This is a Questions and Answers document for Solicitation 2026-R-024, addressing clarifications regarding the U.S. Senate Sergeant at Arms' procurement of Cohesity Backup Storage as a Service from an authorized reseller.

The document clarifies six key points regarding line item specifications and pricing requirements. For Line Items 001-004 (hardware maintenance support renewals), vendors may submit additional quotes for Hardware as a Service if the SAA does not currently own equipment. Line Items 001 and 002 may be merged as they cover the same equipment model with different maintenance support levels. For Line Items 001-003, which reach end of life in February 2027, vendors should contact Cohesity to determine appropriate replacement quotes. The quantity designation for Line Items 009, 011, and 013 has been corrected from 12 to 1 Block, aligning with Line Items 008, 010, and 012, with corresponding amendments to option year line items. Line Items 014 and 015, previously formatted as hourly services, have been amended to use "Each" as the Unit of Measure. For Line Items 016, 017, and 021, vendors should contact Cohesity for clarification on how the 12 TB quantity was determined or leave the quantity blank for SAA follow-up clarification. These amendments were provided through Amendment 002 (Unit of Measure updates) and Amendment 003 (Q&A responses), with Amendment 001 having previously extended the submission deadline to February 2, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Question and Answers 2026-R-024 Cohesity Backup Storage

Question NumberQuestionSAA Response
1For Line Items #001 - #004: these are hardware maintenance support renewals. Do you want the actual hardware aaS amount quoted as well if SAA does not currently own the equipment?Vendor can add an additonal line for Hardware aas to the Pricing worksheet, and/or provide comment(s) with your response. The SAA will consider updating those lines and may contact vendor if clarification is needed.
2Line Item #002 looks to have a different maintenance support that requires defective data storage parts returned. This is different from the other support levels including those of the same model equipment. Do you want to merge those lines #001 and #002 together, since it’s the same equipment?Vendor can merge line items 001 and 002 together, and/or provide comment(s) with your response. The SAA may contact vendor if clarification is needed.
3The Line Items in #0001 - #0003 go end of life in February 2027. How should we quote the replacements?Contact Cohesity to determine how to quote the replacements, and/or provide comment(s) with your response; the SAA may contact vendor if clarification is needed.
4For Line Items #009, #011, #013: what does the quantity of 12 represent, the lines above (#008, #010, #012) are only requesting a quantity of 1 for the hardware.Line items 9, 11, and 13 unit of measure should be 1 Block, the same as line items 8, 10, and 12; will amend the pricing table as well as option year line items to reflect this.
5For Line Items #014 & #015: this is formatted as hourly but cannot be quoted this way. These are services provided by Cohesity. Can the Unit of Measure be changed to “Each”? Attached are the data sheets.Yes.
6For Line Items #016, #017, #021: we are unsure how the quantity of 12 TB was determined, could you please explain?Contact Cohesity to get more detail on how totals are calculated or leave quantity blank; the SAA may contact vendor for clarification if needed.