20R5007 -- Attachment 0001 -- SOW.pdf

PDF 229 KB Posted

Attached to
Sprinkler Project Building 337, Rock Island Arsenal, Illinois
Solicitation number
W52P1J-20-R-5007
Issued by

About this file

This document is a Scope of Work (SOW) for a federal contract opportunity to replace the sprinkler system in Building 337 at Rock Island Arsenal in Illinois. The project consists of designing and installing replacement dry pipe sprinkler systems according to UFC 3-600-01 and NFPA codes. The contractor will submit design drawings and specifications at 30% and 90% completion and provide as-built drawings and O&M documentation upon completion. The base bid includes demolition of the existing systems and installation of new sprinkler systems, nitrogen generation system, and connection to the fire alarm system. The work must be completed within 180 calendar days of the Notice to Proceed. The contractor must also comply with all applicable environmental, safety, security and operations security requirements specified in the SOW.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project # 2020-288 Replace Sprinkler System, Building 337

1 | P a g e

Rock Island Arsenal Scope of Work

PR #2020-288

Replace Sprinkler Systems Building 337 08 April 2020

US Army Garrison‐Rock Island Arsenal

Directorate of Public Works Engineering and Services Division

IMRI‐RIA‐PWF

1 Rock Island Arsenal

Rock Island, IL 61299‐5000

2 | P a g e

PROJECT SUMMARY: This project is a Design-Build Project for Replacement of the Sprinkler System in Building 337. The scope of this project consists of furnishing labor, equipment and material to repair by replacement, the sprinkler system(s) in Building 337.

Preliminary investigation indicates that the sprinkler system is obstructed and the piping has significantly degraded. The project location is on the north side of Rodman Avenue on the Rock Island Arsenal, Rock Island, IL.

1 PART ONE: SPECIFIC PROJECT

1.1 PROJECT DESCRIPTION: US Army Garrison (USAG) – Rock Island Arsenal

(RIA) has a requirement to repair by replacement the sprinkler system(s) in Building

337. The work shall be performed in accordance with this Scope of Work (SOW), the referenced Unified Facilities Criteria (UFC) codes, the referenced National Fire Protection Association (NFPA) codes, and the attached drawings in Appendices A and B. This project will require the following work activities.

1.1.1 Actual sprinkler system drawings for Building 337 are not available. However the system layout is similar to the drawings provided in Appendix B for Building 336.

Appendix A contains the current floor plan for Building 337.

1.1.2 There are four (4) dry pipe sprinkler systems in the Building. All four system were installed in approximately 1945 and are classified as Ordinary Hazard.

1.1.2.1 System 69 serves the southeast half of the loading dock.

1.1.2.2 System 70 serves Room 1, Room 2 and the east half of Room 3.

1.1.2.3 System 71 serves Room 4, Room 5 and the west half of Room 3.

1.1.2.4 System 72 serves the southwest half of the loading dock.

1.1.2.5 None of the systems presently include provisions for In-Rack Sprinklers.

1.1.2.6 The Partial Site Plan in Appendix C shows the Preliminary Flow Data.

1.2 WORK ACTIVITIES:

1.2.1 Base Bid:

1.2.1.1 Prepare and submit a Fire Protection Design Analysis in accordance with UFC 3-

600-01, Section 1-7.2.

1.2.1.2 Design replacement Dry Pipe Sprinkler Systems in accordance with UFC 3-600-

01.

1.2.1.3 In accordance with UFC 3-660-01, Section 9-7.9, all Dry Pipe Sprinkler Systems shall be provided with a Nitrogen Generation System. One system shall be provided to serve all of the Dry Pipe Sprinkler Systems.

1.2.1.4 In accordance with UFC 3-600-01, all Design shall be provided by a Registered Professional Fire Protection Engineer.

1.2.1.5 Demolition of the existing Fire Protection Sprinkler Systems.

1.2.1.6 Installation of the new Fire Protection Sprinkler Systems.

1.2.1.7 Connect the new Fire Protection Sprinkler System components to the existing Fire

Alarm System.

1.3 SPECIAL SERVICES/REQUIREMENTS

1.3.1 Disruption of the tenants and their missions shall be minimized. Any potential interferences with the tenants or the rest of the RIA’s services, personnel or

3 | P a g e entities shall be coordinated with the Contracting Officer (KO) / Contracting Officer’s Representative (COR) so as to minimize disruption.

1.3.2 Work hours for this project are 06:00 to 17:00, Central Time, on Monday through Friday.

1.3.3 Contractor shall be responsible for accurate measurements of all existing site conditions.

1.3.4 Contractor shall provide all services, labor, materials, supervision, equipment, tools, etc. necessary to accomplish the work described in this SOW.

1.4 BASE BID:

1.4.1 The Base Bid consists of furnishing all labor, equipment and material to Design and Install the replacement sprinkler systems.

1.5 BID OPTIONS:

1.5.1 None.

1.6 DRAWINGS:

1.6.1 The As-Built drawings for a similar sprinkler system(s) in Building 336 are attached to this SOW in Appendix B.

1.6.2 The current floor plan drawing for Building 337 is attached to this SOW in

Appendix A.

1.6.3 Electronic AutoCAD Computer-Aided Design and Drafting (CADD) files will be provided by the Department of Public Works (DPW) on compact disc for the preparation of required Shop Drawings and Final As-Built Drawings. These files will be provided to the contractor after the Award of the Solicitation.

1.6.4 Hardcopy and electronic As-Built/Record drawings shall be provided by the Contractor for all projects. The electronic As-Built/Record drawing files shall be provided in AutoCAD format and shall be in accordance with the USAG-RIA DPW CADD Standard in use. The electronic As-Built/Record drawings shall also be provided in Adobe Acrobat format. Printed hardcopy drawing sets shall be supplied on full-sized, 4-mil, double-matte Mylar drawing sheets.

1.6.5 As-Built/Record Drawing creation and submittal sequence shall be in accordance with the requirements of Appendix D.

1.6.6 CAD Drawings shall be prepared in accordance with the requirements of the “A/E/C Graphics Standard, US Army Corps of Engineers, August 2015” and the “A/E/C CAD Standard, US Army Corps of Engineers, August 2015.”

1.7 SUBMITTALS/DELIVERABLES:

1.7.1 Refer to Section 1-7.2 in UFC 3-600-01, Fire Protection Engineering for

Facilities:

1.7.1.1 Fire Protection Design Analysis.

1.7.1.2 Life Safety.

1.7.1.3 Code Compliance Summary Sheet.

1.7.1.4 Preliminary Hydraulic Analysis.

1.7.2 The contractor shall submit Design Drawings and Specifications at 30% and 90%.

4 | P a g e

1.7.2.1 The contractor shall schedule a Design Review Meeting within 14 days of receiving comments on the Design Submittal.

1.7.2.2 Drawings and specifications shall be submitted in PDF format.

1.7.2.3 Specifications shall be prepared using the current version of SpecsIntact. At a minimum, the Specifications shall include the following Specification Sections:

1.7.2.3.1 Section 01 33 00 – Submittal Procedures with Submittal Register

1.7.2.3.2 Section 01 78 00 – Closeout Submittals

1.7.2.3.3 Section 01 78 23 – Operation and Maintenance Data

1.7.2.3.4 Section 21 13 00.00 40 – Fire-Suppression Sprinkler Systems

1.7.2.3.5 Section 21 13 16.00 20 – Dry-Pipe Fire Sprinkler Systems

1.7.2.3.6 Section 21 13 17.00 10 – Dry Pipe Sprinkler System, Fire Protection

1.7.2.3.7 Section 26 00 00.00 20 – Basic Electrical Materials and Methods

1.7.2.3.8 Section 26 05 00.00 40 – Common Work Results for Electrical

1.7.2.3.9 Section 26 05 19.10 10 – Insulated Wire and Cable

1.7.2.3.10 Section 26 20 00 – Interior Distribution System

1.7.2.3.11 Section 28 31 63.00 20 – Analog/Addressable Interior Fire Alarm System

1.8 EXISTING CONDITIONS:

1.8.1 The existing sprinkler systems where installed in the mid 1940’s.

1.8.2 Based upon the conditions of some of the other sprinkler systems on the Rock

Island Arsenal, there is reason to suspect that the sprinkler systems may be subjected to obstructions from internal piping corrosion.

2 PART TWO: GENERAL INFORMATION

2.1 COMMENCMENT, PROSECUTION, AND COMPLETION OF WORK:

2.1.1 The Contractor shall be required to commence work under this contract within 14 calendar days after the date the Contractor receives the Notice to Proceed, prosecute the work diligently, and substantially complete the Base Bid Work in 180 calendar days.

2.2 SPECIAL CONDITIONS:

2.2.1 Staging Area:

2.2.1.1 Parking spaces will be designated by the KO/COR for the storage of construction materials.

2.2.2 Construction Schedule and Closure Periods:

2.2.2.1 The Contractor’s Construction Schedule shall be submitted to the Government for approval.

2.2.3 Federal Holidays:

2.2.3.1 New Year’s Day, January 1; Martin Luther King Day, 3rd Monday in January;

President’s Day, 3rd Monday in February, Memorial Day, last Monday in May;

Independence Day, July 4; Labor Day, 1st Monday in September; Columbus Day, 2nd Monday in October; Veteran’s Day, November 11, Thanksgiving Day, 4th Thursday in November; Christmas Day, December 25.

2.2.3.2 If a holiday falls on Saturday, the preceding Friday is a holiday. If a holiday falls on Sunday, the following Monday is a holiday.

5 | P a g e

2.2.4 Utilities: The Government shall furnish, at no additional charge, the use of the following utilities:

2.2.4.1 Electric

2.2.4.2 Water

2.2.5 Miscellaneous:

2.2.5.1 All site condition information provided by the Government shall be field verified by the Contractor.

2.3 CONTRACTOR MANPOWER REPORTING (CMR): The Office of the Assistant

Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall supply all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, KO, or also known as the COR; (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub- Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub- Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.

3 PART THREE: SECURITY

3.1 OPERATIONS SECURITY (OPSEC) REVIEW:

3.1.1 In order to perform project (Project for Replacing the Sprinkler Systems in

Building 337) the Contractor must do the following:

6 | P a g e

3.1.2 AT Level I training. All Contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the Contracting Officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel.

3.1.3 Access and general protection/security policy and procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

3.1.4 For Contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3.1.5 iWATCH Training. The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the KO/COR. This training shall be completed within 30 calendar days of contract award and within 5 calendar days of new employees commencing performance with the results reported to the KO/COR NLT 30 calendar days after contract award.

3.1.6 For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the Contractor employees must complete Level I OPSEC Awareness training.

New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

3.1.7 RIA specific provision/clause language:

3.1.7.1 A non-disclosure agreement will be signed by the project prime before report/start date of contract.

3.1.7.2 All Training will be face to face, conducted on RIA. Any conflicts with training locations/performance will be directed by the project KO/COR.

7 | P a g e

3.1.7.3 All Training will be face to face, provided by a level II certified ATO and OPSEC officer, conducted on RIA. Any conflicts with training locations/performance will be directed by the project COR.

3.1.7.4 Contractors, sub-contractors will be escorted by the COR in areas where they may be exposed to classified and/or sensitive materials. All contractor employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials. The Vendor will coordinate with the COR and/or the facility security office for access when required.

3.1.7.5 Building Stand-Off: All occupied buildings on Rock Island Arsenal require a 33feet stand-off by all vehicles and equipment. At no time will unoccupied vehicles, equipment or tools/tool boxes be left unattended within 33 feet of installation buildings.

3.1.7.6 All personnel requesting access to Rock Island Arsenal will only enter through a manned and operational Access Control Point and present a United States National or State issued identification that is capable of being scanned for valid entry. All contractor and contractor employees' vehicles, equipment, and packages are subject to inspection or examination (search) at entry/exit of the Rock Island Arsenal. Only authorized individuals that pass a screening and vetting process will be permitted access. All contractor and subcontractor personnel will be required to submit the required identification credentials and must receive a favorable background check as conducted through the National Crime Information Center (NCIC) Interstate ID Index (III) to gain access and work on the installation.

4 PART FOUR: ROCK ISLAND ARSENAL SUPPLEMENTAL GUIDANCE

4.1 EMERGENCY MANAGEMENT CONTRACTOR ORGANIZATION AND

CONTRACTOR REQUIREMENTS:

4.1.1 All contractors working on RIA must comply with Department of Defense Instruction number 6055.17, "DoD Installation Emergency Management Program" (http://www.dtic.mil/whs/directives/corres/pdf/605517p.pdf), Army Regulation 525-27, "The Army Emergency Management Program" (http://www.apd.army.mil) and Department of Army Pamphlet 525-27, "Army Emergency Management Program" (http://www.apd.army.mil). The Army Emergency Management Program serves as the single integrated emergency management program for the planning, execution, and management of response efforts (designed or intended) to mitigate the effects of an all-hazard incident, to include but not limited to, natural, manmade, and technological disasters, chemical, biological, radiological, nuclear, and high-yield explosive (CBRNE) incidents and accidents on or affecting Army installations, facilities, and/or activities.

4.1.2 Contractor Organizations:

4.1.2.1 All contractor organizations must participate in the installation quarterly

Protection Working Group. To attend this working group, contact the KO/COR.

8 | P a g e

4.1.2.1.1 Contractor organizations must comply with the installation emergency guide and Building Marshal Warden Program and write supplemental plans that describe actions to take specific to the area the contractor organization occupies to include but not limited to shelter locations, evacuation points, communication plan and points of contact. The installation emergency guide can be used as a template for this plan. Building Marshal Warden Program Manager can be contacted through the Installation Fire Department (309) 782- 6107.

4.1.2.1.2 Contractor organizations must provide Facility Emergency Response Plans to the KO/COR for inclusion into the installation Emergency Management Plan.

4.1.2.1.3 All contractor organizations must support Public Health Emergency Officer policy and guidance relating to the integration of health surveillance requirements within operational/installation decision support schemes.

4.1.2.1.4 All contractor organizations must comply with installation policies; applicable federal, state, and local laws; regulations; and Executive Orders.

4.1.2.1.5 All contractor organizations must ensure that non-DOD HAZMAT is not stored, treated, or disposed of on the installation unless approved by the Office of the Assistant Secretary of the Army for installations, Energy and Environment, his or her designee, or higher authority.

4.1.2.1.6 All contractor organizations must assess the long-term resource impacts of all environmental agreements in coordination with the acquisition community.

Coordinate resource implications for agreements through command channels as appropriate prior to approval.

4.1.3 Contractors:

4.1.3.1 All contractors must comply with installation emergency procedures. This includes compliance with all emergency communications instructions provided through official channels to include the outdoor speaker system (Giant Voice), AtHoc alert system, building notification systems (Little Voice), or Building Marshal Warden’s.

4.2 FIRE PREVENTION AND SAFETY:

4.2.1 The Contractor and any associated sub-contractors shall as part of this contract comply with all applicable federal laws (Title 15 USC 272) pertaining to the use of technical standards that are developed or adopted by voluntary consensus bodies such as the NFPA. Current National Fire Codes are published by the National Fire Protection Association (NFPA) www.nfpa.org. Current “International” codes are published by the International Code Council (ICC) www.iccsafe.org Additional DoD mandated standards are published as Unified Facilities Criteria (UFC’s) www.wbdg.org/references/pa_dod.php.

4.2.2 Fire Prevention Program. The Contractor and any subordinate sub-contractor(s) shall comply with the most current edition of the RIA Program for Fire and Emergency Services referenced as the “RIAR 420-2 Rock Island Arsenal Program for Fire and Emergency Services” and can be obtained by contacting the installation fire department at (309) 782-6107.

4.3 ENVIRONMENTAL PROTECTION:

http://www.wbdg.org/references/pa_dod.php

9 | P a g e

4.3.1 Regulations and Laws. Contractor shall comply with all Federal, State, and local laws, regulations, and standards. All environmental protection matters shall be coordinated with the Contracting Officer or his designated representative. The Environmental Coordinator's Office will review questions on environmental compliance, and provide guidance as needed. In case of an environmental event or disaster, the Contractor shall comply with the Government's emergency services plan.

4.3.2 Compliance Requirements. Any of the facilities operated by the Contractor may be inspected by the Contracting Officer or his designated representative, the RIA Environmental Coordinator, or other Regulatory Officials on a non-notice basis.

Access for inspection by all authorized personnel shall be granted upon request.

4.3.3 Citations. Citations/Fines for non-compliance with environmental standards on Government facilities operated by the Contractor are a matter for resolution through the Environmental Coordinator's Office and between the RIA Garrison Commander and the issuing office of EPA or State of Illinois Regulatory Authorities. If the citations/fines are issued due to faulty operation or maintenance practices, the Contracting Officer shall deduct the fine from any monies due the Contractor.

4.3.4 Disposal of all wastes generated on site during the course of the project shall be the responsibility of the Contractor. Hazardous waste shall be properly accumulated and managed according to all applicable EPA laws and regulations.

Hazardous waste manifests shall be signed by the Public Works Environmental Office.

4.3.5 Contractor shall submit a non-hazardous solid waste disposal plan identifying methods and locations for solid waste disposal, including clearing debris. The plan shall include schedules for disposal. The Contractor shall identify any subcontractors responsible for the transportation and disposal of solid waste.

Licenses or permits shall be submitted for solid waste disposal sites that are not a commercial operating facility. Evidence of the disposal facilities acceptance of the solid waste shall be attached to this plan.

4.3.6 Contractor shall submit a recycling and solid waste minimization plan. The plan shall detail the Contractor's actions to comply with and to participate in Federal, State, Regional, and local government sponsored recycling programs to reduce the volume of solid waste at the source. It is the goal to recycle and/or divert 60% of the total waste stream from this project. Prior to any work, the Contractor shall submit a preliminary Non-Hazardous Construction/Demolition Debris Disposal/Diversion/Recycling Submittal form, copy included in Appendix E.

Form shall be annotated to depict the various non-hazardous waste streams expected during the work and the anticipated recycle and/or diversion rate.

4.3.7 Prior to final payment, the Contractor shall submit a final Non-Hazardous Construction/Demolition Debris Disposal/Diversion/Recycling Submittal form.

Form shall be annotated to depict the actual quantities for the various non-hazardous waste streams generated during the work and the final recycle and/or diversion rates. Copies of all certified weigh-bills shall also be provided for each load of material that was disposed, diverted, or recycled.

10 | P a g e

4.3.8 Verification of National Environmental Policy Act Documents. Contractor shall obtain from the COR or DGR a copy of the National Environmental Policy Act (NEPA) environmental analysis and/or status of the NEPA review done if analysis was not required. NEPA review and analysis is done in accordance with 32 CFR Part 651 and addresses actions to be taken by contractor prior to and during commencement of contract actions. The NEPA process consists of evaluating the environmental effects of a federal action including its alternatives.

There are three levels of analysis depending on whether or not the construction activity or project could significantly affect the environment. These three levels are: categorical exclusion determination; preparation of an environmental assessment/finding of no significant impact (EA/FONSI); and preparation of an

EIS.

4.3.9 Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).

4.4 ENERGY CONSERVATION:

4.4.1 Contractor shall operate all shops, buildings, structures, and areas included in the performance of this contract in an energy efficient manner to preclude waste of Government furnished utilities and fuels. Temperatures in all contractor areas will be maintained at specified RIA standards.

4.4.1.1 Compliance Requirements: Compliance with the RIA energy conservation requirements includes, but is not limited to:

4.4.1.1.1 Training personnel to conserve energy by turning off unneeded equipment and utilities.

4.4.1.1.2 Use of lights only in areas where work is actually being performed.

4.4.1.1.3 Water faucets or valves shall be turned off after required usage has been accomplished.

4.4.1.1.4 Complying with water bans imposed by local, State, or Federal Agencies.

4.4.1.1.5 All engines in vehicles parked for more than two (2) minutes will be shut off.

4.4.1.1.6 Providing a designated representative, for each building or area permanently occupied by contractor personnel, who may be contacted regarding unnecessary operation of lights, machinery, or heating/cooling systems.

4.4.1.2 Inspection Requirements. General area inspections for energy consumption deficiencies shall be granted on request. Any of the facilities operated by the Contractor may be inspected by the DPW Energy Engineer on a non-notice basis.

4.5 HAZARDOUS/SPECIAL WASTE DISPOSAL: Handling or disposing of hazardous or special waste generated by the Contractor in the performance of this contract, shall be submitted to the Environmental Coordinator’s Office for turn into DLA. Handling or disposing of hazardous or special waste generated by the Contractor in

11 | P a g e maintenance of Contractor owned equipment shall be the responsibility of the Contractor. Contractor shall dispose of it at an approved site off RIA. All disposal procedures will be IAW Federal and State EPA regulations. A copy of any paperwork, including manifests, shall be forwarded to, Environmental Coordinator’s Office, RIA.

4.6 SPACE ASSIGNED/OPERATED: As required in performance of the requirements of this contract. Contractor shall be required to maintain such space (both assigned and operated) in a clean and orderly manner. Each area shall be equal to or better than when it was occupied by the Contractor. Any Contractor configuration changes to such space cannot be made without the expressed written consent of the KO/COR.

All approved configuration changes will be made at the Contractor's expense.

Conversely, the Contractor will, at its own expense, restore this space to its original configuration upon completion of the contract.

5 PART FIVE: DEFINITIONS:

5.1 Not Used.

6 PART SIX: APPLICABLE PUBLICATIONS

6.1 The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures referenced in the SOW and the attached Appendices.

6.2 Contractor shall comply with the following Unified Facilities Criteria publications

(http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc):

6.2.1 Unified Facilities Criteria (UFC) 1-200-01: General Building Requirements with

Change 2

6.2.2 Unified Facilities Criteria (UFC) 3-600-01: Fire Protection Engineering for

Facilities with Change 3

6.2.3 Unified Facilities Criteria (UFC) 3-601-02: Operation and Maintenance:

Inspection, Testing, and Maintenance of Fire Protection Systems

6.3 Contractor shall comply with the following National Fire Protection Association

(NFPA) codes:

6.3.1 NFPA 13, Standard for the Installation of Sprinkler Systems

6.3.2 NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based

Fire Protection systems

6.4 SpecsIntact is available at the following website: https://specsintact.ksc.nasa.gov/.

7 PART SEVEN: PRECEDENCE

7.1 RESOLUTION OF CONFLICTING CRITERIA: In the event of conflict between

References and/or Applicable Military Criteria, the most stringent criteria will apply, unless otherwise specifically noted in the scope of work.

8 PART EIGHT: APPENDICES

8.1 Appendix A: Current Floor Plans – Building 337

8.2 Appendix B: Example Existing Fire Protection

8.3 Appendix C: Site Plan with Preliminary Flow Data

8.4 Appendix D: Engineering Graphics Standard

12 | P a g e

8.5 Appendix E: Non-Hazardous Construction and Demolition Debris Submittal Form

8.6 Appendix F: Record of Environmental Consideration

8.7 Appendix G: Rock Island Arsenal Engineering Standards

File details come from the government source that posted it. Updated .