2026-06-05 PLANS_MTV TAXIWAY EDGE LIGHTS_FOR BID.pdf
PDF 9 MB Posted
- Attached to
- TAXIWAY EDGE LIGHTING PROJECT
- Solicitation number
- IFB-128266
- Issued by
- Buena Vista City, Virginia
About this file
This is a final design plan set for the Taxiway Edge Lighting Project at Blue Ridge Regional Airport in Martinsville, Virginia, prepared by the Blue Ridge Airport Authority with engineering support from Ardurra Group. The project encompasses the removal, relocation, and reinstallation of existing taxiway edge lighting fixtures along Taxiway A and its connectors (Taxiway A6 and A7), as well as the provision and installation of new LED taxiway edge lighting. The work includes demolition of existing conduit and cabling, erosion and sediment control measures, electrical installation with new underground conduit runs and cable systems, and site restoration including permanent seeding and mulching. The plan set consists of 16 sheets detailing critical safety areas, construction sequencing, existing conditions and demolition requirements, erosion control measures, taxiway lighting layout across approximately 6,000 linear feet of taxiway, electrical details for light fixtures and grounding systems, and identification tags for 129 proposed taxiway edge lighting fixtures (designated T001 through T129). The overall contract time is limited to 60 calendar days with runway closures restricted to nighttime hours (8:00 PM to 6:00 AM) and liquidated damages of $1,500 per calendar day for overruns. No construction is permitted between October 29 and November 3, 2026. The contractor must coordinate with airport operations, maintain existing lighting circuits during construction, monitor airport radio communications, and comply with FAA Advisory Circulars regarding operational safety during construction on active airfields.
The project requires strict adherence to construction safety and phasing protocols outlined in the Construction Safety and Phasing Plan (CSPP), including management of runway safety areas (RSA), taxiway safety areas (TSA), and taxiway object free areas (TOFA). The contractor must establish perimeter erosion control measures with compost filter socks at existing storm drain inlets prior to land disturbance and maintain all active airfield pavement free of debris throughout construction. Existing taxiway edge lights designated for salvage must be removed, relocated, and reinstalled without damage to fixture components, base cans, and precast concrete aprons. The project requires installation of new L-867 base cans, L-830 isolation transformers, L-823 connectors, and associated electrical components meeting FAA specifications and the National Electrical Code. Ground rods (5/8" x 8' minimum copper-clad steel) and counterpoise conductors (#6 bare copper) must be installed according to specification requirements, with ground rod resistance not exceeding 25 ohms. All work must coordinate with existing runway and taxiway lighting circuits that must remain operational, potentially requiring temporary jumper cables during conduit removal and relocation phases. Construction activities require 48-hour advance notice to the airport manager and engineer, with the contractor maintaining 24-hour emergency contact personnel for maintaining safety measures and barricades throughout the project duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026-09-10 SPECS_MTV Taxiway Edge Lights_for Bid.pdf | ||
| MTV Taxiway Edge Lighting ADVERTISEMENT FOR BID.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LOCATION MAP VICINITY MAP
(1" = 2000')
NAME CERTIFICATION NUMBER
RESPONSIBLE LAND DISTURBEROWNER CONTACT:
OWNER: BLUE RIDGE AIRPORT AUTHORITY
ATTN: JASON DAVIS
ADDRESS: 525 AIRPORT ROAD
MARTINSVILLE, VA 24112
EMAIL: JDAVIS@FLYBLUERIDGE.COM
PHONE: 276-957-2291
(1" = 5 MILES)
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\
W K
M
TV
-R un w ay E xt en si on
C on st ru ct io n P ha se
C
P S
\C A
D D
\T ax iw ay
E dg e Li gh t P la n
S et
\S he et s\
_C
_S H
T_ C
O V
E R
.d w g
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
C
T
525 AIRPORT ROAD
MARTINSVILLE, VA 24112
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
TAXIWAY EDGE LIGHTING PROJECT
FOR
MARTINSVILLE, VIRGINIA
OWNER: BLUE RIDGE AIRPORT AUTHORITY
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
JUNE 5, 2026
C O
V E
R S
H E
E T
INDEX OF SHEETS
SHEET NUMBER SHEET TITLE
1 COVER SHEET
2 GENERAL LEGEND AND QUANTITIES
3 CSPP - CRITICAL SAFETY AREAS
4 CSPP - SEQUENCE AND SEQUENCING NOTES
5 CSPP - NOTES AND DETAILS
6 EXISTING CONDITIONS AND DEMOLITION - SHEET 1
7 EXISTING CONDITIONS AND DEMOLITION - SHEET 2
8 EROSION AND SEDIMENT CONTROL - SHEET 1
9 EROSION AND SEDIMENT CONTROL - SHEET 2
10 EROSION AND SEDIMENT CONTROL - DETAILS
11 TAXIWAY LIGHTING LAYOUT PLAN - SHEET 1
12 TAXIWAY LIGHTING LAYOUT PLAN - SHEET 2
13 TAXIWAY LIGHTING DETAILS - EDGE LIGHTS
14 TAXIWAY LIGHTING DETAILS - GROUNDS, SPLICES, DUCTS
15 TAXIWAY LIGHT IDENTIFICATION TAGS - SHEET 1
16 TAXIWAY LIGHT IDENTIFICATION TAGS - SHEET 2
06/05/2026
CFS CFS
CON CON
RSA
TLOFA
TSA
RPZ
x
Know what'sbelow.
before you digCall
NOTICE TO CONTRACTOR
1. PRIOR TO CONSTRUCTION, DIGGING, OR EXCAVATION THE
CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UNDERGROUND
UTILITIES (PUBLIC OR PRIVATE) THAT MAY EXIST AND CROSS
THROUGH THE AREA(S) OF CONSTRUCTION, WHETHER INDICATED ON
THE PLANS OR NOT. CALL "811" A MINIMUM OF 72 HOURS PRIOR TO
DIGGING OR EXCAVATING. REPAIRS TO ANY UTILITY DAMAGED
RESULTING FROM CONSTRUCTION ACTIVITIES SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR.
ROFA
TOFA
GENERAL LEGEND
PROPOSEDEXISTING
MAJOR CONTOUR
MINOR CONTOUR
RUNWAY SAFETY AREA
TAXIWAY SAFETY AREA
LOW PROFILE BARRICADE
LIMITS OF DISTURBANCE
TAXILANE OBJECT FREE AREA
TREE LINE
UNDERGROUND ELECTRICAL CONDUIT
STORMWATER PIPE
STANDARD COMPOST FILTER SOCK
TEMPORARY INLET PROTECTION
AIRPORT PROPERTY LINE
FENCE
DROP INLET
RUNWAY EDGE LIGHT
MANHOLE
DUCT BANK
TAXIWAY EDGE LIGHT
OMNIDIRECTIONAL LIGHT (ODAL)
RUNWAY THRESHOLD LIGHT
AIRFIELD GUIDANCE SIGN
RUNWAY END IDENTIFIER LIGHT (REIL)
PRECISION APPROACH PATH INDICATOR (PAPI)
RUNWAY PROTECTION ZONE
RUNWAY OBJECT FREE AREA
TAXIWAY OBJECT FREE AREA
AIRSPACE INTERMEDIATE ELEV. CONTOUR
AIRSPACE INDEX ELEV. CONTOUR1000
D
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\
W K
M
TV
-R un w ay E xt en si on
C on st ru ct io n P ha se
C
P S
\C A
D D
\T ax iw ay
E dg e Li gh t P la n
S et
\S he et s\
_C
_S H
T_ G
E N
E R
A L
N O
TE
S
A N
D L
E G
E N
D .d
A
B
C
D
E
F
G
H
2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
G E
N E
R A
L
LE
G E
N D
A N
D Q
U A
N
TI
TI
E
S
REMOVE EXISTING CONDUIT AND CABLES
NOT IN CONTRACT N.I.C.
WEST
APRON
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
ROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFA
RSARSARSARSARSARSARSARSARSARSARSA
R
SA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
0+00 5+00 10+00 15+00 20+00 25+00 30+00 35+00 40+00 45+00 50+00
MA
TC
HL
IN
E
- T
HI
S
SH
EE
T
MA
TC
HL
IN
E
- T
HI
S
SH
EE
T
AIRCRAFT
HANGARS (TYP)
RWY13 PAPI
LOCALIZER
ANTENNA
LOCALIZER
CRITICAL AREA
RUNWAY
PROTECTION
ZONE (RPZ)
LOCALIZER
EQUIPMENT
BUILDING
AIRPORT ROAD
SUPPLEMENTAL
WINDCONE
x x x xx x xx x x x x x x x x x x x x x x
TSA TSA TSA TSA
TOFA TOFA TOFA TOFA
TSA TSA
TOFA TOFA
TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
UT
T
TLOFA
TLOFA
xx x x x x x x x x x x x x
TSA TSA TSA
TOFA TOFA
R
PZ
RPZ
RPZ
RPZ
RPZ
R
PZ
R
PZ
RPZ
RPZ
RPZ
RPZ
PROPOSED
TAXIWAY EDGE
LIGHTING WORK
AREA (TYP.)
CONTRACTOR TO PLACE
BARRICADES AT EDGE OF
WORK AREA IN ACCORDANCE
WITH AC150/570-2G
0'
R U
N W
AY
S
AF
ET
Y
AR
EA
(R
SA
0'
R U
N W
AY
O
BJ
EC
T
FR
EE
A
R
EA
(R O
FA
4'
T
AX
IW
AY
O
BJ
EC
T
FR
EE
AR
EA
TO
FA
' T
AX
IW
AY
SA
FE
TY
AR
EA
TS
A)
TERMINAL APRON
TSA
TSATOFA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
ROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFA
R
SA
RSARSARSARSARSARSARSARSARSARSARSA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
R
PZ
RPZ
RPZ
RPZ
RPZ
R
PZ
R
PZ
RPZ
RPZ
RPZ
RPZ
TOFA
500'
50+00 55+00 60+00 65+00 70+00 75+00 80+00 85+00 90+00 95+00 100+00
MA
TC
HL
IN
E
- T
HI
S
SH
EE
T
MA
TC
HL
IN
E
- T
HI
S
SH
EE
T
WINDCONE AND SEGMENTED CIRCLE
AIRPORT ROAD
AIRPORT TERMINAL
FUEL FARM
EMS HELICOPTER HANAGR
AIRPORT TERMINAL ENTRANCE
SPENCER-PRESTON
ROAD
AWOS CRITICAL AREA
RELOCATED
ODALS
AWOS
AIRCRAFT
HANGARS (TYP) ROTATING BEACONAIRFIELD LIGHTING
VAULT BUILDING
RELOCATED RWY31 PAPI N.I.C.
RELOCATED RUNWAY
PROTECTION ZONE (RPZ)BYPASS TAXIWAY
(UNDER CONST.
SPRING 2026)
N.I.C
TAXIWAY
RELOCATION
(UNDER CONST.
SPRING 2026)
N.I.C
RELOCATED RUNWAY
THRESHOLD (UNDER CONST.
SPRING 2026)
N.I.C x x x x x x x x x x x x x x x x x x x x x x x x x
TSA
TOFA
TSA TSA
TOFA TOFA
TSA TSA TSA TSA
TOFA TOFA TOFA TOFA
TSA TSA TSA TSA TSA TSA TSA TSA TSA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
x x x x x x x x x x x x
TLOFA TLOFA
TLOFA TLOFATLOFA
TLOFA TLOFA
TLOFA
TLOFA TLOFA
RUNWAY 13-31
6,000' RUNWAY LENGTH
0'
R U
N W
AY
S
AF
ET
Y
AR
EA
(R
SA
0'
R U
N W
AY
O
BJ
EC
T
FR
EE
A
R
EA
(R O
FA
4'
T
AX
IW
AY
O
BJ
EC
T
FR
EE
AR
EA
TO
FA
' T
AX
IW
AY
SA
FE
TY
AR
EA
TS
A)
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\
W K
M
TV
-R un w ay E xt en si on
C on st ru ct io n P ha se
C
P S
\C A
D D
\T ax iw ay
E dg e Li gh t P la n
S et
\S he et s\
_C
_S H
T_ C
S P
P A
R E
A S
.d
B
C
D
E
F
G
H
2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
GENERAL SAFETY NOTES:
1. THE SAFETY AREAS AND CRITICAL AREAS INDICATED ON THIS SHEET HAVE BEEN
ESTABLISHED TO PROTECT CONSTRUCTION PERSONNEL, CONSTRUCTION EQUIPMENT,
AIRCRAFT, AND THE AIR TRAVELING PUBLIC WHEN CONSTRUCTION AND AIRCRAFT OPERATIONS
OCCUR IN CLOSE PROXIMITY. EACH AREA HAS SPECIFIC RESTRICTIONS ON ANY CONSTRUCTION ACTIVITY WITHIN THE LIMITS OF THAT AREA. SEE CURRENT EDITIONS OF FAA AC 150/5370-2
"OPERATIONAL SAFETY ON AIRPORTS DURING CONSTRUCTION" AND FAA AC 150/5300-13
"AIRPORT DESIGN" FOR ADDITIONAL INFORMATION.
2. THE AIRPORT WILL ISSUE APPROPRIATE NOTICES TO AIRMEN (NOTAMS) CONCERNING
ONGOING CONSTRUCTION ACTIVITIES. AS SUCH, THE GENERAL CONSTRUCTION SCHEDULE AND
ASSOCIATED MOVEMENT OF CONSTRUCTION VEHICLES WITHIN THE AIRPORT PERIMETER FENCE
MUST BE COORDINATED WITH THE ENGINEER AND AIRPORT ON A WEEKLY BASIS. ANY CHANGES
TO THIS SCHEDULE AND/OR ANTICIPATED CONSTRUCTION ACTIVITIES MUST BE COMMUNICATED
TO THE ENGINEER AND AIRPORT ON A TIMELY BASIS.
3. CONSTRUCTION TRAFFIC MUST AT ALL TIMES REMAIN ISOLATED FROM AIRCRAFT MOVEMENTS
ON THE RUNWAY AND TAXIWAY SYSTEMS WHENEVER THE RUNWAY AND TAXIWAY ARE
OPERATIONAL. IF FOR ANY REASON THE CONTRACTOR MUST ACCESS OR CROSS THESE AREAS,
ALL SUCH ACTIVITIES MUST BE COORDINATED WITH THE ENGINEER AND AIRPORT. THE
CONTRACTOR MAY BE REQUIRED TO STATION A FLAGGER AT POTENTIAL POINTS OF CONFLICT.
4. CONTRACTOR IS RESPONSIBLE FOR MARKING AND FLAGGING THE SAFETY AREAS AND
OTHER CRITICAL AREAS PRIOR TO BEGINNING CONSTRUCTION ACTIVITIES. MAINTAIN FLAGGING UNTIL CONSTRUCTION IS COMPLETE. COSTS INCIDENTAL TO "MOBILIZATION/DEMOBILIZATION".
5. FOR ANY WORK WHICH IS WITHIN THE RUNWAY SAFETY AREA (RSA), THE RUNWAY WILL NEED
TO BE CLOSED. REQUESTS FOR CLOSINGS MUST BE DIRECTED TO THE AIRPORT AND ENGINEER
AT LEAST 48 HOURS IN ADVANCE TO ALLOW THE AIRPORT TIME TO ISSUE APPROPRIATE
NOTAMS.
6. WORK WITHIN THE ACTIVE TAXIWAY SAFETY AREA (TSA) MAY BE PERMITTED WHEN CERTAIN CONDITIONS ARE MET IN ACCORDANCE WITH FAA AC 150/5370-2G, SECTION 2.22.3.4, PARAGRAPH
2. SEE PLAN SHEET 4 TITLED "CSPP - SEQUENCE AND SEQUENCING NOTES" FOR PROJECT
SPECIFIC INFORMATION ON WORK WITHIN THE TAXIWAY SAFETY AREA (TSA).
7. RUNWAY OBJECT FREE AREA (ROFA): CONSTRUCTION, INCLUDING EXCAVATIONS, MAY BE
PERMITTED IN THE ROFA WHILE THE RUNWAY IS ACTIVE. HOWEVER, EQUIPMENT MUST BE
REMOVED FROM THE ROFA WHEN NOT IN USE, AND MATERIAL SHOULD NOT BE STOCKPILED IN
THE ROFA.
8. TAXIWAY OBJECT FREE AREA (TOFA): UNLIKE THE ROFA, AIRCRAFT WINGS REGULARLY
PENETRATE THE TOFA DURING NORMAL OPERATIONS. THUS THE RESTRICTIONS ARE MORE
STRINGENT. CONSTRUCTION VEHICLES, EQUIPMENT, AND PERSONNEL MUST VACATE OR
"PULL-BACK" FROM THE TOFA TO ALLOW CLEAR PASSAGE OF OPERATING AIRCRAFT.
9. THE RUNWAY PROTECTION ZONE (RPZ) AND AWOS CRITICAL AREA (AUTOMATED WEATHER
OBSERVATION SYSTEM) WILL NOT BE AFFECTED BY CONSTRUCTION OPERATIONS.
10. A CONSTRUCTION SAFETY AND PHASING PLAN (CSPP) REPORT HAS BEEN PREPARED BY THE
ENGINEER. THE CSPP REPORT IS A COMPANION DOCUMENT TO THE CSPP PLANS AND CONTAINS
ADDITIONAL INFORMATION REGARDING SAFETY CONCERNS WHICH ARE UNIQUE TO
CONSTRUCTION AT AN AIRPORT AND SPECIFIC TO THIS PROJECT.
11. AIRSPACE CONTOURS ARE SHOWN AT 10' INCREMENTS.
GENERAL NOTES FOR RUNWAY SAFETY AREA (RSA) / TAXIWAY SAFETY AREA (TSA):
AT ALL TIMES DURING THE PROJECT, WHEN A RUNWAY OR TAXIWAY IS OPEN, THE ASSOCIATED
RSA/TSA MUST BE:
1. CLEARED AND GRADED AND HAVE NO RUTS, HUMPS, DEPRESSIONS, OR OTHER SURFACE
VARIATIONS.
2. DRAINED BY GRADING OR STORM SEWERS TO PREVENT WATER ACCUMULATION.
3. CAPABLE, UNDER DRY CONDITIONS, OF SUPPORTING SNOW REMOVAL EQUIPMENT, AIRCRAFT
RESCUE AND FIREFIGHTING (ARFF) EQUIPMENT, AND THE OCCASIONAL PASSAGE OF AIRCRAFT
WITHOUT CAUSING STRUCTURAL DAMAGE TO THE AIRCRAFT. SOIL COMPACTION OF MUST BE IN
ACCORDANCE WITH SECTION P-152 OF THE PROJECT SPECIFICATIONS.
4. FREE OF OBJECTS, EXCEPT FOR OBJECTS THAT NEED TO BE LOCATED IN THE RSA/TSA
BECAUSE OF THEIR FUNCTION. OBJECTS HIGHER THAN 3" ABOVE GRADE SHOULD BE
CONSTRUCTED ON LOW IMPACT RESISTANT SUPPORTS (FRANGIBLE MOUNTED STRUCTURES)
OF THE LOWEST PRACTICAL HEIGHT, WITH THE FRANGIBLE POINT NO HIGHER THAN 3" ABOVE
GRADE. OTHER OBJECTS SHOULD BE CONSTRUCTED AT GRADE, IN NO CASE SHOULD THEIR
HEIGHT EXCEED 3" ABOVE GRADE.
C S
P P
C
R
IT
IC
A
L S
A
FE
TY
A
R E
A S
SCALE: FEET
500250 x x x
TLOFA
TL
O
FA
TL
O
FA
TLOFA
TL
O
FA
x x x x x x
R
PZ
R
PZ
R
PZ
RPZ
RPZ
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
CONSTRUCTION ACCESS ROUTE.
CONTRACTOR TO MONITOR RADIO AND
YIELD TO AIRCRAFT ON ACTIVE
SECTIONS OF TAXIWAYS.
FULL 6,000' RUNWAY
LENGTH AVAILABLE
(CLOSED AT NIGHT ONLY)
ALL RUNWAY DISTANCE REMAINING SIGNS
TO REMAIN OPERATIONAL THROUGHOUT
CONSTRUCTION. DE-ENERGIZE DURING
RUNWAY CLOSURES. (TYP)
0+
1+
2+
3+
3+
0+
1+
2+
3+
3+
ALL REILS AND RUNWAY
THRESHOLD LIGHTS TO REMAIN
OPERATIONAL THROUGHOUT
CONSTRUCTION. DE-ENERGIZE
DURING RUNWAY CLOSURES. (TYP)
ALL RUNWAY EDGE LIGHTS TO
REMAIN OPERATIONAL
THROUGHOUT CONSTRUCTION.
DE-ENERGIZE DURING RUNWAY
CLOSURES. (TYP)
DAY WORK AREA
NIGHT WORK AREA
DURING RUNWAY CLOSURES PLACE
LIGHTED AND FLASHING RUNWAY
CLOSURE "X" ON BOTH ENDS OF RUNWAY.
ALL OTHER RUNWAY AND TAXIWAY
LIGHTING AND SIGNAGE FROM
TWY A4 TO TWY A1 SHALL REMAIN
OPERATIONAL THROUGHOUT
CONSTRUCTION. DE-ENERGIZE
DURING RUNWAY CLOSURES. (TYP)
RWY 13 PAPI TO REMAIN
OPERATIONAL THROUGHOUT
CONSTRUCTION. DE-ENERGIZE
PAPI CIRCUIT DURING RUNWAY
CLOSURES.
SUPPLEMENTAL WINDSOCK ON TWY CIRCUIT
CAN BE DE-ENERGIZED IF NECESSARY.
NOTIFY AIRPORT OF PERIODS WHEN
WINDSOCK LIGHT WILL BE DISABLED.
0'
R U
N W
AY
O
BJ
EC
T
FR
EE
A
R
EA
(R O
FA
0'
R U
N W
AY
SA
FE
TY
AR
EA
(R
SA
20+00 25+00 30+00 35+00 40+00 45+00
NIGHT WORK AREA
DAY WORK AREA
WEST
APRON
TW
Y
"A 8"
TW
Y
"A 7"
TW
Y
"A 6"
TW
Y
"A 5"
PARALLEL TWY "A" PARALLEL TWY "A"
LEGEND
PROPOSED WORK AREA
CONSTRUCTION ACCESS ROUTE
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\ w k
- m tv
-r un w ay e xt en si on c on st ru ct io n ph as e cp s\
C A
D D
\ta xi w ay e dg e lig ht p la n se t\S he et s\
_C _S
H T_
C S
P P
.d
B
C
D
E
F
G
H
2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
C S
P P
S
E Q
U E
N C
E A
N D
S E
Q U
E N
C
IN
G N
O
TE
S
SCALE: FEET
200100
SEQUENCING NOTES:
1. CONTRACT TIME WILL RUN CONTINUOUSLY UNTIL THE WORK IS ACCEPTED FOR PRACTICAL
USE BY THE AIRPORT. CONTRACTOR MAY MAKE WRITTEN REQUEST THAT CONTRACT TIME
BE STOPPED IN ACCORDANCE WITH THE PROJECT SPECIFICATIONS.
2. TAXIWAY EDGE LIGHTING CONSTRUCTION CAN NOT OCCUR WITHIN THE ACTIVE RUNWAY
SAFETY AREA (RSA). TO MINIMIZE OPERATIONAL IMPACTS, THE RUNWAY CAN ONLY BE
CLOSED DURING NIGHTTIME HOURS. AS SUCH, DAYTIME WORK AREAS HAVE BEEN
DELINEATED TO ALLOW SOME WORK TO OCCUR OUTSIDE THE RSA WHILE THE RUNWAY IS
OPERATIONAL. THIS DAYTIME WORK WILL REQUIRE THE CONTRACTOR TO MONITOR
AIRPORT RADIO AND "PULL-BACK" FOR AIRCRAFT USING TAXIWAYS.
3. AT ANY TIME WHILE A TAXIWAY IS OPEN TO AIRCRAFT OPERATIONS, TAXIWAY EDGE
LIGHTING CONSTRUCTION CAN OCCUR WITHIN THE ACTIVE TAXIWAY SAFETY AREA (TSA)
UNDER THE FOLLOWING CONDITIONS:
3.1. THE TAXIING SPEED MUST BE LIMITED TO 10 MPH.
3.2. THE AIRPORT MUST ISSUE APPROPRIATE NOTAMS.
3.3. LOW PROFILE, RED LIGHTED BARRICADES MUST BE INSTALLED ALONG THE EDGE OF
PAVEMENT ADJACENT TO THE ACTIVE WORK AREA.
3.4. OPEN TRENCHES MUST BE PROMINENTLY MARKED WITH RED OR ORANGE FLAGGING,
AS APPROVED BY THE AIRPORT, AND LIT WITH RED LIGHTS DURING HOURS OF
RESTRICTED VISIBILITY OR DARKNESS.
3.5. THE CONTRACTOR MUST CONTINUOUSLY MONITOR AIRPORT RADIO AND "PULL-BACK"
ALL EQUIPMENT, VEHICLES AND PERSONNEL FOR AIRCRAFT USING TAXIWAYS.
4. SECTIONS OF TAXIWAY MUST BE CLOSED WHEN THE NATURE OF WORK IS NOT CONDUCIVE
TO "PULL-BACK" CONSTRUCTION OPERATIONS. TAXIWAY EDGE LIGHTS AND SIGNS LOCATED
ALONG SECTIONS OF CLOSED TAXIWAY MUST BE COVERED IN A MANNER THAT WILL
PREVENT LIGHT ESCAPING OR REFLECTING. COVERS MUST BE ABLE TO WITHSTAND HIGH
WINDS, SEVERE WEATHER, AND NOT CREATE FOD.
5. TEMPORARY LIGHTING CIRCUIT JUMPER CABLES SHALL BE PLACED AS NECESSARY TO
KEEP TAXIWAY EDGE LIGHTS AND TAXIWAY SIGNS OPERATIONAL FROM EAST OF TWY A5 TO
TWY A1.
6. CONTRACTOR SHALL MAKE PROVISIONS TO KEEP THE ENTIRE RUNWAY LIGHTING CIRCUIT
AND PAPI CIRCUIT OPERATIONAL THROUGHOUT CONSTRUCTION. THIS INCLUDES ALL
RUNWAY THRESHOLD AND EDGE LIGHTS, REILS, ODALS, AND SIGNAGE. TEMPORARY
RUNWAY LIGHTING CIRCUIT JUMPER CABLES MAY BE REQUIRED AT TIMES WHEN THE
CONDUIT CARRYING THE RUNWAY LIGHTING CIRCUIT NEEDS TO BE DEMOLISHED AND
RELOCATED.
7. DURING ALL RUNWAY CLOSURES: CONTRACTOR SHALL PLACE A LIGHTED AND FLASHING
RUNWAY CLOSURE MARKER "X" ON BOTH THRESHOLDS OF THE RUNWAY. THE RUNWAY
LIGHTING CIRCUIT, TAXIWAY LIGHTING CIRCUIT, AND PAPI CIRCUIT SHALL ALL BE
DE-ENERGIZED AT THE ELECTRICAL VAULT. THE AIRFIELD ROTATING BEACON SHALL
REMAIN OPERATIONAL FOR USE BY HELICOPTERS OPERATING FROM THE TERMINAL
APRON.
8. THE LOCALIZER, AWOS, AND ROTATING BEACON WILL BE UNAFFECTED BY THIS PROJECT
AND CAN REMAIN IN OPERATION THROUGHOUT CONSTRUCTION AND DURING RUNWAY
CLOSURES.
9. SUBMIT BARRICADE AND RUNWAY/TAXIWAY CLOSURE MARKER DETAILS TO THE ENGINEER
FOR APPROVAL PRIOR TO USE ON THE AIRFIELD.
10. THE CONTRACTOR IS TO FAMILIARIZE THEMSELVES AND THEIR EMPLOYEES WITH THE
CURRENT EDITION OF FAA ADVISORY CIRCULAR AC 150/5370-2 "OPERATIONAL SAFETY ON
AIRPORTS DURING CONSTRUCTION". CONSTRUCTION WITHIN A RUNWAY SAFETY AREA
(RSA) REQUIRES CLOSURE OF THE RUNWAY. CONSTRUCTION WITHIN A TAXIWAY OBJECT
FREE AREA (TOFA) REQUIRES CLOSURE OF THE ASSOCIATED TAXIWAY.
11. TO ENSURE TIMELY ISSUANCE OF PROPER NOTICES TO AIRMEN (NOTAMS), THE
CONTRACTOR MUST COORDINATE WITH THE ENGINEER AND AIRPORT 48 HOURS IN
ADVANCE OF ALL WORK WITHIN THE RUNWAY SAFETY AREA (RSA) OR TAXIWAY OBJECT
FREE AREA AREA (TOFA). ALSO, THE CONTRACTOR MUST NOTIFY THE ENGINEER AND
AIRPORT IN ADVANCE OF ANY LIGHTING, SIGNAGE, OR NAVAIDS BEING AFFECTED BY
CONSTRUCTION. THE AIRPORT WILL ISSUE ALL NOTAMS AND HANDLE NECESSARY FAA
NOTIFICATIONS.
12. THE CONTRACTOR MUST REMAIN CLEAR OF THE ACTIVE RUNWAY SAFETY AREA (RSA) AT
ALL TIMES. CONTRACTOR MUST PULL-BACK FROM ACTIVE TAXIWAY SAFETY AREA (TSA)
AND TAXIWAY OBJECT FREE AREA (TOFA) WHEN TAXIWAY IS IN USE BY AIRCRAFT.
13. REMOVE ALL RUNWAY/TAXIWAY CLOSURE MARKERS AND BARRICADES AT THE
COMPLETION OF THE ASSOCIATED WORK UNLESS OTHERWISE SPECIFIED.
14. SAFETY MEASURES MAY BE RELOCATED AT THE DISCRETION OF THE ENGINEER AND
AIRPORT. ALL TEMPORARY CLOSURE MARKERS AND BARRICADES COSTS ARE INCIDENTAL
TO THE LUMP SUM ITEM FOR "AIRPORT SAFETY AND PHASING COORDINATION."
15. PHASING LIMITS SHOWN DO NOT ACCURATELY REFLECT THE ACTUAL PROJECT LIMITS OF
DISTURBANCE. THE CSPP PLANS AND REPORT ARE FOCUSED ON MAINTAINING AIRPORT
SAFETY WHILE CONSTRUCTION IS OCCURRING ON AN ACTIVE PUBLIC AIRFIELD. WHILE THE
INTENT IS ALSO TO KEEP THE CONTRACTOR'S PERSONNEL AND EQUIPMENT SAFE DURING
CONSTRUCTION, THE CSPP DOES NOT PRECLUDE THE CONTRACTOR'S RESPONSIBILITY
FOR ALL FACETS OF CONSTRUCTION SAFETY. NOR IS IT THE INTENT OF THE CSPP TO
DIRECT THE CONTRACTOR'S MEANS AND METHODS OR DICTATE THE PHASING/SCHEDULING
OF THE CONTRACTOR'S WORK, EXCEPT WHERE SUCH CONSTRAINTS ARE REQUIRED BY
APPLICABLE FAA RULES AND REGULATIONS TO MAINTAIN PUBLIC SAFETY.
24 HOUR CONTACT:
NOTIFY AIRPORT MANAGER 72 HOURS
PRIOR TO CONSTRUCTION
COMMENCEMENT
AIRPORT MANAGER: JASON DAVIS
(276)-957-2291
CONTRACT TIME:
OVERALL = 60 CALENDAR DAYS
- RUNWAY CLOSURES LIMITED TO NIGHTS (8PM TO 6AM).
- NO CONSTRUCTION ALLOWED OCTOBER 29 TO NOVEMBER 3, 2026.
- NO WORK CAN OCCUR STARTING ON OCTOBER 29 THROUGH NOVEMBER 3, 2026.
LIQUIDATED DAMAGES:
OVERALL CONTRACT TIME OVERRUN = $1,500 PER CALENDAR DAY
AIRFIELD IMPACT MATRIX
SCOPE OF WORK MARKERS / NOTESDURATION LIGHTING
PLACE LIGHTED / FLASHING RUNWAY CLOSURE "X" ON BOTH ENDS OF
RUNWAY. PLACE TAXIWAY CLOSURE "X" AND LOW LEVEL BARRICADES AT
ANY POINT WHERE BASED AIRCRAFT COULD ACCESS RUNWAY.
NAVAIDS
WORK IS PERMITTED AT ANY LOCATION DURING NIGHTTIME FULL RUNWAY AND TAXIWAY
CLOSURE.
WORK INCLUDES: E&S CONTROL, AIRFIELD ELECTRICAL, SOIL BACKFILL AND
RESTORATION, AND SEEDING.
NIGHT CLOSURE HOURS
LIMITED TO 8PM TO 6AM
CONTRACTOR TO MONITOR RADIO AND PULL-BACK FOR PASSING AIRCRAFT.
CLEARLY FLAG OPEN TRENCHES IN TSA. IF WORK NECESSITATES CLOSURE
OF TAXIWAY SECTIONS, COORDINATE WITH ENGINEER AND AIRPORT TO
PLACE TAXIWAY CLOSURE "X" MARKERS, LOW LEVEL BARRICADES, AND
COVER TAXIWAY EDGE LIGHTS AND SIGNAGE AS DIRECTED.
PHASE LIMITS ON AIRPORT OPERATION
TAXIWAY, RUNWAY,
AND PAPI CIRCUITS
DISABLED DURING
NIGHT RUNWAY
CLOSURE
RUNWAY AND ALL TAXIWAYS CLOSED.
HELICOPTERS MAY STILL OPERATE FROM APRON.
TAXIWAY LIGHTING
CIRCUIT PARTIALLY
DISABLED FROM TWY A8
TO TWY A6. LIGHTING
AND SIGNAGE ENABLED
ON REMAINDER OF
AIRFIELD
ENABLEDDAY
LOC, BEACON,
AWOS
ENABLED
NIGHT
ALL WORK MUST BE
COMPLETED WITHIN A
COMBINED 60
CALENDAR DAYS
NO LIMITS TO AIRPORT OPERATIONS UNLESS NATURE
OF WORK REQUIRES PARTIAL CLOSURE OF TAXIWAY(S).
PARALLEL TAXIWAY A CLOSURES WILL REQUIRE
AIRCRAFT BACKTAXI TO RWY 13 END.
HELICOPTER OPERATIONS UNAFFECTED.
NO WORK ALLOWED WITHIN RUNWAY 13-31 RSA.
PULL-BACK WORK PERMITTED ALONG PARALLEL TWY A AND CONNECTOR TAXIWAYS
TWY A8, TWY A7, AND TWY A6.
WORK INCLUDES: E&S CONTROL, AIRFIELD ELECTRICAL, SOIL BACKFILL AND
RESTORATION, AND SEEDING.
4" REFLECTIVE
WHITE/ORANGE TAPE
(TYP. BOTH SIDES)
20"x20" WITH FLUORESCENT
HI-VIZ ALTERNATING
ORANGE/WHITE VINYL
BLEND FLAG (TYP. ONE END
ONLY)
18"
MAX.
HEIGHT
NOTE:
1. BARRICADES SHALL BE WATER FILLED
AND SPACED A MAXIMUM OF 4' APART.
2. THE CONTRACTOR SHALL MAKE
FREQUENT INSPECTION OF THE
BARRICADES AND MAKE PROMPT
REPAIRS AS NECESSARY. LIGHT SHALL
BE OPERATING EVERY NIGHT.
3. BARRICADES SHALL BE ADEQUATELY
SECURED WITH SAND BAGS OR FILLED
WITH WATER TO WITHSTAND HIGH
WINDS AND/OR JET BLAST. BARRICADES
MUST BE EASILY COLLAPSIBLE UPON
CONTACT WITH AN AIRCRAFT OR ANY OF
ITS COMPONENTS.
4. CONTRACTOR SHALL INSTALL
BARRICADES AND MAINTAIN LIGHTS AND
FLAGS THROUGHOUT THE DURATION OF
THE PROJECT.
5. BARRICADES SHALL BE PROVIDED BY
THE CONTRACTOR AND ARE INCIDENTAL
TO MOBILIZATION.
TEMPORARY LIGHTED
BARRICADE DETAIL
NOT TO SCALE
WHITE
4 FT. (TYP.)
WHITE ORANGE WHITE ORANGEORANGE
WORK ZONE
PLAN
EXISTING RUNWAY OR TAXIWAY
OPEN TO AIRCRAFT MOVEMENT
10' MAX. BETWEEN LIGHTS
FLASHING OR STEADY-BURNING
COLOR RED LIGHT (TYPE A)
SECURELY FASTENED AND ORIENTED
PARALLEL WITH THE FLAG POST.
TEMPORARY BARRICADE PLACEMENT DETAIL
NOT TO SCALE
NOTES:
1. ALL VEHICLES WILL BE PROVIDED WITH A FLAG ON A
STAFF ATTACHED TO THE VEHICLE SO THE FLAG WILL
BE READILY VISIBLE.
2. THE FLAG WILL BE A MIN OF 3 FOOT SQUARE WITH A
CHECKERED PATTERN OF INTERNATIONAL ORANGE
AND WHITE AT LEAST 1 FOOT ON EACH SIDE.
3. CONTRACTOR VEHICLES AND EQUIPMENT SHALL BE
MARKED WITH CHECKERED FLAGS AND LIGHTED WITH
FLASHING BEACONS TO COMPLY WITH REQUIREMENTS
OF FAA AC 150/5210-5G.
4. VEHICLE FLAGS SHALL BE PROVIDED BY THE
CONTRACTOR AND ARE INCIDENTAL TO MOBILIZATION.
STAFF
1'X1' ORANGE
AND WHITE
SQUARES
VEHICLE FLAG DETAIL
NOT TO SCALE
NOTES:
1. LIGHTED X SHALL BE L-893 FIXTURE AS
SPECIFIED IN MOST CURRENT AC 150/5345-55A.
2. ITEM TO BE PROVIDED BY THE CONTRACTOR.
COST OF LIGHTED X SHALL BE CONSIDER
INCIDENTAL TO MOBILIZATION.
3. USE OF TRAILERED (LIGHTED) RUNWAY
CLOSURE MARKER IS REQUIRED FOR RUNWAY
CLOSURE.
4. FUEL, OIL, AND LIGHT BULBS FOR LIGHTED X
GENERATOR SHALL BE PROVIDED BY THE
CONTRACTOR. OIL SHALL BE CHANGED PER
MANUFACTURE'S RECOMMENDATIONS. UP KEEP
OF THE LIGHTED X SHALL BE CONSIDERED
INCIDENTAL TO MOBILIZATION.
5. LIGHTED X GENERATOR SHALL BE USED TO
POWER LIGHTED X'S ONLY THROUGH
CONSTRUCTION.
6. CONTRACTOR IS RESPONSIBLE FOR DAMAGE TO
LIGHTED X's AND WILL REPLACE/REPAIR AT NO
ADDITIONAL COST TO OWNER.
7. EQUIPMENT WILL REMAIN PROPERTY OF THE
CONTRACTOR UPON COMPLETION OF
CONSTRUCTION.
TRAILER
LAMP
3'-6"
NOTES:
1. ITEM TO BE PROVIDED BY CONTRACTOR.
2. MARKERS SHALL ONLY BE REMOVED ONCE TAXIWAY IS
OPEN FOR USE. MARKER TO BE PLACED ON THE CLOSED
TAXIWAY ADJACENT TO THE ENTRANCE TO THE RUNWAY.
3. MARKERS TO BE CONSTRUCTED OF EXTERIOR GRADE
PLYWOOD, DOUBLE LAYERED SNOW FENCE, COLORED
PLASTIC, OR A MATERIAL APPROVED BY THE ENGINEER
WHICH WILL LAST UNTIL THE PROJECT IS COMPLETED AND
CAN BE RELOCATED AS REQUIRED. MARKERS SHALL BE
YELLOW IN COLOR.
4. NO SEPARATE PAYMENT WILL BE MADE FOR THE
TEMPORARY CLOSED TAXIWAY MARKER. THE COST SHALL
BE INCIDENTAL TO THE CONTRACTOR'S COST FOR
MOBILIZATION.
TEMPORARY CLOSED TAXIWAY MARKER
NOT TO SCALE
C L
TA
XI
W
AY
5'
90°
TEMPORARY RUNWAY
CLOSURE X
NOT TO SCALE
SAFETY ON AIRPORTS DURING CONSTRUCTION:
(A) FEDERAL AVIATION ADMINISTRATION (FAA) ADVISORY CIRCULARS
(AC), ORDERS AND FEDERAL AVIATION REGULATIONS (FAR)
THE FOLLOWING PUBLICATIONS CONTAIN DEFINITIONS/DESCRIPTIONS OF CRITICAL AIRPORT OPERATING AREAS. THE AREAS DEFINED BELOW PERTAIN TO AIRFIELD SAFETY REQUIREMENTS AND ARE REFERENCED THROUGHOUT THE CONTRACT DOCUMENTS. COPIES OF THESE
PUBLICATIONS ARE AVAILABLE THROUGH THE FAA.
(1) AC 150/5370-2, "OPERATIONAL SAFETY ON AIRPORTS DURING CONSTRUCTION," CURRENT EDITION, SETS FORTH GUIDELINES TO ASSIST AIRPORT OPERATORS IN COMPLYING THE REQUIREMENTS OF FEDERALLY FUNDED CONSTRUCTION PROJECTS.
(2) FAR PART 77 "OBJECTS AFFECTING NAVIGABLE AIRSPACE, CURRENT EDITION:
(a) ESTABLISHES STANDARDS FOR DETERMINING OBSTRUCTION TO NAVIGABLE AIRSPACE, CIVIL AIRPORT IMAGINARY SURFACES ARE
DEFINED IN THE PUBLICATION.
(b) SETS FORTH REQUIREMENTS FOR NOTICE OF CERTAIN PROPOSED CONSTRUCTION OR ALTERATION. NOTICE OF CONSTRUCTION PROVIDES A BASIS FOR RECOMMENDATIONS FOR IDENTIFYING THE CONSTRUCTION OR ALTERATION IN ACCORDANCE WITH AC
70/7460-1 "OBSTRUCTION MARKING AND LIGHTING" CURRENT EDITION.
(3) AC 150/5300-13. "AIRPORT DESIGN", CURRENT EDITION, ESTABLISHES DESIGN, OPERATIONAL, AND MAINTENANCE STANDARDS FOR AIRPORTS, STANDARD TERMS USED IN THE CONTRACT PLANS AND SPECIFICATIONS ARE DEFINED BELOW:
(a) OBSTACLE FREE ZONE (OFZ) - A VOLUME OF SPACE WHICH IS FREE OF ALL FIXED OBJECTS AND CLEAR OF VEHICLES IN THE PROXIMITY OF AN AIRPLANE CONDUCTING AN APPROACH, MISSED APPROACH, LANDING, TAKEOFF, OR DEPARTURE.
(b) RUNWAY PROTECTION ZONE (RPZ) - A TRAPEZOIDAL TWO DIMENSIONAL AREA CENTERED ON THE RUNWAY BEGINNING AT A POINT 200'
BEYOND THE END OF THE AREA USEABLE FOR TAKEOFF OR LANDING.
(c) OBJECT FREE AREA (OFA) - A TWO DIMENSIONAL GROUND AREA SURROUNDING RUNWAY, TAXIWAYS, AND TAXILANES WHICH MUST
REMAIN CLEAR OF OBJECTS EXCEPT FOR OBJECTS WHOSE LOCATION IS FIXED BY FUNCTION.
(d) SAFETY AREA - THE SURFACE ADJACENT TO RUNWAYS, TAXIWAYS, AND TAXILANES OVER WHICH AIRCRAFT SHOULD, IN DRY WEATHER, BE ABLE TO CROSS AT NORMAL SPEEDS WITHOUT INCURRING SIGNIFICANT DAMAGE. A SAFETY AREA IS GRADED, DRAINED AND COMPACTED. IT IS FREE OF ANY HOLES, TRENCHES, BUMPS OR OTHER SIGNIFICANT SURFACE VARIATIONS OR OBJECTS OTHER THAN THOSE WHICH MUST BE THERE BECAUSE OF THEIR ESSENTIAL AERONAUTICAL FUNCTION. THE SAFETY AREA REQUIRES THE CAPABILITY OF SUPPORTING MAINTENANCE VEHICLES AND AIRCRAFT RESCUE AND FIRE FIGHTING VEHICLES UNDER NORMAL (DRY) CONDITIONS. NO CONSTRUCTION EQUIPMENT, PERSONNEL, OR VEHICLES WILL BE PERMITTED INSIDE ANY SAFETY AREA WITHOUT
THE AUTHORIZATION OF THE RESIDENT ENGINEER.
(B) SAFETY PLAN COMPLIANCE DOCUMENT (SPCD)
(1) THE CONTRACTOR MUST PREPARE AND SUBMIT A SAFETY PLAN COMPLIANCE DOCUMENT FOR APPROVAL BY THE ENGINEER PRIOR TO BEGINNING CONSTRUCTION. THE SPCD CONVEYS HOW THE CONTRACTOR INTENDS TO COMPLY WITH THE CONSTRUCTION SAFETY AND PHASING PLANS. THE SPCD ALSO REAFFIRMS THE CONTRACTOR'S UNDERSTANDING AND ACCEPTANCE OF THE CONSTRUCTION SAFETY
AND PHASING PLANS. SOME IMPORTANT ELEMENTS INCLUDE:
(a) IDENTIFYING KEY CONTRACTOR PERSONNEL AND POINTS OF CONTACT.
(b) IDENTIFYING 24-HOUR CONTACT FOR MAINTENANCE OF SAFETY MEASURES AND BARRICADES.
(c) HOW CONTRACTOR INTENDS TO ACCOMPLISH SECURITY OF THE AOA.
(d) HOW CONTRACTOR INTENDS TO UNCOVER AND PROTECT UNDERGROUND UTILITIES.
(e) TYPES OF HAZARD DEVICES (I.E. BARRICADES).
(f) HOW CONTRACTOR INTENDS TO MAINTAIN ACTIVE AIRFIELD PAVEMENT FREE OF DEBRIS.
(g) HOW CONTRACTOR INTENDS TO ADDRESS A POTENTIAL HAZMAT SPILL.
(h) SUBMITTAL OF FAA FORM 7460-1 FOR ANY CONTRACTOR EQUIPMENT (CRANE, CONCRETE PUMP, BATCH PLANT, ETC.) THAT EXCEED
APPLICABLE HEIGHTS PER FAA GUIDELINES.
(C) GENERAL SAFETY REQUIREMENTS
(1) THE CONTRACTOR SHALL ACQUAINT HIS SUPERVISORS AND EMPLOYEES WITH THE AIRPORT ACTIVITY AND OPERATIONS THAT ARE INHERENT TO BLUE RIDGE REGIONAL AIRPORT AND SHALL CONDUCT HIS CONSTRUCTION ACTIVITIES TO CONFORM TO ALL ROUTINE AND EMERGENCY AIR TRAFFIC REQUIREMENTS AND GUIDELINES FOR SAFETY SPECIFIED HEREIN. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALL SAFETY DEVICES AS REQUIRED FOR THE PROTECTION OF HIS PERSONNEL.
(2) PROTECTION OF ALL PERSONS SHALL BE PROVIDED THROUGHOUT THE PROGRESS OF THE WORK. THE WORK SHALL PROCEED IN SUCH A MANNER AS TO PROVIDE SAFE CONDITIONS FOR ALL WORKERS AND GOVERNMENT PERSONNEL. THE SEQUENCE OF OPERATION SHALL BE SUCH THAT PERSONNEL AND WORKERS IN THE WORK AREA ARE NOT SUBJECT TO ANY DANGEROUS CONDITIONS THE CONTRACTOR
MUST PROVIDE SAFETY MEASURES TO GUARD AGAINST INJURY.
(3) DURING PERFORMANCE OF THIS CONTRACT, THE AIRPORT RUNWAYS, TAXIWAYS, AND AIRCRAFT PARKING APRONS SHALL REMAIN IN USE BY AIRCRAFT AS DETAILED IN THE PHASING PLANS. ALL AIRCRAFT TRAFFIC ON ACTIVE AREAS SHALL HAVE PRIORITY OVER CONTRACTOR'S TRAFFIC. THE OWNER OR ITS AUTHORIZED REPRESENTATIVE RESERVES THE RIGHT TO ORDER THE CONTRACTOR AT ANY TIME TO VACATE ANY AREA NECESSARY TO MAINTAIN SAFE AIRCRAFT OPERATIONS. USE OF AREAS NEAR THE CONTRACTOR'S WORK AREA WILL BE CONTROLLED TO MINIMIZE DISTURBANCE TO THE CONTRACTOR'S OPERATION. THE CONTRACTOR SHALL NOT ALLOW EMPLOYEES, SUBCONTRACTORS, SUPPLIERS, OR ANY OTHER UNAUTHORIZED PERSON TO ENTER OR REMAIN IN ANY AIRPORT
AREA WHICH WOULD BE HAZARDOUS TO PERSONNEL OR TO AIRCRAFT OPERATIONS.
(4) ALL WORK TO BE PERFORMED WHICH IS WITHIN 200' OF THE ℄ OF AN ACTIVE RUNWAY (RSA) OR 65.5' OF THE ℄ OF AN ACTIVE TAXIWAY (TOFA), SHALL BE PERFORMED WHEN THE RUNWAY OR TAXIWAY IS NOT IN USE. SUCH WORK SHALL NOT BE ACCOMPLISHED WITHOUT PRIOR PERMISSION FROM THE ENGINEER. REQUESTED CLOSINGS SHALL BE DIRECTED TO THE ENGINEER AT LEAST 48 HOURS IN
ADVANCE.
(5) THE CONTRACTOR SHALL BE RESPONSIBLE FOR PREVENTING/CORRECTING AND ADEQUATELY LIGHTING, BARRICADING, AND
MARKING THE FOLLOWING TYPES OF SAFETY PROBLEMS AND/OR HAZARDS:
· TRENCHES, HOLES, OR EXCAVATION ON OR ADJACENT TO ANY ACTIVE RUNWAY OR IN ANY SAFETY AREAS.
· UNMARKED/UNLIT HOLES OR EXCAVATION ON OR ADJACENT TO ANY ACTIVE RUNWAY, TAXIWAY/LANE, OR OTHER SAFETY AREA.
· MOUNDS OR PILES OF EARTH, CONSTRUCTION MATERIALS, TEMPORARY STRUCTURES, OR OTHER OBJECTS IN THE VICINITY OF ANY
OPEN RUNWAY, TAXIWAY, TAXILANE, OR IN ANY RELATED SAFETY, APPROACH, OR DEPARTURE AREA.
· VEHICLES, EQUIPMENT, EXCAVATION, STOCKPILES, OR OTHER MATERIALS WHICH COULD DEGRADE OR OTHERWISE INTERFERE WITH
ELECTRONIC SIGNALS FROM RADIOS OR ELECTRONIC NAVIGATIONAL AIDS (NAVAIDS).
· PAVEMENT DROP-OFFS OR PAVEMENT TURF-LIPS (EITHER PERMANENT OR TEMPORARY) WHICH COULD CAUSE DAMAGE TO AIRCRAFT IF
CROSSED AT NORMAL OPERATING SPEEDS. THE MAXIMUM ALLOWABLE DROP-OFF OR LIP IS 1-1/2 INCHES.
· UNMARKED UTILITY, NAVAID, WEATHER SERVICE, RUNWAY LIGHTING, OR OTHER POWER OR SIGNAL CABLES THAT COULD BE DAMAGED
DURING CONSTRUCTION.
· OBJECTS, WHETHER OR NOT MARKED OR FLAGGED, OR ACTIVITIES ANYWHERE ON OR IN THE VICINITY OF THE AIRPORT WHICH COULD
BE DISTRACTING, CONFUSING, OR ALARMING TO PILOTS DURING AIRCRAFT OPERATIONS.
· UNFLAGGED/UNLIGHTED LOW VISIBILITY ITEMS SUCH AS TALL CRANES, DRILLS, AND THE LIKE ANYWHERE IN THE VICINITY OF ACTIVE
RUNWAYS, OR IN ANY APPROACH OR DEPARTURE AREA.
· MISLEADING OR MALFUNCTIONING OBSTRUCTION LIGHTS OR UNLIGHTED/UNMARKED OBSTRUCTIONS IN THE APPROACH TO ANY
ACTIVE RUNWAY.
· INADEQUATE APPROACH/DEPARTURE SURFACES (THESE SURFACES ARE NEEDED TO ASSURE ADEQUATE LANDING/TAKEOFF
CLEARANCE OBSTRUCTION, OR WORK OR STORAGE AREAS).
· INADEQUATE, CONFUSING OR MISLEADING MARKING/LIGHTING OF RUNWAYS, TAXIWAYS OR TAXILANES (INCLUDING DISPLACED OR
RELOCATED THRESHOLDS).
· WATER, SNOW, DIRT, DEBRIS, OR OTHER TRANSIENT ACCUMULATION WHICH TEMPORARILY OBSCURES PAVEMENT MARKINGS OR
PAVEMENT EDGES, OR DEGRADES VISIBILITY OF RUNWAY/TAXIWAY MARKINGS OR LIGHTING.
· INADEQUATE OR IMPROPER METHOD OF MARKING, BARRICADING, AND LIGHTING OF TEMPORARILY CLOSED PORTIONS OF THE AIRPORT
OPERATIONS AREA (AOA).
· TRASH OR OTHER MATERIALS WITH FOREIGN OBJECT DAMAGE (FOD) POTENTIAL; WHETHER ON RUNWAYS, TAXIWAYS, OR APRONS; OR
IN RELATED SAFETY AREAS.
· INADEQUATE BARRICADING OR OTHER MARKING WHICH IS PLACED TO SEPARATE CONSTRUCTION OR MAINTENANCE AREAS FROM
OPEN AIRCRAFT OPERATING AREAS.
· FAILURE TO CONTROL UNAUTHORIZED VEHICLE AND HUMAN ACCESS TO ACTIVE AIRCRAFT OPERATING AREAS.
· FAILURE TO MAINTAIN RADIO COMMUNICATION BETWEEN CONSTRUCTION/MAINTENANCE VEHICLES AND THE AIRPORT UNICOM.
· CONSTRUCTION/MAINTENANCE ACTIVITIES OR MATERIALS WHICH COULD HAMPER THE RESPONSE OF AIRCRAFT RESCUE AND FIRE
FIGHTING (ARFF) EQUIPMENT FROM REACHING ALL AIRCRAFT OR ANY PART OF THE RUNWAY/TAXIWAY SYSTEM, RUNWAY APPROACH
AND DEPARTURE AREAS AND AIRCRAFT PARKING LOCATIONS.
· BIRD ATTRACTIONS ON AIRPORT SUCH AS: EDIBLES (FOOD, SCRAPS, ETC.), MISCELLANEOUS TRASH, OR PONDED WATER.
(6) THE CONTRACTOR SHALL CONDUCT ACTIVITIES SO AS NOT TO VIOLATE ANY SAFETY STANDARDS CONTAINED HEREIN. THE CONTRACTOR SHALL INSPECT ALL CONSTRUCTION AND STORAGE AREAS AS OFTEN AS NECESSARY AND PROMPTLY TAKE ALL STEPS NECESSARY TO PREVENT/REMEDY ANY UNSAFE OR POTENTIALLY UNSAFE CONDITIONS OR ACTIVITIES DISCOVERED.
(7) BEFORE ACTUAL COMMENCEMENT OF CONSTRUCTION ACTIVITY, THE CONTRACTOR SHALL NOTIFY, IN WRITING, AT LEAST 48 HOURS IN ADVANCE, THE OWNER OR ITS AUTHORIZED REPRESENTATIVE OF HIS INTENTIONS OF CONSTRUCTION, STATING THE PROPOSED TIME, DATE, AND AREA IN WHICH WORK WILL COMMENCE.
(8) UPON COMPLETION OF WORK AND RETURN OF ALL RELATED AREAS TO STANDARD CONDITIONS, THE CONTRACTOR SHALL AGAIN NOTIFY THE OWNER OR ITS AUTHORIZED REPRESENTATIVE, IN WRITING, AND DESCRIBE THE AREA THAT IS COMPLETE AND AVAILABLE FOR
NORMAL AIRPORT OPERATIONS.
(9) BLUE RIDGE REGIONAL AIRPORT WILL BE RESPONSIBLE FOR ISSUING APPROPRIATE NOTICE TO AIRMEN (NOTAM) CONCERNING
CONSTRUCTION ACTIVITY ON THE AIRFIELD.
(D) MOTORIZED VEHICLES
(1) THIS PROJECT INCLUDES WORK WITHIN THE ACTIVE AIRCRAFT OPERATIONS AREA (AOA) (I.E. THE SECURE PORTION OF THE AIRPORT). ALL PERMITTED VEHICLES SHALL DISPLAY IN FULL VIEW ABOVE THE VEHICLE A 3 FOOT BY 3 FOOT OR LARGER, ORANGE AND WHITE CHECKERBOARD, PLASTIC FLAG. EACH CHECKERBOARD COLOR SHALL BE 1 FOOT SQUARE. ANY VEHICLE OPERATING IN THE AOA DURING THE HOURS OF DARKNESS SHOULD BE EQUIPPED WITH A FLASHING AMBER (YELLOW) DOME-TYPE LIGHT, MOUNTED ON THE TOP OF THE VEHICLE AND OF SUCH INTENSITY TO CONFORM TO LOCAL CODES FOR MAINTENANCE AND EMERGENCY VEHICLES. DARKNESS SHALL BE DEFINED AS ONE HOUR BEFORE OFFICIAL SUNSET UNTIL ONE HOUR AFTER SUNRISE.
(E) RADIO COMMUNICATIONS
(1) RADIO COMMUNICATIONS ARE REQUIRED BETWEEN THE CONTRACTOR AND THE AIRPORT UNICOM. RADIO CONTACT IS REQUIRED AT ALL TIMES WHILE THE CONTRACTOR HAS PERSONNEL AND EQUIPMENT ON THE PROJECT SITE AND WHILE THEY ARE IN AN ACTIVE AIRCRAFT OPERATIONS AREA (AOA) OF THE AIRPORT. THE CONTRACTOR SHALL MAINTAIN A RADIO THAT IS CAPABLE OF TRANSMITTING AND RECEIVING COMMUNICATIONS ON A CTAF/UNICOM FREQUENCY OF 122.7 MHz. THIS UNICOM FREQUENCY IS TO BE USED ONLY FOR
MONITORING AIRCRAFT WHEN WITHIN ACTIVE FACILITIES.
(2) THE CONTRACTOR SHALL USE A SEPARATE FREQUENCY FOR OTHER CONSTRUCTION ACTIVITIES. SUFFICIENT RADIOS SHALL BE ON SITE AND OPERATING AT ALL TIMES SO THAT INSTRUCTIONS OR COMMUNICATIONS MAY BE DISPATCHED TO ALL CREWS AND/OR EQUIPMENT WORKING IN AN ACTIVE AOA WITHIN ONE MINUTE AFTER RECEIPT FROM THE AIRPORT REPRESENTATIVE.
(3) A RADIO SHALL ALSO BE FUNISHED BY THE CONTRACTOR TO THE RESIDENT ENGINEER. THIS RADIO SHALL BE CAPABLE OF TRANSMITTING AND RECEIVING CTAF/UNICOM COMMUNICATIONS ON A FREQUENCY OF 122.7 MHz.
(F) FOREIGN OBJECT DEBRIS (FOD)
(1) DEBRIS, WASTE, AND LOOSE MATERIAL (INCLUDING DUST AND DIRT) CAPABLE OF CAUSING DAMAGE TO AIRCRAFT LANDING GEAR OR PROPELLERS, OR BEING INGESTED INTO JET ENGINES, SHALL NOT BE ALLOWED ON ACTIVE AIRCRAFT MOVEMENT AREAS OR ADJACENT GRASSED AREAS. MATERIALS OBSERVED TO BE WITHIN THESE AREAS SHALL BE REMOVED IMMEDIATELY AND/OR CONTINUOUSLY BY THE CONTRACTOR. THE CONTRACTOR IS REQUIRED TO HAVE A SWEEPING MACHINE AND OPERATOR ON SITE AND READY AT ALL TIMES DURING CONSTRUCTION ACTIVITY. WHERE CONSTRUCTION TRAFFIC ON OR ACROSS RUNWAYS, TAXIWAYS, OR APRONS IS REQUIRED, THE CONTRACTOR SHALL PROVIDE ADEQUATE PERSONNEL AND EQUIPMENT TO KEEP SUCH SURFACES CLEAR OF DEBRIS.
(G) TRAFFIC CONTROL/FLAGMEN
(1) IN ACCORDANCE WITH THE SPECIFICATIONS, THE CONTRACTOR SHALL, AT HIS OWN EXPENSE, FURNISH FLAGMEN AS NECESSARY TO CONTROL HIS, PUBLIC, AND AIRPORT TRAFFIC (UNLESS OTHERWISE DIRECTED BY THE ENGINEER).
(2) ALL CONTRACTOR VEHICLES THAT ARE REQUIRED TO CROSS ACTIVE RUNWAYS, TAXIWAYS AND APRONS SHALL DO SO UNDER THE DIRECT CONTROL OF A COMPETENT FLAGMAN WHO IS IN DIRECT RADIO CONTACT WITH AIRPORT UNICOM. ALL AIRCRAFT TRAFFIC ON RUNWAYS, TAXIWAYS, AND APRONS SHALL HAVE PRIORITY OVER CONTRACTOR'S TRAFFIC. AT NO TIME SHALL THE CONTRACTOR'S VEHICLES OR PERSONNEL BE ALLOWED TO ENTER OR CROSS ACTIVE RUNWAYS, SAFETY AREAS OR CLEAR ZONES WITHOUT PROPER
AUTHORIZATION FROM AN AIRPORT REPRESENTATIVE.
(H) MISCELLANEOUS
· OPEN FLAME, WELDING OR TORCH CUTTING OPERATIONS ARE PROHIBITED UNLESS ADEQUATE FIRE AND SAFETY PRECAUTIONS HAVE
BEEN TAKEN AND THE PROCEDURE PREVIOUSLY APPROVED BY THE ENGINEER.
· EQUIPMENT AND STOCKPILED MATERIAL SHALL BE CONSTRAINED IN A MANNER TO PREVENT MOVEMENT RESULTING FROM AIRCRAFT
JET BLAST OR WIND CONDITIONS IN EXCESS OF 10 KNOTS.
· THE CONTRACTOR SHALL PROVIDE CONSTRUCTION BARRICADES WITH FLASHING RED LIGHTS AS SHOWN ON THE DRAWINGS TO DELINEATE THE WORK AREAS WHEN CLOSED TO AIRPORT TRAFFIC. OPEN TRENCHES, EXCAVATIONS AND STOCKPILED MATERIAL LOCATED IN THE AOA SHALL BE PROMINENTLY MARKED WITH ORANGE FLAGS AND LIGHTED BY APPROVED LIGHT UNITS DURING HOURS
OF LIMITED VISIBILITY AND DARKNESS.
· ALL MATERIALS AND EQUIPMENT WHEN NOT IN USE SHALL BE PLACED IN APPROVED AREAS WHERE THEY WILL NOT CONSTITUTE A HAZARD TO AIRCRAFT OPERATIONS AND NOT PENETRATE CLEARANCE SURFACES DEFINED PREVIOUSLY AS SHOWN ON THE GENERAL
PROJECT LAYOUT. EQUIPMENT SHALL BE PARKED AT THE STAGING AREA WHEN NOT IN USE.
· MAXIMUM EQUIPMENT HEIGHT SHALL NOT EXCEED 20 FEET UNLESS PRIOR APPROVAL IS OBTAINED FROM THE ENGINEER.
· UPON COMPLETION OF ANY STAGE/PHASE OF WORK, THE ENGINEER WILL ARRANGE A PHYSICAL INSPECTION OF THE AREA WITH THE
AIRPORT OPERATIONS PERSONNEL PRIOR TO OPENING ANY PORTION OR WHOLE RUNWAY, TAXIWAY, RAMP AREA OR AIRPORT ROADWAY THAT HAS BEEN CLOSED FOR WORK, USED FOR A CROSSING POINT OR HAUL ROUTE BY THE CONTRACTOR.
· THE CONTRACTOR SHALL PROVIDE THE AIRPORT DIRECTOR WITH A CURRENT LIST OF ALL EMPLOYEES WORKING ON THE AIRPORT. THE LIST SHALL BE MAINTAINED CURRENT BY THE CONTRACTOR AND APPLIES TO THE CONTRACTOR AND ALL SUBCONTRACTORS.
· THE CONTRACTOR SHALL FAMILIARIZE HIS PERSONNEL WITH CLEARANCES NEEDED TO PROVIDE FOR THE SAFE OPERATION OF
RUNWAYS AND TAXIWAYS AS SHOWN IN THE PLANS.
· EXCEPT FOR EMERGENCIES, ALL CONTACT WITH AIRPORT PERSONNEL SHALL BE MADE THROUGH THE RESIDENT ENGINEER. FOR EMERGENCIES INVOLVING SAFETY (INJURIES, FIRES, SECURITY BREACHES, ETC.) THE CONTRACTOR SHALL MAKE DIRECT CONTACT WITH AIRPORT OPERATIONS FOLLOWED BY NOTIFICATION TO THE RESIDENT ENGINEER AS SOON AS POSSIBLE.
· THE CONTRACTOR SHALL PROVIDE THE PHONE NUMBERS OF THREE (3) PERSONNEL, INCLUDING THE PROJECT SUPERINTENDENT, WHO MAY BE CONTACTED IN AN EMERGENCY. THESE PERSONNEL SHALL BE ON CALL 24 HOURS PER DAY FOR MAINTAINING AIRPORT HAZARD LIGHTING AND BARRICADES. IN AN EMERGENCY THE CONTRACTOR SHALL CONTACT THE AIRPORT MANAGER AND ENGINEER.
· IN ACCORDANCE WITH THE SPECIFICATIONS, FEDERAL WAGE RATES SHALL BE POSTED IN THE PRIMARY STAGING AREA IN A
WEATHERPROOF ENCLOSURE.
· CONTRACTOR SHALL MAINTAIN THE SITE IN A MANNER SO THAT WORKMEN AND PUBLIC ARE PROTECTED FROM INJURY.
· LABOR SAFETY REGULATIONS SHALL CONFORM TO THE PROVISIONS SET FORTH BY THE OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION (OSHA) IN THE FEDERAL REGISTER OF THE DEPARTMENT OF TRANSPORTATION.
· ALL SUBSURFACE CONSTRUCTION SHALL COMPLY WITH THE "TRENCH SAFETY ACT." THE CONTRACTOR SHALL INSURE THAT THE
METHOD OF TRENCH PROTECTION AND CONSTRUCTION IS IN COMPLIANCE WITH OSHA REGULATIONS.
· IT SHALL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO COMPLY AND ENFORCE ALL APPLICABLE SAFETY REGULATIONS.
INFORMATION PROVIDED HEREIN HAS BEEN PROVIDED FOR THE CONTRACTOR'S INFORMATION ONLY AND DOES NOT IMPLY THAT THE
OWNER OR ENGINEER WILL INSPECT AND/OR ENFORCE SAFETY REGULATIONS.
· CONTRACTOR SHALL BE RESPONSIBLE TO MAINTAIN SAFETY AT THE AIRPORT AT ALL TIMES. PROMPTLY TAKE ALL ACTIONS NECESSARY TO PREVENT OR REMEDY ANY UNSAFE OR POTENTIALLY UNSAFE CONDITIONS AS SOON AS THEY ARE DISCOVERED. SEE THE CONSTRUCTION SAFETY AND PHASING PLAN (CSPP) DRAWING SHEETS AND REPORT FOR FURTHER INFORMATION.
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\
W K
M
TV
-R un w ay E xt en si on
C on st ru ct io n P ha se
C
P S
\C A
D D
\T ax iw ay
E dg e Li gh t P la n
S et
\S he et s\
_C
_S H
T_ C
S P
P D
E
TA
IL
S
.d
B
C
D
E
F
G
H
2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
C S
P P
N
O
TE
S A
N D
D E
TA
IL
S
TS
TS
A
TS
A
TSA
TSA
TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA
TO
FA
TO
FA
TO
FA
TOFA
TOFA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
TS
A
TSA
TSA TSA TSA TSA TSA
TO
FA
TOFA TOFA TOFA TOFA TOFA
TS
A
TSA
TSA
TSA
TSATO
FA
TO
FA
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
1x C
O N
1x C
O N
1x
CO
N
1x
CO
N
1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
1x
CO
N
1xCON
1xCON 1xCON
1xCON
1xCON
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
1x
CO
N
1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
2xCON 2xCON 2xCON 2xCON 2xCON
1x C
O N
1x C
O N
1x C
O N
1x C
O N
1x C
O N
1x C
O N
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON 1xCON
1xCON
1xCON
1x
CON
1x
CON
D 22 (DI-7)
RIM = 938.64
18" INV IN = 934.44
18" INV OUT = 934.32
D 21 (DI-7)
RIM = 941.37
18" INV OUT = 937.23
RSARSARSARSARSARSARSARSARSARSARSARSARSARSA
19+00 20+00 21+00 22+00 23+00 24+00
0+
1+
2+
3+00 4+00 5+00 6+00 7+00
0+
1+
2+
3+
3+
AL
IG
N M
EN
T:
T W
Y A7
AL
IG
N M
EN
T:
T W
Y A
ALIGNMENT: RWY 13-31
ALIGNMENT: TWY A
SL-1
SL-2
SL-3
SL-4
SL-5
SL-6 SL-7
SL-8
SL-9
SL-10
SL-11
SL-12 SL-13 SL-14
SL-15
SL-16
SL-17
SL-18
SL-19
SL-20
SL-21
SL-22
REMOVE CONDUIT AND
CABLING AS REQUIRED TO
CONSTRUCT PROPOSED
TAXIWAY EDGE LIGHTS
EXIST. 2-WAY 2" CONDUIT:
TWY CIRCUIT
RWY CIRCUIT
EXIST. 2-WAY 2" CONDUIT:
TWY CIRCUIT
RWY CIRCUIT
EXIST. 2-WAY 2" CONDUIT:
TWY CIRCUIT
RWY CIRCUIT
EXIST. 2-WAY 2" CONDUIT:
TWY CIRCUIT
RWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
REMOVE CONDUIT AND
CABLING AS REQUIRED TO
CONSTRUCT PROPOSED
TAXIWAY EDGE LIGHTS
REMOVE CONDUIT AND
CABLING AS REQUIRED TO
CONSTRUCT PROPOSED
TAXIWAY EDGE LIGHTS
REMOVE CONDUIT AND
CABLING AS REQUIRED TO
CONSTRUCT PROPOSED
TAXIWAY EDGE LIGHTS
EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. CABLES TO BE REMOVED FROM
EXISTING CONDUIT TO REMAIN.
EXIST. CABLES TO BE REMOVED FROM
EXISTING CONDUIT TO REMAIN.
SALVAGE TAXIWAY EDGE LIGHTS (TWY A)
POINT NUM.
SL-1
SL-2
SL-3
SL-4
SL-5
SL-6
SL-7
SL-8
SL-9
SL-10
SL-11
SL-12
SL-13
SL-14
ALIGNMENT
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
TWY A
STATION
0+65.24
0+99.82
1+38.98
1+78.80
2+92.11
4+39.41
4+93.83
0+60.00
0+99.65
1+38.81
1+78.65
3+28.94
4+21.80
5+11.44
OFFSET
-27.99
-27.89
-27.78
-27.71
-27.50
-27.50
-27.50
38.68
31.83
29.46
30.52
44.82
44.82
44.82
NORTHING
3394506.2412
3394536.4031
3394570.5581
3394605.3112
3394709.4410
3394646.1639
3394619.6855
3394469.2196
3394507.1902
3394542.5585
3394576.8490
3394636.7442
3394591.5559
3394547.9347
EASTING
11034283.3994
11034300.3149
11034319.4698
11034338.9062
11034418.8393
11034571.1422
11034618.6771
11034339.0967
11034352.4042
11034369.3957
11034389.7050
11034439.4382
11034520.5616
11034598.8719
SALVAGE TAXIWAY EDGE LIGHTS (TWY A7)
POINT NUM.
SL-15
SL-16
SL-17
SL-18
SL-19
SL-20
SL-21
SL-22
ALIGNMENT
TWY A7
TWY A7
TWY A7
TWY A7
TWY A7
TWY A7
TWY A7
TWY A7
STATION
0+60.00
0+99.65
1+38.81
1+78.65
0+60.00
0+99.65
1+38.81
1+78.65
OFFSET
-38.68
-31.83
-29.46
-30.52
38.68
31.83
29.46
30.52
NORTHING
3394418.0583
3394449.3602
3394482.4245
3394517.7425
3394380.4100
3394418.3807
3394453.7490
3394488.0395
EASTING
11034430.9432
11034456.2226
11034477.3502
11034495.8149
11034498.5305
11034511.8379
11034528.8295
11034549.1388 x x x x x x x x x
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\
W K
M
TV
-R un w ay E xt en si on
C on st ru ct io n P ha se
C
P S
\C A
D D
\T ax iw ay
E dg e Li gh t P la n
S et
\S he et s\
_C
_S H
T_ E
X A
N D
D E
M O
.d
B
C
D
E
F
G
H
2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
E X
IS
TI
N G
C O
N D
IT
IO
N S
A N
D D
E M
O
LI
TI
O
N
S H
E E
T
SCALE: FEET
KEY MAP
1" = 500'
SHEET 6 SHEET 7
TSA
TSA TSA TSA TSA TSA
TO
FA
TOFA TOFA TOFA TOFA TOFA
TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
ED3 (GRATE)
TOP=930.99'
INV. OUT=908.54'
INV. IN=911.99'
ED2 (MH)
TOP=933.00'
INV. OUT=912.35'
INV. IN=912.81'
" R
CP
" R
CP
TSA TSA TSA TSA TSA
TSA
TSA
TOFA TOFA TOFA TOFA TOFA
TO
FA
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
1x
CO
N
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON
1xCON
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
2x C
O N
1xCON 1xCON
1xCON
1xCON 1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON
1xCON
1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
1xCON 1xCON
1x C
O N
1x C
O N
1x C
O N
1x C
O N
1xC
ON
1xC
ON
1xC
ON
1xC
ON
1xCON 1xCON
1xCON 1xCON
1xCON 1xCON 1xCON 1xCON 1xCON 1xCON
D 26 (DI-7)
RIM = 930.12
18" INV OUT = 926.47
D 27 (DI-7)
RIM = 931.92
18" INV IN = 924.92
24" INV OUT = 924.41
D 28 (DI-7)
RIM = 931.68
24" INV IN = 923.16
24" INV OUT = 918.19
D
AL
IG
N M
EN
T:
T W
Y A6
29+00 30+00 31+00 32+00 33+00
12+00 13+00 14+00 15+00 16+00
0+
1+
2+
3+
3+
ALIGNMENT: TWY A
ALIGNMENT: RWY 13-31
SL-23 SL-24
SL-25 SL-26
SL-27
SL-28
SL-29
SL-30
SL-31
SL-32
SL-33
SL-34
EXIST. 2-WAY 2" CONDUIT:
TWY CIRCUIT
RWY CIRCUIT
EXIST. 2-WAY 2" CONDUIT:
TWY CIRCUIT
RWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
TWY CIRCUIT
REMOVE CONDUIT AND
CABLING AS REQUIRED TO
CONSTRUCT PROPOSED
TAXIWAY EDGE LIGHTS
REMOVE CONDUIT AND
CABLING AS REQUIRED TO
CONSTRUCT PROPOSED
TAXIWAY EDGE LIGHTS
EXIST. 1-WAY 2" CONDUIT:
PAPI CIRCUIT
EXIST. 1-WAY 2" CONDUIT:
PAPI CIRCUIT
EXIST. RWY 31 PAPI
EXIST. LIGHT TO REMAIN EXIST. LIGHT TO REMAIN
EXIST. LIGHT TO REMAIN
EXIST. CABLES TO BE REMOVED FROM
EXISTING CONDUIT TO REMAIN.
SALVAGE TAXIWAY EDGE LIGHTS (TWY A)
POINT NUM.
SL-23
SL-24
SL-25
SL-26
ALIGNMENT
TWY A
TWY A
TWY A
TWY A
STATION
13+39.41
13+93.83
13+21.80
14+11.44
OFFSET
-27.50
-27.50
44.82
44.82
NORTHING
3394208.1992
3394181.7208
3394153.5913
3394109.9700
EASTING
11035357.3909
11035404.9257
11035306.8103
11035385.1206
SALVAGE TAXIWAY EDGE LIGHTS (TWY A6)
POINT NUM.
SL-27
SL-28
SL-29
SL-30
SL-31
SL-32
SL-33
SL-34
ALIGNMENT
TWY A6
TWY A6
TWY A6
TWY A6
TWY A6
TWY A6
TWY A6
TWY A6
STATION
0+60.00
0+99.65
1+38.81
1+78.65
0+60.00
0+99.65
1+38.81
1+78.65
OFFSET
-38.68
-31.83
-29.46
-30.52
38.68
31.83
29.46
30.52
NORTHING
3393980.0936
3394011.3955
3394044.4598
3394079.7778
3393942.4454
3393980.4160
3394015.7843
3394050.0748
EASTING
11035217.1918
11035242.4713
11035263.5988
11035282.0636
11035284.7791
11035298.0866
11035315.0781
11035335.3874 x x x x x x x x x
M ar ch
9, Z:
\P ro je ct s\ bl ue r id ge a irp or t a ut ho rit y\
W K
M
TV
-R un w ay E xt en si on
C on st ru ct io n P ha se
C
P S
\C A
D D
\T ax iw ay
E dg e Li gh t P la n
S et
\S he et s\
_C
_S H
T_ E
X A
N D
D E
M O
.d
B
C
D
E
F
G
H
2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
N O
D
A
TE
R E
V
IS
IO
N
B Y
FINAL DESIGN FOR BIDDING
(NOT FOR CONSTRUCTION)
DATE:
JOB NO:
JUNE 5, 2026
20240541.00.WK
B
LU
E R
ID
G
E R
E G
IO
N
A L
A
IR
P O
R T
TA
X
IW
A
Y E
D G
E L
IG
H
TI
N
G P
R O
JE
(t) 276-957-2291 www.flyblueridge.com
1872 PRATT DRIVE
SUITE 1900
BLACKSBURG, VA 24060
(t) 540-617-0870 www.ardurra.com
E X
IS
TI
N G
C O
N D
IT
IO
N S
A N
D D
E M
O
LI
TI
O
N
S H
E E
T
SCALE: FEET
EXISTING CONDITIONS & DEMOLITION NOTES:
1. PRIOR TO BEGINNING CONSTRUCTION THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING THAT ALL REQUIRED PERMITS AND APPROVALS HAVE BEEN OBTAINED FROM ALL REGULATORY AUTHORITIES AND SHALL BE THOROUGHLY FAMILIAR WITH CONDITIONS OF SAID PERMITS AND INSPECTION REQUIREMENTS.
2. CONTRACTOR SHALL VERIFY EXISTING CONDITIONS AND REPORT ANY DISCREPANCIES TO THE ENGINEER
PRIOR TO CONSTRUCTION.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD LOCATING ANY WIRING AND UTILITIES THAT MAY PASS THROUGH THE CONSTRUCTION AREA. SHOULD ANY ACTIVE WIRING BE CUT BY EXCAVATION, SUCH SHALL BE PROMPTLY REPAIRED (IN A MANNER APPROVED BY THE ENGINEER AND THE OWNER) AND LEFT IN OPERATING CONDITION AT THE CONTRACTOR'S EXPENSE. THE LOCATIONS OF EXISTING UNDERGROUND UTILITIES IF SHOWN ARE APPROXIMATE ONLY AND HAVE NOT BEEN INDEPENDENTLY VERIFIED BY THE OWNER OR ITS REPRESENTATIVE. THE CONTRACTOR SHALL DETERMINE THE EXACT LOCATION OF ALL EXISTING UTILITIES BEFORE COMMENCING WORK, AND AGREES TO BE FULLY RESPONSIBLE FOR ANY AND ALL DAMAGES TO THE UNDERGROUND UTILITIES AND FACILITIES. ALL UTILITIES AND FACILITIES ARE NOT NECESSARILY SHOWN.
HAND DIGGING TO PROTECT UTILITIES FROM DAMAGE SHOULD BE ANTICIPATED.
4. EXISTING FEATURES NOT SHOWN TO BE REMOVED SHALL BE PROTECTED BY THE CONTRACTOR. ANY DAMAGE SHALL BE REPAIRED AT THE CONTRACTOR'S EXPENSE. ANY UTILITIES OR FACILITIES DAMAGED DURING THE PROJECT BY THE CONTRACTOR'S PERSONNEL OR EQUIPMENT SHALL BE PROMPTLY REPAIRED AT THE
CONTRACTOR'S EXPENSE.
5. CONTRACTOR SHALL REMOVE AND DISPOSE ALL ITEMS SHOWN FOR DEMOLITION AND REMOVAL IN A SAFE AND LEGAL MANNER. CONSTRUCTION DEBRIS AND OTHER WASTE MATERIAL SHALL BE DISPOSED OF OFF-SITE BY THE CONTRACTOR IN ACCORDANCE WITH APPLICABLE REGULATORY AGENCY REQUIREMENTS. DISPOSAL
COSTS ARE INCIDENTAL TO PAYMENT FOR THE ITEM BEING REMOVED.
6. EXISTING AIRFIELD LIGHTS INDICATED FOR REMOVAL AND RELOCATION SHALL BE SALVAGED IN A MANNER THAT WILL ALLOW REUSE OF THE LIGHTING FIXTURE, BASE CAN, AND PRE-CAST CONCRETE APRON.
7. COUNTERPOISE WIRING FOR EXISTING AIRFIELD LIGHTING FIXTURES, SIGNS, JUNCTIONS, AND CABLING WHICH IS NOT BEING RELOCATED, SHALL BE PROTECTED AND REMAIN FUNCTIONAL UNTIL NEW COUNTERPOISE, GROUND RODS, AND THERMOWELD CONNECTIONS ARE MADE.
8. CONTRACTOR TO MAINTAIN FUNCTION OF ENTIRE EXISTING RUNWAY AND PAPI LIGHTING CIRCUITS THROUGHOUT CONSTRUCTION. IN ADDITION, CONTRACTOR TO MAINTAIN FUNCTION OF TAXIWAY LIGHTING CIRCUIT FROM PARALLEL TAXIWAY A STATION 14+50 TO THE RUNWAY 31 THRESHOLD. THIS MAY REQUIRE THE PLACEMENT OF TEMPORARY JUMPER CABLES WHILE SECTIONS OF EXISTING CONDUIT AND CABLING ARE
BEING REMOVED AND RELOCATED.
KEY MAP
1" = 500'
SHEET 6 SHEET 7
TS
A
TS
A
TSA
TSA
TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA
TO
FA
TO
FA
TO
FA
TOFA
TOFA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
TS
A
TSA
TSA TSA TSA TSA TSA
TO
FA
TOFA TOFA TOFA TOFA TOFA
TS
A
TSA
TSA
TSA
TSATO
FA
TO
FA
D 22 (DI-7)
RIM = 938.64
18" INV IN = 934.44
18" INV OUT = 934.32
D 21 (DI-7)
RIM = 941.37
18" INV OUT = 937.23
19+00 20+00 21+00 22+00 23+00 24+00
0+
1+
2+
3+00 4+00 5+00 6+00 7+00
0+
1+
2+
3+
3+
RSARSARS…