23-0013-UT_(418683)_-_Clearwater_NEWRF_Digester_Repairs_Bid_Set_Drawings_M-101_2026-08-24.pdf

PDF 4 MB Posted

Attached to
Northeast WRF Digester Repairs
Solicitation number
23-0013-UT
Issued by
Pinellas County, Clewiston City, Florida

About this file

Bid Set Drawing for Northeast WRF Digester Repairs

This is a bid set drawing (Sheet M-101) prepared by the City of Clearwater, Florida Public Utilities for the Northeast Water Reclamation Facility Digester Repairs project under ITB 23-0013-UT. The drawing provides an enlarged site plan at 3/16" = 1'-0" scale depicting the primary and secondary digesters and the work required within the digester facility. The scope includes draining and cleaning of the primary anaerobic digester (90 feet diameter), lifting and removal of the digester cover, comprehensive internal and external inspections, and subsequent repairs and replacements. Key work items shown on the drawing include replacement of multiple 6-inch and 8-inch plug valves, inspection and potential replacement of digester gas piping and sludge feed piping, inspection and potential replacement of four double mixing nozzles and two single mixing nozzles, and replacement of approximately 18 concrete corbels offset from original locations. The drawing indicates that approximately 200 feet of temporary drainage pipe will be required to direct digester discharge to Lift Station #2, and draining operations must be coordinated with the City. The contract period is 365 consecutive calendar days, with bids due August 26, 2026, and pre-qualification required ten workdays prior to the bid opening.

The bid set drawing notes that all existing piping and valves requiring replacement are flanged connections and that piping not replaced shall be cleaned, surface-prepared, and recoated. The drawing cross-references additional specification details and notes that not all required work is depicted on this plan, requiring contractors to perform all work as specified in the bid form and other contract documents. Concrete inspections will determine repair scope including crack repair, spall repair, and ballast block replacement, with a tabulation of recommended replacements and repairs to be developed by the contractor for City and Engineer approval prior to execution. Bid security of 10 percent of the maximum bid price is required, and subcontract work shall not exceed 50 percent of total work without Engineer approval. The pricing sheet contains 28 base bid line items with various quantity measures (lump-sum, linear feet, square feet, ton, and unit pricing), plus contingency and alternate pricing options for digester cover replacement, with unit prices limited to two decimal points.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENLARGED SITE PLAN

3/16" =1'-0"

2'4'6' 10'5'0

3/16"=1'-0"

REPLACE 6" PLUG VALVE

REPLACE 6" PLUG VALVE

REPLACE 6" PLUG VALVE

REPLACE 8" PLUG VALVE

DOUBLE NOZZLE

(TYP OF 4), SEE NOTE 4SEE NOTE 3

INSPECT PIPING AFTER TANK

HAS BEEN DRAINED AND CLEANED.

REPLACE IF DAMAGED OR

HAS SEVERE CORROSION. EXISTING

PIPING NOT REPLACED SHALL BE

CLEANED, SURFACE-PREPARED, AND

RECOATED.

DEMO AND REPLACE ALL EXISTING

CORBELS OFFSET FROM ORIGINAL

LOCATIONS (TYPICAL OF 18)

REPLACE 8" PLUG VALVE

REPLACE 6" PLUG VALVE

REPLACE 8" PLUG VALVE

NOTES:

1. ALL EXISTING PIPE AND VALVES SHOWN TO BE REPLACED ARE FLANGED.

2. ALL EXISTING PIPING SHOWN TO BE INSPECTED AND POTENTIALLY

REPLACED INCLUDES DIP AND SS DIGESTER GAS PIPING.

3. INSPECT ALL PIPING INSIDE DIGESTER AFTER TANK HAS BEEN DRAINED AND CLEANED.

CONTRACTOR TO COORDINATE WITH OWNER AND ENGINEER TO IDENTIFY

PIPING THAT NEEDS TO BE REPLACED.

4. INSPECT MIXING NOZZLES AFTER TANK HAS BEEN DRAINED AND CLEANED.

CONTRACTOR TO COORDINATE WITH OWNER AND ENGINEER TO IDENTIFY

NOZZLES THAT NEED TO BE REPLACED.

5. NOT ALL REQUIRED WORK INSIDE THE EXISTING PRIMARY DIGESTER AND DIGESTER BUILDING

ARE SHOWN ON THIS DRAWING. CONTRACTOR SHALL PERFORM ALL WORK AS SPECIFIED OR

NOTED IN THE BID FORM.

6. DIGESTER DRAINING DISCHARGE TO BE DIRECTED TO LIFT STATION #2. LIFT STATION #2 LOCATION

IS SHOWN IN SHEET C-101. APPROXIMATELY 200' OF TEMPORARY PIPE WILL BE NEEDED FOR

DRAINAGE. DRAINAGE OPERATION OF THE PRIMARY DIGESTER IS TO BE COORDINATED WITH THE CITY. CONTRACTOR AND CITY TO DETERMINE THE SAFEST METHOD OF PLACING THE PUMP IN THE

TANK FOR DRAINAGE.

7. ALL EXISTING PIPING NOT REPLACED SHALL BE CLEANED, SURFACE-PREPARED, AND RECOATED.

DIGESTER BUILDING WALL

M-301

EXISTING DIGESTER BUILDING WALL

SINGLE MIXING NOZZLE (TYP OF 2)

SEE NOTE 4.

CONTRACTOR SHALL DRAIN , REMOVE

ALL SLUDGE FROM, AND CLEAN PRIMARY

DIGESTER AND PERFORM INSPECTIONS,

REHABILITATION / REPLACEMENT

WORK AND RECOATING, AS SPECIFIED

EXISTING 65' Ø

SECONDARY DIGESTER

EXISTING

DIGESTER

BUILDING

EXISTING 90' Ø

PRIMARY DIGESTER

CONTRACTOR SHALL INSPECT

CONCRETE FOR DAMAGE ONCE

DIGESTER IS DRAINED AND CLEANED.

REPAIR AND RECOATING WORK TO BE

AS SPECIFIED. ADDITIONAL REPAIR

DETAILS IF NEEDED SHALL BE

PROVIDED AT THAT TIME.

A M-301

NOZZLE DETAIL

PUMP TO BE INSERTED

THROUGH THE ENTRANCE

HATCH TO DRAIN DIGESTER

(SEE NOTE 6).

EXISTING PIPING NOT REPLACED SHALL BE CLEANED, SURFACE-PREPARED, AND RECOATED.

RECORD DRAWINGS

SURVEYED BY:

APPROVED BY:

REVIEWED BY:

PROJECT ENGINEER

DRAWN BY:

DATE

DATE

REVISION BY DATE

CALL 811

SHEET NO.:

CONTRACT NO.: DATE DRAWN:

DESIGNED BY:

SURVEYED BY:

APPROVED BY

HORIZ.

DRAWN BY:

VERT.

SCALE:DWG NAME: FIELD BOOK:

CHECKED BY:

DATE

JOB NO.:

INVESTIGATE BEFORE YOU EXCAVATE

SUNSHINE STATE

ONE CALL

OF FLORIDA

www.callsunshine.com

(800) 432-4770

MIN. 48 HOURS

BEFORE YOU EXCAVATE

CITY OF CLEARWATER, FLORIDA

PUBLIC UTILITIES

100 S. MYRTLE AVE.

CLEARWATER, FL 33756

OFDIGESTER PLAN

M-101

418683

MAY 2026 SBD

MSN AW 6 12

This item has been digitally signed and sealed by Michael Stephen Nellis on the date adjacent to the seal.

Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.

BID SET

23-0013-UT

Quantity of double nozzles corrected. MN 8/24/26

1 1