORDERED TO CONFIRM THERE IS ADEQUATE
SPACE AND SUPPORT FOR THE UNIT WITHIN THE TRUSS WEBBING.
INSTALL WATER SOURCE HEAT PUMP AT LOCATION SHOWN. LINE
THE FIRST 10' OF SUPPLY AND RETURN DUCTWORK. PROVIDE AND
INSTALL UNIT ON 3' TALL CUSTOM SUPPORT STAND BUILT OUT OF
1-1/2"x1-1/2" ANGLE IRON WELDED TOGETHER. SUPPORT STAND
SHALL NOT INTERFERE WITH UNIT ACCESS OR DUCT/PIPE
CONNECTIONS.
INSTALL WATER SOURCE HEAT PUMP ON 4" CONCRETE PAD AT
LOCATION SHOWN. LINE THE FIRST 10' OF SUPPLY AND RETURN
DUCTWORK.
INSTALL ENERGY RECOVERY VENTILATOR AT LOCATION SHOWN IN
ATTIC. MOUNT TO EXTERIOR WALL
GENERAL NOTES
1. ALL ASSOCIATED ENERGY RECOVERY VENTILATION
DUCTWORK SHALL BE INSULATED.
RA
ERV-2
(850 CFM)
HP-2
EG-1 700
24"x14" ---
RG-1 2350
40"x20" ---
STORAGE
MECHANICAL
EA
OA
HP-3
HP-1
16"x10"
10"x10"
(ATTIC)
L-1 L-2
16"x10"
10"x10"
14"x8" OA DN
14"x8" OA DN14"x8" OA DNOA
SA
18" Ø 18" Ø
20"x14" RA DN20"x14" RA DN
16"x12" RA DN 14"x8"
16"x12"
16"x10" EA
16"x10" EA
& OA DN
16"x10" EA
& OA DN
18"x18" SA DN
18"x18" SA DN
22"x16" RA
EG-1 150
12"x10" ---
-4
F o re st H il ls
N a tu re C en te r N ew N a tu re C en te r
N
R ic h R d
A lm a
M I
S ev il le T o w n sh ip
G ra ti o t C o u n ty
A lm a M ic h ig a n
M A
T R
I X
M-702
1 HVAC ENLARGEMENT - 124 HALL
SCALE: 1/4" = 1'-0"
0 1 5 10
2 HVAC ENLARGEMENT - 110 MECHANICAL
SCALE: 1/4" = 1'-0"
0 1 5 10
FCPS
V
M C
VI
AV
B
C
DC
M
B
KP
SSCP
CR
SS
AS
TS
G
NCC
M P
E
A L B1 B2
S
SRS
X
X
X
CB
EMERGENCY PUSH STATION
CODE BLUE STATION
TVSS
VFD
TRANSIENT VOLTAGE SURGE SUPPRESSION
VARIABLE FREQUENCY DRIVE
GLASS BREAK
DS
DUPLEX RECEPTACLE
TEACHER STATION
ADMINISTRATION STATION
STUDENT STATION
CARD READER
CO CARBON MONOXIDE DETECTOR
H
DOCK LIGHT FIXTURE
CONTROL MODULE
S
TELEPHONE / DATA OUTLET
DUTY STATION
STAFF STATION
STAFF REGISTER STATION
DOME LIGHT
DUAL BED STATION
SINGLE BED STATION
BED / LIGHT INTERFACE
PENDENT INTERFACE
EMERGENCY PULL STATION
MASTER STATION
NURSE CALL CONTROLLER
NURSE CALL
ADDENDUM NOTE
PLAN NOTE
DEMOLITION NOTE
THREE PHASE MOTOR
BELL
AUDIO / VIDEO INPUT
VIDEO INPUT
WALL MOUNTED SPEAKER / CLOCK COMBO
WALL MOUNTED SPEAKERS
DUAL FACE CLOCK
CCTV CONTROL PANELCCTV
SECURITY SYSTEM CONTROL PANEL
KEY PAD
BEAM DETECTOR
MOTION DETECTOR
DOOR CONTACT
CAMERA
MONITOR MODULE
FIRE CONTROL POWER SUPPLY
VISUAL ONLY UNIT
ELECTRICAL SYMBOLS LEGEND
DH
V
S
C
M
I
J
SINGLE RECEPTACLE (120 VOLT)
EMERGENCY RECEPTACLE
DOUBLE DUPLEX RECEPTACLE
SINGLE FACE CLOCK
FLUSH FLOOR BOX
SURFACE FLOOR BOX
SPECIAL EQUIPMENT RECEPTACLE
TELEPHONE OUTLET
DATA OUTLET
POWER POLE
JUNCTION BOX
WALL JUNCTION BOX
PULL (JUNCTION) BOX
UNDERFLOOR JUNCTION BOX
OUTLETS
LIGHT FIXTURE
STRIP FIXTURE
IN-GRADE LIGHT FIXTURE
SPOTLIGHT (number of heads shown) EXIT SIGN (face & direction as shown)
WALL MOUNT LIGHT FIXTURE
CEILING LIGHT FIXTURE
TRACK & FIXTURE
STREET TYPE POLE FIXTURE
POLE MOUNTED LIGHT FIXTURE
EXTERIOR WALL MOUNT LIGHT FIXTURE
WALLPACK LIGHT FIXTURE
SPECIAL PURPOSE LIGHT FIXTURE
HIGH BAY LIGHT FIXTURE
EMERGENCY EGRESS LIGHT FIXTURE
(number of heads shown)
EMERGENCY LIGHT FIXTURE
FIXTURES
SWITCHES
SINGLE-POLE SWITCH
DIMMER SWITCH
TIME SWITCH
KEY SWITCH
MANUAL MOTOR SWITCH
THERMAL OVERLOAD SWITCH
SWITCH WITH PILOT LIGHT
FOUR-WAY SWITCH
THREE-WAY SWITCH
CIRCUITRY and RACEWAYS
UNDERFLOOR DUCT
BUS DUCT
PLUGMOLD AS SPECIFIED
WIREMOLD AS SPECIFIED
FLEXIBLE PIGTAILS/CONNECTIONS
"CONDUIT RUN CONTINUES" INDICATION
END OF CONDUIT RUN, CAP AND STAKE
END OF CONDUIT RUN
HOME RUN (with circuit numbers)
CONDUIT STUB DOWN
CONDUIT STUB UP
CONDUIT INSTALLED
CONDUIT INSTALLED
MECHANICAL
ELECTRIC WATER HEATER
ELECTRIC UNIT HEATER
PIPE TRACE HEATER
RESISTANCE HEATER, KW SHOWN
SINGLE PHASE MOTOR
SOUND and SIGNAL
INTERCOM OUTLET
MICROPHONE OUTLET
TELEVISION OUTLET
CHIME
BUZZER
VOLUME CONTROL
SPEAKER
SERVICE and EQUIPMENT
THERMOSTAT
CAPACITOR
ENCLOSED CIRCUIT BREAKER
TRANSFER SWITCH
WIREWAY
GROUND CONNECTION PER N.E.C.
TELEPHONE TERMINAL BOARD
GENERATOR, KW SHOWN
CURRENT TRANSFORMERS
UTILITY METER, AS REQUIRED
WEATHERHEAD
PANELBOARD, FLUSH MOUNTED
PANELBOARD, SURFACE MOUNTED
COMB. STARTER
MAGNETIC STARTER
FUSED DISCONNECT SWITCH
TRANSFORMER
CONTROL
xxVA connection by x/C) IRRIGATION CONTROLLER (120 volt
LIGHTING CONTACTOR
CONTROL TRANSFORMER
buttons indicated) PUSHBUTTON STATION (number of TIME CLOCK (24 hour U.O.N.)
PHOTOCELL (voltage as required)
HUMIDISTAT
FIRE ALARM
TAMPER SWITCH (furnished by FP/C) FLOW SWITCH (furnished by FP/C)
FIREFIGHTER COMMUNICATION JACK
MAGNETIC DOOR HOLDER
REMOTE INDICATING LIGHT, CLG. MTD.
REMOTE INDICATING LIGHT, WALL MTD.
END OF LINE DEVICE
ANNUNCIATOR PANEL
FIRE ALARM CONTROL PANEL
PULL STATION
SPEAKER & LIGHT
SPEAKER
HORN
DUCT SMOKE DETECTOR
HEAT DETECTOR
SMOKE DETECTOR
HORN & LIGHT
DESIGNATIONS
(by E.C.)
(by others)
TT
FACP
ANN
EOL
G
WW
PC
CT
TS
T
H
TC
IC
F
FC
F
T
1,3
OR
PM
WM
BD
UFD
B
F S
J
J
D
WH
PP
J
SWITCH STYLE OCCUPANCY SENSOROC
DIGITAL TIME SWITCH
POWER PACK
DUAL TECHNOLOGY SENSOR - 360° - 500 SQ FT
DUAL TECHNOLOGY SENSOR - 360° - 1000 SQ FT
ULTRASONIC SENSOR - 360° - 2 CIRCUIT
OCCUPANCY SENSOR / PHOTOCELL
WALL MOUNT DUAL TECHNOLOGY SENSOR
OS5
OS4
T
OS2
OS3
OS1
PP
DUCT SMOKE DETECTORF/S
CEILING MOUNTED WIFI
DIGITAL EQUIPMENT METER, AS REQUIRED
POLE
PUMP
PANEL
P
PNL
PVC
PRV-
P-
PB
POLY VINYL CLORIDE
POWER ROOF VENTILATOR
PULL BOX
GENERAL CONTRACTOR
GROUND
HUMIDIFIERH-
GND
GFI
GC
GROUND FAULT INTERRUPTER
ABBREVIATIONS LEGEND
POWER
SWITCH
RECEPT
SF-
SWBD
TCC
SPEC
SW
RGC
RTU-
PWR
VOLTS
WATTS
UF
V
W
UL
VL
UNO
UH-
TS
TYP
TR
ROOF TOP UNIT
RECEPTACLE
SWITCHBOARD
UNDER FLOOR
SPECIFICATIONS
RIGID GALVANIZED STEEL CONDUIT
UNLESS NOTED OTHERWISE
UNDERWRITERS' LABORATORIES, INC.
TAMPER PROOF RECEPTACLE
TAMPER PROOF SWITCH
TEMPERATURE CONTROL CONTRACTOR
VERIFY LOCATION WITH OWNER
TYPICAL
UNIT HEATER
SUPPLY FAN
WITH
WITHOUT
W/
XFMR
W/O
WP
TRANSFORMER
WEATHER PROOF
HOUR
LIGHT
JUNCTION BOX
LIGHT CONTROL
ISOLATED GROUND
HORSEPOWER
MINIMUM
MOUNT
MAKE-UP AIR UNIT
MOTOR CONTROL CENTER
MAIN LUG ONLY
MOUNTED
MOUNTING
MAXIMUM
LIGHTING
LT FLEX
MTD
MUAU-
MTG
MLO
MIN
MT
MC
MAX
MCC
LTG
IG
LC
LT
IMC
JB
HR
HVAC
HOA
HP
NORMALLY CLOSED
NOT IN CONTRACT
NORMALLY OPEN
NOT TO SCALE
NIGHT LIGHTNL
NTS
NO
NIC
NC
HAND-OFF-AUTO SELECTOR SWITCH
HEATING/VENTILATING/AIR CONDITIONING
INTERMEDIATE METAL CONDUIT
LIQUID TIGHT FLEXIBLE METAL CONDUIT
MECHANICAL CONTRACTOR
HID HIGH INTENSITY DISCHARGE
A
AC
AFF
ACU-
AHJ
AHU-
AS
B-
BC
AIC
ATS
BLDG
CHLR-
CND (C)
CKT BKR
CKT
CUH-
CU-
DISC
DFU-
EF-
EC
DWH-
EBB-
DWG
CT-
EXIST./EX.
EWC
FLEX
FLA
FLR
FSES
FLUOR
EMT
ABOVE FINISHED FLOOR
AIR CONDITIONING UNIT
AMPS
ABOVE COUNTER
AIR HANDLING UNIT
AUTOMATIC TRANSFER SWITCH
AMPS INTERRUPTING CAPACITY
AUTHORITY HAVING JURISDICTION
ABOVE SHELF
BOILER
BUILDING
BELOW COUNTER
CHILLER
DOMESTIC WATER HEATER
CABINET UNIT HEATER
CIRCUIT
CIRCUIT BREAKER
CONDUIT
CONDENSING UNIT
COOLING TOWER
DUCT FURNACE
DRAWING
DISCONNECT
FOOD SERVICE EQUIP. SUPPLIER
ELECTRIC WATER COOLER
ELECTRICAL CONTRACTOR
ELECTRIC BASEBOARD
ELECTRICAL METALLIC TUBING
EXISTING
EXHAUST FAN
FLOOR
FLUORESCENT
FLEXIBLE CONDUIT
FULL LOAD AMPS
EM EMERGENCY
F/S FIRE/SMOKE
FU- FURNACE
4' SURFACE MOUNTED LINEAR FIXTURE.
FIXTURE
MOUNTING
HEIGHT
LIGHT ENGINEDESCRIPTION AND COMMENTSTYPE MANUFACTURER CATALOG NO.
LIGHTING FIXTURE SCHEDULE
LITHONIA
ELITE
OR EQUAL
CSS-L48-ALO3-MVOLT-MIN10-ZT-40K-80CRI
OEC4-LED-3000L/4000L/5000L-DIM10-MVOLT-25K/40K/50K-85
SL2L-XXFT-FLP-80CRI-40K-400LMF-MIN1-MVOLT-NLTAIR2-API
EV1D-A-HE-840-XX-G1-U-FSD-1-W
LDN6-40/10-LO6-MVOLT-GZ1
6DR-L10-8-40-DIM-UNV-O-M-CS
LITHONIA
H.E. WILLIAMS
OR EQUAL
LG
LD
LA
RECESSED LINEAR FIXTURE WITH INTEGRATED OCCUPANCY SENSORS. COORDINATE
FIXTURE RUN LENGTH WITH FLOORPLAN.
6" LED DOWNLIGHT
SURFACE
MOUNTED
3000 LUMENS
25W, 4000K
LED
RECCESSED
1000 LUMENS
9W, 4000K
LED
RECESSED
DIMMING INFO
S2PID-XXFT-MSL8-80CRI-40K-400LMF-I80CRI-140K-I300LMF-MIN1
-FLL-MVOLT-NLTAIR2-APIR-SAPIR
EX2DI-A-HE-840-840-XX-ACXJB-U-OL5-1-W-SNSLM
SUSPENDED LINEAR FIXTURE WITH DIRECT/INDIRECT LIGHTING AND INTEGRATED
SENSORS. COORDINATE FIXTURE RUN LENGTH WITH FLOORPLAN. PROVIDE REQUIRED
SUSPENSION MOUNTING HARDWARE.
700LUMENS/FT
5.1W/FT, 4000K
LED
LC 8'-6" AFF0-10V
400LUMENS/FT
3.14W/FT, 4000K
LED
0-10V
0-10V
4' SURFACE MOUNTED LINEAR FIXTURE WITH 10W EMERGENCY BATTERY PACK.
LITHONIA
ELITE
OR EQUAL
CSS-L48-ALO3-MVOLT-MIN10-ZT-40K-80CRI-E10W
OEC4-LED-3000L/4000L/5000L-DIM10-MVOLT-25K/40K/50K-85-
O-EMG-LED
LAEM SURFACE
MOUNTED
3000 LUMENS
25W, 4000K
LED
S2PID-XXFT-MSL4-80CRI-40K-600LMF-I80CRI-I40K-I300LMF-MIN1
-FLL-MVOLT-1E10WLCP-NLTAIR2-APIR-SAPIR
EX2DI-A-HE-840HO-840-XX-ACXJB-U-OL5-1-W-FSB-SNSLM
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
LBEM
4' SUSPENDED LINEAR FIXTURE WITH DIRECT/INDIRECT LIGHTING, INTEGRATED
SENSORS, AND 10W EMERGENCY BATTERY PACK. PROVIDE REQUIRED SUSPENSION
MOUNTING HARDWARE.
0-10V
900LUMENS/FT
6.6W/FT, 4000K
LED
S2PID-XXFT-MSL4-80CRI-40K-400LMF-I80CRI-140K-I300LMF-MIN1
-FLL-MVOLT-1E10WLCP-NLTAIR2-APIR-SAPIR
EX2DI-A-HE-840-840-XX-ACXJB-U-OL5-1-W-FSB-SNSLM
4' SUSPENDED LINEAR FIXTURE WITH DIRECT/INDIRECT LIGHTING, INTEGRATED SENSORS
AND 10W EMERGENCY BATTERY PACK. PROVIDE REQUIRED SUSPENSION MOUNTING
HARDWARE.
700LUMENS/FT
5.1W/FT, 4000K
LED
LCEM 8'-6" AFF0-10V
SL2L-XXFT-FLP-80CRI-40K-400LMF-MIN1-MVOLT-NLTAIR2-API
-1E10WLCP
EV1D-A-HE-840-XX-G1-U-FSD-1-W-FSB
LDEM
4' RECESSED LINEAR FIXTURE WITH INTEGRATED SENSORS AND 10W EMERGENCY
BATTERY PACK.
400LUMENS/FT
3.14W/FT, 4000K
LED
0-10V
LE
RECESSED 2X4 TROFFER WITH INTEGRATED SENSORS
3000 LUMENS
21W, 4000K
LED
0-10V
LATSM2-A-120-L07-40K-CR90-MFR
H2-L562S-4090-40D
LUMENPULSE
JESCO
OR EQUAL
LH
LED TRACK LIGHTING
700 LUMENS
7W, 4000K
LED
SURFACE0-10V
WHSPR-LCTR-2X4-80CRI-40K-3000LM-MIN1-MVOLT-SWC-
NLTAIR2-PIR
TR24-W-G9-U-OL2-1-W
RECCESSED
RECCESSED
REFER TO
FLOOR PLAN
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
S2PID-60FT-MSL8-80CRI-40K-600LMF-I80CRI-I40K-I300LMF-MIN1
-FLL-MVOLT-NLTAIR2-APIR-SAPIR
EX2DI-A-HE-840HO-840-60-ACXJB-U-OL5-1-W-SNSLM
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
LB60
60' SUSPENDED LINEAR FIXTURE WITH DIRECT/INDIRECT LIGHTING AND INTEGRATED
SENSORS. PROVIDE REQUIRED SUSPENSION MOUNTING HARDWARE.
REFER TO
FLOOR PLAN0-10V
42000LUMENS
396W, 4000K
LED
VIAWETS-D-PYC-HLO-SW-90CRI-500LMF-27K-4FT-UNV-D1
EX3-WET-N-827-XX-BOR-S-U-FSD-1
LUMENWERX
PINNACLE
OR EQUAL
LI
SURFACE MOUNTED WET RATED FIXTURE
2000 LUMENS
23W, 2700K
LED
SURFACE0-10V
WDGE2-LED-P2-27K-80CRI-TFTM-MVOLT
HRM-1-T4TW-16L-27K8-UNV-WM
LITHONIA
NLS
OR EQUAL
LJ
EXTERIOR WALLPACK. 2700K COLOR TEMPERATURE FOR OUTDOOR USE.
1847 LUMENS
19W, 2700K
LED
BUILDING
MOUNTED0-10V
LF
4' SURFACE MOUNTED LINEAR FIXTURE WITH INTEGRATED OCCUPANCY SENSORS.
600LUMENS/FT
4.7W/FT, 4000K
LED
0-10V
S2SD-LLP-XXFT-80CRI-40K-600LMF-SCT-MIN1-FLL-MVOLT-
NLTAIR2-APIR
EV1D-A-HE-840HO-XX-G1-U-FSD-1-W-FSB
SURFACE
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
LFEM
4' SURFACE MOUNTED LINEAR FIXTURE WITH INTEGRATED OCCUPANCY SENSORS AND
10W EMERGENCY BATTERY PACK.
0-10V
S2SD-LLP-XXFT-80CRI-40K-400LMF-SCT-MIN1-FLL-MVOLT-
E10WLCP-NLTAIR2-APIR
EV1D-A-HE-840HO-XX-G1-U-FSD-1-W-FSB
SURFACE
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
600LUMENS/FT
4.7W/FT, 4000K
LED
LQM-S-3-G-MVOLT-EL-HO
EXIT-G-EM-BLK-D
LITHONIA
H.E. WILLIAMS
OR EQUAL
XA
LED EXIT SIGN WITH BLACK FACE AND GREEN LETTERING
LEDUNIVERSAL0-10V
AIP AI PHONE
LEEM
RECESSED 2X4 TROFFER WITH INTEGRATED SENSORS AND 10W EMERGENCY BATTERY
PACK.
3000 LUMENS
21W, 4000K
LED
0-10V
WHSPR-LCTR-2X4-80CRI-40K-3000LM-MIN1-MVOLT-SWC-E10W
NLTAIR2-PIR
TR24-W-G9-U-OL2-1-FSB-W
RECCESSED
MARK ARCHITECTURAL
PINNACLE
OR EQUAL
ERE-GY-T-SQ-WP
BBXWSEHOB
LITHONIA
BEGHELLI
OR EQUAL
XB
LED BATTERY POWERED EXTERIOR EM LIGHTING
LEDUNIVERSAL0-10V
0-10V
0-10V
GENERAL ELECTRICAL NOTES:
1. ALL WORK SHALL BE INSTALLED IN ACCORDANCE WITH THE LATEST ACCEPTED EDITION OF THE NATIONAL
ELECTRICAL CODE, NEC, AND ALL STATE AND LOCAL CODES.
2. COORDINATE THE INSTALLATION OF ALL ELECTRICAL EQUIPMENT AND CONNECTIONS WITH ARCHITECTURAL, STRUCTURAL, MECHANICAL AND EQUIPMENT DRAWINGS.
3. ELECTRICAL CONTRACTOR SHALL PROVIDE AND INSTALL ALL POWER, CONDUITS, CABLETRAY, AND OTHER COMPONENTS AS SHOWN ON THE EQUIPMENT PROVIDER DRAWINGS FOR INSTALLATION OF SYSTEM.
4. "BACK TO BACK" OR THROUGH THE WALL BOXES SHALL NOT BE USED.
5. INSTALL HANDLE LOCK-ON, ON ALL CIRCUIT BREAKERS CONTROLLING NIGHT LIGHT, EMERGENCY LIGHT AND EXIT
LIGHT CIRCUITS.
6. ALL RECEPTACLES SHALL BE HARD USE, SPECIFICATION GRADE.
7. PROVIDE TAMPER RESISTANT RECEPTACLES WHERE REQUIRED BY APPLICABLE CODES.
8. RECEPTACLES INDICATED AS GROUND FAULT CIRCUIT INTERRUPTER TYPE SHALL BE MOUNTED IN AN ACCESIBLE
LOCATION, PER CODE OR PROVIDED WITH A GFCI BREAKER.
9. ALL CONDUCTORS SHALL BE COPPER. ALUMINUM WIRES SHALL NOT BE USED.
10. MINIMUM CONDUIT SIZE SHALL BE 3/4" FOR POWER FEEDS AND 1" FOR DATA FEEDS.
11. FINAL CONNECTION TO ITEMS SUBJECT TO VIBRATION SHALL BE MADE WITH LIQUIDTIGHT FLEXIBLE METALLIC
CONDUIT.
12. 120/208VAC CIRCUIT WIRING FOR ANY ROOM OR AREA MAY BE GROUPED INTO RACEWAYS UNLESS SEPARATE RACEWAYS ARE REQUIRED BY THE NEC. COMPLY WITH NEC REQUIREMENTS FOR CONDUCTOR DERATING.
13. PROVIDE EQUIPMENT GROUNDING CONDUCTORS FOR ALL POWER AND LIGHTING CIRCUITS.
14. ALL LIGHTING AND POWER CONDUCTORS SHALL BE 12 AWG MINIMUM. ALL CONTROL CONDUCTORS SHALL BE
14 AWG MINIMUM OR AS SPECIFIED BY MANUFACTURER.
15. DEDICATED NEUTRAL SHALL BE PROVIDED FOR ALL CIRCUITS. SHARED NEUTRALS ARE NOT ALLOWED.
16. BASIS OF DESIGN IS FOR A COMPLETE ELECTRICAL SYSTEM, INSTALLED PER CODE REQUIREMENTS.
17. PROVIDE AN UNSWITCHED HOT TO ALL EMERGENCY BATTERY PACKS, LIGHTING INVERTERS AND EMERGENCY LIGHTING UNITS AHEAD OF AN LIGHTING CONTROLS FROM THE BRANCH CIRCUIT SERVING LIGHTING IN THE
SURROUNDING AREA.
18. ALL RECEPTACLES IN GARAGE AREA SHALL BE MOUNTED AT 48" AFF UNLESS OTHERWISE NOTED.
LL
LITHONIA
H.E. WILLIAMS
OR EQUAL
LDN6-27/10-LO6-MVOLT-GZ1
6DR-L10-8-27-DIM-UNV-R-M-0F-CS-CS-IP
6" WET RATED LED DOWNLIGHT. 2700K COLOR TEMPERATURE FOR OUTDOOR USE.
1000 LUMENS
9W, 2700K
LED
RECESSED0-10V
#2 4-
Fo re st H ill s N at ur e C en te r N ew N at ur e C en te r
N
R ic h Rd
, A lm a, M
I 4
Se vi lle
T ow ns hi p, G ra tio t C ou nt y
Al m a, M ic hi ga n
M A
T R
I X
E-100
Propane
CT
SE G
48" AFF
GFI
48" AFF
GFI
GFI J
CHANGING
STATION
GFI
EWC
EWC
F
WP
GFI
WP
GFI
WP
GFI
WP
GFI
WP
GFI
WP
GFI
DRYER
48" AFF
GFI
48" AFF
GFI
GFI
HP-3
HP-2
HP-1
CT-1
18.2A-240V-1Ø
MAIN HALL
VESTIBULE
ENTRY HALL
STAFF
103OFFICE
OFFICE
LAUNDRY
TOILET
STORAGE
109 MECHANICAL
MEN
111 WOMEN
JANITOR
MECHANICAL
CLASSROOM
CLASSROOM
CLASSROOM
HALL
WP
GFI
F
GFI
WP
GFIGFI
GFI GFI
GFI
GFI
GFI
UTILITY
TRANSFORMER
MP1-6
MP1-6
MP1-6
MP1-7
MP1-7
MP1-7
MP1-7
MP1-8
MP1-8MP1-8
MP1-8
MP1-8
MP1-9MP1-10
MP1-10
MP1-10
MP1-11
MP1-11
MP1-12
MP1-12
MP1-12
MP1-12
MP1-13
MP1-14MP1-14MP1-14
MP1-14 MP1-14
MP1-15
MP1-16
MP1-14
MP1-17
MP1-17
MP1-18
MP1-18MP1-18
MP1-19MP1-19
MP1-22
MP1-22
MP1-23
MP1-23
MP1-24
MP1-24
MP1-24
MP1-25
MP-27,29
MP1-31
48" AFF
GFI
NEW
GENERATOR
HP-7
240V-1Ø, 14.3FLA
HP-5
240V-1Ø, 14.3FLA
HP-6
240V-1Ø, 14.3FLA
240V-1Ø, 29.4 FLA
240V-1Ø, 29.4 FLA
240V-1Ø, 17.5FLA
E-700
FENCE
PANEL MP2
240/120V-1Ø
MP2-3
UTILITY METER4
30A/2P N.F.
60A/2P N.F.
MDP-3MDP-4MDP-5
ERV-1
240V-1Ø, 20FLA
ERV-2
240V-1Ø, 6.6A
30A/2P N.F.
MDP-12
30A/2P N.F.
MDP-116
30A/2P N.F.
30A/2P N.F.
30A/2P N.F.
MDP-7MDP-8
MDP-9
J
J
J
J
MP1-26
MP1-28
MP1-30
MP1-32
J
J J
J
J
J
J
MP1-34
MP1-36
MP1-33
MP1-35
MP1-37 MP1-39
WP
GFI
MP2-5
J
J
WP
BATTERY CHARGER
8.3A-120V
BLOCK HEATER
20.8A-240V-1Ø
MP2-1
MP2-27
7 7
CR
CR
CR
CR
CR
CR
CR
CRCR
CR
CR
CR
CRCR
CR
CR CR
CRCR
CR
CR
AIP
MP1-38
F
FACP
S
F
F
F
F
F F
F F
F
CUH-1
240V-1Ø, 3kW
CUH-2
240V-1Ø, 3kW
MP1-41,43
MP1-40,42
CUH-3
240V-1Ø, 3kW
MP1-45,47
MP2-4
MP2-46
WP
GFI
MP1-22
MP1-24
WP
GFI
MP1-49 MP1-50
MP1-23
WP
GFI
MP1-10
GEN E-STOP
GFI
GP-1
240V-1Ø, 9FLA
GP-2
240V-1Ø, 9FLAMP2-8
MP2-7
HD
HD
CT9
MP1-51
WP
WP
48" AFF
GFI
V
WP
GFI
WP
GFI
WP
GFI HP-9
240V-1Ø, 14.3FLA
HP-8
240-1Ø, 14.3FLA
VESTIBULE
VESTIBULE
HALL
CLASSROOM
CLASSROOM
WP
GFI
MP1-20
MP1-21
MP1-22
MP1-22
MP1-22
MP1-23
MP1-23
MP1-18
MDP-10
MDP-14
30A/2P N.F.
30A/2P N.F.
CR
CR
CR
CR
CR
CR
F
F F
F
WP
GFI
MP1-23
ERV-3
240V-1Ø, 7.7 MCA
30A/2P
MDP-19
ELECTRICAL KEY NOTES - PHASE 1
CONTRACTOR SHALL INSTALL SPECIFIED RECEPTACLES ABOVE
DECORATIVE STONE WAINSCOT.
COORDINATE FINAL LOCATION WITH LOCAL UTILITY COMPANY.
(3) #10, (1) #10 GND, (1) 3/4" CND.
COORDINATE MOUNTING HEIGHT AND LOCATION WITH DECORATIVE STONE
WAINSCOT.
GENERAL RECEPTACLES SHALL BE SWITCHED WITH LIGHTING. REFER TO
RECEPTACLE CONTROL DETAILS. PROVIDE POWERPACKS PER BRANCH
CIRCUIT IN BREAKROOMS, OFFICES, AND CLASSROOMS AS REQUIRED.
(2) #8, (1)#10 GND. (1) 3/4" CND.
(2) #10, (1) #10 GND, (1) 3/4" CND.
VERIFY EQUIPMENT LOCATIONS WITH OWNER PRIOR TO INSTALLATION.
FLOOR PEDESTAL SERVICE FITTING WITH GFI RECEPTACLE. SEE SPEC
SECTION 262726 FOR FURTHER INFORMATION.
OWNER FURNISHED. COORDINATE INSTALLATION WITH ACTUAL PHONE
FURNISHER.
ELECTRICAL KEY NOTES - PHASE 2
GENERAL RECEPTACLES SHALL BE SWITCHED WITH LIGHTING. REFER TO
RECEPTACLE CONTROL DETAILS. PROVIDE POWERPACKS PER BRANCH
CIRCUIT IN BREAKROOMS, OFFICES, AND CLASSROOMS AS REQUIRED.
CONTRACTOR SHALL INSTALL SPECIFIED RECEPTACLES ABOVE
DECORATIVE STONE WAINSCOT.
(2) #10, (1) #10 GND, (1) 3/4" CND.
#2 4-
Fo re st H ill s N at ur e C en te r N ew N at ur e C en te r
N
R ic h Rd
, A lm a, M
I 4
Se vi lle
T ow ns hi p, G ra tio t C ou nt y
Al m a, M ic hi ga n
M A
T R
I X
E-500
N FLOOR PLAN - PHASE 1 - POWER NEW
SCALE: 1/8" = 1'-0"
0 1 5 10 20
N FLOOR PLAN - PHASE 2 - POWER NEW
SCALE: 1/8" = 1'-0"
0 1 5 10 20
GEN E-STOP
B-1 6A-120V
HP-4
240V-1Ø, 14.3FLA
GFI
GFI
MP1-18
MECHANICAL
PANEL MDP
240/120V, 1Ø
MDP
ATS
MP1-44
MP1-46
B-2 6A-120V
BOILER E-STOP
MDP-61
SE RATED
DISC
GENERATOR REMOTE
ANNUNCIATOR
PANEL MP1
240/120V, 1Ø
DWH-1
240V-1Ø, 4500W
MDP-13
30A/2P N.F.
30A/2P
GFI
GFU-1
P-4
1.5HP-240V-1Ø
P-3
1.5HP-240V-1Ø
P-1
2HP-240V-1Ø
P-2
2HP-240V-1Ø
MDP-15 MDP-16
MDP-18
MDP-17
GFIF
VFD
VFD
VFD
120V-1/2HP
H
MP1-48 3
CO
ELECTRICAL KEY NOTES
(2) #10, (1) #10 GND, (1) 3/4" CND.
COORDINATE ATTIC ACCESS WITH CONDUITS/DUCTWORK/PIPING TO AVOID
CONFLICTS WITH THE ATTIC ACCESS PANEL.
CONTRACTOR SHALL PROVIDE APPROVED FIRE STOPPING MATERIALS AT
ALL WALL PENETRATIONS OF MECHANICAL ROOMS.
#2 4-
Fo re st H ill s N at ur e C en te r N ew N at ur e C en te r
N
R ic h Rd
, A lm a, M
I 4
Se vi lle
T ow ns hi p, G ra tio t C ou nt y
Al m a, M ic hi ga n
M A
T R
I X
E-700
N
ENLARGED FLOOR PLAN
MECHANICAL ROOM
POWER1
E-700
SCALE: 1/4" = 1'-0"
0 1 5 10
File details come from the government source that posted it. Updated .