This document is a comprehensive set of special provisions and technical specifications for a water treatment plant sanitary sewer replacement project issued by the City of Jackson, Michigan. The project involves replacing 330 feet of sanitary sewer within the City of Jackson Water Treatment Plant grounds, with major bid items including dewatering, 970 square yards of aggregate base, 320 tons of hot mix asphalt, 330 feet of 18-inch PVC sanitary sewer, and three 48-inch diameter sanitary manholes. The project is scheduled for award at the December 10, 2024 City Council meeting, with a Notice to Proceed to be issued shortly thereafter, and the contractor required to begin work within five days of the notice.
The project specifications include detailed requirements for materials, construction methods, groundwater management, soil erosion control, and turf establishment, with specific provisions for dewatering potentially contaminated groundwater and managing site-specific environmental conditions. The technical memo accompanying the specifications reveals groundwater contamination concerns, including PFAS compounds and metals exceeding regulatory criteria, which may impact construction methods. The contract includes provisions for performance bonds, maintenance periods, and detailed testing and quality control requirements. Funding and specific pricing details are not explicitly stated in the provided documents, but the project appears to be a municipal infrastructure improvement initiative with environmental remediation considerations.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 24-14_WTP_SANITARY_SEWER_REPLACEMENT_REQUEST_TO_BID_approval.pdf | ||
| 24-14_WTP_SANITARY_SEWER_REPLACEMENT_CONTRACT_CHECKLIST_101424.pdf | ||
| ENG_24-14_WTP_SANITARY_SEWER_REPLACEMENT_-_RFB.pdf | ||
| 24-14_WTP_SANITARY_SEWER_REPLACEMENT_BID_PLAN_SET.pdf | ||
| 24-14_WTP_SANITARY_SEWER_REPLACEMENT_ENG_ESTIMATE_FOR_LETTING_101424.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEX of SPECIAL PROVISIONS
MDOT Standard Specs and Supp Conditions ........................................ SP 1 of 286
Progress Clause ..................................................................................... SP 2 of 286
Preconstruction Video Documentation ................................................... SP 4 of 286
Utility Coordination ................................................................................. SP 6 of 286
Construction Staking .............................................................................. SP 7 of 286
Maintaining Traffic .................................................................................. SP 9 of 286
Vertical Exploratory Investigation ........................................................... SP 11 of 286
Pavement Sawcut .................................................................................. SP 13 of 286
Pavement Removal, Modified ................................................................ SP 14 of 286
Dewatering and Contaminated Groundwater, Storage, Handling and Disposal ....................................................................... SP 15 of 286
Contaminated Material ........................................................................... SP 20 of 286
Roadway Grading, Special ..................................................................... SP 22 of 286
Noncompliance with Soil Erosion & Sedimentation Requirements ......... SP 24 of 286
Aggregate Base, __inch, CIP, 21AA ...................................................... SP 26 of 286
Sanitary Sewer ....................................................................................... SP 27 of 286
Storm Sewer .......................................................................................... SP 33 of 286
Drainage Structures ............................................................................... SP 35 of 286
Manhole and Catch Basin Covers .......................................................... SP 37 of 286
Utility Structure Cover, Adj, Case 1, Modified ........................................ SP 38 of 286
Acceptance of HMA Mixtures on Local Streets ...................................... SP 39 of 286
HMA Application Estimate ...................................................................... SP 46 of 286
Marshall Hot Mix Asphalt Mixture ........................................................... SP 47 of 286
Recycled Hot Mix Asphalt Mixture .......................................................... SP 49 of 286
Turf Establishment Performance ............................................................ SP 51 of 286
Adjusting Gate Box, Case 1, Modified .................................................... SP 57 of 286
Notice to Bidders for Soil Borings and Pavement Cores ........................ SP 58 of 286
Errata to the 2020 Standard Specifications ............................................ SP 59 of 286
Technical Memo 1, Groundwater Characterization ................................ SP 70 of 286
MDOT STANDARD SPECIFICATIONS AND SUPPLEMENTARY CONDITIONS
COJ 1 of 1 04/12/23
The Michigan Department of Transportation 2020 Standard Specifications for Construction (referenced herein as the “MDOT Standard Specifications for Construction”) are hereby incorporated by reference and shall be deemed to be a part of these contract documents as though herein written in its entirety. The MDOT Standard Specifications for Construction shall be changed and supplemented by the Supplemental Specifications, Special Provisions and errata included in these contract documents. MDOT Standard Specifications for Construction are available for review and download from the MDOT website.
Unless otherwise omitted, changed or supplemented, the Division 1 “General Provisions” of the MDOT Standard Specifications for Construction shall be incorporated into the City’s General Conditions for this contract (pp. G-1 through G-14). In the event of any inconsistency, discrepancy or conflict between the aforementioned MDOT General Provisions and other contract documents including, but not necessarily limited to, pp. G-1 through G-14, said other contract documents shall govern.
Throughout the specifications, the term “Engineer” shall mean the City Engineer of the City of Jackson or his designee. The MDOT Standard Specifications for Construction, Division 1 “General Provisions” shall be changed and supplemented as follows:
Section 102 Bid Submission, Award and Execution of Contract (This section shall be omitted in its entirety)
Section 104.09 Lines, Grades, and Elevations (This section shall be omitted in its entirety.)
Section 104.10 Claim for Extra Compensation or Extension of Time (This section shall be omitted in its entirety.)
Section 104.11 Work Zone Safety and Mobility (This section shall be omitted in its entirety.)
Section 107.10 Indemnification, Damage Liability and Insurance, paragraphs A through D (This section shall be omitted in its entirety)
Section 109.04 Progress and Partial Payments (This section shall be omitted in its entirety)
SP 1 of 286
CITY OF JACKSON, MICHIGAN
PROGRESS CLAUSE
HRC:MAR 1 of 2 8/13/24
a. General
It is expected that this contract will be awarded at the December 10, 2024 City Council meeting, after which a Notification of Award will be provided by the City to the approved bidder.
Within ten (10) days of Notification of Award, the approved bidder must provide certificates of insurance evidencing insurance coverage as required by the Contract. The successful bidder will also be required to sign a contract in three counterparts. A Notice to Proceed will then be provided to the Contractor by the City. The Contractor must begin work within five (5) days of the Notice to Proceed unless specified otherwise below OR on a date agreed upon with the City. In no case shall any work be commenced prior to receipt of formal notice of award by the City.
The approved bidder(s) for the work covered by this proposal will be required to participate in a pre-construction meeting with the City. The City will arrange the time and place for the preconstruction meeting after contract award. The named subcontractor(s) for Designated and/or Specialty Items, as shown in the Proposal, is (are) recommended to be at the preconstruction meeting if such items materially affect the work schedule.
The Contractor shall prepare and submit a complete, detailed, and signed MDOT Form 1130A, Progress Schedule, according to Section 108.05.A within 7 calendar days after award.
The Progress Schedule shall include, at minimum, the controlling work items for the completions of the project, as well as the planned dates or work days that these work items will be controlling operations. All contract dates including open to traffic, project completion, interim completion and any other controlling dates in the contract, must be included in the progress schedule. Failure on the part of the Contractor to carry out the provisions of the Progress Schedule, as established, may be considered sufficient cause to prevent bidding future projects until a satisfactory rate of progress is again established.
The Contractor shall attend regular bi-weekly construction progress meetings throughout the duration of construction and shall provide updates to the City that shall include work completed to date, a two-week outlook for upcoming work, and any necessary updates regarding the Milestone dates identified herein.
b. Milestones
Construction will proceed as shown on the plans and as described in the Maintenance of Traffic Special Provision. The Contractor shall be expected to mobilize sufficient labor and equipment to complete the project within the specified time frames.
1. Substantial Completion
Work shall be substantially completed and the roadway be designated as “Approved for Traffic” within 56 calendar days from mobilization and no later than April 18, 2024. The “Approved for Traffic” condition shall be as defined in section 107.21, Approved for Traffic, of the MDOT 2020 Standard Specifications for Construction.
SP 2 of 286
HRC:MAR 2 of 2 8/13/24
This shall include construction, and installation of street lighting system, curb and gutter, sidewalk ramps; and paving of hot mix asphalt (HMA) through the top course
2. Completion of Delayed Acceptance Items
Delayed acceptance items shall be turf establishment items. No other items shall be considered for delayed acceptance unless approved in writing by the Engineer at the time of acceptance of the Contractor’s Progress Schedule. Delayed acceptance items shall be completed on or before May 26, 2025.
3. Contract Completion
The entire project, including punch list items, establishment of all restored turf grass, and removal of soil erosion control items, shall be completed on or before May 26, 2025.
c. Liquidated damages for failure to meet milestones
Failure by the Contractor to meet interim completion, open to traffic, and/or final completion dates will result in the assessment of liquidated damages in accordance with subsections 108.10.C.1 and 108.10.C.2 of the MDOT 2020 Standard Specifications for Construction.
SP 3 of 286
SPECIAL PROVISION
FOR
PRECONSTRUCTION DOCUMENTATION
Fishbeck 1 of 2 08/07/24
a. Description. This work shall include completing preconstruction documentation to record the condition of existing facilities adjacent to the right-of-way prior to demolition and construction, monitoring existing facilities to determine if construction activities are having adverse effects, and all work necessary to return facilities to their preconstruction condition at the conclusion of the project. All work in this Special Provision shall be in accordance with Division 8 of the current Michigan Department of Transportation Standard Specifications for Construction, except as modified herein.
b. Materials. Provide materials in accordance with the following specifications.
1. Materials needed to return existing facilities to their preconstruction condition shall be new, quality products, and shall match the preconstruction properties of the existing component. Contractor shall submit material choices, including samples and manufacturer’s literature, as applicable, to the Engineer for approval a minimum of 7 days prior to incorporating any materials into an existing facility.
c. Construction.
1. Preconstruction Documentation. The preconstruction documentation shall be conducted by the Contractor and witnessed by the Engineer immediately following the award of the Contract and prior to beginning any work. The Contractor shall employ a professional firm acceptable to the City and actively engaged in preconstruction color audio-video recording.
A. The preconstruction documentation shall include all surface features within the zone of construction influence including existing driveways, sidewalks, parkways, curbs, ditches, streets, landscaping, trees, culverts, retaining walls, fences, visible utilities, bridge piers, abutments, slope paving and all buildings. Documentation shall also include all existing cracks, steps, porches, and all possible areas of concern from various angles on existing buildings that could be affected by the construction. At a minimum, the preconstruction documentation shall include portions of all buildings and structures that are within 30 feet of the street right-of-way and within 50 feet of any buildings shown to be removed on the drawings. The preconstruction documentation may include, but not necessarily be limited to, areaways, basements of buildings, building interiors and building exteriors. Preconstruction documentation shall include an assessment of existing structural conditions and documentation of all existing cracks and structural defects.
B. The preconstruction documentation shall be recorded in the form of preconstruction video in DVD format, pictures, and field notes. At a minimum, three copies of the preconstruction documentation shall be furnished to the Engineer prior to starting construction. The Contractor shall effectively coordinate with private property owners for work performed on private property.
SP 4 of 286
Fishbeck 2 of 2 08/07/24
2. Equipment. Video recording and camera equipment used to record the condition of existing facilities shall be in proper working condition at the time of preconstruction documentation. Flash Drives, CDs, DVDs, or other media used to record the preconstruction documentation images shall be good quality, new materials.
A. Cameras. Cameras shall be high quality 3-chip color video camera, optical stabilization, 20X minimum optical magnification, and shall be capable of producing NTSC 525 lines resolution/60 fields/30 frames per second and minimum illumination capabilities of at least 3-lux. Video recordings shall be time and date stamped on screen, include 2 simultaneous audio tracks (track 1 for SMPTE time code corresponding with number visible on screen and included on computer printout, track 2 with narrative commentary).
d. Measurement and Payment. The completed work as measured for items in this Special Provision will be paid for at the Contract Unit Prices for the following contract items, Pay Item.
Pay Item Pay Unit
Preconstruction Documentation ......................................................................... Lump Sum
Preconstruction Documentation includes recording the condition of existing facilities adjacent to the project, placement and monitoring of 2 crack monitors and 2 settlement markers per project Station, providing required documentation to the Engineer, monitoring, development and implementation of any necessary action plan(s), and the repair or replacement of any building or structure damaged during construction. Contractor will be paid 80 percent of line item once crack and settlement monitors are placed and monitored during construction and will be paid the last 20 percent after crack and settlement monitors are removed after construction activities have ceased unless otherwise instructed by the engineer.
SP 5 of 286
NOTICE TO BIDDERS
UTILITY COORDINATION
HRC:MAR 1 of 1 8/13/24
For protection of underground utilities and in conformance with Public Act 53, the Contractor shall dial 1-800-482-7171 a minimum of three (3) full working days, excluding Saturdays, Sundays, and holidays, prior to beginning each excavation in areas where public utilities have not been previously located. Members will thus be routinely notified.
This does not relieve the Contractor of the responsibility of notifying utility owners who may not be a part of the “Miss Dig” alert system.
Public Utilities
The following Public Utilities have facilities located within the right-of-way:
Consumers Energy – Gas Division Kyle Oak (269) 337-2366
Consumers Energy – Electric Division Dave Southward (517) 788-2400
AT&T Telephone Karen Trudgen (517) 392-1340
City of Jackson – Water Division Randy Lybarger (517) 788-4170
City of Jackson – Traffic Signs & Signals Troy White (517) 788-4160
City of Jackson – Sanitary & Storm Sewer Troy White (517) 788-4160
Comcast - Cable Dave Dostie (248) 459-0246
The owners of existing service facilities that are within grading or structure limits will move them to locations designated by the Engineer or will remove them entirely from the street right-of-way. Owners of Public Utilities will not be required by the City to move additional poles or structures in order to facilitate the operation of construction equipment unless it is determined by the Engineer that such poles or structures constitute a hazard to the public or are extraordinarily dangerous to the Contractor’s operations.
The contractor shall cooperate and coordinate construction activities with the owners of utilities as stated in section 104.08 for the MDOT Standard Specifications for Construction. In addition, for the protection of underground utilities, the contractor shall follow the requirements in section 107.12 of the MDOT Standard Specifications for Construction. Contractor delay claims, resulting from a utility, will be determined based upon section 109.05.E of the MDOT Standard Specifications for Construction.
SP 6 of 286
NOTICE TO BIDDERS
CONSTRUCTION STAKING
HRC:MAR 1 of 2 12/17/20
Location, alignment, elevation datum, and grade of the work will be determined by the Engineer who will set the controls necessary to properly mark these elements. The Contractor shall assume full responsibility for all other detail dimensions and elevations measured from the lines, grades and elevations established.
The Engineer will provide grade and alignment stakes needed for normal progress of the work by the Contractor. Prepare the work area for staking and notify the Engineer least 48 hours in advance of staking needs. Additional time may be required when the Contractor’s staking needs are indeterminate or erratic, or when the magnitude of the staking work makes scheduling necessary. It will be the Contractor’s responsibility to be sure that all information contained on the stakes is understood.
a. Road and Controls. Road Stakes and Controls. Stakes set by the Engineer shall be carefully preserved by the Contractor. Any stakes destroyed due to the Contractor’s carelessness will be replaced at the Engineer’s earliest convenience. When restaking becomes necessary two or more times, the Contractor will be notified in writing and may be charged for the crew time involved.
The following staking will be provided by the Engineer if required:
1. Benchmarks. At locations indicated on the plans.
2. Right-of-way. A right-of-way stake will be set at all corners marking a change in width or direction.
3. Slope and Clearing Stakes. Stakes will be provided at 50-foot intervals or at agreed upon locations and at all break points due to subgrade transitions.
4. Curb Stakes. Stakes will be provided at 25-foot intervals on tangent sections and on curves with radii of 50 feet or more. Curves with radii of less than 50 feet will be staked at tangent points, mid point and center of radii.
5. Drainage, Sanitary and Utility Stakes. Stakes will be set for drainage, sanitary and utility work. Drainage, sanitary and utility structures will be located by means of two or more offset stakes. The following information will be provided on the offset stakes:
A. Distance to center of structure or utility line, B. Cut to flowlines of the utility and pipe openings in the structure, and C. Cut or fill to top of structure.
6. Watermain. Stakes for watermain pipe will be provided at 50-foot intervals and at horizontal bends, valves and hydrants. Offset stakes will be provided and include the cut to the top of the pipe or bend.
7. Structure and Valve Adjustments. Paint marks will be provided for structures and valves located in HMA pavement that need to be adjusted upwards after placement of the top course of HMA. The Engineer, with assistance from the Contractor, will record the locations of all structures and valves located within proposed HMA pavement after the aggregate base is placed. The Contractor shall provide sufficient means to locate
SP 7 of 286
HRC:MAR 2 of 2 12/17/20 and expose structures and valves so that the Engineer may locate the center of the structures and valves. This work is considered part of the related adjustment pay items.
8. Miscellaneous Stakes. Stakes will be provided for MOT signs, sidewalk, retaining walls, guardrail, sign structures, signs, restoration items, and erosion control items.
All staking not addressed but required to construct the project in accordance with the contract documents, shall be the responsibility of the Contractor.
SP 8 of 286
FOR
MAINTAINING TRAFFIC
Jackson: RTM 1 of 2 08-30-12
a. Description. Maintain traffic throughout the project in accordance with section 812 of the MDOT Standard Specifications for Construction and as specified herein.
b. Construction Influence Area (CIA). The CIA shall include the right-of-way of the following roadways within the approximate limits described below:
Mansion Street from Cooper Street to Losey Street.
The Contractor shall coordinate operations with other contractors performing work on other projects within or adjacent to the Construction Influence Area (CIA).
City Maintenance crews may perform maintenance work within or adjacent to the Construction Influence Area (CIA). The City maintenance crews will coordinate their operations with the Engineer to minimize the interference to the Contractor. No additional payment will be made to the Contractor for the joint use of the traffic control items.
c. Traffic Restrictions. No work will be allowed during the Good Friday, Memorial Day, Juneteenth, Fourth of July, Labor Day and Veterans Day holiday periods as defined and directed by the Engineer. Prior to ceasing operations for a given holiday period, the Contractor shall ensure that all traffic control devices required for the current construction stage are in place, cleaned, and fully operational.
All work shall be conducted between 7:00 a.m. and 6:00 p.m., Monday through Saturday. Night or Sunday work will not be permitted without written approval of the City.
New sewer excavation is not permitted after October 15, without written approval from the City.
Access for construction vehicles to work areas will be restricted to specific locations. The number of access points and their locations will require the prior approval of the Engineer.
Maintain local and emergency traffic at all times.
Maintain and protect pedestrian traffic at all times.
Maintain access to all businesses. If a business has multiple drives, one shall remain open at all times.
Walks, driveway and entrances to buildings shall not be unnecessarily blocked. Ingress, egress and maintenance of drive approaches, sidewalks, crosswalks, parkways and open and unopen street subgrade shall be the responsibility of the Contractor throughout construction. Construction shall be completed in such a manner as to maintain the required entrance width for traffic at all times. When partial widths of new pavement area available to local traffic, access to drive shall be
SP 9 of 286
Jackson: RTM 2 of 2 08-30-12 provided immediately. Temporary ramps shall be constructed where necessary as directed by the Engineer to maintain access to properties. Payment for temporary ramps is included with that for other pertinent pay items.
d. Traffic Control Devices. All traffic control devices and their usage shall conform to the Michigan Manual of Uniform Traffic Control Devices (MMUTCD), 2011 Edition, as revised and as specified herein.
Distances shown between construction warning, regulatory, and guide signs shown on the plans are approximate and may require field adjustment, as directed by the Engineer.
All construction warning signs, unless otherwise noted, shall be 48" x 48" mounted at 7 feet bottom heights.
Temporary signs shall be erected only when in use. Where signs are no longer applicable, they shall be removed or have their legends completely covered with plywood.
Temporary traffic control devices not in use shall be kept at the Contractor’s lay down area.
Signs, plastic drums and barricades may be laid down and stored in the parkway for a maximum of 24 hours.
Sign covers shall be used to cover any non-applicable existing signs. Covers shall not leave any marks on, or mar in any way, signs or sign surfaces. Notify the Engineer at least 24 hours in advance of erection or removal of sign covers.
All channelizing devices shall be Plastic Drums, High Intensity. Place channelizing devices at a spacing of 30 feet along tapers, 50 feet along parallel areas.
Place channelizing devices, lighted arrow panels, and other traffic control devices as shown on the plans, or as directed by the Engineer to fit a specific condition.
e.. Measuremen and Payment. The estimate of quantities for maintaining traffic on this project is based on the sequence of operations delineated elsewhere in the Contract documents.
Payment for these devices shall be according to Section 812.04 of the MDOT Standard Specifications for Construction for Construction unless otherwise specified.
Any additional signing or maintaining traffic devices required to expedite the construction shall be at the Contractor’s expense.
SP 10 of 286
20SP-204B-01
MICHIGAN
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
VERTICAL EXPLORATORY INVESTIGATION FOR RELOCATION
COS:MRB 1 of 2 APPR:DMG:NAL:04-30-20
FHWA:APPR:05-06-20
a. Description. When proposed work must be relocated as directed by the Engineer, this special provision is used to compensate the Contractor to locate and expose underground infrastructure and obstructions, such as culverts, sewers and utilities. Perform this work only when conflicts are found in the planned work location. This special provision is not to compensate for the Contractor’s responsibilities in subsection 107.12 of the Standard Specifications for Construction.
b. Materials. Use Granular Material Class III in accordance with section 902 of the Standard Specifications for Construction for backfill. Use material removed during exploratory investigation for backfill only if approved by the Engineer.
c. Construction. The owner of any sewer or utility to be exposed will not take the facilities out of service during the exploratory investigation. Contact utility owners in accordance with subsection 107.12 of the Standard Specifications for Construction.
Advance the exploratory excavation using vacuum excavation, hand digging, conventional machine excavation, or a combination thereof subject to approval of the Engineer. Allow the Engineer access to document the necessary information. If the technique used to advance the excavation causes any damage to the existing facilities, immediately contact the utility owner and cease all work until an alternate method is approved by the Engineer.
Take care to protect the exposed culvert, sewer or utility from damage during construction. The Contractor is responsible for all costs associated with the repair work and out of service time of all broken or damaged existing culverts, sewers or utilities as a result of any action by the Contractor. If the exploratory investigation results in damage to utilities, contact the owner of such utility to coordinate the repair. Repair or replace culvert, sewer or utility, damaged during exploratory excavation, in accordance with the standard specifications and as approved by the Engineer.
Obtain the Engineer's approval before backfilling the excavation. Complete backfilling no later than 24 hours after approval has been given. Backfill in accordance with subsection 204.03.C of the Standard Specifications for Construction. Dispose of excess material in accordance with the standard specifications.
d. Measurement and Payment. The completed work, as described, will be measured and paid for at the contract unit price using the following pay item:
Pay Item Pay Unit
Exploratory Investigation, Vertical ............................................................................... Foot
SP 11 of 286
20SP-204B-01
COS:MRB 2 of 2 04-30-20
Exploratory Investigation, Vertical will be measured by the foot from top of existing grade vertically to the bottom of the excavation for up to a 4-foot maximum diameter hole, or as approved by the Engineer. The excavated depth of each 4-foot maximum diameter hole will be measured separately for payment.
Exploratory Investigation, Vertical includes all costs associated with repair or replacement resulting from the Contractor’s activities. Providing necessary lane, shoulder and/or sidewalk closures required to perform work will be paid for by other associated items in the contract.
Restoration work will be paid for by other associated items.
SP 12 of 286
FOR
PAVT SAWCUT
Jackson: RTM 1 of 1 10-08-11
a. Description. This work consists of sawcutting concrete and HMA pavement.
b. Materials. None specified.
c. Construction. Sawcut concrete or HMA surfaces at locations shown on plans and as directed by the Engineer. In removing old pavement, curb, gutter, sidewalk, crosswalk and similar structures, where portions of the existing structure are to be left in the surface of the finished work, remove the old structure to existing joints or saw to a reasonably true line with a vertical face.
Perform sawcuts with a power driven concrete saw to the full depth of the item being sawcut.
Take precautions to maintain a clean vertical edge on the sawcut throughout the duration of the work. Any resawing or additional removal and replacement of pavement, curb and gutter or sidewalk which may be necessary due to Contractor carelessness will be at the Contractor’s expenses.
d. Measurement and Payment. The completed work, as described, will be measured and paid for at the contract unit price for the following pay item:
Pay Item Pay Unit
Pavt Sawcut ……………………………………………………………………………………..… Foot
Pavt Sawcut will be measured by length and will be paid for all sawcutting of HMA and concrete pavement, curb, driveways and sidewalk.
Payment for this item will not be made when pavement is removed by a milling machine or other method that does not require a sawcut.
SP 13 of 286
FOR
PAVEMENT REMOVAL, MODIFIED
Jackson: RTM 1 of 1 10-08-11
a. Description. This work consists of removing existing concrete and HMA pavement in accordance with sections 204 and 501 of the MDOT Standard Specifications for Construction, except as modified herein. The existing pavement thickness varies. Refer to the soil and pavement borings contained in the proposal.
b. Materials. Use Granular Material Class II in conformance with section 902 of the Standard Specifications for Construction for backfill.
c. Construction. Remove the existing pavement to sawed joints at removal limits as indicated on the plans. Protect existing utilities during removal operations.
d. Measurement and Payment. The completed work, as described, will be measured and paid for at the contract unit price for the following pay items:
Pay Item Pay Unit
Pavt, Rem, Modified ………………………………………………………………………Square Yard HMA Surface, Rem, Modified …………………………………………………………. Square Yard Driveway, Rem ……………………………………………………………………………Square Yard Track Base, Rem ……………………………………………………………………………Cubic Yard
Removal of concrete and masonry pavements including any overlaying HMA surface, will be paid as Pavt, Rem, Modified and will be measured in place from edge to edge of pavement and to saw cut limits, excluding curb and gutter. Pavt, Rem, Modified will be paid for as one quantity, regardless of the thickness or composition of pavement being removed.
HMA Surface, Rem Modified will be measured in place from edge to edge of pavement and to saw cut limits. HMA Surface, Rem, Modified will be paid for as one quantity, regardless of the thickness of the pavement being removed. Removal of the HMA surface overlying a concrete or masonry pavement is considered part of the underlying material (regardless of thickness) and will be included in the quantities of Pavt, Rem, Modified.
Removing concrete and HMA drive approaches will be measured and paid separately as Driveway, Rem. Driveway, Rem will be measured in place by area in square yards and will be paid for as one quantity, regardless of thickness or composition.
Curb and gutter removal will be paid for separately as Curb and Gutter, Rem.
The removal of concrete, timber and masonry base materials from abandoned train or trolley track beds and backfill will be paid for as Track Base, Rem. The Engineering will measure Track Base, Rem volumes using the average end areas method.
SP 14 of 286
FOR
DEWATERING SYSTEM AND
CONTAMINATED GROUNDWATER PROCEDURES
Fishbeck 1 of 5 08-07-24
a. Description. This work consists of lowering the groundwater table to facilitate excavation.
This work will require the use of pumps or well points, deep wells, or other measures that are utilized to control and manage groundwater. Also including of all labor, equipment, and materials necessary to handle, transport, and dispose of potentially contaminated groundwater.
b. Material. Submit a plan for locations and monitoring frequency of the observation wells to the Engineer a minimum of 7 calendar days in advance of placement of the dewatering system.
Include in the dewater plan all the following:
1. System description.
2. Number, size, and length of wells.
3. Estimated pumping rate.
4. Pumping and Storage equipment.
5. Discharge location.
6. Sedimentation control procedures
Governing Standards. Except as modified or supplemented herein, the handling of potentially contaminated groundwater shall be governed by state and federal waste management regulations, by the provisions of Federal Regulation 29 CFR Part 1910.120, and regulations of the Occupational Safety and Health Administration (OSHA).
c. Construction.
1. Performance Requirements. The Contractor is responsible for complying with the requirements of Federal Regulation 29 CFR Part 1910.120, the Health and Safety training for his employees and providing his employees with adequate protective equipment.
A. The Contractor is responsible for the monitoring of City designated clean areas to ensure that the areas remain free from exposure to contaminated materials.
B. The Contractor is responsible for the monitoring of City designated exclusion zones to ensure proper compliance with Federal Regulations.
2. Health and Safety Plan. The Contractor shall prepare a Health and Safety Plan for this project and shall provide a copy to the Engineer if requested.
3. Well Points and Deep Wells. Ensure groundwater control performed by deep well and/or well point pumping systems is done without damage to property or structures and without interference with the rights of the public, owners of private property, pedestrians, vehicular traffic, or the work of other contractors. Any pumping methods used for dewatering and control of groundwater and seepage must have properly designed filters to ensure that
SP 15 of 286
Fishbeck 2 of 5 08-07-24 adjacent soil will not be pumped with the water, thus creating voids underground and around the face of the excavation or under existing structures. Ensure the loss of fines is limited to no more than 5 parts per million by volume in the extracted water. Ensure the filter design is reviewed and approved by the Engineer before placement.
Perform the dewatering operations in a proper and predetermined sequence with the excavation operation such that the perimeter, bottom, and face of the excavation are stable.
Dewatering well diameter, pumping rate and well spacing must provide adequate drawdown of the water level. Properly locate wells to intercept groundwater that otherwise would enter the excavation and interfere with the work. Install observation wells at key locations for observation of groundwater levels during the dewatering operation and excavation. Add additional wells as needed to lower the groundwater to the elevation shown on the plans.
A. Contractor shall provide, maintain, and use at all times during construction adequate means and devices to promptly remove and dispose of all water from every source entering the excavations or other parts of the work. Dewatering shall be accomplished by means which will ensure dry excavations, preserve final lines and grades, not disturb or displace adjacent soil, and avoid contamination of any surface water or storm water. All pumping and drainage shall be done with no damage to property, pedestrians, vehicular traffic, or the work of other contractors and in accordance with all pertinent laws, ordinances, and regulations. Existing drainage facilities shall not be overloaded or obstructed.
4. Excess Water Control/Handling Potentially Contaminated Groundwater.
A. If the groundwater is determined by the Engineer to be potentially contaminated (e.g., hydrocarbon sheen or chemical odor), the Contractor shall immediately cease dewatering operations and shall not resume dewatering until equipment appropriate to store the potentially contaminated groundwater is onsite and operational. Additionally, the Contractor shall manage the groundwater as contaminated until directed otherwise by the Engineer.
B. Potentially contaminated groundwater removed from the trench during the pipe laying operation shall be stored in fractionation tanks located on the project site. Each fractionation tank shall have a minimum capacity of 20,000 gallons.
C. Samples of the stored groundwater will be collected by the Engineer within 48 hours of initial storage in the fractionation tanks. Analytical tests will be performed on the samples to determine if the stored groundwater is contaminated. Laboratory testing of collected samples typically requires 24 to 72 hours to complete. Based on the results of these tests, the Engineer will identify the type of disposal required and notify the Contractor. The following types of disposals may be used:
(1) Uncontaminated Groundwater. If chemical concentrations in the stored groundwater are below federal and applicable state clean up criteria, the Contractor shall dispose of it by pumping in accordance with MDOT Standard Construction Specifications and section c.5 of this Special Provision.
(2) Non-hazardous Contaminated Groundwater. If the stored groundwater is contaminated and non-hazardous, as determined by the Engineer, the stored water shall be disposed of as directed by the Engineer in one of three ways. Disposal will be
SP 16 of 286
Fishbeck 3 of 5 08-07-24 based on the sampling results:
(a) By discharge into the nearest available sanitary sewer in accordance with section c.5 of this Special Provision.
(b) By pumping the stored water through a carbon treatment system and discharging to the nearest available sanitary sewer in accordance with section 5, below. The carbon treatment system shall be operated at a minimum empty bed contact time of 15 minutes. The Contractor shall submit information regarding use, performance, and capacity of the carbon treatment system for review and approval.
(c) By loading, transporting, and disposing at a licensed treatment facility, contingent upon City and Engineer approval.
(3) Hazardous Contaminated Groundwater. If the stored groundwater is contaminated, hazardous, and not treatable by carbon filtration, it shall be loaded, transported, and disposed of at a hazardous waste disposal site by the hazardous waste contractor designated by the City.
E. Fractionation tanks shall be emptied and made available for reuse within 72 hours of notification by the Engineer of the appropriate disposal method of the tank’s contents.
After each tank is emptied, it may require decontamination before reuse. The Engineer will notify the Contractor of this requirement.
5. Storm Sewer, Sanitary Sewer, or Surface Water Discharge. Monitor the volume of water discharged to the storm sewer system, sanitary sewer system or as surface water discharge by using a totalizing turbine type flow meter. Place the flow meter in-line on the dewatering system effluent line, ensure it is designed for high flow applications and has a flow totalizing register that is adequately sealed to eliminate fogging and condensation. Install the type of meter used in accordance with the manufacturer’s instructions and be approved by the Engineer before placement.
Filters or settling devices may be required before discharge to ensure that storm sewers, sanitary sewer systems or surface waters are not adversely affected by construction debris or increased sediment load.
Written permission from the wastewater treatment plant authority is required prior to discharge to the sanitary sewer system. Provide a copy of the written authorization to the Engineer prior to discharging any water to the system.
Secure a NPDES permit from the EGLE prior to any discharge to a storm sewer or directly to a surface water body.
Monitor and document the volume of flow being discharged to the storm sewer, sanitary sewer or the surface water daily by reading the register on the flow meter. Provide this information to the Engineer daily or as otherwise approved.
6. Utility and Structure Placement. Lower the groundwater to 1 foot below the lowest foundation subgrade or bottom of pipe trench. Determine the methods and materials required to accomplish this work, subject to approval by the Engineer before initiation or installation of
SP 17 of 286
Fishbeck 4 of 5 08-07-24 the dewatering system.
The Engineer may order corrective actions to the dewatering system at any time due to deficiencies in the system at no additional cost to the contract.
Remove the dewatering system and all associated appurtenances when no longer needed and restore the area as directed by the Engineer.
Abandon deep wells and observation wells in accordance with EGLE requirements when no longer needed.
d. Measurement and Payment. The completed work, as described, will be measured and paid for at the contract unit price using the following pay item:
Pay Item Pay Unit
Dewatering System ............................................................................................ Lump Sum Contaminated Groundwater, Storage, Handling and Disposal .................................. Dollar
Dewatering System will be measured for as a Lump Sum for the Project. The unit price includes all labor, equipment, materials, wells, piping, supplies, power, and fuel necessary for the installation, operation, maintenance, removal and the disposal of all surplus materials as described herein. This pay item includes the cost of disposal of all water pumped from below ground to facilitate underground construction.
The installation, maintenance and removal of deep wells and observation wells are included in this pay item.
Contaminated Groundwater, Storage, Handling and Disposal is an allowance established to pay for the handling, transporting, storage and disposal of non-hazardous and hazardous contaminated groundwater. All work to be paid under this item shall be pre-approved in writing by the Engineer.
1. Where the work is performed by a subcontractor or supplier, the Contractor will be paid for the amount invoiced plus an additional 6 percent of the invoiced cost as reimbursement for the Contractor’s administrative costs. Where the Contractor will be performing the work with his own forces, the work will be paid for using predetermined, negotiated prices. If the Contractor and Engineer cannot agree upon prices, the work will be paid for by force account in accordance with section 109.05 of the MDOT Standard Specifications for Construction.
2. The cost of the following work items will be paid for from the allowance:
A. All work associated with the supply, use, decontamination, reuse, and removal from site of fractionation tanks.
B. All costs associated with disposing of non-hazardous contaminated groundwater using a carbon treatment system.
C. Loading, transporting and disposing of non-hazardous contaminated groundwater at a licensed treatment facility.
SP 18 of 286
Fishbeck 5 of 5 08-07-24
D. Loading, transporting and disposing of hazardous contaminated groundwater at a hazardous waste disposal site by the hazardous waste disposal contractor designated by the City.
C. Initial storage costs for testing and permit fees associated with disposing of non-hazardous contaminated groundwater by disposal to the nearest available sanitary sewer.
3. The following work items will not be paid for separately, but are considered included in payment for the utility and/or grading work requiring the excavation or dewatering:
A. Crushed stone or gravel used to aid dewatering operations.
B. All costs associated with disposing of uncontaminated groundwater.
C. All costs associated with disposing of non-hazardous contaminated groundwater by disposal to the nearest available sanitary sewer, excluding permit fees and initial storage costs for testing.
SP 19 of 286
20SP-205A-01
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
NON-HAZARDOUS CONTAMINATED MATERIAL HANDLING AND DISPOSAL
ENV:JCW 1 of 2 APPR:DMG:DBP:02-26-20
FHWA:APPR:03-02-20
a. Description. This work consists of handling, transporting, disposing of non-hazardous contaminated material, including all laboratory testing required for the proper disposal of the material and site restoration of temporary storage locations. Ensure this special provision is not employed without authorization by the Engineer. The laboratory testing will be used to solicit landfill approval and is not intended to determine whether or not the material is contaminated.
Soil delineated on the plans and classified as non-hazardous contaminated cannot be used elsewhere on the project regardless of the laboratory test results unless otherwise directed by the Engineer.
b. Materials. None specified.
c. Construction. Complete this work in accordance with sections 204 and 205 of the Standard Specifications for Construction, except as modified herein or as directed by the Engineer.
1. Excavation of Non-hazardous Contaminated Material. Excavate non-hazardous contaminated material as shown on the plans or as directed by the Engineer.
2. Temporary Storage of Non-hazardous Contaminated Material. Place excavated non-hazardous contaminated material which is to be temporarily stockpiled on plastic sheeting or tarps having a minimum thickness of 6 mils or in trucks, roll off boxes, or other containers, such that no liquid may escape from the containment. Cover the non-hazardous contaminated material securely with plastic sheeting of 6 mils thickness or greater at the end of each work day.
Dispose of excavated non-hazardous contaminated material as soon as approval is received from the disposal site. This material cannot be stockpiled for longer than 30 days prior to disposal.
Restore temporary storage locations to the condition prior to conducting the work.
3. Sampling and Analysis of Non-hazardous Contaminated Material. Sample and analyze non-hazardous contaminated material prior to disposal. The analysis required is dictated by the Type II disposal facility to be utilized for disposal. Should the results of the analysis show the material to be hazardous waste, as defined by the 1994 PA 451, Part 111, of the Natural Resources and Environmental Protection Act, notify the Engineer immediately.
The material must then be disposed of as directed by the Engineer.
4. Disposal of Non-hazardous Contaminated Material. Dispose of non-hazardous contaminated material at a licensed Type II sanitary landfill. Submit at the preconstruction
SP 20 of 286
20SP-205A-01
ENV:JCW 2 of 2 02-26-20 meeting the name of the Type II landfill to be used for disposal, the sampling and analysis requirements of that landfill, and verification that use of the proposed landfill will meet the requirements of the county solid waste plan.
Ensure the proposed landfill is acceptable to the Department and approval is obtained from the Engineer prior to commencing disposal operations. Provide a copy of the laboratory analysis to the Engineer as a requirement of approval for disposal. Following disposal and prior to approval for payment provide to the Engineer landfill receipts for all non-hazardous contaminated material disposed of.
d. Measurement and Payment. The completed work, as described, will be measured and paid for at the contract unit price using the following pay item:
Pay Item Pay Unit
Non Haz Contaminated Material Handling and Disposal, LM ........................... Cubic Yard
Non Haz Contaminated Material Handling and Disposal, LM will be measured by volume in cubic yards, LM. Provide to the Engineer receipts from the disposal facility for the number of cubic yards disposed of at that facility prior to payment. Payment will include all costs for materials, labor and equipment needed for storage, loading, transportation, testing, restoration of temporary storage locations and disposal of the non-hazardous contaminated material. Disposal costs will include all documentation required by the landfill.
Payment for excavation of non-hazardous contaminated material will be included with the related items of work.
Delays in testing and disposal of non-hazardous contaminated material that are not the fault of the Contractor may be considered valid reasons for extension of time. However, these delays and the resultant extensions of time will not be considered valid reasons for additional payment.
Should the analysis of the material document that it is hazardous waste, then payment for disposal of hazardous waste will be measured and paid for as extra work. Disposal includes hauling by a licensed hazardous waste hauler and disposal at an appropriate licensed disposal facility.
Prequalification is waived.
SP 21 of 286
FOR
ROADWAY GRADING
Fishbeck 1 of 2 08/07/24
a. Description. This work consists of all earthwork required to construct the proposed cross sections within the full depth construction limits shown on the Plans, including the removal of subgrade material to the line and grade called for on the Plans and the preparation of the subgrade. This work shall also include removal of miscellaneous structures and materials. All work shall be completed in accordance with Section 205 of the MDOT Standard Specifications for Construction and this special provision. This work shall also include grading of all ADA ramps within the project limits of all street segments.
b. Materials. Additional material required to achieve the typical cross sections shall meet the requirements of MDOT Granular Material, Class II.
c. Construction. As required to achieve proposed cross sections, Roadway Grading includes, but is not limited to, the following work.
1. Removing miscellaneous structures and materials.
2. Removing trees less than 6 inches in diameter.
3. Removing rocks or boulders less than 0.5 cubic yard in volume.
4. Removing landscaping items within the right-of-way, including plants, edging, landscaping blocks, and other miscellaneous landscaping items.
5. Sawing existing pavement when not called out separately in the Plans or included in the bid form.
6. Topsoil stripping.
7. Grading to Heavy Line and compacting subgrade shown on typical sections.
8. Compacting of existing subbase or aggregate base left in place during utility or road reconstruction and meeting the proposed cross-section.
9. Final grading…