20R5007 -- Attachment 0007 -- SOW -- Appendix F - Record of Environmental Consideration.pdf

PDF 208 KB Posted

Attached to
Sprinkler Project Building 337, Rock Island Arsenal, Illinois
Solicitation number
W52P1J-20-R-5007
Issued by

About this file

This solicitation requests proposals for a design/build project to replace the sprinkler system in Building 337 at Rock Island Arsenal in Illinois. The project scope involves furnishing labor, equipment, and materials to repair and replace the sprinkler system, as the existing system is obstructed and piping degraded. Proposals are due by May 8, 2020. The total estimated value of construction is between $500,000 and $1,000,000. The soliciting agency is the Department of the Army Materiel Command Joint Munitions Command. Preference will be given to proposals from HUBZone small businesses. All work must be completed according to the attached scope of work, specifications, and drawings.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Record of Environmental Consideration (REC)

Project Title: Replace Sprinkler System, Building 337

Project # 2020-0288

Anticipated date and/or duration of proposed action: 120 days

Brief Description of the Project: The scope of this project consists of furnishing labor, equipment and material to repair by replacement, the sprinkler system(s) in Building 337.

Preliminary investigation indicates that the sprinkler system is obstructed and the piping has significantly degraded.

This Project is Categorically Excluded Under:

a. Per 32 CFR Part 651.29 (a) (1, 2, and 3): The action has not been segmented, no exceptional circumstances exist (b) (1-14), and one or more of the Categorical Exclusions (CX’s) encompass the proposed action.

b. Per 32 CFR Part 651, Appendix B, Section II, the following CX applies which states: (g) Repair and maintenance activities: (1) Routine repair and maintenance of buildings, airfields, grounds, equipment, and other facilities. Examples include, but are not limited to: Removal and disposal of asbestos containing material (for example, roof material and floor tile) or lead-based paint in accordance with applicable regulations; removal of dead, diseased, or damaged trees; and repair of roofs, doors, windows, or fixtures or work on historic structures.

Environmental Considerations

*Contractor is responsible for proper collection/disposal of any solid/hazardous waste generated.

*Stated repairs have been identified in Stipulation IV.A. of the draft Programmatic Agreement.

*ACM and LBP shall not have an impact on this project.

Record of Environmental Consideration (REC)

George J. Schaub _________________________ Cultural Resource Manager

Reita A. Kuster _________________________ Chief, Environmental Division Installation Environmental Coordinator

Robin Gaines _________________________ NEPA Program Manager

2020-04-07T06:58:12-0500
SCHAUB.GEORGE.JOHN.1268938474
2020-04-07T08:51:56-0500
KUSTER.REITA.A.1230448511
2020-04-07T09:29:51-0500
GAINES.ROBIN.ANNE.1139344029

File details come from the government source that posted it. Updated .