This document is an Amendment to a federal solicitation (RFQ 2031ZA25Q00190) for Off-Site Destruction of Government Securities issued by the Bureau of Engraving and Printing. The solicitation seeks a contractor to provide off-site destruction services for government securities, with quotes due by 2:00 PM EST on July 31, 2025. The contract will be a single firm fixed-price agreement under NAICS code 562213 for Solid Waste Combustors and Incinerators, with an unrestricted set-aside and a $47 million size standard.

The amendment introduces key changes including incorporating a Questions and Answers document, revising the Performance Work Statement (Attachment 1), removing a specific contract clause (H.7), and updating the Technical Factor 1, Subfactor 4 evaluation criteria. Quoters must submit a technical approach with five subfactors (Key Personnel, Camera Coverage, Incinerate/Shred, Quality Control, and Physical Security), a past performance section, and a price quote. The government will evaluate quotes using a Lowest Price Technically Acceptable (LPTA) methodology, with technical and past performance factors being approximately equal to price in importance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE

DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

2031ZA25Q00190 0001

Summary of Changes

Section H - Special Contract Requirements

The following clauses are modified:

Clauses incorporated by full text

Section H

H.1 TYPE OF CONTRACT

This is a firm fixed-price (FFP) contract.

H.2 INTERPRETATION OF CONTRACT REQUIREMENTS

No interpretation of any provision of this contract, including applicable specification or attachments, shall be binding on the Government unless furnished or agreed to in writing by the CO.

H.3 NON-DISCLOSURE OF CONFIDENTAL INFORMATION & DATA

During the period of performance of the contract, the Contractor might gain access to confidential and Non Public information and data, which is the sole property of BEP, as well as proprietary information and data, which is the sole property of entities other than the contracting parties. The Contractor agrees to maintain the confidentiality of all such information and data and shall not disclose any information and data, interpretations of, and/or derivatives of, such information and data to any unauthorized party without the express written approval of the CO, or of the party in which title is wholly vested. The Contractor hereby agrees to include this clause in all subcontracts or consulting agreements relating to work under this contract. The Contractor shall be required to sign a nondisclosure agreement from BEP which will apply to all personnel working under this contract.

H.4 CONFIDENTIALITY OF INFORMATION

The Contractor agrees that all information provided by representatives of BEP, either before or after award, concerning the production and processes of this award is nonpublic. Such information will be shared only with employees or agents of the company having a need to know, and will not be disclosed to other persons without the written consent of the CO.

H.5 NOTICE TO THE GOVERNMENT OF DELAYS

If the Contractor encounters difficulty in meeting the performance requirements, or when the Contractor anticipates difficulty in complying with the Contractdelivery schedule or date, or whenever the Contractor has knowledge thatany actual or potential situation is delaying or threatens to delays the timely performance of this contract, theContractor shall immediately notify the CO and COR, in writing, giving pertinent details; provided, however, thatthis data shall be informational only in character and that this provision shall not be construed as a waiver by theGovernment or any delivery schedule or date or any rights or remedies provided by law or under this contract.

H.6 SECURITY REQUIREMENTS

BEP's facilities are considered to be secure government facilities; therefore visitors to BEP may be given a visitor's security badge by security personnel and escorted by Government authorized personnel. Visitor security badges shall be worn above the waist, clearly visible, with picture or front side front forward at all times. Visitor security badges are to be returned upon leaving the site.

H.7 Reserved.

H.8 ORGANIZATIONAL CONFLICTS OF INTEREST

(a) The Contractor warrants that, to the best of the Contractor's knowledge and belief, there are no relevant facts or circumstances which could give rise to an organizational conflict of interest (OCI), as defined in FAR 9.5, Organizational and Consultants Conflicts of Interest, or that the Contractor has disclosed all such relevant information.

(b) The Contractor agrees that if an actual or potential OCI is discovered after award, the Contractor shall make a full disclosure in writing to the Contracting Officer. This disclosure must include a description of actions, which the

Contractor has taken or proposes to take, after consultation with the Contracting Officer, to avoid, mitigate, or neutralize the actual or potential conflict.

(c) The Contracting Officer may terminate this contract for convenience, in whole or in part, if it deems such termination necessary to avoid an OCI. If the Contractor was aware of a potential OCI prior to award or discovered an actual or potential conflict after award and did not disclose or misrepresented relevant information to the

Contacting Office, the Government may terminate the contract for default, debar the Contractor from Government contracting, or pursue such other remedies as may be permitted by law or this contract.

(d) The Contractor must include this clause in all subcontracts and in lower tier subcontracts unless a waiver is requested from, and granted by, the Contracting Officer.

(e) In the event that a requirement changes in such a way as to create a potential conflict of interest for the

Contractor, the Contractor must:

(1) Notify the Contracting Officer of a potential conflict, and;

(2) Recommend to the Government an alternate approach which would avoid the potential conflict, or

(3) Present for approval a conflict of interest mitigation plan that will:

(i) Describe in detail the changed requirement that creates the potential conflict of interest; and

(ii) Outline in detail the actions to be taken by the Contractor or the Government in the performance of the task to mitigate the conflict, division of subcontractor effort, and limited access to information, or other acceptable means.

(4) The Contractor must not commence work on a changed requirement related to a potential conflict of interest until specifically notified by the Contracting Officer to proceed.

(5) If the Contracting Officer determines that it is in the best interest of the Government to proceed with work, notwithstanding a conflict of interest, a request for waiver must be submitted in accordance with FAR 9.503.

H.9 DISCLOSURE OF CONFLICTS OF INTEREST

It is the BEP policy to award contracts to only those offerors whose objectivity is not impaired because of any related past, present, or planned interest, financial or otherwise, in organizations regulated by BEP or in organizations whose interests may be substantially affected by Departmental activities. Based on this policy, if at any time during the performance of this contract the Contractor knows of any Conflict of Interest situation affecting the organization, any of its officers or Key Persons working under this contract, has reason to believe that a conflict of interest situation might arise, or is made aware of an actual or potential conflict of interest situation:

(a) The Contractor shall immediately provide to the Contracting Officer a written statement which describes in a concise manner all past, present or planned organizational, financial, contractual or other interest(s) with that organization regulated by BEP, or with that organization or individual whose interests may be substantially affected by Departmental activities, and which is related to the work under this contract. The interest(s) described shall include those of the Contractor, its affiliates, consultants, Subcontractors and key personnel of any of the above. Past interest shall be limited to within one year of the date of the offeror's technical proposal. Key personnel shall include any person owning more than 20% interest in the organization, and the organization's corporate officers, its senior managers and any employee who is responsible for making a decision or taking an action on this contract where the decision or action can have an economic or other impact on the interests of a regulated or affected organization.

(b) The Contractor shall describe in detail when it became aware of the actual or potential conflict of interest, what action the organization has taken or proposes to take to mitigate and / or rectify the situation, and why it believes, in light of the interest(s) identified in (a) above, that performance of the contract can still be accomplished in an impartial and objective manner.

(c) In the absence of any relevant interest identified in (a) above, the Contractor shall certify in its statement that to its best knowledge and belief no affiliation exists relevant to possible conflicts of interest. The Contractor must obtain the same information from any potential Subcontractors prior to award of a subcontract.

(d) The Contracting Officer will review the statement submitted and may require additional relevant information from the Contractor. All such information, and any other relevant information known to BEP, will be used to determine whether a conflict of interest exists or a situation exists that may create a conflict of interest. If any such conflict of interest is found to exist, the Contracting Officer may (1) terminate the contract, or (2) determine that it is otherwise in the best interest of the United States to continue the contract with the Contractor and (3) modify the contract to include appropriate provisions to mitigate or avoid such conflicts in the contract.

(e) If the Contractor refuses to provide the written statement called for in paragraph (a), or any additional information that the Contracting Officer may require, the Contracting Officer may terminate thecontract for convenience if he or she deems that termination is in the best interest of the Government.

H.10 EVALUATION OF CONTRACTOR PERFORMANCE

(a) Interim and final evaluations of Contractor performance will be prepared on this contract in accordance with

FAR 42.1503. The final performance evaluations will be prepared at the time of completion of work.

(b) The Contractor can elect to review the evaluation and submit additional information or a rebuttal statement. The

Contractor will be permitted 60 calendar days to respond. Contractor response is voluntary. If the Contractor does not respond within 60 days, the Government will presume that the Contractor has no comment. Any disagreement between the parties regarding an evaluation will be referred to an individual at a level above the Contracting Officer, whose decision is final.

(c) Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contractfile and may be used to support future award decisions.

Bureau of Engraving and Printing utilizes the Contractor Performance Assessment Reporting System (CPARS), Federal Awarded Performance and Integrity Information System (FAPIIS), Architect-Engineer Contract

Administration Support System (ACASS) or Construction Contractor appraisal Support System (CCASS) to record and maintain past performance information. The past performance systems hosts a suite of web-enabled applications that are used to document Contractor performance information that is required by Federal Regulations.

The CPARS module assesses performance on contracts for Systems, Services, Information Technology, and

Operations Support, Architect-Engineer Contracts and performance on Construction Contracts. CPARS reference material can be accessed at http://www.cpars.csd.disa.mil/cparsfiles/cpars/refmatl.htm.

Federal Awarded Performance and Integrity Information System (FAPIIS) http://www.fapiis.gov/fapiis/govt/datareports.jsp

Architect-Engineer Contract Administration Support System (ACASS) http://www.acq.osd.mil/dpap/ccap/cc/jcchb/Files/Topical/Past_Performance/guides/acass_policy_manual_2010.pdf

Construction Contractor appraisal Support System (CCASS) http://www.409csb.army.mil/Library/COI/ACASSCCASSUserManual-Nov2012.pdf

The registration process requires the Contractor to identify an individual that will serve as a primary contact. This individual will be authorized access to the evaluation for review and comment. In addition, the Contractor is encouraged to identify a secondary contact in the event the primary contact is unavailable to process the evaluation within the required 60-day time period. After the BEP Contract Specialist registers the contract in one of the systems listed above, the Contractor will receive a system generated e-mail notifying him/her that the contract is registered.

A system generated e-mail will also provide the Contractor with a User ID if the person does not already have a system User ID.

Once a performance evaluation has been prepared and is ready for comment, the Contractor representative will receive a system generated e-mail notification that the performance evaluation is electronically available for review and comment. The Contractor representative will receive an automated e-mail whenever an assessment is completed and can subsequently retrieve the completed assessment from system.

Contractors may access evaluations at one of the website listed above for review and comment in CPARS.

H.11 INDEMNIFICATION

(a) Responsibility for Government Property: The Contractor assumes full responsibility for and shall indemnify the Government against any and all losses or damage of any kind and nature to any and all Government property, including any equipment, supplies, accessories, or parts furnished, while in his custody care for storage, repairs, or service to be performed under the terms of this contract, resulting in whole or in part from the negligent acts or omissions of the Contractor, any subcontractor, or any employee, agent or representative of the Contractor or subcontractor. If due to the fault, negligent acts (whether of commission or omission) and/or dishonesty of the

Contractor or its employees, any Government-owned or controlled property is lost or damaged as a result of the

Contractor's performance of this contract, the Contractor shall be responsible to the Government for such loss or damage, and the Government, at its option, may in lieu of payment thereof, require the Contractor to replace at his own expense, all property lost or damaged.

(b) Hold Harmless and Indemnification Agreement: The Contractor shall save and hold harmless and indemnify the Government against any and all liability claims, and cost of any kind and nature for injury to or death of any person or persons and for loss or damage to any Contractor property or property owned by a third party occurring in connection with or in any way incident to or arising out of the occupancy, use, service, operation, or performance of work under the terms of this contract, resulting in whole or in part from the acts or omissions of the

Contractor, any subcontractor, or any employee, agent, or representative of the Contractor or subcontractor.

(c) Government's Right of Recovery: Nothing in the above paragraphs shall be considered to preclude the

Government from receiving the benefits of any insurance the Contractor may carry which provides for the indemnification of any loss or destruction of, or damages to property in the custody and care of the Contractor where such loss, destruction or damage is to Government property. The Contractor shall do nothing to prejudice the

Government's right to recover against third parties for any loss, destruction of, or damage to Government property, and upon the request of the CO shall, at the Government's expense, furnish to the Government all reasonable assistance and cooperation (including assistance in the prosecution of suit and the execution of instruments of assignment in favor of the Government) in obtaining recovery.

(d) Government Liability: The Government shall not be liable for any injury to the Contractor's personnel or damage to the Contractor's property unless such injury or damage is due to negligence on the part of the

Government and is recoverable under the Federal Torts Claims Act, or pursuant to other Federal statutory authority.

H.12 BEP WORKING RESTRICTIONS

(a) When performing work during BEP's working hours, such work must be performed without:

(1) Interfering with Government business;

(2) Unduly restricting traffic;

(3) Causing unsafe conditions for employees and visitors; and

(4) Adversely affecting the operation of BEP equipment.

(b) Failure to adhere to this requirement is considered grounds for termination. In addition, if the CO determines that the Contractor is performing work in violation of any of the above, the Contractor shall be required to perform the work at such time and under such conditions as are in the best interest of BEP at no additional cost to the

Government.

H.13 VENDOR WARRANTIES

The Contractor shall require subcontractors and vendors to provide all normal and customary warranties, including, but not limited to those, on new equipment, materials, supplies, and spare parts. The Contractor shall include in its contractual arrangements with its subcontractors and vendors provisions whereby said warranties are for the benefit of BEP as well as the Contractor and are directly enforceable by BEP. BEP shall receive a copy of all warranties in effect at contract completion. The warranty period shall also be indicated on all reimbursable item invoices which are to be submitted with any request for payment.

H.14 POST AWARD MEETING

After contract award, the Government may conduct a post award meeting. The objectives of this meeting are to include; introduce key participants and explain their roles, review the tasks to ensure a common understanding of task requirements and objectives for all participants and review Deliverables and other matters.

Section J - List of Documents, Exhibits, and other Attachments

Amendment specific attachments:

File Attachments:

Title Description File Name Entity Reference

Attachment 1_PWS_Off-

Site Destruction rv1

Attachment 1_PWS_Off-Site Destruction rv1.pdf

Header

Questions and Answers

Questions and Answers 2031ZA25Q00190.xlsx

Header

Section L - Instructions, Conditions and Notices to Offerors

52.212-1

INSTRUCTIONS TO QUOTERS

ADDENDUM to FAR 52.212-1 INSTRUCTIONS TO QUOTEORS—COMMERCIAL ITEMS

GENERAL INSTRUCTIONS

The sole points of contact for this acquisition are the Contract Specialist and the Contracting Officer. The Quote must be sent by email to the Contract Specialist listed below on or before July 31, 2025 at 2:00 PM Eastern Time (ET).

All questions, comments, and requests for information regarding this acquisition shall be sent by email, cite the solicitation number, and be directed to the Contract Specialist and copy the Contracting Officer, using the following contact information:

Name: Ashley Johns | Contract Specialist

E-mail: ashley.johns@bep.gov

Name: JerKendra Holloway| Contracting Officer

E-mail: jerkendra.holloway@bep.gov

1. Questions/Comments for the RFQ must be submitted via email to the Contract Specialist identified above on or before July 22, 2025 at 12:00 PM ET to ensure Government consideration.

a. When submitting questions and comments, please refer to the specific text of the RFQ in the following format:

Subject: RFQ No. 2031ZA25Q00190

Reference: RFQ Section ______, Paragraph(s)______, Page(s)_____.

b. Answers to questions will be provided to all quoters being solicited, giving due regard to the proper protection of proprietary information.

2. This portion of Instructions to Quoters provides general information preparing the quote.

a. The Quoter's quote must include all data and information requested herein and must be submitted in accordance with these instructions.

b. The Quoter's quote shall be clear, concise, and include sufficient detail for effective evaluation of the Quoter's capabilities to perform the requirements outlined in the PWS.

c. Quoter is advised that their quote should agree to hold the prices in its quote firm for90 calendar days. Provision 52.212-1, paragraph (c) is hereby tailored to extend the 30- day response period out to 90 days.

3. This section provides specific instructions on the format and content of the quote. Each section shall be a "stand alone" document and be complete by itself. All quote documents shall use 12-point font in either Arial, Calibri, or Times New Roman fonts. Page limits are listed with each Section and are not- to-exceed; each Section must be submitted as separate files (preferably PDF).

Each quote shall consist of three (3) separate documents:

• Factor 1 -Technical Approach o Subfactor 1- Key Personnel o Subfactor 2- Camera Coverage o Subfactor 3- Incinerate/Shred o Subfactor 4- Quality Control o Subfactor 5- Physical Security

• Factor 2 – Past Performance

• Factor 3 – Price

FACTOR 1 – Technical Approach (10-page limitation)

Quoter shall submit a written response of their proposed solution for meeting or exceeding the Government's requirements set forth in the PWS. Technical description shall address each of the subfactors listed below:

a. Subfactor 1- Key Personnel: The Quoter shall submit the name of a candidate identified as key personnel as stated in Section 1.6.12 of the PWS.

b. Subfactor 2- Camera Coverage: The Quoter shall clearly demonstrate in their response to the solicitation their security surveillance video recording capabilities as stated in Section 5.2.9 of the PWS.

c. Subfactor 3- Incinerate/Shred: The Quoter shall clearly demonstrate their ability to incinerate to ash and/or shred beyond reuse as stated in Section 5.2.8 of the PWS.

d. Subfactor 4- Quality Control: The Quoter shall clearly demonstrate in their response to the solicitation a summary of their Quality Control Plan (QCP) as stated in Section 1.6.2 of the PWS.

e. Subfactor 5- Physical Security: The Quoter shall clearly demonstrate in their response to the solicitation their Physical Security plan as stated in section 1.6.8.1 of the PWS.

TECHNICAL ASSUMPTIONS

No Assumptions, Conditions, Exceptions are permitted. Any response containing Assumptions, Conditions, or Exceptions will be rejected and ineligible for award

FACTOR 2 – Past Performance (No page limitation)

Quotes will be evaluated based on the information contained in the Quoter's quote and the information that the Government obtains through reference checks in relation to the issuance of Past Performance Questionnaires (PPQ) (See Attachment 4 Past Performance Questionnaire) or other means. The quoter will provide no more than 3 most relevant examples of projects that were carried out within the last 5 years. Most relevant contracts are those for which it has performed relevant work similar in size, scope and complexity to all the requirements of this solicitation. Each example will include the following project information:

• Contract Title and Number

• Period of Performance

• Name and contact information of the client (for Government agencies, provide the name of the agency and either the Contracting Officer or the Contracting Officer's Technical Representative)

• Approximate number of personnel, by major position and skill category, used on each project

• Approximate dollar value of each project

• A synopsis of work carried out under each contract that describes the key tasks carried out and an explanation of how that effort is comparable to the requirements of the PWS and how the successful completion of that contract will facilitate the quoter's ability to carry out the requirements of the PWS and perform all tasks at a level that consistently meets or exceeds the AQL of the performance standards.

The Government will assess the degree of success of quoter's recent and relevant past performance. References will be asked to comment on items such as business relations, timeliness, quality of work, and cost. The Government will give an acceptable rating to documented successful outcomes that are supported by outside source confirmation (e.g. but not limited to telephone interviews with points of contact identified in the quote, agency performance databases such as Contractor Performance Assessment Reports (CPARS), quoter furnished references, or personal knowledge). Successful outcomes are defined as having received a rating of satisfactory or better, or the equivalent. If the Government does not obtain past performance information and cannot establish a past performance record for the quoter through other sources, or if the quoter has no past performance record, past performance will be rated neither favorably nor unfavorably and considered neutral. In the context of acceptability/unacceptability, a neutral rating shall be considered acceptable.

FACTOR 3 – Price (No page limitation)

Quoters shall complete a Schedule/Supplies table and attach this page separately. Quoters must quote prices for all service line items in order to be considered for award. All pricing shall be inclusive of all quoter's direct cost (labor, training and travel), indirect costs, and profit. Quoter shall provide a full break down of all cost. (Please refer to PWS)

The price quote will be evaluated (but not scored) based on total price reasonableness. The quoter's quote is presumed to represent the quoter's best efforts in response to the solicitation. Any inconsistency, whether real or apparent, between promised performance, and cost or price, shall be explained in the quote.

Quoters shall not include any price data in the technical quotes.

PRICE ASSUMPTIONS

No additional Assumptions, Conditions, Exceptions are permitted. Any response containing Assumptions, Conditions, or Exceptions will be rejected and ineligible for award.

(End of provision)

NOTICE: "System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in Bureau solicitations, including 52.223- 22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider or use these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

Section M - Evaluation Factors for Award

52.212-2

52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)

A detailed and complete analysis of each Offeror's quote will be performed. The Government contemplates the award will be made based on the lowest evaluated price of quotes meeting or exceeding the acceptability standards for non-cost factors.

Tradeoffs are not permitted. Quotes are evaluated for acceptability but not ranked using non-cost/price factors. The following factors shall be used to evaluate quotes:

• Factor 1 -Technical Approach o Subfactor 1- Key Personnel o Subfactor 2- Camera Coverage o Subfactor 3- Incinerate/Shred o Subfactor 4- Quality Control o Subfactor 5- Physical Security

• Factor 2 – Past Performance

• Factor 3 – Price

Technical and past performance, when combined, are approximately equal to price.

TECHNICAL EVALUATION CRITERIA

The Government will evaluate technical quotes based on the following factors:

Factor 1 – Technical Approach

The Government will evaluate quotes for technical acceptability. Quote must meet or exceed the specifications stated in the performance work statement and all factors and sub factors as stated in the solicitation.

The Government will evaluate each quoter's technical quote to determine the quoters overall understanding of this requirement.

Subfactor 1- Key Personnel: The Quote shall be evaluated to determine if the quoter submitted the name of a candidate identified as key personnel as stated in Section 1.6.12 of the PWS.

Subfactor 2- Camera Coverage: The Quote shall be evaluated to determine if the quoter demonstrated in their response to the solicitation their security surveillance video recording capabilities as stated in Section 5.2.9 of the

PWS.

Subfactor 3- Incinerate/Shred: The Quote shall be evaluated to determine if the quoter demonstrated their ability to incinerate to ash and/or shred beyond reuse as stated in Section 5.2.8 of the PWS.

Subfactor 4- Quality Control: The Quote shall be evaluated to determine if the quoter demonstrated in their response to the solicitation a summary of their Quality Control Plan (QCP) as stated in Section 1.6.2 of the PWS.

Subfactor 5- Physical Security: The Quote shall be evaluated to determine if the quoter demonstrated in their response to the solicitation their Physical Security plan as stated in section 1.6.8.1 of the PWS.

Factor 1 and all subfactors will be evaluated using an Acceptable or Unacceptable rating approach. The following ratings standards shall be used:

Rating Standard for Factor 1: Technical Approach

ACCEPTABLE UNACCEPTABLE

Quote meets the requirements of the solicitation as described in the Performance Work Statement.

Quote does not meet the requirements of the solicitation as described in the Performance Work Statement.

Factor 2will be assigned one of the ratings defined below:

Rating Standards for Factor 2: Past Performance

HIGH CONFIDENCE SOME CONFIDENCE NEUTRAL LOW CONFIDENCE

The Government has high confidence that the Offeror understands the requirement, proposes a sound approach, and will be successful in performing the contract with

The Government has some confidence that the Offeror understands the requirement, proposes a sound approach, and will be successful in performing the contract with

No recent/relevant past performance record is available, a meaningful assessment rating cannot be assigned

The Government has low confidence that the Offeror understands the requirement, proposes a sound approach, or will be successful in performing the contract even little or no Government intervention.

some Government intervention.

with Government intervention.

PRICE QUOTE EVALUATION

Factor 3 – Price

The quoter's price quotation will be evaluated to assess for price reasonableness in accordance with FAR 13.106-3(a).

Specifically,

1. The Total Evaluated Price (TEP) will represent the vendor's quote under Factor 3. The vendor's TEP will be calculated as follows:

a. Firm Fixed Price (FFP) CLINs: Total prices submitted for (a) the base period, (b) all option periods, and

(c) the six month extension authorized by FAR clause 52.217-8. For purposes of determining the evaluated price for the six month 52.217-8 extension, the total price is calculated as one-half of the total price of the final option year.

b. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

c. The price factor will not receive a rating, but the evaluated price must be found to be fair and reasonable in order to be eligible for award as indicated in Factor II - Price. The pricing evaluation will be based on price analysis techniques found in FAR 15.404-1 to determine if they are fair and reasonable. Price realism may be used when a fair and reasonable price cannot be determined through price analysis alone. The Government has the right to open discussions and/or negotiations. If an offeror's price is not found to be fair and reasonable, the offeror will not be eligible for award. Evaluation of options shall not obligate the Government to exercise the option(s).

2. The Government reserves the right to reject any quotation that includes overtime or extended hours billing practices.

Basis of Award

The Government intends to award a single firm fixed-price contract resulting from this solicitation to the responsible quoter whose quote is based on the Lowest Price Technically Acceptable (LPTA) procedures in accordance with FAR Part 12 and 13 as supplemented. Award will be made to the acceptable quoter with the lowest evaluated price, which is deemed responsible in accordance with the Federal Acquisition Regulation (FAR), 13.106-2 Evaluation of Offers, and whose quote conforms to the solicitation requirements. The Government will not award a contract on the basis of an unacceptable quote.

Options. The Government will evaluate quotes for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that a quote is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s). The Government will calculate any six (6) month extension, exercised under FAR 52.217-8 Option to Extend Services, based on the average price of the last six (6) months of the final Contract Line Item Number (CLINs) with a period of performance ending in 2030.

A written notice of award or acceptance of a quote, emailed or otherwise furnished to the successful quoter within the time for acceptance specified in the quote, shall result in a binding contract without further action by either party. Before the quote's specified expiration time, the Government may accept a quote (or part of a quote), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

Selection of a Quoter for contract award will be based on evaluation of quotes against the factors identified in this section.

Principles and procedures of Subpart 15.3 do not apply. The Government reserves the right to make an award based on initial quotes received, without discussion of such quotes in accordance with FAR provision 52.215-1, or the Government may make award after clarifications of some aspects of the quote.

Accordingly, the Government reserves the right to do any or all of the following:

a. Award on initial quotes, without discussion.

b. Ask clarifying questions during the question-and-answer period if needed. Clarification questions may include asking quoters to clarify their written technical quotes. As a result, the Government may have communications with some, but not all, quoters; these communications, however, will be clarifications and not discussions. In these situations, the Government will consider the quoter's clarifying response(s) without allowing quote revisions.

c. Have communications; ask clarifying questions, request corrections relative to minor errors in the written quote or request substantiating documentation to facilitate the Government's final evaluation with one or some quoters.

These communications, clarifications, or requests for corrections or substantiating documentation will not materially change the quoter's quote in terms of conformance to RFQ requirements, constitute discussions such as the removal of an unacceptable assumption.

Quotations shall set forth full, accurate, and complete information as required by this solicitation package (including Attachments). The penalty for making false statements in quotations is prescribed in 18 U.S.C. 1001.

(End of provision)