About this file

This document is an Addendum for a construction project solicitation issued by the Florida Army National Guard Construction & Facility Management Office. The project involves supplying and installing a 40' x 60' enclosed lightweight metal storage building with a divider wall, roll-up doors, electrical service, and HVAC system at the Camp Blanding Joint Training Center in Starke, Florida. Key details include a bid opening date of October 31, 2023 at 2:00 PM, and a requirement for substantial completion within 80 calendar days of the Notice to Proceed. The solicitation also includes two alternate bid items for site preparation and concrete ramps.

The estimated construction cost is $150,000. The solicitation requires that bidders be licensed and qualified per Florida Statutes, and that they acknowledge the addendum on the bid proposal form. The project must comply with applicable building codes, regulations, and permitting requirements. No specific brand requirements are stated for the fire alarm or sprinkler systems, which are not required for this project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Army National Guard

Construction & Facility Management Office

ISSUED ADDENDUM

Rev. 11/2018

Date October 26, 2023

ADDENDUM Number 1

Project Number and Name 223102 CBJTC Lodging Cart Storage Building

Invitation to Bid Date October 6, 2023

Number of Attachments 2

Bid Opening Date and Time Tuesday, October 31, 2023 2:00PM

From: Department of Military Affairs, CFMO Contracting Office

This addendum and the listed attachments forms a part of the contract documents and modifies the original bidding documents. Acknowledgement of this addendum on Bid Proposal form is required.

Concerns with this addendum should be addressed to:

ng.fl.flarng.list.cfmo-contracting@army.mil

Answers to Questions (Q) / Clarifications (C) / Modifications (M)

Q1. Supplementary terms and conditions state that the project is to be substantially complete in 80 calendar days. Current lead time in the building fabrication is between 16 to 20 weeks. The owner is requested to consider this lead time to amend the project duration.

A1. The project duration will not be amended. The substantial completion date is from the date of Notice to Proceed, schedule of which will be coordinated between Contractor and Project Manager. Contractor does not need to wait for NTP to order materials.

Q2. What will be the material for the divider wall from floor to ceiling?

A2. Either metal stub/ 1/2” sheetrock or the same material as the rest of the building.

Q3. What type/material of doors should be the exterior pedestrian ones, aluminum, metal, etc? Can you provide a hardware schedule?

A3. Provide exterior metal door with Best Lockset compatible with Best seven-pin tumblers (spec attached) Best rep. Dormakaba (Jose Droira 1-561-718-0387).

Q4. What type/material of doors should be the interior one, aluminum, metal, wood, etc? Can you provide a hardware schedule?

mailto:ng.fl.flarng.list.cfmo-contracting@army.mil

A4. Provide Interior metal with Best Lockset compatible with owner furnished Best seven-pin tumblers (spec attached) Best rep. Dormakaba (Jose Droira 1-561-718- 0387).

Q5. Does the new fire alarm system have to be a specific brand in order to match with any existing system?

A5. Fire alarm/sprinkler not required

Q6. Can the owner representative locate the fire sprinkler main point of connection?

A6. Fire alarm/sprinkler not required

Attachment List

1. Door Hardware Specifications.PDF

2. Door Specifications.PDF

END OF ADDENDUM #1