This is a Request for Qualifications (RFQ) document issued by Johnson County Wastewater (JCW) in Kansas for a Construction Manager at Risk (CMAR) engagement on the Middle Basin Wastewater Digester & Solids Improvement Project (IMB1-C040). JCW seeks SOQs from qualified CMAR firms or teams to supplement the Design Engineer with pre-construction services and cost modeling during the design phase, with the objective of developing a Guaranteed Maximum Price (GMP) anticipated to be finalized at approximately 90% design completion. The project will follow a two-phase format in which Phase 1 involves pre-construction services and GMP negotiation, with Phase 2 consisting of construction execution contingent upon BOCC approval and favorable GMP terms. The RFQ outlines that multiple GMPs may be permitted if mutually agreeable and beneficial to the project schedule. If a satisfactory GMP cannot be negotiated, JCW reserves the right to discontinue the CMAR relationship, complete design to 100%, and proceed with a separate hard-bid procurement process.
The RFQ document does not explicitly disclose pricing terms, set-asides, incumbent information, or specific funding amounts and sources in the available content. The procurement structure indicates that qualified CMAR firms will be evaluated based on their ability to collaborate effectively with JCW and the Design Engineer during the pre-construction phase while maintaining cost control and schedule adherence. The document emphasizes the importance of the CMAR's role in developing a defensible cost model that serves as the foundation for GMP negotiations, with the understanding that project progression beyond Phase 1 is contingent upon achieving financial and operational alignment among all parties.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS (RFQ)
FOR
CONSTRUCTION MANGER AT RISK (CMAR) –
MIDDLE BASIN WASTEWATER DIGESTER AND
SOLIDS IMPROVEMENT PROJECT (IMB1-C040)
RFQ NUMBER: 2026-043
ISSUE DATE: NOVEMBER 12, 2026
OPEN DATE & TIME: DECMEBER 18, 2026 2:00 PM
Purchasing Administrator: Nicole Averell, CPPO, CPPB
Contact Information: nicole.averell@jocogov.org 913-715-0595
RFQ NO. 2026-043
CONSTRUCTION MANGER AT RISK (CMAR) – MIDDLE BASIN WASTEWATER DIGESTER AND SOLIDS IMPROVEMENT PROJECT
Table of Contents
1. TENTATIVE TIMELINE
2. INTRODUCTION
2.1. BACKGROUND
2.2. PROJECT DESCRIPTION
2.3. PROJECT SCHEDULE
2.4. DOCUMENTS PROVIDED WITH THE RFQ
2.5. THE COUNTY WILL PROVIDE TO FINALISTS
3. QUESTIONS
4. NON-MANDATORY PRE-SELECTION CONFERENCE
5. SCOPE OF SERVICES
5.1. PHASE 1 PRE-CONSTRUCTION PHASE AND PREPARATION OF GUARANTEED MAXIMUM
PRICE……………………………………………………………………………………………………………….8
5.2. PHASE 2 CONSTRUCTION PHASE
6. CONTRACT TERM
7. QUALIFICATIONS
7.1. PAST PROJECT EXPERIENCE
7.2. BONDING CAPACITY
7.3. LICENSING
7.4. INSURANCE
8. EVALUATION PROCESS
9. STANDARD TERMS AND CONDITIONS
9.1 TERMINOLOGY/DEFINITIONS
9.2 OPEN COMPETITION
9.3 PREPARATION OF SUBMITTAL
9.4 SUBMISSION OF STATEMENT OF QUALIFICATIONS
9.5 REQUEST FOR QUALIFICATONS OPENING
9.6 EVALUATION/AWARD
9.7 DELIVERY
9.8 INSPECTION AND ACCEPTANCE
9.9 WARRANTY
9.10 CONFLICT OF INTEREST
9.11 COMMUNICATIONS AND NOTICES
9.12 AMERICANS WITH DISABILITIES ACT
9.13 GOVERNING LAW AND VENUE
9.14 HOLD HARMLESS
9.15 TITLES
9.16 RIGHT TO EXAMINE AND AUDIT RECORDS
9.17 HIPAA COMPLIANCE
9.18 TAX CLEARANCE FOR TAXES OWED TO LOCAL GOVERNMENTS
9.19 TIME LIMIT TO SUBMIT SUPPORTING DOCUMENTS
9.20 ADDITIONAL SERVICES
9.21 NEGOTIATIONS
9.22 TRAVEL EXPENSES
9.23 PUBLICITY CLAUSE
9.24 OWNERSHIP
9.25 OBJECTIONS
9.26 SAM (System of Award Management)
9.27 LICENSES AND PERMITS
9.28 CODES AND REGULATIONS
9.29 PERFORMANCE AND STATUTORY BONDS
9.30 TARIFFS
9.31 MINIMUM CYBER SECURITY STANDARDS
9.32 THIRD-PARTY SECURITY AUDITS
9.33 DIGITAL ACCESSIBILITY
9.34 ARTIFICIAL INTELLIGENCE
10 SPECIAL CONDITIONS
10.1 INSURANCE
11 INSTRUCTIONS FOR RESPONDING TO RFQ
11.1 LETTER OF TRANSMITTAL
11.2 TABLE OF CONTENTS
11.3 CONSTRUCTION MANAGER PROFILE
11.4 ILLUSTRATIVE WORK
11.5 PROJECT MANAGEMENT AND TEAMING APPROACH
ATTACHMENT A - INSURANCE REQUIREMENTS…………………………….……………………………….24
1. TENTATIVE TIMELINE
Issue RFQ 11/12/2026
Virtual Non-Mandatory Pre-Selection Conference 12/2/2026 at 1:00 PM
RFQ Clarification Deadline 12/8/2026 at 2:00 PM
SOQ Submission Deadline 12/18/2026 at 2:00 PM
Issue RFP – Shortlisted Firms 1/15/2027
Confidential Meetings(s) and Site Visits Week of 2/1/2027
Proposal Clarification Deadline 2/18/2027 at 2:00 PM
Proposal Deadline 2/26/2027 at 2:00 PM
Interviews March 30, 2027 & March 31, 2027
Contract Negotiations 4/5/2027 - 4/30/2027
Board Approval 4/30/2027 - 6/10/2027
Notice to Proceed July 2027
2. INTRODUCTION
Johnson County is a local government organized on September 7, 1857 and located in the Kansas City metropolitan area of northeast Kansas. The County serves a diverse and expanding population through four county agencies and 26 county departments and offices. The County has more than 4,000 public servants serving in more than 52 offices located through-out the County and dedicated to helping Johnson County’s more than 600,000 residents remain part of a safe and vibrant community. Johnson County is governed by a seven-member, non-partisan, elected Board of County Commissioners (BOCC). The BOCC appoints a County Manager. Johnson County also has both an elected Sheriff and District Attorney.
In addition to the traditional governmental operations of public health and safety, codes regulations, and tax collection, Johnson County operates a major intermodal transportation system, two (2) airports, railroad and business park, fourteen libraries, four multi-service centers, a parks and recreation district, mental health and developmental support centers, a community corrections program, and a countywide wastewater system. More information on Johnson County can be found on our public website (www.jocogov.org), as this site provides information on the organization and a complete directory of services provided as well as the wide range of public resources available.
Johnson County Wastewater (JCW) is part of County government. JCW is responsible for providing sanitary sewer services for more than 500,000 people in the County. To meet these commitments, JCW must continually manage, maintain, and improve a variety of infrastructure assets, including six major wastewater treatment facilities (WWTFs), 32 pump stations, 2,300 miles of gravity sewer lines, 58,000 manholes, 23 miles of low-pressure sewers and 42 miles of force mains. JCW has made great strides proactively maintaining and upgrading these assets. JCW has planned for and is dedicated to large infrastructure projects that are in alignment with its mission statement – to protect our environment, serve our customers, and enhance our communities.
This is a Construction Management at Risk (CMAR) services procurement. Johnson County Wastewater (JCW) is seeking a statement of qualifications (SOQ) from firms to provide CMAR services for the Middle Basin Wastewater Treatment Facility (WWTF) Digester & Solids Improvements (“Project”), Contract No. IMB1-C040. This Request for Qualifications (RFQ) is the first phase of a three-phase procurement process for selection of a Construction Manager. Phase I shall be the solicitation of an SOQ and prequalifying a shortlist of firms to advance to Phase II.
Phase II shall be the solicitation of a Request for Proposal (RFP) for a more in-depth response from Phase I shortlisted firms, and Phase III shall include an interview with each firm to present their proposed team members, qualifications, project plan, and answer questions.
2.1. BACKGROUND
The Middle Basin WWTF is located at 10001 College Blvd in Overland Park, Kansas and was built in the early 1980s. The WWTF is rated for 14.5 million gallons per day average day flow (ADF) with an actual ADF of 11.4 MGD over the past two years. Middle Basin is a biological nutrient removal (BNR) facility with a solids treatment train consisting of primary treatment, gravity thickener, fermenters, waste activated sludge (WAS) to rotary drum thickeners, Fats, Oils, and Grease (FOG) waste receiving station, anaerobic digestion, belt filter press dewatering, and truck load out conveyor. The BNR facility also has inDENSE in two of the four BNR trains for sludge densification and the waste sludge for these trains is returned to the head of the plant where it settles out in the primaries. The solids treatment train must remain in service throughout construction. Design and construction plans need to maintain operations while performing construction.
In 2022, JCW commissioned a consulting team to develop an overall Facility Plan for the Middle Basin WWTF with recommended improvements to current and future objectives. A supplemental Solids Treatment Conceptual Facility Plan (Solids FP) was developed in 2025 to further detail solids processing improvements at the facility. Influent flows and loads are not expected to increase so the focus is on significant renewal and replacement needs surrounding the solids treatment systems while maintaining operation of the existing system.
Both facility plans are available through IonWave.
The primary scope items for the improvements to the Middle Basin WWTF Digester & Solids Improvements Project are grouped into the following items which include, but are not limited to the following:
http://www.jocogov.org/
• Digester Rehabilitation and Improvements (including the conversion of a secondary digester to a primary digester, a new Digested Sludge Storage Tank (DSST), and rehabilitation of the existing digesters, digester building, and associated equipment)
• New Dewatering Building and associated equipment
There are currently three primary digesters and one secondary digester. This system is at capacity and providing additional digester capacity is a high priority to provide redundancy and allow for the ability to maintain the associated digestion equipment. FOG received from haulers is pumped directly into the primary digesters and this service needs to continue throughout construction. In addition, many of the equipment associated with the digester complex are at the end of their useful life and the Digester Building (Building #4) will need to be brought up to code.
The existing Solids Processing Building (Building #2) is in poor condition with recurring structural failures.
The dewatering equipment and associated equipment in this building are at the end of their useful lives. The Solids FP recommended a new Solids Processing Building to improve system reliability.
The initial project scope is defined as line items in table below from the Solids FP with priority medium and higher. Potential future scope could include additional items with medium-low and lower priority as budget and schedule allow or if any of these items become higher priority between the issuance of this RFQ and the completion of design.
1. Initial scope items (Priority High, Medium-High, Medium)
Project Scope Item Description Priority Group Rank
Anaerobic Digester Rehab Digester gas piping to flares High 1 New DSST and Support Bldg. New road to FOG Building High 2
New DSST and Support Bldg. Demolition of gas membrane pad, DSST Tank and Support Building, associated piping and equipment, boiler relocation
High 3
New DSST and Support Bldg. Converting Digester No. 2 to a primary digester and Digester No. 2 cover replacement and cleaning
High 4
Anaerobic Digester Rehab All digester equipment – pumps and heat exchangers
High 5
Anaerobic Digester Rehab Digester gas safety equipment High 6 Anaerobic Digester Rehab Digester No, 1 and 3 cover replacement and cleaning High 7
Anaerobic Digester Rehab Replace piping in Building No. 4 Medium- High
Anaerobic Digester Rehab Dedicated digester feed lines for TPS, Scum, and TWAS
Medium- High
Anaerobic Digester Rehab Digester No. 4 cover replacement and cleaning
Medium- High
New DSST and support Bldg. Truck staging area for dewatered cake and fog hauling
Medium 11
New Dewatering Building Demolition of CHP’s Medium 12 New Dewatering Building Demolition of Building 10 and temporary electrical power Medium 13
New Dewatering Building Dewatering building including equipment, piping, and access roads. (Does not include centrate EQ tank and pump station)
Medium 14
Centrate EQ Centrate EQ tank and pump station Medium 15 Building No. 2 Modifications Demolition of BFP’s Medium 16 Primary Sludge Handling Digester feed pump replacement Medium 17
Note: refer to the 2025 Solids FP for more details on each scope item.
2. The Design Engineer may consider potential scope items (Priority Medium-Low, Low) from the Solids FP based on risk, available funds, and schedule:
a) Primary Sludge Handling Modifications
b) New Waste Gas Burners
c) FOG Receiving Equipment
d) Ferric Chloride System
e) Biogas Utilization
Key Success Factors for the Project are:
1. Coordination with Operations staff and maintaining plant operations during construction.
2. Completing the project on schedule to minimize impact to operations and minimize inflation risks
3. Completing the original project scope under budget
2.2. PROJECT DESCRIPTION
JCW is seeking SOQs from qualified CMAR firms (or CMAR teams) to supplement JCW’s Design Engineer with assistance during design phase engineering services and develop the cost model that becomes the basis for the Guaranteed Maximum Price (GMP). The Construction Manager will follow a two-phase format. In Phase 1, the Construction Manager will be responsible for working with JCW and the Design Engineer to provide pre-construction services and reach an agreeable GMP anticipated to be finalized around 90% design. Multiple GMPs may be allowed assuming they are mutually agreeable, that schedule allows, and that benefit the project.
Depending on the cost and the progress of the project, if the GMP is favorable then JCW will seek BOCC approval to amend the agreement and continue into the Phase 2 construction phase with the Construction Manager. If a satisfactory GMP cannot be reached, JCW may elect to off-ramp the project and continue design services to 100% design and issue a separate hard-bid for the project.
The estimated total project cost, including engineering, easements, land acquisitions, and construction is $150 million, which includes escalation to midpoint of construction in 2031.
2.3. PROJECT SCHEDULE
The selection of the Design Engineer is currently underway and is anticipated to be complete prior to interviews for a Construction Management firm. It is JCW’s intent to have the Construction Manager authorized close to the start of design to have early involvement in alternative selections, cost models, and maintenance of operation plans. The following overall project milestones have been established:
Preliminary Design Commences March 2027 CMAR Notice to Proceed July 2027 Final Design and GMP Development June 2027 – June 2029 Begin Construction June 2029 Substantial Completion May 2033 Final Completion June 2033
The BOCC approval process requires sixty days assuming that all the information, data, costs, contracts, etc. are ready at the start of this process. The Construction Manger shall take this duration into account for any schedule planning.
2.4. DOCUMENTS PROVIDED WITH THE RFQ
The following documents are provided with the RFQ for the benefit of the firms in preparing their SOQ and determining if this is a project worth pursuing. These documents will be made available in IonWave.
- Facility Plan for the Middle Basin WWTF
- Solids Treatment Conceptual Facility Plan
- Resolution WD 26-035 – Selection Process for CMAR
2.5. THE COUNTY WILL PROVIDE TO FINALISTS
The Evaluation Process is described in Section 8. The finalist firms will be determined by the rank and will be “short listed” for the RFP phase selection process. For all firms that are shortlisted after the submission of SOQs, the County will provide the following:
• A draft contract based on the County’s standard Agreement and General Conditions based on the Engineers Joint Contract Documents Committee (EJCDC) No. 1910-8 (1996 Ed.) including JCW’s standard Supplementary Conditions and Additional Supplementary Conditions that modify the general conditions.
• A draft scope of services for Pre-Construction Phase Services
The finalists will also be provided an opportunity to participate in a confidential meeting with representatives from the County to discuss a wide range of project related topics that may include, but not be limited to, project cost/schedule drivers, construction sequence(s), potential site layouts, maintenance of plant operations required, and community engagement strategies. At the confidential meeting, finalists will have an opportunity to ask questions, present ideas on project approach, and solicit feedback from County representatives. Items discussed in the confidential meeting will not be shared with other firms advancing to the second phase of the selection process to protect proprietary information and proposed solutions.
3. QUESTIONS
To ensure open and fair competition for all potential respondents, ALL questions and contact concerning this RFQ shall be directed to the Johnson County Purchasing Administrator.
We encourage you to submit questions up until the cutoff date and time by selecting ‘Ask Question’ on the solicitation event at: https://jocogov.ionwave.net
Respondent should make NO CONTACT, either written or verbal, with the Board of County Commissioners, Johnson County legal counsel, department personnel, consultants, or other county boards beginning with the issuance of this document through approval of award.
4. NON-MANDATORY PRE-SELECTION CONFERENCE
A non-mandatory Pre-Selection Conference will be held on December 2, 2026, at 1:00 p.m. CT via Zoom Video Conferencing. This Conference is optional and not mandatory for responding to this RFQ. The purpose of this meeting is to explain the solicitation process and go over general information for the Project. Access is available here:
Join Zoom Meeting:
https://us02web.zoom.us/j/81328316557?pwd=8rKbqALZMcB4JgcgitX1gNz031LpTz.1
Meeting ID: 813 2831 6557 Passcode: 658629
5. SCOPE OF SERVICES
5.1. PHASE 1 PRE-CONSTRUCTION PHASE AND PREPARATION OF GUARANTEED
MAXIMUM PRICE
The Construction Manager shall consult with the County and the JCW’s Design Engineer throughout the development of pre-design, final design, and a Guaranteed Maximum Price (GMP). The expectation is that collaboration with a Construction Manager throughout the design process, starting at preliminary design, will facilitate a construction solution that balances constructability, construction sequence, impacts to surrounding community, operability, quality, budget, and schedule. The general scope of services anticipated for the Pre- Construction Phase includes:
• Develop the Project Execution Plan, including schedule.
https://jocogov.ionwave.net/ https://us02web.zoom.us/j/81328316557?pwd=8rKbqALZMcB4JgcgitX1gNz031LpTz.1
• Evaluate site storage and staging needs, determine if any off-site space or facilities are required, and if so, develop a plan to secure them.
• Develop a Project Risk Register and Risk Mitigation Plan.
• Prepare and maintain a Project Cost Model and submit detailed cost estimates as the design is advanced.
Maintain a list of potential value engineering items along with their impact to the Project Cost Model.
• Collaboratively determine with the County what level of design is appropriate prior to the development of GMP(s) (Phase 2 Construction Costs) and the level of discipline for each design deliverable to facilitate meeting the project schedule. County preference is 90% Design for GMP Development.
• Evaluate and coordinate appropriate contingencies and allowances. All or a majority portion of savings from value engineering, contingencies, and allowances under the GMP may return to JCW and will be further defined in Phase 1 services.
• Collaborate, coordinate, and lead efforts with JCW and Design Engineer on constructability plans, maintenance of plant operations plans, sequencing of work.
• Early Work Package(s) and Ordering of long lead equipment.
• Perform value engineering and constructability reviews on pre-design and design development submittals in conjunction with the County and the Design Engineer.
• Maintain a list of design decisions to track key decisions made throughout design that affect cost and updates to the scope of work.
• Submit and negotiate GMP proposals for performance of Construction Phases services (including possible early-out equipment and/or construction packages).
• JCW may allow Construction Manager to self-perform certain construction activities, however, Construction Manager shall submit a bid proposal under the same conditions as all other competing firms for bid packages.
• Coordinate work with JCW and Design Engineer on permitting requirements and initiate certain permitting activities.
• Participate, as needed, in JCW’s public outreach efforts to better understand public concerns and aid in determining solutions for mitigation, when feasible.
The full preconstruction scope of services will be included with the RFP.
5.2. PHASE 2 CONSTRUCTION PHASE
It is Johnson County’s intent to contract with the top ranked finalist for Pre-Construction Services; however, at the conclusion of this phase, the County will evaluate service provided to date to determine whether or not to extend the contract for the Construction Phase. If the County and Construction Manager reach agreement on a GMP and schedule for the Work, County staff will present the GMP Proposal to the Johnson County BOCC for approval. Should the County choose not to continue with the firm providing the Pre-Construction Services, the project delivery options will be reevaluated, including the possibility of bidding the project or issuing another RFQ. The general scope of services anticipated for the Construction Phase includes:
• Secure necessary permits.
• Procure equipment, materials, and subcontractors.
• Construct the Project.
• Communicate progress to JCW and the Design Engineer
• Provide updates for Public Outreach as necessary
• Manage project schedule.
• Mitigate project risks.
• Provide equipment O&M Manuals and training
• Conduct startup, commissioning, and performance testing.
• Provide warranty coverage.
The full phase 2 scope of services will be included with the RFP.
6. CONTRACT TERM
The Contract resulting from this solicitation process shall be effective once duly executed and will remain in full force and effect until the Project is completed and final payment has been made by the County to the Contractor.
7. QUALIFICATIONS
The County expects that each vendor will perform all contracted services in a good, thorough and professional manner consistent with industry and professional standards for similar services.
To be deemed a responsible respondent the following criteria shall be assessed:
• Demonstrate the means and ability to satisfactorily perform the contract, with relevant experience, facilities, reputation, and financial resources.
• Submit a response that aligns with all specifications and requirements outlined in the solicitation.
• Show capacity to meet required delivery schedules and possess adequate financial means to complete the contract successfully.
• Provide a history of satisfactory performance on previous contracts, indicating reliability and competency.
• Be a legally registered entity authorized to conduct business in the State of Kansas and supply proof of registration, as well as all necessary licenses or certifications relevant to the contract.
• Ensure all employees engaged in performing the contract hold valid licenses issued by the appropriate authorities.
• Not listed on the Excluded Parties List System on the SAM.gov platform.
• Have no suspensions or revocations, of any state, county, or county-issued business, trade, or contracting license associated with the firm or its directly owning entities or individuals.
• Satisfy any additional requirements stipulated in the specific solicitation request.
Minimum Selection Criteria: Respondents submitting a SOQ must meet the following minimum criteria. Firms unable to meet the minimum criteria will be ineligible for this RFQ:
7.1. PAST PROJECT EXPERIENCE
Provide past project experience with similar projects using traditional, CMAR, or progressive design build collaborative delivery methods demonstrating the firm’s ability to construct complex wastewater treatment facilities, emphasizing experiences with solids process and existing plant operations had to be maintained.
Include references from design professionals and owners, a description of the firm’s project management approach, and financial statements. Show that the team met budgets, deadlines, and overall schedules.
7.2. BONDING CAPACITY
Ability to secure required performance and payment bonds with a qualified surety company up to a project cost of $150,000,000, demonstrated through a letter from the Surety stating the bonding capacity of the firm and rating of Surety. Firms submitting a SOQ shall be capable of providing a public works bond in accordance with K.S.A. 60-1111.
7.3. LICENSING
Pursuant to Sections 17-7301 through 17-7308, Kansas Statutes Annotated, if the selected CMAR firm is a corporation organized outside the State of Kansas, it will, in most instances, be necessary to qualify with the Secretary of State of Kansas to do business within the State. The determination should be made by the Construction Manger with the advice of counsel. Pursuant to Sections 79-1008 through 79-1014, Kansas Statutes Annotated, nonresident individuals or partnerships and corporations organized outside the State of Kansas which are not already registered with the Secretary of State are required to register with the Director of Revenue, to file a Bond to assure payment of taxes, and to pay a fee of $10.00 for each contract or subcontract which exceeds $1,000.00. If selected for the project, the Construction Manager will be required to be a licensed contractor in Johnson County.
7.4. INSURANCE
Provide evidence that the Respondent is insurable at least to the limits and coverages identified in Section 10.1.
7.5. CONFLICTS OF INTEREST
A potential conflict of interest exists if the Respondent, or any team member, has any interest that would conflict, or has the appearance of conflicting, in any manner or degree with the performance of work on the project.
7.6. SAFETY RECORD
The firm must have achieved an experience modification rate (EMR) of not greater than 1.0 for the current and past two years. Include days-away-from-work injury incident rate as well as EMR for the CMAR firm and key subcontractors.
7.7. SAFETY PROGRAM/PLAN
Each firm shall be responsible for their own safety and have an established safety program including hazard prevention, training, emergency response protocols, personal protective equipment (PPE), etc. Provide a copy or summary of the firm’s safety program for information.
8. EVALUATION PROCESS
The CMAR solicitation is a three-stage qualifications-based selection process. All responsive responses will be evaluated by an Evaluation Committee usually composed of County personnel and/or other governmental agencies.
Members of the Evaluation Committee will independently review and score each submittal based on the criteria listed herein.
The first step in the process consists of firms submitting a statement of qualifications for this RFQ. Numerical scores from the Evaluation Committee will be tabulated and ranked by the Purchasing Administrator. The finalist firms will be determined by this rank and will be “short listed” for the second phase of the CMAR solicitation process – RFP.
Those firms shortlisted to participate in the second phase of the CMAR solicitation process will be provided an RFP.
The firm’s Cost Proposal is required of all finalists and is due with the proposal.
Interviews will be conducted with each firm who submitted a proposal as part of the third phase of theCMAR solicitation process. After the interviews, each Evaluation Committee member will independently evaluate the finalist firms’ proposal and interview based on the total points and criteria listed herein. These numerical scores will be tabulated and ranked by the Purchasing Administrator in the same manner as the first phase. The Evaluation Committee will select and/or recommend one (1) firm to provide the County the required CMAR services. Staff will then endeavor to negotiate a contract with the successful firm. In the event a mutually agreeable contract cannot be negotiated with said firm, staff will then enter into contract negotiations with the next highest ranked firm, and so on until a mutually agreeable contract can be negotiated.
SAMPLE SCORING GUIDELINES
35 Point 30 Point 25 Point 20 Point 15 Point 10 Point 5 Point Question Question Question Question Question Question Question Outstanding 29-35 25-30 21-25 17-20 13-15 9-10 5 Exceeds Acceptable 22-28 19-24 16-20 13-16 10-12 7-8 4 Acceptable 15-21 13-18 11-15 9-12 6-9 5-6 2-3 Marginal 0-14 0-12 0-10 0-8 0-5 0-4 0-1
STATEMENT OF QUALIFICATIONS
Construction Manager Profile: 25 Points
Consider organization of CMAR firm proposed, capabilities, experience, financial capacity, support structure, safety record, and the Respondent’s ability to effectively complete this project according to the project success factors.
Illustrative Work: 40 Points
Consider completed projects referenced by the Respondents in the submittal. Consider the Respondent’s ability to complete a project on schedule and on budget while building high quality assets including startup and commissioning. Are the referenced projects analogous to the proposed project: project costs, region, procurement
Project Management and Teaming Approach : 25 Points
Evaluate Respondent’s overall management approach with a focus on differentiators between each Respondent’s approach. Does the firm have sufficient depth to function without one or more Key personnel.
How likely is the firm to complete a timely and high-quality project. Compare the quality of the firm’s Key Personnel. Does the firm have the necessary staff to complete all phases of the project?
Overall Responsiveness to the RFQ. 10 Points
Consider whether all requested information was furnished by the firm in the format required by RFQ.
PROPOSAL & INTERVIEW
Project Understanding and Approach: 30 Points
Key Team Members and Proposed Utilization: 30 Points
Interview: 30 Points
Cost: 10 Points
(Will only be required of finalists and is due at the time of the interview)
9. STANDARD TERMS AND CONDITIONS
9.1 TERMINOLOGY/DEFINITIONS
Whenever the following words and expressions appear in this solicitation document or any amendment hereto, the definition or meaning described below shall apply.
Agency and/or Department mean(s) the statutory unit of County government in Johnson County, Kansas for which the equipment, supplies, and/or services are being purchased by the Financial Management and Administration, Purchasing Division.
Amendment/Addendum means a written, official modification to a solicitation document or to a contract.
Attachment applies to all forms which are included with a solicitation document to incorporate any informational data or requirements related to the performance requirement.
CMAR means the collaborative project delivery method where the Construction Manager will provide preconstruction services and later deliver the project within a Guaranteed Maximum Price (GMP).
Construction Manager means the entity that will enter into the CMAR Contract with the Owner and that will be the single point of accountability to the Owner for delivery of the services and Project.
RFQ Opening Date and Time and similar expressions mean the exact deadline required by the solicitation document for the electronic submission of the Request for Qualifications by the Financial Management and Administration, Purchasing Division.
Respondent mean(s) the person, firm, or organization that responds to a solicitation document by submitting a proposal with price to provide the equipment, supplies, and/or services as required in the solicitation document.
Board of County Commissioners or BOCC means the governing body of Johnson County, Kansas.
Purchasing Administrator means the procurement staff member of the Financial Management and Administration, Purchasing Division. The Contact Person as referenced herein is usually the Purchasing Administrator.
Contract means a legal and binding agreement between two or more competent parties for the purchase of equipment, supplies, and/or services.
Contractor means a person, firm, or organization who is a successful respondent as a result of a proposal and who enters into a contract.
County means Johnson County, Kansas.
Exhibit applies to forms which are included with a proposal for the respondent to complete and return with the electronic submission prior to the specified opening date and time.
Key Firms—Firms fulfilling the key roles that must be identified in Respondent’s SOQ and are committed to work on the Project if Respondent is selected as the Construction Manager.
Key Personnel—The individuals, employed by the Respondent who would fill certain key roles in delivery of the Project and related services, including the positions described in the RFQ.
Request for Qualifications (RFQ) means the solicitation document issued by the Financial Management and Administration, Purchasing Division, to potential respondents for the purchase of equipment, supplies, and/or services as described in the document. This definition includes these Terms and Conditions as well as all Pricing Pages, Exhibits, Attachments, and Amendments thereto.
Request for Proposal (RFP) means the solicitation document issued by the Financial Management and Administration, Purchasing Division, to potential respondents for the purchase of equipment, supplies, and/or services as described in the document. This definition includes these Terms and Conditions as well as all Exhibits, Attachments, and Amendments thereto.
Statement of Qualifications (SOQ) A response to this RFQ, submitted by a Respondent for the Project.
May means that a certain feature, component, or action is permissible, but not required.
Must means that a certain feature, component, or action is a mandatory condition. Failure to provide or comply will result in a proposal being considered non-responsive and not evaluated any further.
Shall has the same meaning as the word must and is an obligation to the condition.
Should means that a certain feature, component and/or action is desirable and not mandatory.
9.2 OPEN COMPETITION
It shall be the respondent’s responsibility to ask questions, request changes or clarification, or otherwise advise the Financial Management and Administration, Purchasing Division, in writing, if any language, specifications, or requirements of a RFQ appear to be ambiguous, contradictory, and/or arbitrary, or appear to inadvertently restrict or limit the requirements stated in the proposal to a single source. Any and all communication from respondents regarding specifications, requirement, competitive RFQ process, etc., must be directed to the purchasing administrator from the Financial Management and Administration, Purchasing Division, as indicated on the first page of the RFQ. Such communication should be received at least seven (7) calendar days prior to the official RFQ opening date.
Every attempt shall be made to ensure that the respondent receives an adequate and prompt response. However, in order to maintain a fair and equitable RFQ process, all respondents will be advised, via the issuance of an amendment to the RFQ, of any relevant or pertinent information related to the procurement. Therefore, respondents are advised that unless specified elsewhere in the RFQ, any questions received by the Financial Management and Administration, Purchasing Division, less than seven (7) calendar days prior to the RFQ opening date may not be answered.
Respondents are cautioned that the only official position of the County is that position which is stated in writing and issued by the Financial Management and Administration, Purchasing Division, in the RFQ or an amendment thereto. No other means of communication, whether oral or written, shall be construed as a formal or official response or statement from the County.
The Financial Management and Administration, Purchasing Division, monitors all procurement activities to detect any possibility of deliberate restraint of competition, collusion among respondents, price-fixing by respondents, or any other anti-competitive conduct by respondents which appears to violate state and federal antitrust laws. Any suspected violation shall be referred to the Kansas Attorney General’s Office for appropriate action.
The Financial Management and Administration, Purchasing Division, reserves the right to officially modify or cancel a solicitation after issuance. Such a modification shall be identified by an amendment/addendum.
9.3 PREPARATION OF SUBMITTAL
Respondents must examine the entire RFQ carefully. Failure to do so shall be at respondent’s risk.
Unless otherwise specifically stated in the RFQ, all specifications and requirements constitute minimum requirements. All RFQ’s must meet or exceed the stated specifications/requirements.
9.4 SUBMISSION OF STATEMENT OF QUALIFICATIONS
The SOQ submission must be submitted electronically at https://jocogov.ionwave.net by a respondent and must:
(1) be signed electronically by a duly authorized representative of the respondent’s organization; and (2) contain all information required by the RFQ. If there is difficulty submitting an SOQ electronically, contact the purchasing administrator for assistance. Arrangements may be made to receive sealed paper SOQ’s by solicitation close by the Department of Financial Management and Administration, Purchasing Division, Johnson County Administration Building, 111 South Cherry Street, Suite 2400, Olathe, Kansas 66061-3486. You must register as a supplier at https://jocogov.ionwave.net at least two (2) business days prior to the RFQ opening to ensure a successful registration. No other method of submitting SOQ’s will be accepted.
A response may be modified or withdrawn prior to the official opening date and time specified. No respondent may submit more than one response.
9.5 REQUEST FOR QUALIFICATONS OPENING
Virtual RFQ openings are held via Zoom Meeting publicly on the opening date and at the opening time specified on the RFQ document at the link provided below. Respondents may notify the purchasing administrator no less than two (2) business days before the bid opening if they wish to attend the opening in person for accommodation.
Zoom Meeting:
Join Zoom Meeting https://us02web.zoom.us/j/89041147629?pwd=NTihoo5MJmrST5G4tpTUjQ9b5NIdDU.1
Meeting ID: 890 4114 7629 Passcode: 198824
It is the respondent’s responsibility to ensure that the SOQ is submitted electronically by the official opening date and time at https://jocogov.ionwave.net. Late submissions will not be considered regardless of the degree of lateness or the reason related thereto, including causes beyond the control of the respondent.
Unofficial results of the SOQ’s that have been submitted will be available electronically at https://jocogov.ionwave.net within 24 hours of the RFQ opening.
https://jocogov.ionwave.net/ https://jocogov.ionwave.net/ https://us02web.zoom.us/j/89041147629?pwd=NTihoo5MJmrST5G4tpTUjQ9b5NIdDU.1
9.6 EVALUATION/AWARD
When evaluating a response, the County reserves the right to consider relevant information and fact, whether gained from a submittal, from a respondent, from respondent’s references, or from any other source.
All submitted qualification statements and associated documentation shall be subject to the provisions of the Kansas Open Records Act (K.S.A. 45-215 et seq.). The Kansas Open Records Act does permit limited materials to be protected from disclosure. Generally, protected exceptions are financial information submitted as qualification statements and materials privileged under the rules of evidence. These documents should be properly labeled proprietary or confidential. The technical and cost/pricing response documents should not be labeled proprietary, confidential, or in any other manner to restrict dissemination.
The Financial Management and Administration, Purchasing Division, reserves the right to request written clarification of any portion of the respondent’s response in order to verify the intent of the respondent. The respondent is cautioned, however, that respondent’s response shall be subject to acceptance without further clarification.
The Financial Management and Administration, Purchasing Division, reserves the right to award by item, groups of items, or on all or none basis; and reserves the right to reject any or all submittals in part, or in its entirety, to waive any minor technicality or irregularities of submittals received.
Respondents who protest the conditions, specifications or scope of services, or other requirements contained in this solicitation are encouraged to review the County’s Administrative Purchasing Policies and Procedures located at the County’s website at Johnson County Administrative Policy & Procedures.
9.7 DELIVERY
Time is of the essence. Deliveries of equipment, supplies, and/or services must be made no later than the time stated in the contract or within a reasonable period of time, if a specific time is not stated.
If applicable, prior to delivery of equipment, each unit must be completely serviced and lubricated in accordance with factory service specifications. Successful respondent is responsible to furnish any equipment needed for unloading of equipment at the F.O.B. destination point.
9.8 INSPECTION AND ACCEPTANCE
No equipment, supplies, and/or services received by an agency of the County pursuant to a contract shall be deemed accepted until the agency has had reasonable opportunity to inspect said equipment, supplies, and/or services.
All equipment, supplies, and/or services which do not comply with the specifications or requirements or which are otherwise unacceptable or defective may be rejected. In addition, all equipment, supplies, and/or services which are discovered to be defective or which do not conform to any warranty of the contractor upon inspection (or at any later time if the defects contained were not reasonably ascertainable upon the initial inspection) may be rejected.
The County reserves the right to return any such rejected shipment at the contractor’s expense for full credit or replacement and to specify a reasonable date by which replacements must be received.
The County’s right to reject any unacceptable equipment, supplies, and/or services shall not exclude any other legal, equitable or contractual remedies available to the County.
9.9 WARRANTY
The contractor expressly warrants that all equipment, supplies, and/or services in accordance with generally accepted industry standards, practices and principles applicable to the work and shall: (1) conform to each and every specification, drawing, sample or other description which was furnished or adopted by the Financial Management and Administration, Purchasing Division; (2) be fit and sufficient for the purpose expressed in the RFP; (3) be of good materials and workmanship; and (4) be free from defect. The contractor shall replace a defective product at its own cost.
http://www.jocogov.org/sites/default/files/documents/TRE/Administrative_Pol_and_Proc_revised072014.pdf
9.10 CONFLICT OF INTEREST
The contractor hereby covenants that at the time of the submission of the RFQ the contractor has no other contractual relationships which would create any actual or perceived conflict of interest. The contractor further agrees that during the term of this contract neither the contractor nor any of its employees shall acquire any other contractual relationships which create such a conflict.
9.11 COMMUNICATIONS AND NOTICES
Any notice or other communication to the contractor shall be made in writing via email, delivered personally, or by United States mail, postage prepaid, to the address listed in the contractor’s submittal.
9.12 AMERICANS WITH DISABILITIES ACT
In connection with the furnishing of equipment, supplies, and/or services under the contract, the contractor and all subcontractors shall comply with all applicable requirements and provisions of the Americans with Disabilities Act (ADA).
9.13 GOVERNING LAW AND VENUE
All contractual agreements shall be subject to, governed by, and construed according to the laws of the State of Kansas, and the District Court of Johnson County, Kansas shall have jurisdiction over any controversy or claim arising out of, or relating to, the contractual agreements or their performance or interpretation.
9.14 HOLD HARMLESS
The contractor agrees to protect, defend, indemnify and hold the BOCC, its officers, employees and agents free and harmless from and against any and all losses, penalties, damages, settlements, costs, charges, professional fees or other expenses or liabilities of every kind and character arising out of or relating to any and all claims, liens, demands, obligations, actions, proceedings or causes of action of every kind and character in connection with or arising directly or indirectly out of the error, omission, recklessness, negligent act or willful misconduct of the contractor (collectively hereinafter “claims”). Without limiting the generality of the foregoing, any and all such claims, relating to personal injury or of any other tangible or intangible personal or administrative order, rule or regulation, or decree of any court, shall be included in the indemnity hereunder. The contractor further agrees to investigate, handle, respond to, provide defense for and defend any such claims at contractor’s sole expense and agrees to bear all other costs and expenses related thereto, even if such claim is groundless, false or fraudulent.
9.15 TITLES
Titles of paragraphs used herein are for the purpose of facilitating reference only and shall not be construed to infer a contractual construction of language.
9.16 RIGHT TO EXAMINE AND AUDIT RECORDS
The Contractor agrees that the County, or any of its authorized representatives, shall have access to and the right to examine and audit any and all books, documents, papers and records of the Contractor hereunder, or any change order or contract modification thereto, or with compliance with any clauses thereunder. Such records shall include hard copy as well as computer readable data. The Contractor shall require all of its payees including but not limited to, subcontractors, insurance agents or material suppliers to comply with the provisions of this clause by including the requirements hereof in a written agreement between the Contractor and payee. Further, the Contractor agrees to cooperate fully and will cause all related parties and will require all of its payees to cooperate fully in furnishing or making available to the County any and all such books, documents, papers, and records.
9.17 HIPAA COMPLIANCE
The contractor agrees to comply with the Health Insurance Portability and Accountability Act of 1996 (“HIPAA”), the privacy and security regulations promulgated under Title II, Subtitle F, §§ 261-264 of HIPAA, the administrative regulations issued by the Department of Health and Human Services (“DHHS”) as found in 45 C.F.R. Parts 160 through 164 (the “HIPAA or DHHS regulations”), and the Health Information Technology for Economic and Clinical Health Act, Public Law 11-005 (the “HITECH Act”), as such laws and regulations may be amended from time to time, and enter into a Business Associate Contract with the County, as may be required, so as to provide necessary reasonable assurances to the County that the contractor as an Business Associate will comply with the portions of those laws and regulations made applicable to business associates by HIPAA and the HITECH Act.
9.18 TAX CLEARANCE FOR TAXES OWED TO LOCAL GOVERNMENTS
The local governments of Johnson County, KS, City of Kansas City, MO, Jackson County, MO, and the Unified Government of Wyandotte County, KS (collectively the “Local Governments”), have agreed to cooperate with each other to ensure that tax funded contracts are performed by Contractors in compliance with the Tax Laws of the Local Governments. Contactor agrees that the Contractor shall be in compliance with the respective Tax Laws of the Local Governments throughout the term of this contract and any contract renewals and that proof of Contractor’s compliance with the Tax Laws of the Local Governments shall be a condition of award. Upon award of contract and all subsequent renewals with Johnson County in the amount of $150,000.00 or more, contractor must obtain a Tax Clearance Certification. The Tax Clearance Certification must be signed by an authorized official from all four (4) of the “Local Governments” and submitted to the Johnson County Purchasing Department prior to a notice of award (or) contract renewal. The Tax Clearance Certification shall be valid for a period of one year from the date of issuance and shall not be dated more than sixty (60) days prior to any notice of intent to contract by the County.
9.19 TIME LIMIT TO SUBMIT SUPPORTING DOCUMENTS
Within ten (10) calendar days after notification to enter into contract, the successful respondent must furnish the specified insurance and bonds required, if any. If any successful respondent fails to furnish said documents within ten (10) calendar days, the award to that respondent may be withdrawn and awarded to the next acceptable proposal.
9.20 ADDITIONAL SERVICES
The County reserves the right to add additional services to the contract with the mutual consent of the contracting parties within the contract period.
9.21 NEGOTIATIONS
The County reserves the right to negotiate any and all elements of a contract resulting from this RFQ.
9.22 TRAVEL EXPENSES
The County will reimburse reasonable and necessary travel and related expenses to the successful contractor based on the following conditions: travel expenses for airline expenses for business class based on actual cost.
Lodging, mileage, and food will be based on the GSA per diem rates for the Kansas City Metro region. All such expenses will be up to but not in excess of the per diem rate for this area based on actual receipts. The applicable GSA per diem information can be located at http://www.gsa.gov/portal. Additional expenses such as ground transportation to and from the airport and vehicle rental may also be approved. All travel expenses are subject to the County's prior approval and must have receipts to verify expenses.
9.23 PUBLICITY CLAUSE
Respondent must obtain prior written approval from the County for use of information relating to the County or the contract in advertisements, brochures, promotional materials or media, press releases or other informational avenues.
9.24 OWNERSHIP
Any work product or deliverable report or date provided to the County as a result of work performed while under contract shall be considered property of the County and may be used in any fashion the County deems appropriate.
9.25 OBJECTIONS
Any objections or concerns to the RFQ language, terms and conditions, scope or other elements of the RFQ must be included with the respondent’s response. Failure to note such concerns will indicate respondent’s acceptance of the same.
9.26 SAM (System of Award Management)
Federal Grant shall be verified through SAM for supplier suspension or debarment:
https://sam.gov/content/home http://www.gsa.gov/portal https://sam.gov/content/home
9.27 LICENSES AND PERMITS
The contractor shall be, without expense to the County, responsible for obtaining any necessary licenses and permits.
9.28 CODES AND REGULATIONS
All work within the scope of this RFQ shall be completed by the successful respondent to all…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .