This is a Questions and Answers document for RFQ 2031ZA26Q00031 addressing clarifications on an unarmed security guard and rigging services contract with the Bureau of Engraving and Printing (BEP).
The solicitation seeks rigging services for equipment removal and disposal at two locations: a facility at 14th & C Street in Washington, DC, and a warehouse in Landover, Maryland. At the DC location, major scope items include a Komori Lithrone G40P printing press (approximately 39,990 kg) and a Chandler & Price Craftsman Automatic press, both requiring removal and scrapping. At the Landover facility, multiple pieces of equipment marked for removal require contractor-supplied lifting equipment, as no overhead crane systems are available onsite. The contract is structured as a Blanket Purchase Agreement (BPA) with estimated quantities of eight visits per year at each location, though actual visit quantities may fluctuate based on government needs. Work is anticipated to be primarily emergent throughout the ordering period, with individual call orders allowing scope-specific pricing adjustments beyond the awarded unit price. Each rigging visit must include pre-inspection, rigging plan development, certification by a DC-licensed Structural Engineer (cost included in unit price), equipment removal, and disposal documentation including certificates of destruction. The government will provide equipment weights and pictures upon request and will handle utility disconnections, lockout/tagout procedures, and drainage of hazardous fluids prior to contractor arrival. DC environmental compliance applies, and equipment will be scrapped with no reinstallation required. The pricing submitted at proposal serves as sample pricing for award determination, with post-award specifications to be finalized regarding insurance limits, documentation standards, and other operational details.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 2031ZA26Q00031 - Unarmed Security Guard- Request for Clarifications (Questions & Answers) Questions Government Responses
1. Based on the site visits, potential rigging efforts appear to range from relatively small equipment removals to significantly larger and more complex moves. Q. For pricing purposes, can the Government clarify whether a single “visit” is intended to represent a generally consistent level of effort, or if visit scopes are expected to vary significantly depending on mission needs?
Visit scopes are expected to vary depending on mission needs. A single visit will be used to determine award. Please see updated solicitation and attachment 2 pricing sheet.
2. The solicitation references estimated annual visit quantities across the ordering period. Q. Can the Government clarify whether the estimated annual quantities are intended to reflect a representative mix of typical work scopes, or if the distribution of effort is expected to vary meaningfully year-to-year? Please see response to question #1
3. Following the site visits, it appears that some equipment removals may be identifiable in the near term, while future requirements may arise over time. Q. Can the Government clarify whether the majority of task orders are expected to be driven by currently known requirements or if work is anticipated to be primarily emergent throughout the ordering period? Work is anticipated to be primarily emergent throughout the ordering period
4. At both site visits we noticed multiple pieces of equipment currently marked as "ready" for removal or relocation, but without direct instruction on how or when the decision will be made about which pieces to move. Q. Can the Government confirm whether a single visit may encompass multiple pieces of equipment or work areas, or if visits are generally expected to be limited in scope per task order? Each visit will have a different scope.
5. During the site visits the Project Managers showed us a couple pieces of equipment at C street and several pieces of equipment at the Landover warehouse. They seemed to think the current solicitation was related to only these items. Q.The current solicitation requests unit pricing for 8 mobilizations a year at each location; how do we reconcile that and know what to provide pricing for based on the belief from the PM team that we were only providing pricing for the items shown to the group. See response to question #1
6. I understand pictures with weights and dimensions will be provided could you confirm? Pictures were be provided per request. Site visit screening was reasoning for customers to screen each piece of equipment and to self assess. We can contact production to assist with weights.
7. We will need the equipment weights for all items to be relocated. See response to question #1.
8. Please clarify who will be responsible for disassembling the platform surrounding the equipment at the 14th & C St. location prior to our arrival for removal. Contractor will be responsible
9. Is the Government expecting offerors to propose:
- A single fully burdened average price per call, regardless of scope?
- A ceiling or not-to-exceed price per visit?
- Or pricing based on a defined representative scope? Please see updated attachment 2 pricing sheet.
10. Will individual call orders allow scope-specific pricing adjustments, or will payment strictly be limited to the awarded unit price per visit? Individual call orders will allow scope specific adjustments.
11. Is the quantity of eight (8) visits per year intended solely for evaluation purposes? Visits may vary pending need and requirements for task order. Please see updated attachment 2 pricing sheet.
12. Section 5.1.2 requires that the rigging plan be certified by a D.C.-licensed Structural Engineer Is engineering certification required for every call order? If so, should this cost be fully included within the unit price per visit, or priced separately at the call order level?
Engineering certification may or may not be required for every call order. It will depend on the size of the equipment. In the case your plan should be certified by a Licensed Structural Engineer. The cost should be fully included within the unit price per visit. Also, for purposes of pricing this solicitation please include the certification.
28. Landover Location: What are the loading dock dimensions and weight capacities? Will review drawing and provide if applicable at later date.
29. Landover Access & Rigging: What are floor load ratings in the removal areas? The rating at that area is unknown. Additonally, the slab on grade load rating is unknown. Drawings aren't available at this time. 600 PSF is the estimated floor load at each dock leveler; however, the docking leveler capacity will be verified and sent at a later date.
30. Landover Access & Rigging: Are there overhead crane systems available onsite? No.
31. Landover Access & Rigging: Are forklifts permitted or must contractor supply all lifting equipment? Contractors are to supply all equipment required for removal.
32. Landover Access & Rigging: Are there ceiling height or doorway constraints beyond listed dimensions? No ceiling height or doorway contraints beyond listed dimensions.
33. Landover Utilities & Disconnect: Will BEP disconnect electrical, hydraulic, and compressed air lines? Yes.
34. Landover Utilities & Disconnect: Are lockout/tagout procedures managed by BEP or contractor? BEP's Electro Machinists shop will perform any lock out tag out if needed.
35. Landover Utilities & Disconnect: Are there hazardous fluids (oil, coolant, hydraulic fluid) that require special disposal? No
36. Landover Disposal: Is equipment to be scrapped, auctioned, or returned to OEM? Scrapped.
37. Landover Disposal: Are there ITAR, Treasury, or asset destruction documentation requirements? TBD post award
38. Landover Disposal: Does BEP require certificates of destruction? Yes, please see updated Statement of Work (SOW) Section 5.3 dated 24March2026
39. Landover Dispoal: Are there hazardous materials (PCB oil, lead paint, mercury switches)?
This information will be verified post award but prior to any work being performed. If there are any hazardous materials BEP will further investigate and address issue before rigging call is completed. This will be verified post award if hazardous materials are present and clean out procedures with BEP's Safety Division.
40. DC Location: Lithrone G40P (Major Scope Item) Equipment:
Lithrone G40P – Komori Corporation Approx. 80’ x 20’ with raised metal decking Exit via:
10’H x 9’W hallway OR 10’x10’ window via crane
Depending on the dismantling process and dimensions, some items may able to travel through the hallway, pending freight elevator dimensions.
41. DC-Critical Technical Disassembly: Has the machine ever been relocated before? (Komori) No.
42. DC-Critical Technical Disassembly: Are OEM drawings available? Equipment manuals are available post award, upon request.
43. DC-Critical Technical Disassembly: Will BEP require OEM-certified disassembly (Komori technician involvement)? Komori tech will not be available.
44. DC-Critical Technical Disassembly: What is the total estimated weight? 39,990 kg for Komori Press
45. DC-Critical Technical Disassembly: What is the heaviest single component section? Information unknown at this time.
46. DC-Critical Technical Disassembly: Does the raised decking need to be removed and disposed of? Yes.
47. DC-Crane Option: Has a structural engineer verified window opening for load-bearing crane lift? No this is removal only
48. DC-Crane Option: What is the distance from building to crane staging area? 10-20 feet
49. DC-Crane Option: Are street closures required in Washington, DC? not for this project
50. DC-Crane Option: Will DC permits and police details be required? TBD post award before each call
51. DC-Crane Option: What are the allowable crane setup hours? As early as 5am is acceptable
52. DC-Hallway Option: Is the 10’H x 9’W hallway clear of obstructions? Yes
53. DC-Hallway Option: What is the hallway floor load rating? Will verify and provide post award
54. DC-Hallway Option: Are there turns or tight radius points? Yes; will verify and provide additional info post award. Hallways will be clear of any obstructions.
55. DC-Hallway Option: Are there elevators involved? YES-pending if freight elevator are needed
56. DC-Hallway Option: Is there a path survey available? Will verify and provide if available post award 57: DC-Chandler & Price Craftsman Automatic (6’ x 4.5’): What is the approximate weight? Will verify and provide if available post award 58: DC-Chandler & Price Craftsman Automatic (6’ x 4.5’): Is the unit bolted to the floor? Will verify and provide if available post award 59: DC-Chandler & Price Craftsman Automatic (6’ x 4.5’): Are there embedded anchor points requiring concrete repair? Will verifty and provide info if available post awared 60: DC-Chandler & Price Craftsman Automatic (6’ x 4.5’): Is it to be relocated or scrapped? Scrapped.
61: DC-Chandler & Price Craftsman Automatic (6’ x 4.5’): Does it contain ink systems or hazardous chemicals? Please see response to question #39 62: DC-Installation Scope (If Reinstallation Required): Will reinstallation occur at the same facility or new site? No this is removal only 63: DC-Installation Scope (If Reinstallation Required): Who is responsible for foundation pads and leveling grout? No this is removal only 64: DC-Installation Scope (If Reinstallation Required): Are vibration isolation pads required? No this is removal only 65: DC-Installation Scope (If Reinstallation Required): Are utility stub-ups provided? No this is removal only 66: DC-Installation Scope (If Reinstallation Required): Will alignment calibration require OEM technicians? No this is removal only 67: DC-Installation Scope (If Reinstallation Required): Are FAT/SAT procedures required? No this is removal only 68: DC-Installation Scope (If Reinstallation Required): What are uptime deadlines? No this is removal only
69. Environmental & Compliance: Are there EPA or Maryland/DC environmental compliance requirements?
The BEP facility is located in the District of Columbia and DC environmental compliance requirements apply. Before equipment is released to riggers for removal, BEP will drain all oils and fluid reservoirs and clean surficial deposits for inks, oils, and other production related materials from the equipment. BEP will not strip paint from the equipment and after cleaning some residual staining may remain on equipment surfaces.
70. Environmental & Compliance: Are waste manifests required?
No, the equipment that is released to riggers for removal from the site will not contain hazardous wastes and will not require hazardous waste manifests for shipment off-site.
Note that the manifest requirements for any wastes generated by the rigging company during the removal of the equipment would depend on the chemicals used by the rigging company.
71. Environmental & Compliance: Is there a sustainability reporting requirement? No.
72. Environmental & Compliance: Are there noise restrictions during removal?
There aren’t, generally, any noise restrictions imposed. However, if noise generated during the rigging services is extraordinarily loud where it may present a hazard to building occupants, then some restrictions or controls may be implemented.
73. Environmental & Compliance: Is LEED compliance required? No.
74. Insurance & Risk Allocation: Required limits for:
| 75. Insurance & Risk Allocation: • | General Liability—are there limits? This can be addressed post award with the awardee |
| 76. Insurance & Risk Allocation: • | Riggers Liability—are there limits? Please see response to question #75. |
| 77. Insurance & Risk Allocation: • | Professional Liability—are there limits? Please see response to question #75. |
| 78. Insurance & Risk Allocation: • | Pollution Liability—are there limits? Please see response to question #75. |
79. Insurance & Risk Allocation: Is a crane rider required? Please see response to question #75.
80. Insurance & Risk Allocation: Is builder’s risk provided by BEP? Please see response to question #75.
81. Insurance & Risk Allocation: Who assumes risk once equipment is disconnected? Please see response to question #75.
82. Insurance & Risk Allocation: Are liquidated damages included? Please see response to question #75.
83. Documentation & Deliverables: Asset inventory verification requirements? Please see response to question #75.
84. Documentation & Deliverables: Photo documentation standards? Please see response to question #75.
85. Documentation & Deliverables: Rigging plans required for approval? Yes, please see updated Statement of Work (SOW) Section 5.1.2
86. Documentation & Deliverables: Lift plans stamped by PE? Please see response to question #75.
87. Documentation & Deliverables: Close-out documentation checklist? Please see response to question #75.
88. Documentation & Deliverables: Serialized tracking of removed assets? Please see response to question #75.
89. Logistics & Transportation: Are there weight restrictions for transport in DC? Please verify with the District of Columbia
90. Logistics & Transportation: Are escorts required for oversized loads? Please verify with the District of Columbia
91. Logistics & Transportation: Is temporary storage required? No this is removal only
92. Logistics & Transportation: Is climate-controlled storage required? No this is removal only
93. Logistics & Transportation: Are there restrictions on staging equipment on site? There are limits. BEP will direct you to a specific location
94. Attachment 2-Pricing Sheet: Please clarify how the unit prices provided in column F of Attachment 2, the Pricing Sheet, will be used, as the solicitation states: "Pricing will be reviewed on a per call basis."
Do the unit prices establish a FFP value from which each BPA call is drawn, a Not-to-Exceed cost for each rigging project, or is this the cost for each rigging pre-inspection? Please see response to question #1
95. Attachment 2-Pricing Sheet: The pricing template has a quantity of 8 listed for each row in column D.
Is this the exact quantity for each year, an estimate that may fluctuate higher or lower each year depending on need, or a Not To Exceed quantity?
The quantity is an anticipated estime and it may fluctuate each year depending onn the Governments needs.
96. Attachment 2-Pricing Sheet: If the quantity may change each year, what is the minimum number the government will award each year? Please see response to question #1.
97. Attachment 2-Pricing Sheet: Please clarify the "quantity of visits" column D in F of Attachment 2 Pricing Sheet.
Is this intended to indicate each rigging day, or each day spent on site during a pre-inspection?
Is this intended to indicate each rigging day, or each day spent on site during a pre-inspection? Column D "quantity of visits" is intended to indicate each rigging call.
98. Attachment 2-Pricing Sheet: Does each row in the pricing template need to be inclusive of all tasks, such as pre-inspection, creation of rigging plan, rigging plan certification by a D.C. licensed Structural engineer, equipment demolition and removal, equipment disposal, and program management? Yes, each row in the pricing templates needs to be inclusive of all task necessary to complete the work.
99. Attachment 1-Rigging Services SOW: SOW 5.1.1 Pre-Inspection states "Upon each new call order, the contractor will coordinate and schedule a site visit with the COR to assess the scope of work, develop rigging plan, and provide initial quote within 15 business days of site visit." How does the quote for each new call order differ from the FFP quote provided with the bidder's Blanket Purchase Agreement Proposal? Is the pricing due now a non-binding sample pricing? The pricing due at proposal is a sample pricing to determine award.
RIGGING Q&A