23. GRO MultBldg LS Specs.pdf

PDF 323 KB Posted

Attached to
USFS Job Corps South East Facilities Construction MATOC
Solicitation number
1282A724R0001
Issued by

About this file

This document outlines a solicitation for Multiple Award Indefinite Delivery/Indefinite Quantity construction contracts to support Job Corps facilities in seven southeastern states. The Forest Service Job Corps seeks IDIQ contracts up to $5 million total over five years to provide new construction, alterations, maintenance, roofing, plumbing, HVAC, electrical, and other trades work at Job Corps centers in Arkansas, Kentucky, Missouri, North Carolina, Tennessee, Virginia, and West Virginia. The NAICS code is 236220 for commercial and institutional building construction, with a small business size standard of $45 million.

View the file

Other files

File Type Posted
1282A724Q0016.pdf PDF
ConstructionExperienceForm.docx DOCX document
1282A724Q0012.pdf PDF
1282A724Q0013.pdf PDF
1282A724Q0014.pdf PDF
QA Document_003.pdf PDF
PPQ.doc DOC document
QA Document.pdf PDF
1282A724R0001_0002.pdf PDF
11. 1282A724Q0013.pdf PDF
Q_A Document.pdf PDF
1282A724R0001.pdf PDF
19. 1282A724Q0014.pdf PDF
24. WDOL_DBA_EDMONDSON.pdf PDF
11. 1282A724Q0013.pdf PDF
10. WDOL_DBA_EDMONDSON.pdf PDF
20. 1282A724Q0016.pdf PDF
15. GRO MultBldg HVAC MapsPlans 2023 09 18.pdf PDF
9. GRO Water Tower LS Spec.pdf PDF
17. GRO B4 Raider HVAC SOI.pdf PDF
4. B554 DishWasher Specs.pdf PDF
1. B554 Dishwasher App B photos.pdf PDF
14. GRO MultBldg HVAC Pics 2023 09 18.pdf PDF
13. GRO MultBldg HVAC Spec 2023 09 18.pdf PDF
18. SustainableProducts.pdf PDF
16. WDOL_DBA_EDMONDSON.pdf PDF
2. 1282A724Q0012.pdf PDF
7. B554 DishWasher AppA MapsPlans.pdf PDF
3. B554 Dishwasher SOI.pdf PDF
12. GRO WATER TOWER LS DRAWINGS.pdf PDF
21. GRO MultBldg LS Drawings.pdf PDF
6. WDOL_WD_Menifee.pdf PDF
5. Sustainable Products.pdf PDF
8. GRO Water Tower LS SOI.pdf PDF
22. GRO MultBldg LS SOI.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MULTIPLE BUILDING LIFE SAFETY 010150 – 1

GREAT ONYX JOB CORPS CCC GENERAL REQUIREMENTS

GREAT ONYX JOB CORPS CIVILIAN CONSERVATION CENTER

MULTIPLE BUILDING LIFE SAFETY

SECTION 010150

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK

3.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses for the work summarized as follows:

1. Base Item No. 1 – Admin/Medical Dispensary (B001) Duct Smoke

2. Base Item No. 2 – Food Service (B002) Fire Alarm Pull Stations and Detector

3. Base Item No. 3 – Food Service (B002) Mezzanine Stair Handrail

4. Base Item No. 4 – Raider Dormitory (B004) Masonry Lintel

5. Optional Bid Item No. 5 – Urban Forestry/Maintenance (B005) Smoke Detector

Installations Optional Bid Item No. 6 – Warehouse (B010) Smoke Detector Installation

3.2 LOCATION

A. This project is located at the Great Onyx Job Corps Center campus located at Lat/Long:

37.248, -86.234 in Edmonson County, Kentucky. The address is 3115 Ollie Ridge Rd, Mammoth Cave, KY 42259. Driving directions can be obtained by calling the Center at

(270) 286-4514.

3.3 WORK HOURS

A. Work hours for this project are between 8:00 AM-4:30 PM Monday through Friday.

3.4 USE OF PREMISES

A. Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the work so as not to interfere with Government's day-to-day operations.

C. Keep driveways, parking areas, loading areas and entrances to buildings clear and available to Government, Government's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials. Do not close or obstruct

MULTIPLE BUILDING LIFE SAFETY 010150 – 2

walkways, corridors, or other occupied or used facilities without written permission from Government.

3.5 DEFINITIONS

A. The following terms in any combination relating to the installation of products/materials:

install, furnish, provide, or similar statements; mean that the contractor is responsible for the procurement and installation of the products unless it is specifically designated as either a government furnished item, supply only product, or spare.

3.6 STANDARDS AND CODES

A. All contract work shall adhere to the most recent version of:

1. All the International Code Council Family of codes (ICC) e.g. International

Building Code (IBC), International Fire Code (IFC), and International Mechanical Code (IMC).

2. All National Fire Protection Association (NFPA) codes and Standards e.g. , NFPA 70: National Electrical Code (NEC), NFPA 1: Fire Code, and NFPA 101- Life Safety Code.

3. Architectural Barriers Act Standards (ABA or ABAAS).

4. Product Manufacturer’s installation instructions.

3.7 QUALIFICATIONS

A. When applicable to specific contract work items:

1. Electrical work shall be performed by journey level electricians licensed in the

State of contract performance or trainees/apprentices working under the direct supervision of State-licensed electrical supervisors (or State equivalent).

2. Plumbing work shall be performed by journey level plumbers licensed in the State of contract performance or trainees/apprentices working under the direct supervision of State-licensed plumbing supervisors (or State equivalent).

3. Fire Alarm work shall be performed by NICET certified fire alarm technicians.

3.8 ELECTRICAL INSPECTIONS

A. This Federal contract is exempt from State permitting requirements. However, electrical work must be inspected by a third-party Inspector who is either State-licensed or ICC-certified. The Contractor will arrange for the inspection and pay any fees required for the inspection and associated report; arrangement may include completion and submission of load calculations, permit applications, and any other required coordination. The Inspector does not have any jurisdictional authority on Federal projects. The USFS is the jurisdiction having authority. The inspection will be based on the most recent version of the NFPA 70 National Electric Code (NEC) and currently adopted State codes. A list of deficiencies with corresponding code reference is to be provided in a report signed by the

MULTIPLE BUILDING LIFE SAFETY 010150 – 3

inspector. The addressee in the report is to be the Job Corps Center. The Inspector will provide a copy of their current inspection credentials with the inspection report. The Contractor will submit the report to the COR. The CO will determine which deficiency/violations will be enforced for the Contractor to fix.

3.9 WORK RESTRICTIONS

A. Smoking is permitted on campus only in the designated smoking area.

3.10 SCHEDULE OF ITEMS

A. Schedule of Items:

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items may or may not be awarded, depending on funding availability.

B. Base Items (BI):

1. Base Item No. 1 – Admin/Medical Dispensary (B001) Duct Smoke Detectors

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to duct smoke detectors for two air handlers and connect to existing fire alarm control panel.

c. Deficiencies: #144670.

2. Base Item No. 2 – Food Service (B002) Fire Alarm Pull Stations and Detector

d. Measurement: This item is measured as a Lump Sum quantity.

e. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to furnish and install two fire alarm manual pull stations and a smoke detector and connect to existing fire alarm control panel.

f. Deficiencies: #144941, 144942.

3. Base Item No. 3 – Food Service (B002) Mezzanine Stair Handrail

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to furnish and install an ADA compliant handrail on one side of an existing stairwell.

c. Deficiencies: #137239.

MULTIPLE BUILDING LIFE SAFETY 010150 – 4

4. Base Item No. 4 – Raider Dormitory (B004) Masonry Lintel Replacements

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to replace damaged masonry lintel, block, brick, and properly flash and refinish affected surrounding finishes over two doorways.

c. Deficiencies: #126959.

C. Optional Items (OI):

1. Optional Bid Item No. 5 – Urban Forestry/Maintenance (B005) Smoke Detector

Installations

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to install four smoke detectors and connect to existing fire alarm control panel.

c. Deficiencies: #144951.

2. Optional Bid Item No. 6 – Urban Forestry/Maintenance (B005) Smoke Detector

Installations

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to install a smoke detector and connect to existing fire alarm control panel.

c. Deficiencies: #144977.

PART 2 – PROJECT SCHEDULE

4.1 PROJECT SCHEDULE

ITEM* REQUIRED DUE DATE (calendar days)

Pre-Construction Conference

Within 10 days of Award (virtually)

Notice To Proceed (NTP)

Issued first weekday after Pre-Construction Conference

MULTIPLE BUILDING LIFE SAFETY 010150 – 5

Bonds 10 days after Award

Action and Informational Submittals

12 days after NTP (CORs have 12 days to return)

Closeout Submittals

Prior to CO acceptance of project

Contract Release form and final pay request

10 days after CO acceptance of project

* All items above must be included in Contractor’s construction schedule

PART 3 – SUBMITTAL PROCEDURES

5.1 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Government approval.

B. Informational Submittals: Written information that does not require Government approval. Submittals may be rejected for not complying with requirements.

5.2 PROCEDURES

A. Contractor Responsibilities

1. Review each submittal and check for compliance with the Contract Documents.

2. Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

3. Include the following information on label or cover sheet for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Date of Contractor’s approval.

MULTIPLE BUILDING LIFE SAFETY 010150 – 6

i. Statement certifying that submittal has been reviewed, checked, and approved by the Contractor for compliance with the Contract Documents.

4. The Government will not review submittals that do not bear Contractor's approval and will return them without action.

5. Unless additional copies are required for final submittal, and unless the Contracting Officer (CO) observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

6. Submittals must be submitted in electronic PDF format. Submit to CO via email or electronic file transfer site.

7. Only final submittals with mark indicating action taken by Government are to be used for construction.

8. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

B. Processing Time: Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Government will review initial submittal within 12 calendar days.

Additional time may be needed if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittals: If resubmittal is necessary, it will be resubmitted within 3 calendar days, and reviewed by the Government within 3 calendar days.

5.3 ACTION SUBMITTALS

A. Prepare and submit Action Submittals required in the Technical Specifications in this contract, if applicable, and as indicated at the end of this subsection.

B. Collect information into a single submittal for each element of construction and type of product or equipment.

1. Mark up each submittal to show which products and options are applicable.

2. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Required Action Submittals

1. Product Data: See Technical Specification Sections.

5.4 INFORMATIONAL SUBMITTALS

MULTIPLE BUILDING LIFE SAFETY 010150 – 7

A. Prepare and submit Informational Submittals required in the Technical Specifications in this contract, if applicable, and as indicated below:

B. Required Informational Submittals:

1. Accident Prevention Plan.

2. Construction Schedule.

3. Current licensure and/or certifications for individuals indicated in

QUALIFICATIONS paragraph above or as required in individual technical sections.

5.5 CLOSEOUT SUBMITTALS

A. Prepare and submit Closeout Submittals, as follows:

1. See Technical Specification Sections.

2. One-Year Warranty on Entire Project as required by FAR 52.246–21

3. Project Record Documents.

PART 4 – TEMPORARY FACILITIES AND CONTROLS

8.1 USE OF UTILITIES

A. Utilities: Use of Government existing facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in an acceptable condition. At Substantial Completion, restore these facilities to condition existing before initial use. The following are available for use by the contractor: water, and electrical power services. The following are not available: telephone service. The contractor is expected to provide whatever phone service he deems necessary for the duration of the project.

8.2 SANITARY FACILITIES

A. Sanitary facilities are available for use by the Contractor. Facilities must be cleaned and maintained daily.

8.3 STAGING AND STORAGE

A. Coordinate on-site staging and storage requirements with the Center Point of Contact or the Contracting Officer Representative (COR).

MULTIPLE BUILDING LIFE SAFETY 010150 – 8

8.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Use of Government waste containers will not be permitted.

8.5 SAFETY AND ENVIRONMENTAL PROTECTION

A. Environmental Protection: Contractor shall provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Barricades, Warning Signs, and Lights: Comply with the national or state Manual on Uniform Traffic Control Devices (MUTCD) for erecting structurally adequate barricades, paint with appropriate colors, graphics, and warning signs/lights to inform personnel, students, and the public of possible hazards.

C. Fire Protection.

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 5 – EXECUTION REQUIREMENTS

9.1 EXAMINATION

A. Before beginning work, examine areas and document existing conditions. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

B. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

C. Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

9.2 INSTALLATION

MULTIPLE BUILDING LIFE SAFETY 010150 – 9

A. Locate the Work and components of the Work accurately, in correct alignment and elevation to fit with existing construction.

B. Make vertical work plumb and make horizontal work level.

C. Install per manufacturer's written instructions and recommendations.

9.3 PROGRESS CLEANING

A. Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Comply with NFPA 241 requirements for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

B. Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

9.4 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide protection and maintain conditions that ensure installed Work does not get damaged or deteriorated prior to Substantial Completion.

9.5 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

PART 6 – CLOSEOUT PROCEDURES

10.1 SUBSTANTIAL COMPLETION

A. Definition of Substantial Completion: The Date certified by the CO when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise the CO of pending insurance changeover requirements.

MULTIPLE BUILDING LIFE SAFETY 010150 – 10

3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.

4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities.

5. Deliver tools, spare parts, extra materials, and similar items to location designated by Government. Label with manufacturer's name and model number where applicable.

6. Complete startup testing of systems.

7. Submit changeover information related to Government occupancy, use, operation, and maintenance.

8. Complete final cleaning requirements, including touchup painting.

9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final

Completion.

10.2 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspections: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

MULTIPLE BUILDING LIFE SAFETY 010150 – 11

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

10.3 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit two copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

10.4 PROJECT RECORD DOCUMENTS

A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.

B. Provide Draft of Project Record Drawings at Substantial Completion. CO will return reviewed copy. Provide Final Project Record Drawings at Final Completion.

C. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.

1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.

b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.

4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;

bind each set with durable paper cover sheets. Include identification on cover sheets.

10.5 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

MULTIPLE BUILDING LIFE SAFETY 010150 – 12

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

D. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

042200 - 1

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

SECTION 042200 - CONCRETE UNIT MASONRY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Concrete masonry units.

2. Steel Lintels

3. Steel reinforcing bars.

1.2 DEFINITIONS

A. CMU(s): Concrete masonry unit(s).

B. Reinforced Masonry: Masonry containing reinforcing steel in grouted cells.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.4 INFORMATIONAL SUBMITTALS

A. Material Certificates: For each type and size of product. For masonry units, include data on material properties.

B. Mix Designs: For each type of mortar and grout. Include description of type and proportions of ingredients.

1. Include test reports for mortar mixes required to comply with property specification. Test in accordance with ASTM C109/C109M for compressive strength, ASTM C1506 for water retention, and ASTM C91/C91M for air content.

2. Include test reports, in accordance with ASTM C1019, for grout mixes required to comply with compressive strength requirement.

1.5 FIELD CONDITIONS

A. Cold-Weather Requirements: Do not use frozen materials or materials mixed or coated with ice or frost. Do not build on frozen substrates. Remove and replace unit masonry damaged by frost or by freezing conditions. Comply with cold-weather construction requirements contained in

TMS 602/ACI 530.1/ASCE 6.

B. Hot-Weather Requirements: Comply with hot-weather construction requirements contained in

TMS 602/ACI 530.1/ASCE 6.

042200 - 2

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

PART 2 - PRODUCTS

2.1 UNIT MASONRY, GENERAL

A. Masonry Standard: Comply with TMS 602/ACI 530.1/ASCE 6, except as modified by requirements in the Contract Documents.

B. Defective Units: Do not use units with chips, cracks, or other defects.

2.2 CONCRETE MASONRY UNITS

A. Shapes: Provide shapes indicated and as follows, with exposed surfaces matching exposed faces of adjacent units unless otherwise indicated.

1. Provide special shapes for lintels, corners, jambs, sashes, movement joints, headers, bonding, and other special conditions.

B. CMUs: ASTM C90.

2.3 CONCRETE LINTELS

A. Steel-Masonry Lintels: Galvanized steel, double-tee lintel.

1. Powers Steel Composite Lintels.

a. Other manufacturer’s products may be accepted provided the product information associated with the alternate meets or exceeds the load capacity of the specified composite lintel.

2.4 MORTAR AND GROUT MATERIALS

A. Portland Cement: ASTM C150/C150M, Type I or II, except Type III may be used for cold-weather construction. Provide natural color or white cement as required to produce mortar color indicated.

B. Hydrated Lime: ASTM C207, Type S.

C. Portland Cement-Lime Mix: Packaged blend of portland cement and hydrated lime containing no other ingredients.

D. Masonry Cement: ASTM C91/C91M.

E. Aggregate for Mortar: ASTM C144.

F. Aggregate for Grout: ASTM C404.

G. Cold-Weather Admixture: If utilized; Nonchloride, noncorrosive, accelerating admixture complying with ASTM C494/C494M, Type C, and recommended by manufacturer for use in masonry mortar of composition indicated.

042200 - 3

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

H. Water: Potable.

2.5 REINFORCEMENT

A. Uncoated-Steel Reinforcing Bars: ASTM A615/A615M or ASTM A996/A996M, Grade 60.

B. Reinforcing Bar Positioners: Wire units designed to fit into mortar bed joints spanning masonry unit cells and to hold reinforcing bars in center of cells. Units are formed from 0.148-inch steel wire, hot-dip galvanized after fabrication. Provide units designed for number of bars indicated.

C. Masonry-Joint Reinforcement, General: ASTM A951/A951M.

1. Exterior Walls: Hot-dip galvanized carbon or Stainless steel.

2.6 TIES AND ANCHORS

A. Materials: Provide ties and anchors specified in this article that are made from materials that comply with the following unless otherwise indicated:

1. Hot-Dip Galvanized, Carbon-Steel Wire: ASTM A82/A82M, with ASTM A153/A153M, Class B-2 coating.

2. Steel Sheet, Galvanized after Fabrication: ASTM A1008/A1008M, Commercial Steel, with ASTM A153/A153M, Class B coating.

3. Steel Plates, Shapes, and Bars: ASTM A36/A36M.

B. Adjustable Anchors for Connecting to Structural Steel Framing: Provide anchors that allow vertical or horizontal adjustment but resist tension and compression forces perpendicular to plane of wall.

1. Tie Section: Triangular-shaped wire tie made from 0.187-inch- diameter, hot-dip galvanized-steel wire.

C. Adjustable Anchors for Connecting to Concrete: Provide anchors that allow vertical or horizontal adjustment but resist tension and compression forces perpendicular to plane of wall.

1. Corrugated-Metal Ties: Metal strips not less than 7/8 inch wide with corrugations having a wavelength of 0.3 to 0.5 inch and an amplitude of 0.06 to 0.10 inch made from 0.060-inch-thick steel sheet, galvanized after fabrication 0.105-inch-thick steel sheet, galvanized after fabrication with dovetail tabs for inserting into dovetail slots in concrete.

D. Partition Top Anchors: 0.105-inch-thick metal plate with a 3/8-inch-diameter metal rod 6 inches long welded to plate and with closed-end plastic tube fitted over rod that allows rod to move in and out of tube. Fabricate from steel, hot-dip galvanized after fabrication.

2.7 EMBEDDED FLASHING MATERIALS

A. Metal Flashing: Provide metal flashing complying with SMACNA's "Architectural Sheet Metal Manual" and as follows:

1. Stainless Steel: ASTM A240/A240M or ASTM A666, Type 304, 0.016 inch thick.

042200 - 4

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

2. Fabricate continuous flashings. Provide splice plates at joints of formed, smooth metal flashing.

B. Adhesives, Primers, and Seam Tapes for Flashings: Flashing manufacturer's standard products or products recommended by flashing manufacturer for bonding flashing sheets to each other and to substrates.

2.8 MISCELLANEOUS MASONRY ACCESSORIES

A. Bond-Breaker Strips: Asphalt-saturated felt complying with ASTM D226/D226M, Type I (No. 15 asphalt felt).

2.9 MORTAR AND GROUT MIXES

A. General: Do not use admixtures, including pigments, air-entraining agents, accelerators, retarders, water-repellent agents, antifreeze compounds, or other admixtures unless otherwise indicated.

1. Do not use calcium chloride in mortar or grout.

2. Use portland cement-lime or masonry cement mortar unless otherwise indicated.

B. Mortar for Unit Masonry: Comply with ASTM C270, Proportion Specification. Provide the following types of mortar for applications stated unless another type is indicated.

1. For exterior, above-grade, load-bearing and nonload-bearing walls and parapet walls; for interior load-bearing walls; for interior nonload-bearing partitions; and for other applications where another type is not indicated, use Type N.

C. Grout for Unit Masonry: Comply with ASTM C476.

1. Use grout of type indicated or, if not otherwise indicated, of type (fine or coarse) that will comply with TMS 602/ACI 530.1/ASCE 6 for dimensions of grout spaces and pour height.

2. Proportion grout in accordance with ASTM C476, Table 1.

3. Provide grout with a slump of 8 to 11 inches as measured in accordance with

ASTM C143/C143M.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Use full-size units without cutting if possible. If cutting is required to provide a continuous pattern or to fit adjoining construction, cut units with motor-driven saws; provide clean, sharp, unchipped edges. Allow units to dry before laying unless wetting of units is specified. Install cut units with cut surfaces and, where possible, cut edges concealed.

042200 - 5

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

3.2 TOLERANCES

A. Dimensions and Locations of Elements:

1. For dimensions in cross section or elevation, do not vary by more than plus 1/2 inch or minus 1/4 inch.

2. For location of elements in plan, do not vary from that indicated by more than plus or minus 1/2 inch.

3. For location of elements in elevation, do not vary from that indicated by more than plus or minus 1/4 inch in a story height or 1/2 inch total.

B. Lines and Levels:

1. For bed joints and top surfaces of bearing walls, do not vary from level by more than 1/4 inch in 10 feet, or 1/2-inch maximum.

2. For conspicuous horizontal lines, such as lintels, sills, parapets, and reveals, do not vary from level by more than 1/8 inch in 10 feet, 1/4 inch in 20 feet, or 1/2-inch maximum.

3. For vertical lines and surfaces, do not vary from plumb by more than 1/4 inch in 10 feet, 3/8 inch in 20 feet, or 1/2-inch maximum.

4. For conspicuous vertical lines, such as external corners, door jambs, reveals, and expansion and control joints, do not vary from plumb by more than 1/8 inch in 10 feet, 1/4 inch in 20 feet, or 1/2-inch maximum.

5. For lines and surfaces, do not vary from straight by more than 1/4 inch in 10 feet, 3/8 inch in 20 feet, or 1/2-inch maximum.

C. Joints:

1. For bed joints, do not vary from thickness indicated by more than plus or minus 1/8 inch, with a maximum thickness limited to 1/2 inch.

2. For head and collar joints, do not vary from thickness indicated by more than plus 3/8 inch or minus 1/4 inch.

3. For exposed head joints, do not vary from thickness indicated by more than plus or minus 1/8 inch.

3.3 LAYING MASONRY WALLS

A. Lay out walls in advance for accurate spacing of surface bond patterns with uniform joint thicknesses and for accurate location of openings, movement-type joints, returns, and offsets.

Avoid using less-than-half-size units, particularly at corners, jambs, and, where possible, at other locations.

B. Bond Pattern for Exposed Masonry: Unless otherwise indicated, lay exposed masonry in running bond; do not use units with less-than-nominal 4-inch horizontal face dimensions at corners or jambs.

C. Built-in Work: As construction progresses, build in items specified in this and other Sections.

Fill in solidly with masonry around built-in items.

D. Fill space between steel frames and masonry solidly with mortar unless otherwise indicated.

042200 - 6

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

E. Where built-in items are to be embedded in cores of hollow masonry units, place a layer of metal lath, wire mesh, or plastic mesh in the joint below, and rod mortar or grout into core.

F. Fill cores in hollow CMUs with grout 24 inches under bearing plates, beams, lintels, posts, and similar items unless otherwise indicated.

3.4 MORTAR BEDDING AND JOINTING

A. Lay hollow CMUs as follows:

1. Bed face shells in mortar and make head joints of depth equal to bed joints.

2. Bed webs in mortar in all courses of piers, columns, and pilasters.

3. Bed webs in mortar in grouted masonry, including starting course on footings.

4. Fully bed entire units, including areas under cells, at starting course on footings where cells are not grouted.

B. Lay solid CMUs with completely filled bed and head joints; butter ends with sufficient mortar to fill head joints and shove into place. Do not deeply furrow bed joints or slush head joints.

C. Tool exposed joints slightly concave when thumbprint hard, using a jointer larger than joint thickness unless otherwise indicated.

3.5 MASONRY-JOINT REINFORCEMENT

A. General: Install entire length of longitudinal side rods in mortar with a minimum cover of 5/8 inch on exterior side of walls, 1/2 inch elsewhere.

B. Provide continuity at wall intersections by using prefabricated T-shaped units.

3.6 FLASHING

A. General: Install embedded flashing at ledges and other obstructions to downward flow of water in wall where indicated.

B. Install flashing as follows unless otherwise indicated:

1. At lintels, extend flashing a minimum of 6 inches into masonry at each end. At heads and sills, extend flashing 6 inches at ends and turn up not less than 2 inches to form end dams.

3.7 REINFORCED UNIT MASONRY

A. Temporary Formwork and Shores: Construct formwork and shores as needed to support reinforced masonry elements during construction.

1. Construct formwork to provide shape, line, and dimensions of completed masonry as indicated. Make forms sufficiently tight to prevent leakage of mortar and grout. Brace, tie, and support forms to maintain position and shape during construction and curing of reinforced masonry.

042200 - 7

GREAT ONYX JOB CORPS CCC

CONCRETE UNIT

MASONRY

2. Do not remove forms and shores until reinforced masonry members have hardened sufficiently to carry their own weight and that of other loads that may be placed on them during construction.

B. Placing Reinforcement: Comply with requirements in TMS 602/ACI 530.1/ASCE 6.

C. Grouting: Do not place grout until entire height of masonry to be grouted has attained enough strength to resist grout pressure.

1. Comply with requirements in TMS 602/ACI 530.1/ASCE 6 for cleanouts and for grout placement, including minimum grout space and maximum pour height.

3.8 REPAIRING, POINTING, AND CLEANING

A. In-Progress Cleaning: Clean unit masonry as work progresses by dry brushing to remove mortar fins and smears before tooling joints.

B. Final Cleaning: After mortar is thoroughly set and cured, clean exposed masonry as follows:

1. Clean concrete masonry by applicable cleaning methods indicated in NCMA TEK 8-4A.

3.9 MASONRY WASTE DISPOSAL

A. Excess Masonry Waste: Remove excess masonry waste and legally dispose of off Owner's property.

END OF SECTION 042200

GREAT ONYX JOB CORPS CCC

055213 - 1

PIPE AND TUBE RAILINGS

SECTION 055213 - PIPE AND TUBE RAILINGS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Steel railings.

1.2 ACTION SUBMITTALS

A. Product Data:

1. Handrail brackets.

2. Shop primer.

3. Intermediate coats and topcoats.

PART 2 - PRODUCTS

2.1 METALS, GENERAL

A. Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller marks, rolled trade names, stains, discolorations, or blemishes.

B. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as supported rails unless otherwise indicated.

1. Provide type of bracket with predrilled holes for exposed bolt anchorage and that provides 1-1/2-inch clearance from inside face of handrail to finished wall surface.

2.2 STEEL RAILINGS

A. Pipe: ASTM A53/A53M, Type F or Type S, Grade A, Standard Weight (Schedule 40), unless another grade and weight are required by structural loads.

B. Cast Iron Fittings: Either gray iron, ASTM A48/A48M, or malleable iron, ASTM A47/A47M, unless otherwise indicated.

2.3 FASTENERS

A. Fastener Materials:

1. Ungalvanized-Steel Railing Components: Plated steel fasteners complying with ASTM F1941/ASTM F1941M, Class Fe/Zn 5 for zinc coating.

055213 - 2

PIPE AND TUBE RAILINGS

B. Post-Installed Anchors: Fastener systems with working capacity greater than or equal to the design load, according to an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC193.

1. Material for Interior Locations: Carbon-steel components zinc-plated to comply with ASTM B633 or ASTM F1941/F1941M, Class Fe/Zn 5, unless otherwise indicated.

2.4 MISCELLANEOUS MATERIALS

A. Handrail Brackets: ADA compliant cast iron. Kee Safety 570-7 or approved equal.

B. Handrail Returns: ADA compliant wall returns with wall mount flange. Kee Safety 565-7 or equal.

C. Welding Rods and Bare Electrodes: Select in accordance with AWS specifications for metal alloy welded.

D. Epoxy Zinc-Rich Primer: Complying with MPI#20 and compatible with topcoat.

E. Intermediate Coats and Topcoats: Gloss, zero VOC latex paint compatible with primer.

2.5 FABRICATION

A. Cut, drill, and punch metals cleanly and accurately.

1. Remove burrs and ease edges to a radius of approximately 1/32 inch unless otherwise indicated.

2. Remove sharp or rough areas on exposed surfaces.

B. Form work true to line and level with accurate angles and surfaces.

C. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove flux immediately.

4. At exposed connections, finish exposed welds to comply with NOMMA's "Voluntary

Joint Finish Standards" for Finish #2 welds; good appearance, completely sanded joint, some undercutting and pinholes okay.

D. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings.

Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.

E. Form changes in direction as follows:

1. By bending or by inserting prefabricated elbow fittings.

055213 - 3

PIPE AND TUBE RAILINGS

F. Bend members in jigs to produce uniform curvature for each configuration required. Maintain cross section of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming exposed surfaces of components.

G. Close exposed ends of hollow railing members with prefabricated cap and end fittings of same metal and finish as railings.

H. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated.

I. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated.

J. Provide inserts and other anchorage devices for connecting railings to concrete or masonry work.

1. As detailed.

2.6 STEEL AND IRON FINISHES

A. For nongalvanized-steel railings, provide nongalvanized ferrous-metal fittings, brackets, fasteners, and sleeves.

B. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with SSPC- SP 6/NACE No. 3.

1. Railings Indicated To Receive Zinc-Rich Primer: SSPC-SP 6/NACE No. 3.

C. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1 for shop painting. Primer need not be applied to surfaces to be embedded in concrete or masonry.

D. Shop-Painted Finish: Comply with manufacturer’s instructions.

1. Color: Black.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Perform cutting, drilling, and fitting required for installing railings.

1. Fit exposed connections together to form tight, hairline joints.

2. Install railings level, plumb, square, true to line; without distortion, warp, or rack.

3. Set railings accurately in location, alignment, and elevation; measured from established lines and levels.

4. Do not weld, cut, or abrade surfaces of railing components that are coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting.

5. Align rails so variations from level for horizontal members and variations from parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet.

055213 - 4

PIPE AND TUBE RAILINGS

3.2 ATTACHING RAILINGS

A. Attach handrails to walls with wall brackets, except where end flanges are used. Provide brackets with 1-1/2-inch clearance from inside face of handrail and finished wall surface.

B. Secure wall brackets and railing end flanges to building construction as follows:

1. As scheduled or:

a. For concrete and solid masonry anchorage, use drilled-in expansion shields and hanger or lag bolts.

b. For hollow masonry anchorage, use toggle bolts.

C. Touchup Painting:

1. Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material used for shop painting to comply with SSPC-PA 1 for touching up shop-painted surfaces.

3.3 CLEANING

A. Clean by washing thoroughly with clean water and soap and rinsing with clean water.

END OF SECTION 055213

MULTIPLE BUILDING LIFE SAFETY 283111 – 1

GREAT ONYX JOB CORPS CCC ADDRESSABLE FIRE ALARM SYSTEM

SECTION 283111

ADDRESSABLE FIRE ALARM SYSTEM

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes addressable fire alarm and carbon monoxide devices; including detectors, manual stations, notification devices, fire alarm panels, annunciators, wiring, conduits, and other related items.

1.2 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplemen-tary Conditions and Division 1 Specifications, apply to this Section.

1.3 SUBMITTALS

A. As specified in Specification 01-0150 “Submittal Procedures.”

1. Product Data: Submit manufacturer's literature for detectors, manual stations, and control panels including all required modules, wire and raceway, detector removal tool, detector tester.

B. Closeout Submittals: As specified in Specification 01-0150 “Closeout Procedures.”

1. Field quality-control test reports.

2. Final Documentation including the following:

a. Approval and Acceptance: Provide the “Record of Completion” form according to NFPA 72 and NFPA 720.

b. Record Drawings: Provide the “Permanent Records” according to NFPA 72 and 720. Drawings shall include:

1) Plan views showing the actual location, designation, and interconnection of all system devices, including junction boxes.

2) Detailed single-line wiring schematics showing wiring terminations at panels and devices remote from the panel for each loop or zone.

3. Manufacturer's operation and maintenance data for all initiation, annunciation, and control devices.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: Personnel trained and certified by manufacturer for installation of equipment. All work has to be done or supervised by a NICET Level 3 or 4.

MULTIPLE BUILDING LIFE SAFETY 283111 – 2

B. Source Limitations for Fire Alarm Systems and Components:

C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in

NFPA 70.

D. Performance: Comply with NFPA 72 and NFPA 720.

PART 2 – PRODUCTS

2.1 MANUFACTURER

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the manufacturers specified. Matching the current systems of the center is preferred.

1. Furnish devices of the same manufacturer and compatible with existing fire alarm systems.

2.2 DETECTORS

A. General: Comply with UL 268, operating at 24-V dc, nominal two or four wire type.

1. Integral Addressable Module: Communicates detector status (normal, alarm, or trouble) to fire alarm panel.

2. Base: Twist-lock module that connects to a fixed base. Provide terminals in the fixed base for connection to building wiring.

3. Self-Restoring detectors that do not require resetting or readjustment after actua-tion to restore them to normal operation.

4. Integral Visual Indicating Light: LED or similar type light indicating detector has operated and power-on status.

B. Photoelectric/Thermal: Actuated by either photoelectric or thermal inputs with remote sensitivity adjustment.

2.3 DUCT SMOKE DETECTORS

a. Comply with UL 268A.

b. Base Mounting: Detector and associated electronic components shall be mounted in a twist-lock module that connects to a fixed base. The fixed base shall be designed for mounting directly to air duct. Provide terminals in the fixed base for connection to building wiring.

1) Weatherproof Duct Housing Enclosure: NEMA 250, Type 4X; listed for use with the supplied detector.

c. Sampling Tubes: Design and dimensions as recommended by manufactur-er for specific duct size, air velocity, and installation conditions where ap-plied.

d. Relay Fan Shutdown: Rated to interrupt fan motor-control circuit.

MULTIPLE BUILDING LIFE SAFETY 283111 – 3

2.4

A. General: Comply with UL 2075, operating at 24-V dc, nominal.

1. Internal electro-chemical sensor with on-board microprocessor and automatic drift compensation to track CO levels over time.

2. 150mA output relay: Normally open or normally closed relay allows interface with intrusion or fire alarm systems.

3. CO Alarm Level: 70 ppm/60-240 minutes.

4. Sounder: 85 dBa temporal 4-sounder for local notification.

5. Sensor Service Life: 10 years with end-of-life timer to indicate the device re-quires service. End-of-life timer to provide indication at the detector and control panel.

2.5 PULL STATION

A. Manual Fire Alarm Station: Comply with UL 38.

1. General: Single action, pull lever type, finished in red with molded, raised-letter operating instructions. Provide with integral addressable module to communi-cate pull station status (normal, alarm, trouble) to fire alarm panel.

2. Outlet box: Manufacturer’s recessed or surface mounted back box.

3. Station Reset: Key-or wrench operated switch. Provide reset tool with pull sta-tion.

4. Indoor Protective Shield: Where indicated, provide factory-fabricated wire guard or clear plastic enclosure hinged at the top to permit lifting for access to initiate an alarm.

2.6 INITIATING AND INTERFACE DEVICES

A. Intelligent, microprocessor based, interface module, single input to monitor normally open or closed dry contact and reports the contact’s status to the control panel.

2.7 RACEWAYS

A. General: All cables and conductors shall be installed in raceways.

B. EMT: UL 797 electrical metallic tubing; ANSI C80.3, zinc-coated steel.

1. Fittings and Conduit Bodies: ANSI/NEMA FB 1; steel compression or set screw type.

2.8 WIRE:

A. General: UL listed and labeled.

B. Signaling Line Circuits: Twisted, shielded pair, No. 18 AWG unless other size recommended by system manufacturer. Red insulation jacket.

MULTIPLE BUILDING LIFE SAFETY 283111 – 4

C. Non-Power-Limited Circuits: Solid-copper conductors with 600-V rated, 75oC, color-coded insulation. Red insulation jacket.

1. Low-Voltage Circuits: No. 16 AWG, minimum.

2. Line-Voltage Circuits: No. 12 AWG, minimum.

PART 3 – EXECUTION

3.1 FIRE DETECTION REMOVAL AND EXTENSION OF EXISTING FIRE

DETECTION WORK

A. Verify that abandoned wiring and equipment serve only abandoned facilities. Main-tain electrical continuity to remaining wiring and equipment.

B. If during construction electrical conductors, conduits, or equipment to remain is dam-aged in appearance or is unserviceable, remove damaged or unserviceable portions and replace with new products of equal capacity and quality.

C. Where the reuse of existing conduits, outlets, junction boxes, etc. is permissible, make certain that the wiring for them is continuous from device to device.

D. Provide temporary wiring and connections to maintain existing systems in service dur-ing construction.

E. Remove exposed abandoned conduit, including abandoned conduit above accessible ceiling finishes. Cut conduit flush with walls and floors, and patch surfaces.

F. Repair adjacent construction and finishes damaged during demolition and extension work. Provide modifications to assure that circuits or systems wiring shall not pass through outlet or junction boxes that may be rendered inaccessible by changes made to the building.

G. Connect new work to existing work in a manner that will assure proper raceway grounding throughout in conformance with the National Electrical Code.

H. Removed conduits, wire, devices, fixtures, etc. become the property of the Contractor unless otherwise noted.

3.2 EQUIPMENT INSTALLATION

A. Comply with NFPA 72 for installation of fire alarm equipment.

B. Detectors, Panels, and Related Equipment: Install in accordance with manufacturer's recommendations.

C. Connecting to Existing Equipment: Verify that existing fire alarm system is operational prior to purchasing any equipment or making any modifications.

MULTIPLE BUILDING LIFE SAFETY 283111 – 5

Demonstrate to the Contracting Officer that the existing fire alarm system operates correctly in trouble and alarm modes and that all existing devices operate correctly.

1. Provide expansion and module cards to enable new equipment to connect to ex-isting devices.

2. Verify the manufacture and type of devices connected to each fire alarm system undergoing modifications.