2026_Pavement_Preservation_Project_Specs_Final_signed.pdf
PDF 26 MB Posted
- Attached to
- 2026 Pavement Preservation Project
- Solicitation number
- E5141
- Issued by
- San Mateo County, California
About this file
Summary of 2026 Pavement Preservation Project Specifications
This is a sealed-bid construction specification document issued by the County of San Mateo, California for the 2026 Pavement Preservation Project. The project encompasses approximately 14.6 miles of pavement preservation work in the unincorporated areas of San Mateo County, including the Montara Area and Miramar Area, with work consisting of pavement repairs, micro-surfacing, traffic striping, pavement markings, and pavement markers. Sealed bids must be received by 2:30 p.m. on Thursday, June 4, 2026, at the County Executive's Office, 500 County Center, 5th Floor, Redwood City, California 94063. The project includes estimated quantities of 190,700 square yards of micro-surfacing, 4,120 tons of asphalt concrete pavement repair, 55 channelizers, 8,000 square feet of white thermoplastic markings, 1,100 square feet of yellow thermoplastic markings, 3,800 square feet of green thermoplastic markings, 700 linear feet of white traffic striping, 5,500 linear feet of detail striping, 1,200 linear feet of additional striping, and 200 pavement markers. The Notice to Proceed is anticipated to be issued approximately four weeks after Board of Supervisors contract award by the end of July 2026. Contractors must begin work within ten calendar days of receiving the Notice to Proceed and complete the project within sixty working days. Contract awards may be extended to 60 days after bid opening if necessary.
The Engineer's estimate of project costs is $3,115,000. The County will retain five percent of progress payments and five percent of material costs as security for contract fulfillment. Liquidated damages of $4,800 per calendar day will apply for delays beyond the sixty working days, with additional task-based liquidated damages of $500 per day for specific items including payroll record submission, progress schedule compliance, micro-surfacing work, channelizer installation, thermoplastic markings, and pavement marker installation. Contractors must be registered with the California Department of Industrial Relations and possess either a Class A license or applicable combination of Class C licenses. The project is subject to prevailing wage requirements under California Labor Code, equal employment opportunity compliance, employee jury service ordinance compliance for contracts $100,000 or more, and employee benefits compliance for contracts $5,000 or more. Contractors must submit various certifications including compliance with off-road diesel vehicle fleet regulations, equal employment opportunity programs, and non-collusion declarations. The County reserves the right to reject any or all bids and may award to the lowest responsible bidder whose proposal complies with all requirements. Bidders may not withdraw bids for forty-five days after opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026_Pavement_Preservation_Project.pdf | ||
| 2026_Pavement_Preservation_Project_Plans_Final_signed.pdf | ||
| Notice_to_Contractors.pdf | ||
| Standard_Contract_Template_-_Under_$200K_DRAFT.docx | DOCX document | |
| Standard_Contract_Template_-_Over_$200K_DRAFT.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TitleSht. E5141
Last Updated: May 19, 2026 F:\Users\design\C3D\S5141000_2026 Pavement Preservation Project\12 Design\100% Draft P&S\2026 Pavement Preservation Project_Specs_Draft100%.docx
COUNTY OF SAN MATEO
STATE OF CALIFORNIA
CONTRACT DOCUMENTS
AND
SPECIFICATIONS
FOR
2026 PAVEMENT PRESERVATION PROJECT
TOTAL PROJECT APPROXIMATELY 14.6 MILES IN LENGTH
WITH APPURTENANT WORK THERETO
IN SAN MATEO COUNTY
COUNTY PROJECT NO. RW624
PROJECT FILE NO. E5141
KRZYSZTOF LISAJ
(R.C.E. No. 84003) County Engineer
Department of Public Works
San Mateo County 555 County Center, 5th Floor
Redwood City, California 94063-1665
APPROVED: May 15 , 2026 klisaj Image
TableCon. E5141 i
TABLE OF CONTENTS
NOTICE TO CONTRACTORS
Bid Opening Date Engineer's Estimate General Bidder's Information
SPECIAL PROVISIONS
Section
1. Definitions
2. Bidding 2-1. Plans and Specifications 2-2. In-Use Off-Road Diesel-Fueled Vehicle Fleet Compliance Certification
3. Contract Award and Execution
4. Description of Work
5. Control of Work 5-1. Differing Site Conditions 5-2. Repair of Equipment 5-3. Cooperation 5-4. Permits and Licenses 5-5. Project Appearance 5-6. Preservation of Property 5-7. Air Pollution Control 5-8. Obstructions 5-9. Sound Control 5-10. Public Convenience 5-11. Disposal of Material Outside the Highway Right Of Way 5-12. Sanitary Sewer Monitoring and Reporting Requirements 5-13. Subcontracting
6. Control of Materials 6-1. Certificates of Compliance 6-2. Materials Testing
7. Legal Relations and Responsibility 7-1. Equal Employment Opportunity Program for Minority Employment 7-2. Prevailing Wages 7-2.1. Payroll Records 7-2.2. Contractor Employee Jury Service 7-3. Highway Construction Equipment 7-4. Public Safety
8. Progress of Work and Time of Completion 8-1. Time of Completion 8-2. Liquidated Damages 8-3. Progress Schedule
9. Measurement and Payment 9-1. Force Account Work 9-2. Payments to Contractor ii
TABLE OF CONTENTS (Continued)
SPECIAL PROVISIONS (Continued)
Section 9-3. Payments Withheld from Contractor 9-4. Stop Notices 9-5. Construction Claims
11. Mobilization
12. Maintaining Traffic 12-1. Property Owner Secondary Notification 12-2. Traffic Control Plan 12-3. Temporary Pavement Delineation
13. Water Pollution Control
14. Construction Waste Management 14-1. Diversion Goals 14-2. References and Resources 14-3. Waste Management Plan and Daily Transport Report 14-4. Waste Management Plan Implementation
15. Existing Facilities
37. Bituminous Seals 37-1. Micro-surfacing
39. Asphalt Concrete (Type A) 39-1. Compaction Testing 39-2. Asphalt Emulsion (Tack Coat) 39-3. Pavement Repair (HMA Type A, 3/4” Maximum, Medium Grading)
81. Miscellaneous Traffic Control Devices 81-1. Channelizers
84. Markings 84-1. Thermoplastic Pavement Markings, Legends, and Striping
85. Pavement Markers
100. Construction Staking
Note: Gaps in Section numbering, above, indicate that the Section is either blank or does not apply.
APPENDIX A
County of San Mateo Waste Management Plan Form Waste Management Daily Transport Report
APPENDIX B
Sanitary Sewer Monitoring and Reporting Requirements:
State Water Resources Control Board Order No. WQ 2013-0058-EXEC iii
TABLE OF CONTENTS (Continued)
APPENDIX C
Sample “Payment Bond” Form Sample “Performance Bond” Form
APPENDIX D
Daily Personnel and Equipment Log
APPENDIX E
Construction Claims:
Public Contract Code Sections 9204 and 20104 et seq.
APPENDIX F
Encroachment Permits
APPENDIX G
Prompt Payment Certification
APPENDIX H
County of San Mateo B-33 for Senate Bill 1383 Compost, Mulch, and Renewable Natural Gas Procurement Reporting Form
PROPOSAL
Contractor’s Check-Off List Name and Address of Bidder Contractor Declaration Statement Bid Schedules Bidder's Bond Signature of Bidder Subcontractors San Mateo County Equal Employment Opportunity Program Equal Benefits Compliance Ordinance No. 04026 (Title 2, Chapter 2.84, San Mateo County Ordinance Code) Equal Benefits Compliance Declaration Form Contractor Employee Jury Service Ordinance No. 04269 (Title 2, Chapter 2.85, San Mateo County Ordinance Code) Contractor Employee Jury Service Compliance Declaration Form Non-Collusion Declaration Form In-Use Off-Road Diesel-Fueled Vehicle Fleet Acknowledgement Form
AGREEMENT
Signature Sheet
NC.E5141
NOTICE TO CONTRACTORS
NOTICE IS HEREBY GIVEN, that
Sealed bids will be received either by mail to the office of the County Executive’s Office, or hand-delivered prior to the bid opening to the County of San Mateo at 500 County Center, 5th Floor, Redwood City, California, 94063 until the hour of
2:30 p.m., Thursday, June 4, 2026 where the bids will be publicly opened and read aloud for the following project in accordance with the specifications therefore and to which special reference is made as follows:
Bids are required for the entire work described herein. The Contractor’s attention is directed to the forms included in, and required to be completed and submitted with, the Proposal.
Bidders are further advised of the following:
1. Contractor should be placed on a Plan Holders List for bidding. To be placed on the Plan Holders List, the Contractor shall either:
a. Bidder shall register and create an account on the OpenGov website to download all bidding documents, including forms of proposal and contract, directly from https://procurement.opengov.com/portal/smcgov/projects/265791
Project’s OpenGov Reference:
RFP – RW624 - 2026 PAVEMENT PRESERVATION PROJECT -
Project ID: E5141
b. If bidding documents are obtained through a source other than those outlined in 1a above, complete and sign the following Plan Holder’s Affidavit and return to the County by PDF via email to alai@smcgov.org and enacpil@smcgov.org
Plan Holder’s Affidavit
Project Title 2026 PAVEMENT PRESERVATION PROJECT
Project No. RW624 Project Engineer Avery Lai
Project Manager: Alex Zhang
Bid Open Date and Time: 2:30 p.m., Thursday, June 4, 2026
Company Name:
Mailing Address:
Phone Number: Fax Number:
E-mail Address:
(Name and Title of Authorized Representative of Bidder)
(Signature of Authorized Representative of Bidder)
2. The Plan Holders List will be posted to the County of San Mateo’s Public
Works website two (2) working days prior to the bid open date.
3. Questions regarding the Contract Documents concerning items such as discrepancies, conflicts, omissions, doubts as to meanings, or regarding scope of bid items shall be referred to the Engineer. Inquiries must be received in writing via email, to alai@smcgov.org and enacpil@smcgov.org not less than five (5) working days prior to bid opening. Inquiries will be answered in writing via email response if written clarification is warranted, in the opinion of the Engineer, then inquiries and responses will be posted to the Project’s page on the County of San Mateo’s Public Works website. It will be the Contractor’s sole responsibility to ensure that they receive responses, if any. The County will not be responsible for oral clarifications.
4. It will be the Contractor’s sole responsibility to ensure that they have received addendums, if any, which will be posted to the County of San Mateo’s Public Works website on the same day issued. Said addendums will also be sent to all current plan holders and made available during purchase of Plans and Specifications.
5. Proposals in which the prices obviously are unbalanced may be rejected.
6. No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
For bids and contract updates, the Department of Public Works website will be updated as needed and can be accessed under the Department’s tab found on the
County of San Mateo website https://www.smcgov.org/publicworks/2026-pavement-preservation-project-0.
ENGINEER’S ESTIMATE
Item No.
Section No.
Estimated Quantity
Unit of Measure
Item Description
1 11 1 LS Mobilization
2 12 1 LS Maintaining Traffic
3 13 1 LS Water Pollution Control
4 14 1 LS Construction Waste Management
5 37-1 190,700 SY Micro-surfacing
6 39-3 4,120 TON
Pavement Repair (HMA Type A, 3/4” Maximum, Medium Grading)
7 81-1 55 EA
Channelizers (White, Bolted with Flexible Base)
8 84-1(F) 8,000 SF
Thermoplastic Pavement Markings and Legends (White)
9 84-1(F) 1,100 SF
Thermoplastic Pavement Markings and Legends (Yellow)
10 84-1(F) 3,800 SF
Thermoplastic Pavement Markings and Legends (Green)
11 84-1(F) 700 LF Thermoplastic Traffic Striping, 4” White
12 84-1(F) 5,500 LF Thermoplastic Traffic Striping, Detail 22
13 84-1(F) 1,200 LF Thermoplastic Traffic Striping, Detail 27B
14 85-1(F) 200 EA
Pavement Markers, Blue, Reflective, Fire Hydrant Markers
Engineer's Estimate of Costs: $ 3,115,000
(F) Final Pay Quantities - See Section 9-1.02C, “Final Pay Item Quantities,” of the Standard Specifications.
(Note: Gaps in section numbering, above, indicate the Section is blank or does not apply.)
The foregoing quantities are approximate only, being given as a basis for the comparison of bids, and the County of San Mateo does not, expressly or by implication, agree that the actual amount of work will correspond herewith, but reserves the right to increase or decrease the amount of any class or portion of the work, or to omit any portion of the work, as may be deemed necessary or expedient by the Engineer.
Payment to the Contractor for materials furnished and work completed shall be made by the County in accordance with Section 9 of the “Special Provisions” portion of these Contract Documents. Pursuant to Section 22300 of the Public Contract Code, Contractor may, upon his request and at Contractor's expense, substitute equivalent securities for any moneys retained from such payment for the fulfillment of the Contract.
When applicable, both Contractor and Subcontractor hereby agrees to pay not less than prevailing rates of wages and be responsible for compliance with all the provisions of the California Labor Code, Article 2-Wages, Chapter 1, Part 7, Division 2, Section 1770 et seq and Section 1810 et seq. A copy of the prevailing wage scale established by the Department of Industrial Relations is on file in the office of the Director of Public Works, and available at www.dir.ca.gov/DLSR or by phone at 415-703-4774. California Labor Code Section 1776(a) requires each contractor and subcontractor keep accurate payroll records of trades workers on all public works projects and to submit copies of certified payroll records upon request.
Additionally, pursuant to State Senate Bill SB 854 (Stat. 2014, chapter 28), effective January 1, 2015:
(1) No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
(2) No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
(3) This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
Wage rates for overtime shall be paid at not less than one and one-half (1-1/2) times the above rates. Wage rates for Sundays and holidays shall be paid at not less than two (2) times the above rates.
The holidays upon which such rates shall be paid shall be all holidays recognized in the collective bargaining agreement applicable to the particular craft, classification, or type of worker employed on the Project.
It is the policy of the County that Contractors on public projects employ their workers and craftsmen from the local labor market whenever possible. “Local Labor Market” is defined as the labor market within the geographical confines of the County of San Mateo, State of California. Consistent with this policy, the Contractor is requested to employ craftsmen and other workers from the local labor market whenever possible to do so.
Each bidder shall submit with the bid, Certificates of Compliance and Intent on a form provided in the “Proposal” section of these Contract Documents, a certificate that bidder is in compliance with the provisions of the Title VII of the Civil Rights Act of 1964, the California Fair Employment and Housing Act and any other federal, State and local laws and regulations relating to equal employment opportunity. With the execution of said certificates, bidder also agrees that bidder will maintain or develop and implement, during the course of the work concerned, a program of hiring and employment, conducted without regard to race, religion, color, national origin, ancestry, sexual orientation, or sex of the applicants. With this certification, bidder shall submit any and all information that may be required by the County in connection with the particular project.
Each bidder is hereby notified of Section 9204 and Section 20104 et seq. of the Public Contract Code as those Sections (attached hereto as Appendix E) relate to resolution of construction claims, and to Section 3186 of the Civil Code, as amended January 1, 1999 with regard to stop notices and public entity’s rights to retain monies in order to provide for that entity’s reasonable cost of litigation. The bidder is further notified that all provisions of Section 9204 and Section 20104 et seq. of the Public Contract Code and Section 3186 of the Civil Code, as outlined above shall be considered as incorporated into and become an integral part of these specifications.
Questions relating to equal employment should be directed to the San Mateo County Department of Public Works, Equal Employment Opportunity Program, 555 County Center, 5th Floor, Redwood City, CA 94063-1665, telephone (650) 363-4100.
Additional technical questions should be directed to the Department of Public Works, 555 County Center, Redwood City, California, 94063-1665, telephone
(650) 363-4100.
The Contractor shall possess either a Class A License or a combination of Class C licenses that are applicable for the majority of the work at the time this contract is awarded. No Contract will be awarded to a Bidder who is not licensed as required by laws of the State of California.
The County of San Mateo reserves the right to reject any or all bids and/or waive any informalities or irregularities in any bid received.
Bidders may not withdraw their bid for a period of FORTY-FIVE (45) DAYS after the date set from the opening thereof.
BY ORDER OF THE
BOARD OF SUPERVISORS
DATE: May 15 , 2026
Michael Callagy, County Executive/ Clerk of the Board of Supervisors
SP.E5141
SPECIAL PROVISIONS
FOR
DATE: May 15, 2026
SECTION 1.
DEFINITIONS OF TERMS TO BE USED IN THE SPECIAL PROVISIONS,
NOTICE TO CONTRACTORS, PROPOSAL, AGREEMENT OR
OTHER CONTRACT DOCUMENTS
Except as specifically stated herein, the definitions contained in the Standard
Specifications of the State of California, Department of Transportation, as set forth per Section 2-1, “Plans and Specifications,” of these Special Provisions and hereafter referred to as “Standard Specifications,” shall be applicable with the understanding that where said definitions specifically refer to the State of California, a department or division of the State or an official, officer or employee of the State, said definition shall be interpreted to refer to the County of San Mateo, the Department of Public Works, or other appropriate department, division, official, officer or employee of the County of San Mateo.
Definition 7-1.02L, “Public Contract Code,” of the Standard Specifications shall not be interpreted to include the provisions of Article 7.1 of Division 2, Part 2, Chapter 1 of the Public Contract Code.
END OF SECTION
SECTION 2.
BIDDING
The Bidder’s attention is directed to all the provisions of Section 2, “Bidding,” of the Standard Specifications and these Special Provisions. The County will accept a Bidder’s Bond in the form issued by an admitted surety insurer in lieu of the sample forms provided herein in Appendix C of these Special Provisions. The County will not be responsible for any oral interpretations to Bidders with respect to any of the work embraced herein.
Failure of the bidder to fulfill the requirements of the Special Provisions for submittals required to be furnished after bid opening, including but not limited to escrowed bid documents, where applicable, may subject the bidder to a determination of the bidder's responsibility in the event it is the apparent low bidder on a future public works contract.
All proposals must be made upon the blank form contained herein.
2-1. Plans and Specifications Subject to the exceptions stated herein, the work embraced herein shall be done in accordance with the Standard Plans and Specifications as adopted by the County of San Mateo insofar as the same may apply, and in accordance with the following Special Provisions.
As set forth in Resolution No. 077227 of the Board of Supervisors of the
County of San Mateo, adopted February 11, 2020, which approved and adopted the 2018 Standard Plans and Standard Specifications of the State of California, Department of Transportation as the Standard Plans and Standard Specifications of the County of San Mateo, State of California.
In the event that a discrepancy arises between the project Plans, these
Special Provisions, the Standard Plans and the Standard Specifications, the provisions of Section 5-1.02, “Contract Components,” of the Standard Specifications shall apply.
2-2. In-Use Off-Road Diesel-Fueled Vehicle Fleet Compliance Certification
In conformance with Title 13 CCR § 2449 et seq., bidders must submit the In-Use Off-Road Diesel-Fueled Vehicle Fleet Acknowledgement Form. A copy of a valid and unexpired Certificate of Reported Compliance Off-Road Diesel Vehicle Regulation for all fleets meeting this criteria must be submitted with the bid or within three (3) business days from bid opening. Failure to submit the valid and unexpired Certificate of Reported Compliance Off-Road Diesel Vehicle Regulation may result in a non-responsive bid.
SECTION 3.
CONTRACT AWARD AND EXECUTION
The bidder's attention is directed to the provisions in Section 3, “Contract Award and Execution,” of the Standard Specifications and these Special Provisions for the requirements and conditions concerning award and execution of contracts.
However, the following supersedes the second paragraph in Section 3-1.04, “Contract Award,” of the Standard Specifications:
“The award of contract, if awarded, will be made to the lowest responsible bidder within SIXTY (60) DAYS after the opening of the proposals. If the lowest responsible bidder refuses or fails to execute the contract, the County may award the contract to the second lowest responsible bidder. If the second lowest responsible bidder refuses or fails to execute the contract, the County may award the contract to the third responsible bidder. The period of time after that specified above within which the award of the contract may be made shall be subject to extension for such further period as may be agreed upon, in writing, between the County and the bidder concerned.”
Bidders who wish to lodge a protest for consideration as to the bidding process or the award of a contract to the lowest responsible bidder must do so as follows:
(1) Protests based upon alleged improprieties in a solicitation, which are apparent prior to bid opening, shall be filed two (2) business days prior to bid opening.
(2) Protests other than those covered by paragraph 1, above, shall be filed no later than ten (10) calendar days after the bid opening.
(3) All protests shall be delivered to:
Director of Public Works County of San Mateo 555 County Center, 5th Floor Redwood City, CA 94063
Untimely protests, which do not meet the deadline requirements specified above, will not be accepted or considered.
Bid protests must be submitted in writing to the addressee and address listed above. Bid protests must at a minimum include the following:
• Project Name
• Project File Number
• A complete statement describing the basis for the bid protest, which includes a detailed statement of all legal and factual grounds for the protest
• Documentation supporting the protestor's grounds for the protest
• The type of relief requested and the legal basis for such relief
If a valid protest is filed timely, the Department will investigate the bid protest.
The protested bidder shall have three (3) business days to respond to the Department and to provide any information requested by the Department. The Department shall respond to the protesting party, stating its findings. The Department Director shall make a recommendation to the San Mateo County Board of Supervisors regarding the bid protest.
Bid protests are to be delivered to the following address: 555 County
Center, 5th Floor Redwood City, CA 94063.
The award of the contract, if it is awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed.
The contract shall be executed by the successful bidder and shall be returned, together with the contract bonds, to the County so that it is received within ten (10) days, not including Saturdays, Sundays and legal holidays, after the bidder has received the contract for execution. Failure to do so shall be just cause for forfeiture of the proposal guaranty. The executed contract documents shall be delivered to the following address:
555 County Center, 5th Floor Redwood City, CA 94063.
SECTION 4.
DESCRIPTION OF WORK
The work to be done consists, in general, of performing pavement repairs, placing micro-surfacing on various roads in the Montara Area and Miramar Area in the unincorporated areas of San Mateo County, including but not limited to replacement of traffic striping, pavement markings, pavement markers, channelizers, as well as any other items and details not mentioned above, but required by the Project Plans, Standard Specifications and these Special Provisions, and the directions of the Engineer.
SECTION 5.
CONTROL OF WORK
Attention is directed to the provisions of Section 5, “Control of Work,” of the Standard Specifications, except as herein provided, and to Section 2-1, “Plans and Specifications,” of these Special Provisions.
5-1. Differing Site Conditions
This section shall be used in lieu of Section 4-1.06, “Differing Site Conditions (23 CFR 635.109),” of the Standard Specifications. Section 4-1.06 of the Standard Specifications shall not apply.
The following shall apply to digging trenches or other excavations that extend deeper than four feet (4') below the surface:
A. The Contractor shall promptly, and before the following conditions are disturbed, notify the Engineer, in writing, of any:
(1) Material that the Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, II, or III disposal site in accordance with provisions of existing law.
(2) Subsurface or latent physical conditions at the site differing from those indicated.
(3) Unknown physical conditions at the site of any unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.
B. The Engineer shall promptly investigate the conditions, and if he finds that the conditions do materially differ, or do involve hazardous waste, and cause a decrease or increase in the Contractor's cost of, or the time required for, performance of any part of the work, shall issue a change order, excluding loss of anticipated profits, under the procedures described in the contract. No contract adjustment that results in a benefit to the Contractor will be allowed unless the Contractor has provided the required written notice.
C. In the event that a dispute arises between the Engineer and the Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor's cost of, or time required for, performance of any part of the work, the Contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. The Contractor shall retain any and all rights provided either by contract or by law that pertain to the resolution of disputes and protests between the contracting parties.
D. In the event conditions materially differ from those indicated, the
Contractor shall have no claim for construction delays, unless said conditions are determined by the Engineer to impact the controlling item of work.
5-2. Repair of Equipment The work of installing, assembling, repairing or reconditioning, or other work of any nature on machinery, equipment or tools used in or upon the work shall be considered a part of the work to be performed under the contract and any laborers, workers or mechanics working on the machinery, equipment or tools, unless employed by bona fide commercial repair shops, garages, blacksmith shops or machine shops, which have been established and operating on a commercial basis for a period of at least 2 months prior to the award of the contract, shall be subject to all the requirements relating to labor set forth in these specifications and in the special provisions.
5-3. Cooperation
Attention is directed to Sections 5-1.20, “Coordination with Other Entities,” and 5-1.36, “Property and Facility Preservation,” of the Standard Specifications, and to these Special Provisions. The utility companies may be rearranging their facilities within the project area and it is expected that they will cooperate with the Contractor to the end that the work may be handled in an efficient manner.
The Contractor shall contact USA North811 (USA) service alert a minimum of forty-eight (48) hours in advance of any excavation or trenching work. USA may be contacted either on-line at usanorth811.org or by phone by dialing (800) 642-2444 or 811.
5-4. Permits and Licenses
Attention is directed to Section 5-1.20B, “Permits, Licenses, Agreements, and Certifications,” of the Standard Specifications and these Special Provisions.
The Contractor shall have at least two employees trained in confined space entry regulations CAL/OSHA Confined Space Regulations, Title 8 CCR GISO 5156, 5157, and 5158 at the site whenever there are open trenches or underground work going on. It is understood that all fall protection, retrieval and atmospheric monitoring equipment shall be furnished and maintained by the Contractor at the Contractor’s expense. This shall include but not be limited to cost associated with compliance with Confined Space Entry Regulations shall be at the expense of the Contractor.
The Contractor’s attention is directed to the fact that, prior to start of work either within the State of California right-of-way or affecting State of California facilities, the Contractor will be required to obtain an Encroachment Permit Authorization Form (TR-0429) in accordance with the conditions stated in the Encroachment Permit obtained by the County.
The Contractor’s attention is directed to the fact that, prior to start of work either within the City right-of-way or affecting City facilities, the Contractor will be required to obtain an Encroachment Permit in accordance with the conditions stated in the Encroachment Permit (See Appendix F) at the following City office:
CITY OF HALF MOON BAY
PUBLIC WORKS
501 Main Street Half Moon Bay, CA 94019
County shall deduct $5,000 from Contractor’s Progress Payment until Contractor has provided proof of obtaining encroachment permit.
Full compensation for conforming to the requirements of this permit, including the cost of the permit, if any, shall be considered as included in the unit prices paid for the various Contract items of work, and no additional compensation will be allowed therefore.
5-5. Project Appearance
The Contractor shall maintain a neat appearance to the work. Full compensation for conforming to the provisions in this section, not otherwise provided for, shall be considered as included in the unit prices paid for the various Contract items of work involved, and no additional compensation will be allowed therefore.
5-6. Preservation of Property
The Contractor's attention is directed to Section 5-1.36, “Property and Facility Preservation,” of the Standard Specifications.
5-7. Air Pollution Control
Air pollution control shall conform to the provisions of Section 14-9.02, “Air Pollution Control,” of the Standard Specifications.
5-8 Obstructions
Attention is directed to the provisions in Sections 5-1.36C, “ Nonhighway Facilities,” 15, “Existing Facilities,” and 51-1.03E(9), “Utility Facilities,” of the Standard Specifications.
5-9. Sound Control
Sound control shall conform to the provisions in Section 14-8.02, “Noise Control,” of the Standard Specifications.
5-10. Public Convenience
Public Convenience shall conform to the provisions in Section 7-1.03, “Public Convenience,” of the Standard Specifications and to these Special Provisions.
5-11. Disposal of Material Outside the Highway Right of Way
Disposal of Material Outside the Highway Right Of Way shall conform to the provisions of Sections 5-1.20B(4), “Contractor-Property Owner Agreement,” and 14-10, “Solid Waste Disposal and Recycling,” of the Standard Specifications, and Section 14, “Construction Waste Management,” of these Special Provisions.
The Contractor’s attention is further directed to Appendix “A”, “Construction Waste Management Plan,” of these Special Provisions.
5-12. Sanitary Sewer Monitoring and Reporting Requirements
The Contractor’s attention is directed to Appendix B for sanitary sewer monitoring and reporting requirements.
5-13. Subcontracting Attention is directed to the provisions in Section 5-1.13, “Subcontracting,” of the Standard Specifications.
SECTION 6.
CONTROL OF MATERIALS
Attention is directed to Section 6, “Control of Materials,” of the Standard
Specifications and these Special Provisions.
The Contractor shall furnish all materials required to complete the work under this Contract.
6-1. Certificates of Compliance Certificates of Compliance, conforming to the provisions in Section 6-
2.03C, “Certificates of Compliance,” of the Standard Specifications shall be furnished for all manufactured products, unless otherwise waived by the Engineer.
6-2. Materials Testing
Whenever the specifications require compliance with specified values for the following applicable properties, tests will be made as indicated:
Material To Be Tested
Property Being Tested
Acceptable Test Method(s)
Description
Asphalt Concrete Relative Compaction
CT 375 or
ASTM D2950
Determines field densities using a nuclear gage.
Any costs to the County for testing layers which fail the compaction requirements may be deducted from any progress payment due to the Contractor when, in the opinion of the Engineer, such failure results from the Contractor's lack of diligence in pursuing compaction effort. In the event that a test fails, any testing after the first shall be at the Contractor’s expense.
SECTION 7.
LEGAL RELATIONS AND RESPONSIBILITY
Attention is directed to the provisions of Section 7, “Legal Relations and
Responsibility to the Public,” of the Standard Specifications, these Special Provisions, and to the provisions of paragraph VIII, “Insurance,” of the Agreement (AG) portion of the Contract Documents for insurance requirements
7-1. Equal Employment Opportunity Program for Minority Employment
It is the intent of the Board of Supervisors of the County of San Mateo to prohibit and eliminate employment discrimination and to further the opportunities for minority persons to be gainfully employed in the performance of County construction contracts. Award of a contract to a low bidder will not be made until such bidder has complied with the provisions of Section 2.50.040 of Title 2, Chapter 2.50, as amended, of the San Mateo County Ordinance Code and with these guidelines.
7-1.1. Definitions
EQUAL EMPLOYMENT OPPORTUNITY PROGRAM: An Equal Employment Opportunity Program (EEOP) is a set of specific and result oriented procedures to which a Contractor commits himself in order to achieve equal employment opportunity.
COMPLIANCE OFFICER: The Compliance Officer (CO) means the
County official designated by the County Executive to represent him in the administration of these guidelines and in the enforcement of the provisions of Sections 2.50.040 and 2.50.050 of Title 2, Chapter 2.50.
7-1.2. Certifications of Compliance and Intent
Every bidder will submit with his bid, as required by Section 2.50.050 of Title 2, Chapter 2.50, a Certification of Compliance with the laws prohibiting discrimination and a Certification of Intent to implement an equal employment opportunity program on the form furnished in the Proposal section of these
7-1.3. Equal Employment Opportunity Program
In addition to furnishing the Certifications of Compliance and Intent, each bidder will submit his equal employment opportunity program with his bid proposal. The EEOP shall contain the following information:
A. Analysis of current work force
(1) Total number of employees;
(2) Numerical racial breakdown of employees by job classification;
(3) Information on apprentices.
These figures will provide the base by which the low bidder's EEOP will be evaluated. Factors to be considered both in the original statistics and in any plans for future employment will include the percentage of minority population in San Mateo County, the availability of minority construction workers and the present minority representation in the various construction trades.
B. The affirmative actions the bidder has taken and will take to ensure equal employment opportunity. These shall include:
(1) Recruiting and hiring minority persons. If non-union personnel are employed, this would involve employment advertising through sources serving the minority population. These include local minority newspapers, referral agencies, high schools, vocational schools and community groups. Specific information on these sources may be obtained from the Compliance Officer. Union employees will be recruited in accordance with applicable labor agreements. The bidder will seek to have included or will reaffirm clauses in all labor agreements prohibiting discrimination based on race, religion, color, national origin, age, disability, ancestry, sexual orientation, or sex. It is also suggested that bidders assist in admitting minority workers who are over the traditional apprenticeship entry age to the various craft training programs.
(2) Providing adequate opportunity for the upgrading or further training of all employees to insure equal opportunity in advancement and promotion. This might include a counseling service, information and assistance with night classes, or special career-directed program information.
(3) Appointing an Equal Employment Opportunity Coordinator, full time or as an additional duty. This person will have the responsibility of administering an active program, informing company personnel and union representatives of company policy, and advising all subcontractors of their obligation to this program.
(4) Establishing or maintaining an apprenticeship/training program designed to ensure hiring of additional minority employees in the journeyman and skilled classes. Each bidder is urged to support or develop and implement an Apprenticeship Program for his trade.
(5) Selecting minority subcontractors or subcontractors who are known for their ongoing programs of apprenticeship for minorities. This includes advising minority Contractor associations of opportunities for subcontracts. Joint ventures with minority sub-contractors are encouraged.
C. The EEOP should state any previous experience the bidder has had with similar plans and the results of that effort. Current affirmative action plans should be described in detail.
7-1.4. Equal Employment Opportunity Program Evaluation
A. The Compliance Officer (CO) will review the EEOP submitted by the low bidder in order to determine whether the program submitted complies with the provisions of Section 2.50.040 of Title 2, Chapter 2.50, as amended, of the San Mateo County Ordinance Code, and these guidelines. If deficiencies are indicated, CO may request additional information from the bidder or suggest appropriate remedies. The CO will be available to answer questions relative to the guidelines and to advise those seeking assistance of other sources. CO will not be responsible for the service or lack of service rendered by the consultant recommended, nor will the CO develop an EEOP or serve as a recruiter for any bidder.
The low bidder may withdraw his EEOP for revision after consultation with the CO; however, the revised program must be resubmitted by a date not later than fifteen (15) calendar days after the opening of bids.
B. All subcontractors listed in the low bidder's proposal shall be required to file completed Certificates of Compliance and Intent and their EEOP with the Bidder for submission to the County. The EEOP of each subcontractor will be evaluated by criteria established for the low bidder's
EEOP.
C. The CO, upon conclusion of the EEOP review, will report his findings and recommendation to the Director of Public Works. The CO will keep acceptable EEOP’s on file for six (6) months. During this time period, if the bidder or subcontractors bid for other County contracts, they may refer to the EEOP on file and state any changes, but will not be required, unless specifically requested, to re-file their program.
7-1.5. Inclusion of EEOP and Certificates
Upon award of the Contract by the Board of Supervisors, the EEOP and certifications for the bidder and all subcontractors, which have been approved and accepted by the County, will become an integral part of the Contract and subject to the provisions thereof.
7-1.6. Compliance of Contractor
A. The Contractor will post, in conspicuous places available to employees and applicants for employment, notices, provided by the County, stating that the Contractor is obliged to comply with the provisions of these guidelines and the provisions of Section 2.050.040 of Title 2, Chapter 2.50, as amended, of the San Mateo County Ordinance Code.
These notices will also be sent to all unions, employee organizations and other recruiting sources providing employees to the Contractor.
B. All announcements of job openings will include the statement, “An Equal Opportunity Employer.”
C. The Contractor will make written progress reports on a form provided by the County to illustrate the effectiveness of his EEOP at intervals established by the County.
D. The CO will monitor the Contractor's EEOP until completion of the Contract and will report non-compliance of the Contractor in adhering to his EEOP to the Director of Public Works.
E. The Contractor will permit, during Contractor's normal business hours and at Contractor's place of business, access by the County to his records of employment, employment advertisements, application forms and other data and records pertaining to Contractor's employment practices, for the purpose of determining whether Contractor is complying with the non-discrimination and equal employment opportunity rules of the County.
7-1.7. Compliance of Subcontractor
All subcontractors listed by the bidder are subject to all the provisions of these guidelines and the provisions of Section 2.050.040 of Title 2, Chapter 2.50, as amended, of the San Mateo County Ordinance Code.
7-1.8. Penalties for Non-Compliance
The penalties for non-compliance are listed in Title 2, Chapter 2.50, Section 2.50.050, which states:
a. “Every public works contract shall provide that a contractor who, within the time specified in the contract, does not submit an equal employment plan and make the certifications required in this chapter shall be in breach of the contract.”
“If, after an award is made, the contractor is found by the County or by a Federal or State agency empowered to make such findings to be in substantial or material violation of the Fair Employment Practices Act of the State of California Title VII of the Civil Rights Act of 1964, or of the provisions of this chapter or of the Board-established guidelines implementing them, he may be found to be in material breach of contract, and the County shall have the power to cancel the contract in whole or in part, or alternatively, to deduct for each working day during which the contractor is found to have been in such non-compliance, two percent (2%) of the total amount payable to the contractor.”
7-1.9. Waiver of Compliance
In the event that any of the requirements of Sections 2.050.040 and
2.050.050 of Title 2, Chapter 2.50, as amended, of the San Mateo County Ordinance Code, are found to result in an undue hardship upon a low bidder, bidder may submit evidence of hardship and a petition for waiver of such requirements to the Director of Public Works for recommendation to the Board of Supervisors. Such a waiver may only be granted by the Board and, if approved, shall become an integral part of the contract.
7-1.10 Employee Benefits
All Contractors with contracts with the County of $5,000 or more shall comply with the provisions of Title 2, Chapter 2.84, as amended, of the San Mateo County Ordinance Code with respect to the provisions on employee benefits. As set forth in the ordinance, such contractors are prohibited from discriminating in the provisions of employee benefits between an employee with a domestic partner and an employee with a spouse. A copy of the Ordinance and Compliance form is attached to the Proposal Section of these Specifications.
In the event it is determined, by the County, that any portion of the County Ordinance Code regarding employee benefits conflict with Federal or State regulations, the Federal or State regulations shall take precedence over the County Ordinance Code.
7-1.11 Non-Discrimination
No person shall be excluded from participation in, denied benefits of, or be subject to discrimination under this Agreement on the basis of their race, color, religion, national origin, age, sex, sexual orientation, pregnancy, childbirth or related conditions, medical condition, mental or physical disability or veteran’s status. Contractor shall ensure full compliance with Federal, State and local laws, directives and executive orders regarding non-discrimination for all employees and Subcontractors under this Agreement.
Violation of the non-discrimination provisions of this Agreement shall be considered a breach of this Agreement and subject the Contractor to penalties, to be determined by the County Executive, including but not limited to:
(1) termination of this Agreement;
(2) disqualification of the Contractor from bidding on or being awarded a County contract for a period of up to 3 years;
(3) liquidated damages of $2,500 per violation;
(4) imposition of other appropriate contractual and civil remedies and sanctions, as determined by the County Executive.
To effectuate the provisions of this paragraph, the County Executive shall have the authority to:
(1) examine Contractor’s employment records with respect to compliance with this paragraph;
(2) set off all or any portion of the amount described in this paragraph against amounts due to Contractor under the Contract or any other Contract between Contractor and County.
Contractor shall report to the County Executive the filing by any person in any court of any complaint of discrimination or the filing by any person of any and all charges with the Equal Employment Opportunity Commission, the Fair Employment and Housing Commission or any other entity charged with the investigation of allegations within thirty (30) days of such filing, provided that within such thirty (30) days such entity has not notified Contractor that such charges are dismissed or otherwise unfounded. Such notification shall include the name of the complainant, a copy of such complaint and a description of the circumstance. Contractor shall provide County with a copy of its response to the Complaint when filed.
In the event it is determined, by the County, that any portion of these requirements regarding non-discrimination conflict with Federal or State regulations, the Federal or State regulations shall take precedence over County requirements.
7-2. Prevailing Wages
Attention is directed to Section 7-1.02K(2), “Wages,” of the Standard
In accordance with the provisions of Section 1770 of the California Labor
Code, the Board of Supervisors of the County of San Mateo has ascertained the prevailing rate of wages applicable to the work to be done, which prevailing wage rates have been established as indicated in the Notice to Bidders and are incorporated herein by reference.
The Contractor’s attention is further directed to the following requirements of State Senate Bill SB 854 (Stat. 2014, chapter 28), effective January 1, 2015:
(1) No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
(2) No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
(3) This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
7-2.1 Payroll Records Reference is made to Section 7-1.02K(3), “Certified Payroll Records
(Labor Code § 1776),” of the Standard Specifications. In particular, the Contractor’s attention is directed ‘to the last paragraph, which is amended to read:
“The Department withholds from progress payments for delinquent or inadequate records (Labor Code § 1771.5). If you have not submitted an adequate record by the month's 7th day for the period ending on or before the 1st of that month, the Department withholds up to ten percent (10%) of the monthly progress estimate, exclusive of mobilization. The Department does not withhold more than $10,000 or less than $1,000.”
The Contractor is advised that Contractor shall submit either
Contractor’s Daily Dispatch Report at the start of each working day OR a Daily Personnel and Equipment Log (included as Appendix D of these Special Provisions) to the Engineer by the start of the first working day subsequent to the performance of the work, or Contractor may incur task-specific liquidated damages in the amount of $500 per calendar day for every day hence until submittal is made.
The Contractor is further advised that, pursuant to State Senate Bill SB 854 (Stat. 2014, chapter 28), effective January 1, 2015, all contractors and subcontractors working on a contract for public work on a public works project must furnish electronic certified payroll records to the Labor Commissioner.
7-2.2. Contractor Employee Jury Service All Contractors with contracts with the County of $100,000 or more shall comply with the provisions of Title 2, Chapter 2.85, as amended, of the San Mateo County Ordinance Code, with respect to provision of jury duty pay to employees and have and adhere to a written policy that provides that its employees shall receive from the Contractor, on an annual basis, no less than five (5) days of regular pay for actual jury service in San Mateo County. The policy may provide that employees deposit any fees received for such jury service with the Contractor or that the Contractor deduct from the employees’ regular pay the fees received for jury service. A copy of the Ordinance and a Compliance Form is attached to the Proposal Section of these Specifications.
Award of a Contract to a low bidder will not be made until such bidder has certified compliance with the provisions of Title 2, Chapter 2.85, as amended, of the San Mateo County Ordinance Code.
7-3. Highway Construction Equipment
Attention is directed to Section 7-1.02O, “Vehicle Code,” of the Standard Specifications and these Special Provisions.
Pursuant to the authority contained in Section 591 of the Vehicle Code, the County has determined that, within such areas as are within the limits of the project and are open to public traffic, the Contractor shall comply with all the requirements set forth in Divisions 11, 12, 13, 14 and 15 of the Vehicle Code.
Attention is directed to the statement in Section 591 that this section shall not relieve him or any person from the duty of exercising due care. The Contractor shall take all necessary precautions for safe operation of his equipment and the protection of the public from injury and damage from such equipment.
7-4. Public Safety Public Safety shall conform to the provisions in Section 7-1.04, “Public
Safety,” of the Standard Specifications and to these Special Provisions.
Full compensation for conforming to the requirements of this section shall be considered as included in the unit prices paid for the various Contract items of work, and no additional compensation will be allowed therefore.
SECTION 8.
PROGRESS OF WORK AND TIME OF COMPLETION
Attention is directed to the provisions of Section 8, “Prosecution and Progress,” of the Standard Specifications, except as herein provided.
8-1. Time of Completion The Contractor shall begin work within TEN (10) CALENDAR DAYS after receiving the Notice to Proceed from the Department of Public Works, and shall diligently prosecute the same to completion before the expiration of
SIXTY (60) WORKING DAYS
from the date of said beginning, as described above.
The Notice to Proceed (NTP) is anticipated to be issued approximately four weeks after the Board of Supervisors awards…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .