22. Attachment A - Specifications.pdf

PDF 1 MB Posted

Attached to
Lovell Control Building and Breaker Replacement
Solicitation number
89503222BWA000051
Issued by

About this file

This document outlines specifications for a federal construction contract opportunity to replace control buildings and breakers at the Lovell Substation. Key work includes replacing five 115-kV circuit breakers, installing new voltage transformers, resistors, and a service building. The contractor must furnish concrete foundations, steel structures, electrical equipment, precast cable trenches, and complete construction. Bids are due on specified items such as miscellaneous sitework, demolition, concrete foundations, cable trenches, and steel structures. The government will furnish switchboards, breakers, and other equipment by certain dates. The contractor must provide testing, grounding systems, conduit runs, bus systems, cables, and complete installations. The service building scope includes foundations, electrical/mechanical systems, and security requirements. Pricing is included for estimated government-furnished equipment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A

Specifications

89503222BWA000051

27 May 2022

LOVELL SUBSTATION

SERVICE BUILDING AND

BREAKER REPLACEMENT

Spec. No. 1048

SECTION C

DESCRIPTION/SPECIFICATIONS

WYOMING

SECTION C

DESCRIPTION/SPECIFICATIONS

DCS AND BREAKER REPLACEMENT

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

B. DESCRIPTION OF WORK

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

1. Submittal And Coorespondance Response Time

2. Commencement of Control Work

3. Outage and Construction Schedule Restrictions

4. Protective Ground Leads

5. Maximum Available Fault Current

6. Typical Foundations for Government-Furnished Electrical Equipment

7. Typical Foundations for Contractor-Furnished Electrical Equipment

E. CONSTRUCTION SCHEDULE

1. Submittal Time

2. Format and Detail

F. MATERIAL

1. Points-of-Delivery

2. Protection of Material

G. RIGHTS-OF-WAY

1. General

H. GEOLOGIC INVESTIGATIONS

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

J. WATER FOR CONSTRUCTION PURPOSES

K. CONTRACTOR’S SAFETY AND HEALTH PROGRAM

L. EXPLOSIVES AND BLASTING

M. BURIED UTILITIES

N. ELECTRICAL MINIMUM APPROACH DISTANCES

O. SUBMITTALS AND CORRESPONDENCE

1. General

2. Transmittal

3. Submittal Response

4. Physical Sample Submittals

5. Project Protocol

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Miscellaneous sitework”

2. Bidding Schedule item “Demolition”

3. Bidding Schedule does not contain separate items

DIVISION 3 – CONCRETE

A. GENERAL

1. Material

2. Test for Potential Reactivity of Sand and Coarse Aggregate

3. Mix Design

4. Rebar Development (LD) and Lap Length

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Concrete foundations”

2. Bidding Schedule item “Cable trenches”

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL

1. Government-Furnished Drawings

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Steel structures, welded (galvanized)”

DIVISION 9 – SUBSTATION - ELECTRICAL

A. GENERAL

1. Bidding Schedule for Government-furnished items

2. Bidding Schedule for items (not furnished by the Government)

3. Associated Support Structures Provided for each Electrical Equipment Rated above 7-kV

4. Installation and Painting of Electrical Equipment and Material

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule items “Power circuit breaker, 115-kV, 3000-amps (Government-furnished)” . 20

2. Bidding Schedule item “Voltage transformer, 34.5-kV, single-phase”

3. Bidding Schedule item “Coupling capacitor voltage transformer, 115-kV, single-phase”

4. Bidding Schedule item “Voltage transformer, 25-kV, single-phase”

5. Bidding Schedule item “Resistor, 20-ohms, 2000-watts”

6. Bidding Schedule item “Associated electrical equipment and material”

7. Bidding Schedule item “Existing outdoor electrical equipment and material”

8. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable” and “Furnishing 12/c

No. 10 AWG control cable”

9. Bidding Schedule items “Installing 5/c No. 10 AWG control cable” and “Installing 12/c

No. 10 AWG control cable”

10. Bidding Schedule item “Vertical Switchboard Sections (12) CHA1-CHA8, CHB1-CHB2 and

Cable Termination Cabinets (2) CHT1-CHT2 (Government-furnished)”

11. Bidding Schedule item “DC and AC distribution boards”

12. Bidding Schedule item “Station battery system”

13. Bidding Schedule item “Battery chargers”

DIVISION 11 – BUILDINGS

A. DESCRIPTION OF BID ITEMS

1. Bidding Schedule item “Service Building”

2. Bidding Schedule item “Security System”

B. STANDARD 11 SPECIFICATIONS

C. SUBMITTALS

SECTION 01 00 00 – GENERAL REQUIREMENTS

01 10 00 SUMMARY

1. The Bidding Schedule item “Service building”

01 33 00 SUBMITTAL PROCEDURES

1. General

2. Contractor Review

3. Procedures

4. Shop Drawings

5. Product Data

6. Installation Data

7. Samples

8. Maintenance Material

9. Test Reports

10. Project Record Documents

11. Maintenance Data

01 78 23 OPERATION AND MAINTENANCE DATA

1. Requirement

2. Submittals

3. Manual Format

4. Manual Content

5. Instruction of Wapa Personnel

SECTION 31 00 00 – EARTHWORK

31 23 00 EXCAVATION AND FILL

1. General

31 23 23 COMPACTION, BACKFILL AND GRAVEL FILLS

1. General

31 31 16 TERMITE CONTROL

1. General

2. Quality Assurance

3. Submittals

4. Operation and Maintenance Data

5. Material

6. Installation

SECTION 03 00 00 – CONCRETE

1. General

03 30 00 CAST-IN-PLACE CONCRETE:

1. General

2. Concrete Requirements

SECTION 04 00 00 – MASONRY

1. General

04 05 13 MASONRY MORTARING

1. General

2. Material

3. Mixes

4. Installation

04 22 00 UNIT MASONRY

1. General

2. Submittals

3. Protection

4. Environmental Requirements

5. Material

6. Preparation

7. Installation

SECTION 05 00 00 – METALS

1. General

05 50 00 METAL FABRICATIONS

1. General

2. Submittals

3. Material

4. Fabrication

5. Preparation

6. Installation

7. Shop Finish Schedule

SECTION 06 00 00 – WOOD, PLASTICS AND COMPOSITES

1. General

06 10 00 ROUGH CARPENTRY

1. General

2. Quality Assurance

3. Material

4. Site Treatment of Wood Material

5. Installation

06 17 53 SHOP FABRICATED WOOD TRUSSES

1. General

2. Quality Assurance

3. Submittals

4. Delivery, Storage And Handling

5. Material

6. Fabrication

7. Installation

SECTION 07 00 00 – THERMAL AND MOISTURE PROTECTION

07 21 13 BOARD INSULATION

1. General

2. Submittals

3. Material

4. Installation

07 25 00 WEATHER BARRIERS

1. General

2. Submittals

3. Material

4. Installation

07 26 00 VAPOR RETARDERS

1. General

2. Submittals

3. Material:

07 41 13 METAL ROOF PANELS

1. General

2. Submittals

3. Performance

4. Material

5. Installation

07 42 13 METAL SOFFIT AND SIDING PANELS

1. General

2. Submittals

3. Material

4. Installation

5. Repairs

6. Painting

07 42 93 PLYWOOD SOFFIT PANELS

1. General

2. Submittals

3. Material

4. Installation

07 57 13 SPRAYED POLYURETHANE FOAM

1. General

2. Submittals

3. Material

4. Installation

5. Cleanup

07 91 00 JOINT SEALANTS

1. General

2. Submittals

3. Material

4. Installation

5. Schedule

SECTION 08 00 00 – OPENINGS

08 11 13 HOLLOW METAL DOORS AND FRAMES

1. General

2. Submittals

3. Product Handling and Protection

4. Material

5. Fabrication

6. Installation

7. Field Painting

8. Adjustment

08 71 00 DOOR HARDWARE

1. General

2. Submittals

3. Material

4. Installation

5. Hardware Schedule

6. Door Systems

08 80 00 GLAZING

1. General

2. Submittals

3. Material

4. Installation

SECTION 09 00 00 – FINISHES

09 29 00 GYPSUM BOARD:

1. General

2. Submittals

3. Material Storage

4. Environmental Requirements

5. Material

6. Installation

7. Painting

09 65 13 RESILIENT BASE

1. General

2. Submittals

3. Material

4. Installation

09 69 00 ACCESS FLOORING

1. General

2. System Description

3. Structural System Performance Requirements

4. Electrical and Mechanical System Performance Requirements

5. Submittals

6. Material

7. Installation

SECTION 26 00 00 – ELECTRICAL

1. General

26 05 00 COMMON WORK RESULTS FOR ELECTRICAL

1. General

2. Drawings

3. Submittals

4. Cutting and Patching

5. Painting

6. Acceptance Demonstration

7. Cleanup

26 05 19 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

1. General

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

1. General

26 05 53 IDENTIFICATION PLACARDS

1. General

26 05 83 WIRING CONNECTIONS

1. General

2. Mounted Height

26 05 83.03 DOOR ALARMS FOR OPERATIONS

1. General

2. Material

3. Installation

26 06 20.16 ELECTRICAL EQUIPMENT AND CIRCUITS SCHEDULES

1. General

26 09 23 LIGHTING CONTROL DEVICES

1. Lighting Contactor

2. Photocell

26 27 26 WIRING DEVICES

1. Receptacles

2. Wallplates

3. Circuit Breakers

26 51 13 INTERIOR LUMINAIRES, LAMPS AND BALLASTS

1. Material

2. Illuminance

3. Installation

26 51 14 EXTERIOR LUMINAIRES, LAMPS AND BALLASTS

1. Material

2. Illuminance

3. Installation

26 53 00 EXIT SIGNS

1. Material

2. Installation

DIVISION 14 – COMMUNICATION FACILITIES

A. COMMUNICATION FACILITIES

1. Communication Facilities, General

2. Construction

B. COMMUNICATION MONOPOLE

1. Communication Monopole General

C. FOUNDATIONS

1. Foundations, General

2. Foundations Type

D. WAVEGUIDE BRIDGE, SUPPORTS AND ENTRIES

1. Waveguide Bridge And Supports

E. GROUNDING SYSTEM

1. Grounding System

F. LIGHTNING PROTECTION

1. Lightning Rod

G. ANTENNAS AND WAVEGUIDES

1. Antennas and Waveguides, General

2. Antennas

3. Waveguides

H. FIBER OPTIC CABLE AND ASSOCIATED EQUIPMENT

1. Bidding Schedule item “Furnishing, installing and testing fiber optic cables and associated equipment”

DIVISION 15 – DRAWINGS

A. CONSTRUCTION DRAWINGS

1. General

B. AS-BUILT DRAWINGS

1. General

2. Recording Information

3. Drawing Markup

4. Drawing Review

5. As-Built Information To Be Recorded

C. REVIEW OF AS-BUILT DRAWINGS

1. As Built Drawing Submittal

2. Review

3. Acceptance

SERVICE BUILDING AND BREAKER REPLACEMENT

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete Lovell Substation, building and breaker replacement, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; WAPA’s Construction Standards, including Standard 1 – General Requirements (March 2021), Standard 2 – Sitework (March 2021), Standard 3 – Concrete (March 2021), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (March 2021), Standard 5 – Transmission Line Steel Pole Structures (March 2021), Standard 6 – Light Duty Steel Pole Structures (March 2021), Standard 7 – Wood Poles (March 2021), Standard 8 – Glued Laminated Structures (March 2021), Standard 9 – Substation – Electrical (March 2021), Standard 10 – Transmission Line – Electrical (March 2021), Standard 11 – Buildings (March 2021), Standard 12 – Painting (March 2021), Standard 13 – Environmental Quality Protection (March 2021), Standard 14 – Communication Facilities (March 2021), Standard 15 – Drawings (March 2021); Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

WAPA’s Construction Standards, Standard Drawings and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DESCRIPTION OF WORK:

1. The principal components of work include:

a. Substation:

(1) Provide foundations for substation structures, electrical equipment and material, and service building.

(2) Furnish and install galvanized steel structures.

(3) Furnish and install precast cable trench

(4) Install Government-furnished power circuit breakers.

(5) Furnish and install voltage transformers, resistors, high voltage bus, grounding system, conduit, and terminal boxes.

(6) Furnish and install a site-built service building complete with electrical and mechanical systems.

(7) Install Government-furnished switchboards, cable termination cabinets.

(8) Installing Government Furnished 30-foot monopole.

(9) Furnish and install Microwave facilities.

The summary of “Bidding Schedule Items” are more fully described in the following divisions in this specification and in the Construction Standards listed in Division 1, Section A above”.

The work is located near Lovell, Wyoming, as shown on Drawing LV 0016.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Prepare and submit a Construction Schedule and furnish a Safety and Health Program.

D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: See FAR 52.211-10 in

Section F of the solicitation/contract.

1. SUBMITTAL AND CORRESPONDENCE RESPONSE TIME: Except as otherwise provided for specific submittals, WAPA will require 20-calendar days for review of drawings or data submitted for approval.

2. COMMENCEMENT OF CONTROL WORK: Do not perform any control board or outdoor equipment wiring until receipt of Government-furnished wiring diagrams. WAPA will furnish outdoor wiring and schematic diagrams no sooner than March 15, 2023. Control board wiring and schematic diagrams will be furnished no sooner than July 3, 2023. Include these restrictions in the Construction Program.

3. OUTAGE AND CONSTRUCTION SCHEDULE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:

a. Concurrent outages may be granted for breakers 162 and 462.

b. A total of (8) main bus outages will be granted for removing the old breakers and bringing in the new breakers underneath the main bus.

c. A main bus outage will only be granted for 6 hours at a time and will need to be taken at night after 20:00 pm.

d. The Contractor’s work hours shall not exceed 60-hours in 1 calendar week without prior approval from the Contracting Officer’s Representative (COR).

e. The Contractor shall allow 6-weeks per power circuit breaker for WAPA to complete commissioning.

f. The Contractor shall submit a 2-week notification to the COR, prior to removal of each power circuit breaker to allow for WAPA to disconnect cables.

g. Dependent upon time of year; if ambient temperatures are less than 32-degrees-Fahrenheit during power circuit breaker commissioning, the Contractor shall create an environment to bring local ambient temperatures above 32-degrees-Fahrenheit.

h. Make all outage requests in writing to the onsite WAPA representative a minimum of 30-days in advance. Meeting the minimum advance notice requirements of 30-days does not guarantee an outage will be approved. To improve the chances of an outage being approved, all outages should be submitted with as much advance notice as practicable.

Weather conditions and other system conditions such as other scheduled and nonscheduled (forced) outages will be evaluated by WAPA against an outage request before approval can be granted.

At any time because of transmission system electrical loads, system configurations, weather conditions or any condition which may cause an adverse effect on the transmission system operation or any condition which may cause an adverse effect on transmission system operation or reliability, WAPA may deny an outage request or direct the Contractor to return facilities to operating conditions and release the applicable Special Work Permit.

4. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).

5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current in the 115-kV area is 4,526-amps and the X/R ratio is 5.5.

b. A minimum of 1 (one) 1/0 grounds shall be used in the 115-kV area.

c. The maximum available fault current in the 34.5-kV area is 6,586-amps and the X/R ratio is 12.4.

d. A minimum of 1 (one) 1/0 grounds shall be used in the 34.5-kV area.

e. The maximum available fault current in the KY1A 12.47-kV area is 4,310-amps and the X/R ratio is 14.5.

f. A minimum of 1 (one) 1/0 grounds shall be used in the KY1A 12.47-kV area.

g. The maximum available fault current in the KY4A 12.47-kV area is 8,038-amps and the X/R ratio is 14.4.

h. A minimum of 1 (one) 1/0 grounds shall be used in the KY4A 12.47-kV area.

6. TYPICAL FOUNDATIONS FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT:

Typical foundations are shown in Drawing LV 2300. WAPA will design these foundations after receipt of the seismic report and informational drawings and data, including the seismic report from the equipment manufacturer. WAPA will forward the revised construction drawings for these foundations no later than 45-days prior to the “NLT” delivery date listed in the “Material” section.

If the “NLT” delivery date is adjusted by WAPA, forwarding of revised foundation construction drawings will be automatically adjusted in a like manner.

7. TYPICAL FOUNDATIONS FOR CONTRACTOR-FURNISHED ELECTRICAL EQUIPMENT:

Typical foundations are shown on Drawing LV 2301. Regarding foundations noted as “design not firm” WAPA will design these foundations after receipt and final approval of seismic qualification documents and informational drawings and data from the Contractor.

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the CO within 45-calendar days after date of Notice to Proceed.

2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:

ITEM

ESTIMATED

WEIGHT

(LBS)

ESTIMATED

DELIVERY

DATE

ESTIMATED

COST

1. Five (5) 3-phase, power circuit breaker, 115-kV, 3,000 amp 6,500 ea NST _05-15-2023_

NLT _05-26-2023_ $92,000 ea

2. Twelve (12) Vertical switchboard sections, CHA1-CHA8, and CHB1-

CHB4

1,000 ea NST _06-20-2023_ NLT _07-03-2023_ $65,000 ea

3. Two (2) Cable termination cabinets, CHT1-CHT2. 450 ea NST _06-20-2023_

NLT _07-03-2023_ $4,500 ea

4. 30-foot monopole for communications tower. 2800 On-Site $9,000

NST – No sooner than.

NLT – No later than.

1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to Lovell Substation. The

Contractor is responsible for unloading of WAPA-furnished material. The Contractor shall inspect the equipment and report any damages to the Contracting Officer’s Representative (COR).

2. PROTECTION OF MATERIAL: Provide suitable indoor or warehouse storage for indoor equipment. Provide protection against the elements after being removed from indoor storage and before installation.

G. RIGHTS-OF-WAY:

1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior COR approval. During the contract period, WAPA reserves the right to use Contractor-obtained access.

H. GEOLOGIC INVESTIGATIONS:

The 8000-series geologic logs of subsurface explorations included in the “Drawings” Division constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown on the Drawings.

Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant. WAPA does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.

The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations and doing other work affected by geology and ground water elevations at the worksite.

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

Electric power up to a maximum of approximately 25-kVA for construction purposes will be available without cost. Source of supply is located in the receptacles throughout the substation. The Contractor may furnish power for his operations by other means at no additional cost to WAPA. Power made available by WAPA will be delivered as single-phase, 60 Hz, AC, at approximately 120-240 V.

Coordinate with the COR for establishing electric power service.

Until permanent power is available, provide temporary power to the service building to serve all building loads including HVAC, lighting and station battery system. Provide temporary heating prior to beginning finish work, sufficient to keep the interior of the building at a minimum of 70-degrees Fahrenheit for 24-hours a day, until permanent heating is available.

Any Contractor furnished power shall require the Contractor to provide any necessary transmission lines, distribution circuits, transformers, and other electrical equipment for distributing the power to the places of use. At contract completion, the Contractor shall remove temporary electrical equipment and distribution lines.

J. WATER FOR CONSTRUCTION PURPOSES:

Furnish water for construction purposes. Make arrangements for obtaining the water and provide for conveying the water to the points of use.

K. CONTRACTOR’S SAFETY AND HEALTH PROGRAM: Shall include designation of the Safety

Professional with resume of qualifications, experience and training as related to this subject.

L. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

M. BURIED UTILITIES:

Prior to excavation, examine the area and determine the location of buried utilities. Utilities shall be identified with a marker denoting the type of service.

N. ELECTRICAL MINIMUM APPROACH DISTANCES:

Refer to WAPA Construction Standard 1.4.9. In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.

O. SUBMITTALS AND CORRESPONDENCE:

1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:

a. Submittals shall be in the following formats: standard PDF, Microsoft Word (docx), Microsoft

Excel (xlsx), Electronic CAD (.dwg) (AutoCAD version 2018). All submittals in .dwg format shall also be submitted in .pdf format.

b. Each submittal shall include label at the top of the first page or drawing with the WAPA

Contract number with the Specification number, if applicable (89503222CWA000XXX- 1048), WAPA project title, the Bidding Schedule Contract Line Item Number (CLIN), equipment designation, or if a designation is not available the applicable division number and applicable division paragraph number.

c. Multiple CLIN’s on a single submittal are not permitted. For Associated Electrical Equipment and Material’s CLIN, which contains multiple equipment types, each type shall be submitted separately with the exception that Phase Identification Signs and Equipment Identification Signs can be submitted together.

d. A cover transmittal letter will be provided by WAPA (in both a Microsoft Word and PDF format) and shall be included with each email submittal. The transmittal shall also contain a contact name, the WAPA Contract number with the 4-digit Specification number, if applicable (89503222CWA000XXX-1048), WAPA project title, CLIN and applicable division number and applicable division paragraph number.

2. TRANSMITTAL: The Contractor shall submit all correspondence (Request for Information, Submittals, etc.) to the following email addresses care of the COR.

Rocky Mountain

ATTN: J5600

Email: RMR-J5600-CS@wapa.gov

3. SUBMITTAL RESPONSE: WAPA will provide a response to all submittals in accordance with

Division 1.D.2 of these specifications with an “Acceptable” or “Not Acceptable” status, with comments as appropriate to the email address where the submittals originated.

4. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e., brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlining the physical sample submittal prior to sending the sample (including tracking data when applicable), and shall deliver physical specimens to:

Western Area Power Administration

ATTN: A7900

12155 W. Alameda Parkway Lakewood, CO 80228-2802

5. PROJECT PROTOCOL:

a. Electronic Correspondence:

EMAIL SUBMITTAL FORMAT:

Subject Line in Email Submittal number, Subject, Applicable Standard Number, Project Name/Number, and Contract Number Example: Submittal 017, Steel Compression Dead Heads-Std 10, Lovell Service Building &

Breaker Replacement, 89503222CWA000XXX -1048

b. Payment Requests:

EMAIL PAYMENT REQUEST FORMAT:

Invoice number and Project Name/Number and Contract Number Example: Invoice 01, Lovell Service Building & Breaker Replacement, 89503222CWA000XXX -1048

c. Certified Payrolls-Prime and Subcontractors:

EMAIL CERTIFIED PAYROLL FORMAT:

Certified Payroll (CP), Contractor’s names, Week ending (WE), and Project Name/Number, and Contract Number Example: CP-(Smith Inc., Bob’s Electrical), WE 09/12/18 & 09/19/18, Lovell Service Building &

Breaker Replacement, 89503222CWA000XXX -1048

d. Request for Information:

EMAIL (REQUEST FOR INFORMATION) FORMAT:

Request for Information (RFI), Project Name/Number, and Contract Number Example: RFI-003, Labeling Info, Lovell Service Building & Breaker Replacement, 89503222CWA000XXX -1048

BUILDING AND BREAKER REPLACEMENT

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Miscellaneous sitework” includes the following:

a. Replacing and protecting existing gravel surfacing where disturbed by this project.

b. Providing new gravel surfacing as needed due to demolition and foundation work.

c. Modifying existing concrete foundations as shown on Drawing LV 2048. Modification involves cutting off existing anchor bolts flush with the top of concrete, painting exposed end of anchor bolts with zinc-rich paint and installing new adhesive anchors.

2. Bidding Schedule item “Demolition” includes the following:

a. Completely removing concrete foundations designated on Existing Installation Drawings

LV 2000.

b. Removing the following structures:

(1) One (1) Equipment Support Type III (115-kV Voltage Transformer) on foundation designated 8ES3 as shown on Existing Installation Drawing LV 2000. Equipment Support Type III shown on drawing LV 2052.

Drawings are included showing typical structure details.

3. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.

a. Excavations for foundations, structures, and trenches.

b. Placing and compacting earth material and backfill.

c. Providing clean crushed gravel fills for the Service Building and under concrete foundations as shown on the Drawings.

d. Unless otherwise directed by the COR, material shall not be wasted in drainage channels.

Waste banks shall be left with reasonably even and regular surfaces as approved by the COR. Material from excavations not suitable or required for earthwork shall be removed from the substation and access road right-of-way. The Contractor shall make arrangements required for disposal of waste material in an approved landfill.

e. Epoxy adhesive anchors.

DIVISION 3 – CONCRETE

A. GENERAL:

1. MATERIAL:

a. Cement: Type II cement. Types are according to ASTM C 150.

2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: All fine and coarse aggregates shall be tested in accordance with Standard 3. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source shall be obtained by the Contractor.

a. Acceptance criteria specified in Standard 3 are based on 14-day readings after the zero reading.

3. MIX DESIGN: Provide a performance based concrete mix design in accordance with ACI 211.1 and Table 3.1 below.

a. Net water-cementitious materials ratio (w/c) is maximum, by weight. Cementitious material weight is portland cement plus supplementary cementitious material (SCM).

b. Air Entrainment: Percent air by volume of concrete as discharge at point of placement.

TABLE 3.1

DESCRIPTION F’C (PSI) MAX W/C

NOMINAL

MAXIMUM SIZE

AGGREGATE

(NMSA)

SLUMP

(INS)

AIR

CONTENT

Substation, Building and other General Structural Concrete

4500 at 28-days 0.45 No. 67 2 – 5 4 - 7

Building Slabs on Ground In accordance with Standard Drawing 01 2006-1

Mix designs shall meet the performance-based design criteria above and Standard 3.

Alternatively, the minimum cement content for mix designs can follow Standard 3, section 3.1.1.5.(5) for the required 28-day compressive strength.

4. REBAR DEVELOPMENT (LD) AND LAP LENGTH:

a. Class B lap splices apply unless noted otherwise; refer to Table 3 on Standard Drawing

01 2004-1 General Outline and Reinforcement Notes.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Concrete foundations” includes the following:

a. Earthwork, formwork, reinforcement, material used in concrete, void forming material, drilling and grouting anchor bars, anchor bolts, curing, finishing, joints and other related work and material needed to complete the concrete construction.

b. Concrete foundations for steel structures.

c. Concrete foundations for electrical equipment.

d. Unwatering foundation excavations, if required.

e. Casing auger excavations, if required.

Measurement for quantities for concrete foundations will be made on the basis of concrete quantities shown on Drawing LV 2001-2. If separate quantities of formed and auger concrete for each type of foundation are shown on the Drawing, the concrete quantity shall be the total of the formed and auger concrete quantities. Regardless of the concrete quantities actually placed, payment will be based on the quantities of concrete shown on the Drawing. Concrete quantities in augered foundation bells are based on a 45-degree bell angle and 6-inch toe height.

2. Bidding Schedule item “Cable trenches” includes providing precast concrete cable trenches, vehicular crossings, complete with sandfill, polymer modified concrete covers and other accessories.

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL:

1. GOVERNMENT-FURNISHED DRAWINGS: Existing shop drawings for steel structures are not available.

a. MEASUREMENT: Measurement for quantities for Bidding Schedule items “Steel structures, welded (galvanized)” will be made on the basis of weights calculated in accordance with LRFD, “AISC Code of Standard Practice for Steel Buildings and Bridges”, except those weights for nonrectangular shapes and plates are to be based on actual detailed dimensions.

b. Steel structure weights, calculated as noted above, are shown on the Government-furnished shop drawings and shall be shown on the Contractor-furnished final shop drawings and payment will be based thereon. Steel estimated weights are shown on the specifications drawings for the structures requiring approval drawings as noted in the Bidding Schedule items “Steel structures, welded (galvanized)”.

1. Bidding Schedule item “Steel structures, welded (galvanized)” includes providing the following:

a. *Two (2) Bus and Equipment Supports – Type I as shown on LV 2600.

b. *Five (5) Equipment Cabinet Platforms – Type VII, including grating, as shown on LV 2925.

*Denotes structures requiring approval drawings.

The above material including connection bolts, nuts, washers and lock nuts shall be galvanized.

DIVISION 9 – SUBSTATION - ELECTRICAL

A. GENERAL: Electrical equipment and material shall be as specified in WAPA’s “WAPA ES” standard equipment specifications, as shown on project drawings and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL and Federal specifications and standards as applicable. Applicable requirements shall be met under the following service conditions:

Ambient Temperatures:

Maximum .............................................................................. +40°C Maximum 24-Hour Average ................................................. +30°C Minimum ................................................................................ -40°C

Elevation:

Above Mean Sea Level .................................................4,100-Feet

*ASCE-7 Wind Load:

Minimum Basic Wind Speed ............................................. 90-MPH Importance Factor ................................................................... 1.15

*IEEE 693 Seismic Qualification ............................................... Moderate

*May include support structure in accordance with STANDARD 9.1.1.2. Wind and seismic loads are non-simultaneous.

1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:

a. Unless otherwise indicated, unloading and inspecting Government-furnished items.

b. Installing Government-furnished items as shown on drawings.

c. Furnishing equipment and material not furnished by WAPA.

2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the

Contractor and shall include the following:

a. Providing (furnishing and installing) bidding schedule items.

b. Furnishing equipment and material not furnished by WAPA.

c. Installing bidding schedule items as shown on drawings.

3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel.

Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.

4. Installation and painting of electrical equipment and material shall be provided in accordance with

Standards 9 and 12 respectively.

1. Bidding Schedule items “Power circuit breaker, 115-kV, 3000-amps (Government-furnished)”:

DESIGNATION JY1A, JY2A, JY3A,

JY4A, JY6A

Manufacturer Mitsubishi

Type SF6 gas Nominal Voltage Rating (kV) 115

Maximum Voltage Rating (kV) 123

Basic Impulse Insulation Level 550

Continuous Current (Amps) 3,000

Short Circuit Fault Rating (KA) 40

Rated Interrupting Time (cycles) 3

Number CT’s per Bushing 3

a. Special tools and appliances will be furnished with the power circuit breaker. The Contractor shall deliver the special tools and appliances furnished with the breakers to Western’s onsite representative. Included is One (1) SF6 gas breaker filling connection assembly (i.e., including hose, pressure gauge, and the hose end connections to the breaker and SF6 gas cylinder), Two (2) trip coils and two (2) close coils.

b. The Contractor shall deliver the spare parts listed above to Western’s on-site representative.

c. WAPA forces will fill the breaker with SF6 and perform the other breaker services

2. Bidding Schedule item “Voltage transformer, 34.5-kV, single-phase”: Includes providing voltage transformer in accordance with WAPA ES 6.1 equipment standard:

DESIGNATION

(SINGLE-PHASE) VX1B1, VX1B2, VX1B3

Type Single-phase, 60 Hz, wound type, outdoor

Nominal Rated Primary Voltage (kV) 34.5

Maximum System Voltage (kV) 38

Basic Impulse Level (kV) 200

Ratio Primary to Secondary*

175/300:1 175/300:1

ANSI Accuracy Class 0.3% W, X, M, Y, Z, ZZ

DESIGNATION

(SINGLE-PHASE) VX1B1, VX1B2, VX1B3

Type Dry Type

Thermal Burden Rating at 30°C Ambient (VA) 400

Mounting Base

3. Bidding Schedule item “Coupling capacitor voltage transformer, 115-kV, single-phase” include[s] providing coupling capacitor voltage transformers in accordance with WAPA ES 6.3 equipment standard and associated support structure for VY3A1.

DESIGNATION

(SINGLE-PHASE)

VY2A1, VY4A1, VY6A1,

VY7A1 VY3A1

Type Single-phase, outdoor, 60 Hz

Single-phase, outdoor, 60 Hz

Nominal System Voltage (kV) 115 115 Maximum System Voltage (kV) 123 123

Basic Impulse Insulation Level (kV) 550 550

Performance Reference Voltage (kV) 69 69

Primary to Secondary Ratios 600/1000:1 600/1000:1

600/1000:1 600/1000:1

ANSI Accuracy Rating 0.3% M, W, X, Y, Z 0.3% M, W, X, Y, Z

Thermal Burden Rating (minimum VA) 400 at 55°C rise 400 at 55°C rise

Mounting Base Base

Support Structure required No Yes

4. Bidding Schedule item “Voltage transformer, 25-kV, single-phase” includes providing voltage transformers in accordance with WAPA ES 6.1 equipment standard:

DESIGNATION (SINGLE-PHASE) VW1B1, VW1B2, VW1B3, VW4A1,

VW4A2, VW4A3

Type Single-phase, 60 Hz, outdoor, dry type, self-cooled

Manufacturer ABB type VOZ-15 or equal

Primary Voltage Rating (L-G/L-L) 14,400/24,940Y

Basic Impulse Level (kV) 150

DESIGNATION (SINGLE-PHASE) VW1B1, VW1B2, VW1B3, VW4A1,

VW4A2, VW4A3

Number of High Voltage Bushings 2

Special Feature Two secondary windings

Ratio Primary to Secondary 120:1 120:1

ANSI Accuracy Class 0.3W, X, Y, Z Thermal Burden Rating at 30°C Ambient

(VA) 2,000

Terminal Connector NEMA 2-hole pad*

Mounting Position Vertical

*In lieu of Standard 6.1.2.5

Voltage transformers shall have dual secondaries windings, or a secondary and a tertiary. A single tapped secondary is not acceptable. Dual tapped secondaries with 120/200:1 each is acceptable. If the transformer bushing only has a stud, a NEMA 2-hole terminal pad accessory shall be included. Transformers’ primary voltage will be arranged in a grounded wye configuration.

The transformers, in combination with a resistor, are used for ground fault detection.

5. Bidding Schedule item “Resistor, 20-ohms, 2000-watts” includes furnishing a resistor in accordance with WAPA ES 9.3 equipment specifications:

DESIGNATION RW1B, RW4A

Type

Single phase, 60 Hz, outdoor, furnished in a weatherproof enclosure suitable for bracket mounting

Insulated Rating (V) 208

Resistance (ohms) 20

Amperage rating (minimum) 10

Power rating (minimum) (watts) 2000

Enclosure

Weatherproof with two conduit entrances for 2-inch rigid conduit. One entrance shall be at the top and one at the bottom. One grounding pad and clamp-type terminal for No.

4/0 AWG bare copper cable shall be furnished with enclosure.

Terminal Block Resistor shall be wired to terminal block containing a minimum of six points.

The resistor, in combination with 25-kV voltage transformers, is used for ground fault detection.

6. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material and services required to complete the following substation installations as shown on the Drawings:

a. Electrical Testing: Includes providing electrical testing in accordance with Standard 9, paragraph 9.1.2 Acceptance Tests – Method A.

b. Substation Grounding System. Includes providing material and services required to complete and test the substation grounding system. All new exposed ground wire shall be copper clad steel. The included drawings and standards have not been revised to show this new requirement. In leu of the WAPA Standard 9, exothermic or bolt-on fittings will not be acceptable. Unless otherwise specified on the Drawings, splices, crosses, tees and other fittings used on grounding system shall be compression or swage type (DMC Power Swage system, AFL Swage system, or equal. It’s recommended to obtain the necessary tooling from respective manufacturer.) Bolts, washers and lock washers used for terminal pad to terminal pad connections shall be made of stainless steel. Nuts shall be made of silicon bronze. Informational drawings and data are not required for this item.

NOTE: CCS conductor shown on drawings and standard drawings as 7 No. 4 shall be an equivalent conductor rated to meet or exceed the short circuit rating of the ground grid conductor (per IEEE Std. 80 table 3). For example, CCS connections to a 4/0 AWG ground grid shall have a short circuit fault current of 40kA or higher for 30-cycles (500-ms).

Substation fence and metallic trench cover lid grounds shall have CCS conductor with fault current rating of 5-kA or higher for 30-cycles (500-ms). New cable trench grounding shall have to CCS conductors with a short circuit fault current of 25-kA or higher (per conductor) for 30-cycles (500-ms) in lieu of two (2) 2/0 AWG copper conductors as indicated in WAPA Standard 9.2.1.2 (7) and as shown on Drawing 31 1061.

c. Electrical Conduit System: Electrical conduit system including embedded and exposed conduit. Conduit entering the cable trench with a 90-degree bend is allowed to be Schedule 40 PVC as shown on Drawing 31 1006. All other 90-degree bends shall be rigid metal. A red or yellow polyethylene detectable warning tape shall be installed directly above each conduit run and located 12-inches below finished grade. All conduits shall have sealing compound installed at both ends. Informational drawings and data are not required for this item.

d. Outdoor Bus System: Outdoor strain and jumper buses, rigid buses and overhead ground wire unless otherwise specified on the Drawings, splices, elbows, pad type terminal connectors and other fittings used on rigid or cable buses shall be compression type (DMC Power’s Bus & Cable Connectors and Swage System, AFL Swage system, or equal. If required, tools shall be obtained from respective manufacturers.). Bolts, washers and lock washers used for terminal pad to terminal pad connections shall be made of stainless steel.

Nuts shall be made of silicon bronze. Post insulators for new structures shall use industry standard 3-, 5- or 7-inch base cap bolt circles in lieu of WAPA Standard 9.3.1.1.3.2 and Drawing 31 1081. Replacement insulators shall match existing bolt circles. Insulators shall be ANSI 70 gray. Informational drawings and data are required for the rigid bus, conductors, overhead ground wire and insulators only.

e. Insulated Conductors: Insulated conductors and cables except 5/c and12/c No. 10 AWG control cable and power cable with insulation greater than 15,000 V. Informational drawings and data are not required for this item.

f. Terminal Boxes: Terminal boxes’ internal components arrangements shown on Drawings

31 1085 and 31 1086 are typical and the Contractor shall provide internal components for

Type A and Type F (option 2 with fuse block and knife switch locations swapped from what is shown on the standard drawing) terminal box configuration. Actual internal arrangements will be determined by the COR. In leu of the drawings, the enclosures shall be rated NEMA 4X and include a three-point latching door handle that is also pad lockable. NOTE: on Drawing 31 1085, note 7 should be: “Ground all boxes to the main ground grid with 3 conductor No. 7 bare copper-clad cable. 7 conductor No. 4 bare copper-clad cable may be substituted.” Regardless, the Contractor shall size and provide the ground connector, item 4, to fit the provided grounding conductor in lieu of Burndy ground connector type K2C20B1.

g. Substation signs – Sign materials shall adhere to Division 13 and as follows:

h. Phase Identification Signs (31 1000):

(1) One (1) on each phase at both ends of main and transfer buses, at each high voltage circuit terminating structure and on each phase of an instrument transformer or single-phase transformer:

(a) Phase A – 8 required.

(b) Phase B – 3 required.

(c) Phase C – 3 required.

i. Equipment Identification Signs (31 1000): Lettering on the signs shall be as shown on

Drawing LV 1101.

7. Bidding Schedule item “Existing outdoor electrical equipment and material” also includes removal, disposal and modifying existing electrical equipment and material.

a. Material to be removed and disposed of is as follows:

(1) Five (5) 115-kV power circuit breakers designated JY1A, JY2A, JY3A, JY4A and

JY6A.

(2) Four (4) 115-kV coupling capacitor voltage transformers designated VY2A1, VY4A1, VY6A1 and VY7A1.

(3) One (1) 115-kV coupling capacitor voltage transformer and associated support structure designated VY3A1.

(4) Three (3) 34.5-kV voltage transformers designated VX1B1, VX1B2 and VX1B3.

(5) Seven (7) terminal boxes designated EZ1A, EZ1B, EY2A, EY3A, EY4A, EY6A and

EY7A.

(6) Substation control, power cables and conduit as designated on the Drawings.

Portions of cables in conduit, trench and/or trays shall be removed and disposed of.

b. Material to be modified by the Contractor is as follows:

(1) Rewire five (5) existing terminal boxes designated EY1A, EY5A, EX1B, EW1A and

EW2A.

c. The Contractor shall include any credit to the Government for salvage of the equipment and/or materials in this bid item.

8. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable” and “Furnishing 12/c No. 10 AWG control cable” include furnishing 5/c No. 10 and 12/c No. 10 AWG control cable, respectively, according to LV T600. Control Cable material shall meet the requirements of Standard 9 – Substation – Electrical, Section 9.2.3.2. “Material”.

9. Bidding Schedule items “Installing 5/c No. 10 AWG control cable” and “Installing 12/c

No. 10 AWG control cable” include installing 5/c No. 10 and 12/c No. 10 AWG control cable, respectively, according to LV T600.

a. The Contractor shall terminate all control cables in the de-energized outdoor equipment, the control cable termination cabinets (CHT1 & CHT2) and the new control panels (CHA1 – CHA8 and CHB1 – CHB4) according to Drawing LV T600. All control cables shall be labeled according to Drawing LV T600 and Standard 9 – Substation Electrical (September 2013), paragraph 9.2.3.4 (10) and shall be able to reach the furthest point in the designated control panel or termination cabinet.

b. WAPA will terminate all control cable in the existing energized control panels in the control building and energized outdoor equipment. The Contractor shall include enough additional cable length so that any conductor in the cable can reach the furthest connection point in the equipment plus 10-feet. Neatly coil excess cable near the equipment and provide protection from damage and/or weather.

10. Bidding Schedule item “Vertical Switchboard Sections (12) CHA1-CHA8, CHB1-CHB2 and

Cable Termination Cabinets (2) CHT1-CHT2 (Government-furnished)” includes furnishing material not furnished by WAPA and performing work required to receive, unload, and install the Government-furnished vertical switchboard sections CHA1-CHA8, CHB1-CHB4 and cable termination cabinets CHT1 through CHT2 in the locations shown on Drawing LV 4000.

Switchboard frames are required to be anchored through the raised floor system directly to the concrete subfloor in accordance with Option A – Threaded Rod and Channel System shown on standard Drawing 31 2049-1 – Control Switchboard Equipment and Communication Rack Base Anchorage Details (Sheet 1 of 2). Refer to structural for Seismic Design Category (SDC) and/or Seismic Qualification Level (SQL).

11. Bidding Schedule item “DC and AC distribution boards” includes providing the DC and AC distribution board systems as shown on Drawings LV 3403 and LV 6000. The AC distribution boards are designated DHA and DHB and the DC distribution boards are designated BHA1 and BHA2. The enclosed main circuit breakers are designated BHA1-Main and BHA2-Main. The distribution boards shall be in accordance with WAPA ES 2.4 equipment standard.

12. Bidding Schedule item “Station battery system” includes furnish and install the battery specified below. Furnish material not supplied by the manufacturer and perform work required to install the station battery, battery rack and spill containment in the location shown on Drawing LV 4000. The battery rack will be installed on the floor of the battery room. The Building Manufacturer shall provide any additional shims or mounting hardware required to level the battery racks. Conductors between the battery and the DC panelboard main disconnect circuit breakers will be routed through four (4) 2-inch PVC conduits as shown on Drawing LV 4000.

Battery shall be EnerSys EC-9M, or equal.

a. Battery Ratings, Characteristics and Requirements (EnerSys EC-9M, or equal):

(1) Minimum rated 8-hour nominal capacity: 365 Ah.

(2) Flooded-cell, heavy-duty, lead-acid with calcium-lead alloy grids.

(3) Designed for constant voltage charging in float service.

(4) Float service life warranted for at least 20-years.

(5) Designed for switchgear and control applications.

(6) External cable connections on the left side (cell No.1 (+) on the top left).

(7) Cell quantity: 58; 1-cell per jar.

(8) Jar construction: Styrene-acrylonitrile-copolymer (SAN).

(9) Final voltage (80-percent) rating: 1.75-Volts/cell.

(10) Electrolyte specific gravity: 1.215 at 77-degrees-Fahrenheit.

(11) Rated float charge voltage: 2.17-2.26-Volts/cell.

(12) Positive plate thickness must be a minimum of 0.3-inches. Negative plate thickness must be a minimum of 0.2-inches. Outside negative plate thicknesses must be a minimum of 0.125-inch.

b. Accessories:

(1) Thermometer, hydrometer and holder kit.

(2) Flame arrestors with dust caps.

(3) Rack rail lubricant and non-oxidizing grease.

(4) Cell lifting device.

(5) Intercell connectors and connector bolts for 0.25-inch (1/4-inch) spacing between cells.

(6) Inter-step cables and connectors, with heat shrink insulation preinstalled.

(7) Terminal plates for main external cable connection (2-4/0 AWG copper conductor per terminal).

(8) Cell number stickers (1-60).

(9) Funnel, two (2)-pair of rubber gloves and one (1)-acid syringe.

(10) Flame-proof battery post/inter-cell connector insulating clear covers.

(11) Instruction manual.

c. Rack:

(1) Provide 1-Tier, 2-row system with both rows at same height: top of battery posts at

42-inches above floor. Batteries will be installed in two (2) rows of 29 cells, back-to-back. Racks shall have a minimum of 4-inches between front and rear rack. The battery rack system shall fit within a 51-inches wide by 172-inches long footprint.

(2) Same manufacturer as battery or qualified for use with provided battery model.

(3) Manufactured for IEEE-693 Seismic Qualification Level Moderate.

(4) Acid resistant, painted steel racks.

(5) Flame retardant, electrically insulating rails.

(6) Grounding point at each end of the rack to accommodate up to 4/0 AWG cable.

(7) Maximum installed length of rack and the spill containment system are 15-feet.

d. Spill Containment Enclosure:

(1) Liquid-tight, formed steel, covered with acid resistant coating.

(2) Steel Barrier shall be 4-inches high and sized to accommodate the length and width of the battery rack plus 2-inches on each side.

(3) Designed for installation without drilling holes for anchors.

(4) Corrosive resistant 80-millimeter-thick liner, factory formed.

(5) Adhesive for installation of…

This is the start of the file's text. The full file is on GovTribe.