22. Attachment D - DPO.pdf
PDF 512 KB Posted
- Attached to
- Lovell Control Building and Breaker Replacement
- Solicitation number
- 89503222BWA000051
About this file
This document outlines contractor requirements for the Department of Energy Order 442.2 concerning Differing Professional Opinions. Contractors must ensure all employees, including subcontractors, are notified quarterly of their right to report unresolved environment, safety, and health technical concerns through the DOE Differing Professional Opinion process. Notification must include contact information for DPO Managers and the DOE DPO website address. Contractors are also responsible for protecting employees from reprisal for filing a DPO, providing reasonable time and resources to use the DPO process, assisting DOE in resolving DPOs as requested, and reporting on implementation and closure of actions resulting from DPO resolutions.
The related federal contract opportunity is solicitation number 89503222BWA000051 from the Department of Energy Western Area Power Administration to replace the control building and breaker at the Lovell facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment D
DPO
89503222BWA000051
15 June 2022
DOE O 442.2 Attachment 1 7-29-11 Page 1-1
CONTRACTOR REQUIREMENTS DOCUMENT
DOE O 442.2, Differing Professional Opinions for Technical Issues Involving Environment, Safety and Health
Regardless of the performer of the work, the contractor is responsible for complying with the requirements of this CRD. The contractor is responsible for flowing down the requirements of this CRD to subcontractors at any tier to the extent necessary to ensure the contractor’s compliance with the requirements. The contractor must:
1. Ensure that all employees and subcontractor employees are notified quarterly that they have the right to report environment, safety, and health technical concerns that have not been resolved through routine work processes through the Department of Energy Differing Professional Opinion (DPO) process (the DOE DPO process can be found in Attachment 2 to DOE O 442.2 found at https://www.directives.doe.gov/directives-documents/400-series/0442.2-BOrder-chg1-pgchg. The notification must provide points of contact (name, phone number and email addresses of DPO Managers) as listed on the DOE DPO web page, as well as the DOE DPO web page address.
2. Protect employees from reprisal or retaliation for reporting a DPO.
3. Provide employees reasonable time and resources to use the DPO Process.
4. Assist DOE as requested in the resolution of DPOs.
5. Report to the DOE when requested on the status of assigned implementation actions resulting from the DPO resolution and on the closure of these implementation actions.
https://www.directives.doe.gov/directives-documents/400-series/0442.2-BOrder-chg1-pgchg https://www.directives.doe.gov/directives-documents/400-series/0442.2-BOrder-chg1-pgchg
File details come from the government source that posted it. Updated .