22R0006_Attachment_3_Sample Lifting Requirements.pdf

PDF 61 KB Posted

Attached to
Mobile Crane and Qualified Crane Operator Services IDIQ- PNSY Federal contract opportunity
Solicitation number
N3904022R0006
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Component Load Weight Radius Where Time Min Duration Type of Crane Notes

Topside Diesel 12,500 74' Berth 6 area As Needed 2 hours 120T (265T in wind)

Removal. Sits 2' STBD from CL. 120T crane can't support in wind.

Forward Ship Lifts 2,500 & 6,800 80' Berth 6 area As Needed 2 week 120T Installation

Sail Population 4,320 (Project SM) 7,400 (Project SM)

74' Berth 6 area As Needed 3 weeks 120T Preferred 2 hooks or 2 cranes

Blast Facility Components

43,500 (59,500 ‐ 85,500)

55' Berth 6 area As Needed 1 day (multiple times) 120T or 265T

Moving parts into / out of blast facility.

Blast Equipment 18,000 ‐ 24,500 55' Berth 6 area As Needed

1 day (multiple times)

120T

Forward Ship Lifts 10,500 72' Berth 6 area As Needed 1 week 120T (265T in wind) 120T crane can't support in wind.

Mid Ship Lifts 30,000 75' Berth 6 area If Needed 4 hours 265T Mid Ship Lifts 25,500 75' Berth 6 area If Needed 4 hours 265T Coast Guard Needs Various Various Berth 6 / 7 area If Needed Various CG sits closer to pier than submarines.

Pease Needs Various Various Pease Air Port If Needed Various

Time Period: Oct 2021 to Oct 2026

Center of rails to Piers Edge: 29' 9.7" Piers Edge to CL: 42' 2" Piers Edge to CL: 44' 10"

This chart identifies examples of lifting requirements that have been performed on prior contracts. This list is not all inclusive and future requirements may not be similar to the examples depicted.